    MAIN PROJECT DATA

    - 17.064 m long hydraulic tunnel

    - 1 double shield TBM having a boring

    diameter of 4,88 m

    - 4,2 m internal section

    - Excavation will be associated with hexagonal precast segments lining

  • 8/12/2019 Mttbm Seli

    3/27

    LINING OF HEXAGONAL PRECAST SEGMENTS

  • 8/12/2019 Mttbm Seli

    4/27

    The method with double shield + hexagonal segments

    has been adopted by SELI in many other completed projects, namely:

    The Yindaruquin irrigation project China (18 km)

    The Evinos aqueduct project Greece (30 km)The Guadiaro aqueduct project Spain (12 km)

    The Whanjazhai Yellow River Diversion Project China (90 km)

    The Esperanza-Poza Honda project Ecuador (23 km)The Mohale project Lesotho (30 km)

    The Pieve Vergonte water power project Italy (9 km)

  • 8/12/2019 Mttbm Seli

    5/27

    It is now applied in the following projects under

    construction:

    The La Joya water projectCostarica (9 km)

    The Dez-Ghomrud water tunnel projectIran (18 km)

    The MonteGiglio ground

    conveyance project Italy

    (9 km)

    The Kerman LongTerm water supply

    project Iran (65 km)

    The Gigel Gibe - Omohydroelectric power project

    Ethiopia (28 km)

  • 8/12/2019 Mttbm Seli

    6/27

    THE TUNNELING SYSTEMGENERAL DESCRIPTION

    The System is composed of:

    A double shield TBM having a boringdiameter of 4,88 m

    A back up system for this TBM The rolling stock to muck out, to transport

    material and personnel

  • 8/12/2019 Mttbm Seli

    7/27

    The system is able to execute the tunnel in a single pass operation, including the following works:

    - Excavation of tunnel

    - Erection of precast lining- Backfill grouting of annular space between the

    excavation and the precast lining

  • 8/12/2019 Mttbm Seli

    8/27

  • 8/12/2019 Mttbm Seli

    9/27

    The principal improvements of proposed doubleshield are:

    the cutterhead design

    the exploration drilling rock consolidation measures

  • 8/12/2019 Mttbm Seli

    10/27

    PRELIMINARY TUNNEL TYPICAL SECTION

    - Boring diameter: 4,88 m

    - Outer dia. of the segmental lining: 4,70 m

    - Inner dia. of the segmental lining: 4,20 m

    - Segmental lining tickness: 25 cm

    - Longitudinal lenght: 1,30 m

  • 8/12/2019 Mttbm Seli

    11/27

    TBM DS Excavation cycle of double shield

    STEP 1:STARTING

    STEP 2:

    TUNNEL EXCAVATION AND INSTALLATION OF

    SEGMENT

    STEP 3:

    ADVANCING THEGRIPPER SHIELD

    (REGRIPPING)

    STEP 4:

    BACK UP ADVANCE

  • 8/12/2019 Mttbm Seli

    12/27

    Back - up

    The main targets at the base of its design development have been: shortest possible length of the back-up without compromise on

    capacity, efficiency and completeness

    reduced time for back-up assembly and connection to the TBM

    physical separation, inside the tunnel section, of the back-upequipment & working area from the rail track transport line

    provide all along the tunnel a safe walkway and working space onthe side of the transport train

    reduced overall weight and dimensions of the back up decks for more economic packing and transport

    to be fully in respect with safety standards and CE certified

  • 8/12/2019 Mttbm Seli

    13/27

  • 8/12/2019 Mttbm Seli

    14/27

    The back up main components are:

    hydraulic power units

    main power transformers

    ZED system

    operator control cabin

    electric switchboard

    Variable speedfrequency converters

    TBM auxiliary equipment General Services

    fresh air ventilationand air distributionsystem

    train pusher segments unloadingand trasport system

    pea gravel system

    grouting system

    gas monitoring

    air scrubbing system

    compressor

    emergency gen set

    MV cable and reels

    lighting system

    close circuit TVcamera system

    muck conveyors

  • 8/12/2019 Mttbm Seli

    15/27

    Rolling stock

    Conveyor

    Equipment

    Walkway foroperators

    SECTION

    PLAN VIEW

  • 8/12/2019 Mttbm Seli

    16/27

    Rolling Stock

    Each tunnel train includes:

    10 muck cars with acapacity of 10 m 3 each

    1 pea gravel car

  • 8/12/2019 Mttbm Seli

    17/27

    4 flatbed cars for the transport of precast segments

    1 personnel car

  • 8/12/2019 Mttbm Seli

    18/27

  • 8/12/2019 Mttbm Seli

    19/27

    MAIN AUXILIARY EQUIPMENT AND SYSTEM

    Ventilation system and dust control Gas detection and alarm system Tunnel ground water pumping system

    Electric power supply Industrial water line Compressed air system

    Lighting system Telephone system

  • 8/12/2019 Mttbm Seli

    20/27

    VENTILATION SCHEME ON TBM AND

    BACK UP AREA

  • 8/12/2019 Mttbm Seli

    21/27

    MONITORING OF THE TBM PARAMETERS AND

    TUNNEL INSTRUMENTATIONSA data-taker registers on electronic support thefollowing parameters:

    - Total thrust- Total power - Working torque- ZED readings- Cutterhead RPM- Penetration rate- Stroke

  • 8/12/2019 Mttbm Seli

    22/27

    MONITORING OF THE TBM PARAMETERSAND TUNNEL INSTRUMENTATIONS

    Moreover it could be recorded:

    - Duration of each 65 cm stroke- Altitude and position of the TBM relative to the tunnel

    axis- Pressure distribution in the thrust cylinders- Cause and duration of any advance stoppage

  • 8/12/2019 Mttbm Seli

    23/27

    PRELIMINARY ORGANIZATION OF

    TUNNELLING ACTIVITIES

    maintenance + eventual probe drilling

    boring shift 1

    boring shift 2

    10 h 10 h4 h

    per 6 days/week

  • 8/12/2019 Mttbm Seli

    24/27

    TBM to advance in unstable ground: cavity filling

  • 8/12/2019 Mttbm Seli

    25/27

    TBM to advance in unstable ground: front consolidation

  • 8/12/2019 Mttbm Seli

    26/27

  • 8/12/2019 Mttbm Seli

    27/27