MS for Masonry

23
METHOD STATEMENT FOR MASONRY WORK 1.0. Materials (i) Internal and External brick/ block Wall a) Brick / Block b) Cement c) Sand d) water (ii) Internal and External plastering a) Cement b) Sand or sieved crushed dust c) Lime or chemicals d) Water e) Chicken mesh with nails f) Wall ties ( For cavity walls)

description

method statement for masonry work

Transcript of MS for Masonry

Page 1: MS for Masonry

METHOD STATEMENT FOR MASONRY WORK

1.0. Materials (i) Internal and External brick/ block Wall

a) Brick / Block b) Cement c) Sandd) water

(ii) Internal and External plasteringa) Cement b) Sand or sieved crushed dustc) Lime or chemicalsd) Watere) Chicken mesh with nailsf) Wall ties ( For cavity walls)

Page 2: MS for Masonry

2.0.Tools

Page 3: MS for Masonry

3.0. Work Description

3.1 Setting Out Work

Wall lines or the plaster lines will be marked at site according to the layout drawing. Specially marked opening for doors & windows in the floor.

3.1 Damp Proof Courses

Bituminous material will be applied on concrete floor prior to start the block / brick work wherever the drawing shows.

4.0. Work Procedure

4.1 Cleaning

After removing all formwork , cleaning will be done with removing of timber strip and removal of dust before commencing the block / brick work. Once the brick / block wall is done the surface shall be clean to ready for the plastering work.

4.2 Marking

At the stage of structure following marking would have done.

1.1000 mm off line each grid has provided.2.Centerline as well as 200 mm off line for each column also marked3.F.F.L + 1000 mm level will be marked for each and every columns.4.200 mm off line for wall line.5.Center line for door opening.

The above lines will be used as base lines for marking of wall, doors and window openings. For each wall line, 200mm off lines will be provided and it will be used for monitoring of location and vertically of wall or the plaster. Each opening will be marked with cross lines.

Page 4: MS for Masonry

4.3 Surface Preparation

The surface belong to walls be prepared under this stage. When surface preparation is done for plastering work, cleaning will be done of the wall surface in order to remove the dust , laitance, loose particles and pins.

4.4 Scaffolding Arrangement

Around working areas necessary scaffolding, ladders and safety requirement will be provided . For perimeter walls

external scaffolding will be used with catwalk panels.

4.5 Water

Temporary water supply line will be provided by connecting flexible hose to deliver the water to the particular place.

Page 5: MS for Masonry

4.6 Sand sieving :

Sand sieving is doing by using sand siever. In order to have fine particles for plastering, 10 squares per inch mesh is used. The meshes are varies from 6,8,10,12 squares per inch.

4.7 Mortar Mixing :

Sand mixing will be done particular floor itself and it will be hand mix for small quantity. For that timber mortar pan is used.

When quantity become more according to give specification mortar will be with mortar mixture.

Mortar mixing is doing by with the help of gauge box as a volume batching . The gauge box has made according to the one cement bag volume.

Page 6: MS for Masonry

4.7 Procedure

After finishing all the markings, brick/block work will be started according to following manner.

1)After inspection of consultant brick/block work will be started.2)The mortar mixing will be done by both machine mixing and hand mixing . The mortar mixing will be done according to the specification. Hand mixing will be done in timber mortar pan or steel motor tray.

By following marking, 1st layer of brick/block will be laid and alignment at the courses will be done as follows. Two corners are carefully laid. Next in between two portions wall will be built. A cord of stretched along the headers by the help of corners vertical strings and level and plumbing will be checked. When walls raised up to lintel level stiffener columns if necessary will be cast.

The gap between two brick/block layers (motor thickness) will be almost 10mm to 15 mm. Where brick/ block walls about underside of concrete beams or slab 20mm thick rigid polyurethane foam will be laid between brick/block wall and concrete beams or slab as a specification strip

The places where block/brick wall contact with structural concrete or stud column will be treated with 150mm width chicken mesh. The mesh will be nailed to the wall and concrete by centering with the block concrete joint.

The bonding technology for the brick walls are given below. Cement blocks are laid in stretcher or running bond as given in section 4.8. The various thicknesses of the blocks are used to suit the wall thickness. (100 x 190 x 390, 150 x 190 x 390, 200 x 190 x 390 -Dimensions are in mm).

The plastering of above brick / block walls shall be categorized into two, as follows.

Page 7: MS for Masonry

Internal plastering:a) Smooth lime finish b) Semi rough finish c) Other finish

1:5 Cement :Sand proportion is used with the thickness of 16mm.

External Plastering :a)Rough plastering b) Tyrolean finish

Plastering thickness and the cement sand proportion is same. The surface finished will taken as semi rough. Which is taken by using sponge.

Page 8: MS for Masonry

4.8 Brick / block construction technology1) 215mm brick wall

2) 328mm brick wall

Page 9: MS for Masonry

3) 440mm brick wall

4) 552 brick wall

Queen closer

Queen closer

Page 10: MS for Masonry

5) Turn brick wall - 102.5 x 102.5mm

6) Turn brick wall - 215 x 215 mm brick wall

Queen closer

Page 11: MS for Masonry

7) Turn brick wall - 328 x 328mm

8) Brick ‘T’ – junction - 102.5 x 102.5 mm

Queen closer

Page 12: MS for Masonry

9) Brick ‘T’ junction - 215 x 102.5mm

10) Brick ‘T’ junction - 328 x215 mm

Queen closer

Half closer

Page 13: MS for Masonry

11) Brick ‘T’ junction - 350 mm cavity wall

Buffer fly ties are put every 1m interval horizontally and 600 center to center vertically.

Each 4m interval put a stat column (if not states only)

1000 mm

Butter fly

350 mm

Page 14: MS for Masonry

12) Block – Stretcher bond

13) Block – Runner bond

Page 15: MS for Masonry

When plastering is done, level gauges shall be set up initially. For internal walls center plum bob will be used to make the level gauges which is plumb to the 200mm off line from both top edges of the walls. Next by keeping measuring tape perpendicular to the plumb string top and bottom level gauges pasted over the wall according to the specified thickness of the plaster will be embedded top of level gauges.

Next by stretching a string to the both end level gauges and intermediate level gauges will be pasted in order to accommodate level bar.

Page 16: MS for Masonry

External wall alignment will be checked by using center plumb bob for corners of the each wall. Straight walls level gauges will be provided from top to bottom . Other steps are as the internal wall arrangement.

Figure 04 :- External level gauge

Mesh Providing :

Figure 05 :- External level gauge

Page 17: MS for Masonry

Surface finished will be taken by scouring with a steel trowel (chemical add to the internal plasters).Plaster corners are made by using corner trowels and aluminum level bar and which is checked by using try square.

5.0. Responsibility

•Survey gang should check all off line and level line.•Surface preparation shall be checked by the Engineer.•Required brick quantity brought to site and kept required location•Brick wall height , opening size & lintel level inthis consideration•Type of brick wall, Limits of the work clearly instruct to assistance . (Level wise and Line wise limits where we can finish)•Sample plastering done prior to plastering .Engineer should get the approval, from one of the sample plaster•Type of plastering, Limits of the plastering clearly instruct to assistance.(Level wise and Line wise limits where we can finish)•Type of mix and ratio of mixes should conformed by Engineer.•Working platform and material supply be ensure by Engineer.•Safety of worker to be confirm by Safety officer.

Page 18: MS for Masonry

Description Quantity Unit

Materials

Bricks 59.20 nos

Add for wastage 5% 2.96 nos

Cement 0.14 bags

Sand 0.03 m³

Sand (50 kg bag) 0.95 bags

Water 24.22 liters

Labour

Mason 0.16 days

U/Sk labour 0.22 days

scaffolding - add 5%

6.0.Calculation

1)For brick / block walls, first calculate the area.2)For plastering calculate the area for plastering. (Internal area and as well as external areas separately)3)According to the given specified mixes, calculate the required cement, sand & chemical amount.*Check with works norms pre arrange materials*4)Calculate the scaffolding materials and make the working platform

7.0.Material and Manpower Requirement

7.1. Brick wall in cement sand 1:5 in 112.5mm(4½”) thick wall in ground floor per m2

Page 19: MS for Masonry

Description Quantity Unit

Materials

Bricks 117.33 nos

Add for wastage 5% 5.87 nos

Cement 0.32 bags

Sand 0.06 m³

Sand (50 kg bag) 1.90 bags

Water 55.71 liters

Labour

Mason 0.24 days

U/Sk labour 0.35 days

scaffolding – add 3%

7.2. Brick wall in cement sand 1:5 in 225mm(9”) thick wall in ground floor per m2

7.3. Brick wall in cement sand 1:5 in 337.5mm(13 ½”) thick wall in superstructure in ground floor per m2

Description Quantity Unit

Materials

Bricks 175.46 nosAdd for wastage 5% 8.77 nos

Cement 0.48 bags

Sand 0.09 m³

Sand (50 kg bag) 2.85 bags

Water 82.35 liters

Labour

Mason 0.38 days

U/Sk labour 0.59 days

scaffolding – add 2%

Page 20: MS for Masonry

7.4. Block wall in cement sand 1:5 in 8” thick wall in ground floor per 100 ft2

Description Quantity Unit

Materials

Blocks 112 nos

Add for wastage 5% 5.6 nos

Cement 0.75 bags

Sand 0.17 m³

Labour

Mason 1.5 days

U/Sk labour 2.5 days

scaffolding - add 5%

Page 21: MS for Masonry

Description Quantity Unit

Materials

Bricks 112 nos

Add for wastage 5% 5.6 nos

Cement 0.40 bags

Sand 0.09 m³

Labour

Mason 1.0 days

U/Sk labour 2.0 days

scaffolding – add 3%

7.5. Block wall in cement sand 1:5 in 4” tk wall in ground floor per 100 ft2

Page 22: MS for Masonry

7.6. Application of 16 mm thick 2:5 cement sand plaster on walls – Cost per 1m2

Description Quantity Unit

Materials

Cement 0.14 Bags

Sand 0.021 m3

Lime or chemicals

Water 45 l

Labour

Mason 0.108 Days

U/Sk labour 0.188 Days

Scaffolding - add 3%

Page 23: MS for Masonry

7.7. Application of 16 mm thick 1: 3 cement sand plaster on walls – Cost per 1m2

Description Quantity Unit

Materials

Cement 0.15 Bags

Sand 0.018 M3

Lime or chemicals

Water 45 l

Labour

Mason 0.108 Days

U/Sk labour 0.161 Days

scaffolding - add 3%