MRP Case studies by Prof Girish Phatak

Section A

Q.1 A firm has 4 work centres a, b, c and d in series with individual capacities in units

per day shown in the figure below. The actual output is also shown in the figure:

A B C D

Actual

output

310/day

(i) What is the system capacity,

(ii) What is the system efficiency.

Q.2. A work centre operates 5 days a week on a 2 shifts per day basis, each shift of 8

hours duration. There are five machines of the same capacity in this work centre. If the

machines are utilized 80% of the time at a system efficiency of 90%, what is the rated output in

standard hours per week.

Q.3. The following is a tentative master schedule for four weeks:

Product Week

1 2 3 4

A

B

C

3000

2000

1200

4000

1500

1800

1200

3000

2500

2500

3500

2000

The bill of labour in key centres for the company’s three major products A, B &c is as

below:

Department Product

A B C

X

Y

Z

0.20 hr

0.08hr

0.11hr.

0.05 hr

0.15 hr

0.08hr

0.10hr

0.20 hr,

0.05hr.

Determine the load on department x, y & z over the next 4 weeks

Q.4 Why Master Production Schedule is prepared ? Explain with suitable examples

A firm produces two products P and Q on produce-to-order basis. The demand for the products

come from several sources. The estimated demand for the two products over the next 5 weeks

are given below:

Sources of demand Product P Product Q

430 380 350 410

Page 3: MRP-CaseStudies2008 (1)

Week Week

1 2 3 4 5 1 2 3 4 5

Intra company

orders

- - 20 10 10 - - 10 - 10

Branch warehouse

orders

- 20 - - - - - - 20 -

R & D orders - 10 10 - - - - - 10 10

Customer demand

(forecast + on

hand order)

25 25 20 25 20 30 30 25 25 20

The safety stock for product P is 25 and for Q is 30. The lot size for P is 60 and for Q is

70. The beginning inventory for P is 50 and for Q is 60. Prepare a master production schedule for

these two products.

Page 4: MRP-CaseStudies2008 (1)

Q.5 What do you mean by Master Production Schedule ? Explain with suitable examples

A firm has developed a MPS for 5 weeks for the products P and Q as shown below:

MPS for 5 weeks

Product Qty. to be produced per week

1 2 3 4 5

P - 60 60 60 -

Q - 70 - 70 70

Determine whether the above MPS underloads or overloads the final assembly line

that produces products P and Q. The final assembly line has an available weekly capacity of

200 hours. Each of product ‘P’ requires 2 hours and each of product ‘Q’ requires 3 hours of

final assembly capacity:

(a) Compute the actual final assembly capacity required to produce the MPS for both

products.

(b) Compare the load with the final assembly capacity available in each week and for the

total 5 weeks.

(b) Does sufficient final assembly capacity exist to produce the MPS ?

(c) What changes to the MPS would you recommend ?

Q.6 What do you mean by level output capacity plan ? Explain

The following information is available regarding a product:

Regular time production capacity = 2500 units per month

Overtime production costs = Rs 10 per unit

Inventory carrying cost = Rs 3 per unit per month

Backlog costs = Rs 5 per unit per month

Beginning inventory = 400 units

Demand in units for four months is 4000, 3500, 2500 and 2800 respectively.

Develop a level output capacity plan that yields zero inventory at the end of 4th month.

What is the total cost that will result from this plan ?

Q.7 Recommend the inventory strategy while launching new product.

A firm has developed the following demand forecast in units for a product:

Month Demand (Units) Month Demand (units)

Jan. 210 July 400

Feb. 100 Aug 220

Mar. 200 Sept 200

April 400 Oct 120

Page 5: MRP-CaseStudies2008 (1)

May 600 Nov 100

June 700 Dec 250

(a) Determine the production rate required to meet the average demand if the

available working days are as below:

Month Working Days Available Month Working Days Available

Jan 22 July 21

Feb 18 Aug 22

Mar 21 Sept 20

April 22 Oct 23

May 22 Nov 19

June 20 Dec 20

(b) Determine the monthly inventory balance required to follow a plan of letting the

inventory absorb all fluctuations in demand. Assuming a constant workforce, no idle time or

overtime, no back orders, no use of sub-contractors and -no capacity adjustment, and no safety

stock, determine the beginning inventory to avoid backlogging of order during any month

(i.e., no negative inventory).

Q,8 Why aggregate planning strategies are necessary?

XYZ Manufacturing company produces a product which has a 6 months demand cycle as below:

Month Forecast demand (units) Work days / month

Jan 300 22

Feb 500 19

Mar 400 21

April

May

100

200

21

22

June 300 20

The company works on a single shift basis of 8 hours per shift. Each unit requires 10

labour-hours to be produced at a labour cost of Rs.6 per hour (regular rate) or Rs.9 per hour

(overtime rate). Units can be sub-contracted at a cost of Rs.208 per unit where as the in-

house manufacturing cost is estimated at Rs.200/- per unit. There are currently 20 workers

employed. The hiring and training costs of additional workers are Rs.300/-per person

whereas the lay-off costs are Rs.400/- per person. Company’s policy is to retain a safety stock

of 20% of monthly forecast and each month’s safety stock becomes the beginning

inventory for the next month. The beginning inventory in January is 50 units and the

inventory carrying cost is estimated to be Rs.2 per unit per month, Stock out cost is estimated as

Rs 20 per unit per month. Three aggregate plans arc proposed.

Plan 1:Vary the workforce size to accommodate demand.

Page 6: MRP-CaseStudies2008 (1)

Plan 2:Maintain a constant workforce of 20 and use overtime and allow idle time to meet

demands.

Plan 3:Maintain a constant workforce of 20 and build inventory or incur stock-out cost.

Plan 4: Maintain a constant workforce of 20 and allow subcontracting and idle time to

meet demand

Plan 5: Maintain a constant workforce of 20 and build inventory or incur subcontracting

cost

Compare the cost of these 3 plans and choose the best plan.

Q.9 What do you mean by Hire and Fire strategy ? Explain

The monthly production requirements of an item for a six-month period was arrived at, keeping

in view the opening stock, forecast demand and safety stock etc. as below.

Month Production

Requirement (units)

Working days

July

August

Sept.

Oct.

Nov.

Dec.

1850

1425

1000.

850

1150

1850

22

19

21

21

22

20

The information relating to the cost is as follows: Manufacturing cost per unit = Rs 100/-

Storage cost (obsolescence, opportunity cost etc.) = 1.5% per month of the

manufacturing cost.

Marginal cost of stockout = Rs 5 per unit per month.

Marginal cost of sub-contracting = Rs.2 per unit (sub-contracting cost of Rs.102 less

mfg. cost of Rs. 100/- per unit).

Man hours required per unit = 5 hours.

The company wants to meet the production requirements by adopting one of the two

levels of manning as mentioned below:

Strategy I: maintain a constant work force level based on average production

requirements during the 6 months, allow inventory to accumulate and fill shortages from

next month’s production.

Strategy II: fix the constant workforce level at the minimum necessary to meet the low

October demand (i.e., it is assumed that workers required = 850 6 5 125 days

8 hrs per day = 25 workers) and sub-contract any monthly difference between

requirements and production. Which strategy should the firm adopt ?

Q.10 What are the advantages and disadvantages of various aggregate planning strategies?

A company adopts a counter seasonal product strategy to smooth production requirements. It

manufacturers its spring product line during the first four months of the year and would like to

Page 7: MRP-CaseStudies2008 (1)

employ a strategy that minimises production costs while meeting the demand during these four

months. The company presently has on its rolls, 30 employees with an average wage of Rs 1000

per month. Each unit of the product requires 8 man hours. The company works on single shift

basis (8 hours shift/day) Hiring an employee costs Rs 400 per employee per occasion and

discharging an employee costs Rs 500 per person per occasion. Inventory carrying costs are Rs.

5 per unit per month and shortage costs are Rs.100 per unit per month. The company forecasts

the demand for the next four months:

Month Demand (Unit) No. of working days

in the Month

January

February

March

April

500

600

800

400

22

19

21

21

The company is thinking of adopting one of the following pure strategies:

Plan I: Vary workforce levels to meet demand

Plan II: Maintain 30 employees and use inventory and stock outs to absorb demand

fluctuations. Which strategy would you recommend?

You may assume nil inventory at the start.

Q.11 Discuss the importance of aggregate planning ?

The order position (i.e, requirements of despatch) for the next 12 months in respect of a

particular product is as under

Month Required units Month Required Units

1 13000 7 11000

2 12000 8 7000

3 10000 9 15000

4 9000 10 13000

5 11000 11 12000

6 13000 12 10000

The production capacity of the shop is 10,000 units per month on regular basis and 3000 units

per month on overtime basis. Subcontracting can be relied up on upto a capacity of 3000 units

per month after giving a lead time of 3 months.

Cost data reveal as under

Rs.5 per piece on regular basis;

Rs.9 per piece on over-time basis;

Rs.7 per piece on sub-contract basis.

Cost of carrying inventory is Re.1.00 per unit per month. Assuming an initial inventory of 1000

units and that no back logging of order is permissible. Suggest an optimal production schedule.

Also, workout the total cost on the basis of the suggested schedule.

Q.12. What do you mean by aggregate planning?

Page 8: MRP-CaseStudies2008 (1)

The demand forecast for a particular product of ABC company for a demand cycle of 10 weeks

is as below. The demand cycle is expected to repeal for the future period,

Week Forecast Week Forecast

1 500 6 1000

2 500 7 600

3 600 8 200

4 800 9 200

5 1200 10 500

Five aggregate planning strategies arc- considered.

Strategy 1: Vary the labour force from an initial capability of 400 units / week to whatever

capacity is required to meet the demand. The incremental cost to change labour

force is as given below.

Amount of change / week Incremental cost to change labour force

200 units

400 units

600 units

Increase

Rs 10,000

Rs. 15,000

Rs. 18,000

Decrease

Rs.10,000

Rs, 18,000

Rs.30.000

Strategy 2: Maintain a stable workforce capable of producing 600 units per week and meet demand by overtime at a

premium of Rs.50 per unit. Idle time costs are equivalent to Rs.60 per unit.

Strategy 3: Vary inventory levels, but maintain a stable workforce producing at an average demand rate with no

overtime or idle time. The carrying cost per unit per week is Rs. 20. (Assume that the company can

arrange to have whatever inventory level is required before week 1 at no additional cost

Strategy 4: Produce at a steady rate of 400 units per week and accept a limited number of back orders during weeks,

when demand exceeds 400 units. The stock out. cost of lost sale is Rs.100 per unit.

Strategy 5: Produce at a steady rate of 200 units per week and sub contract for excess demand at a marginal cost of

Rs,50 per unit

Which strategy do you recommend?

Section B

Q.13 The lead times needed to produce or procure the items were given. Suppose, now we complete the product structure tree by writing the lead time for any item next to it as shown in Fig. below

P, LT = 2

Q (3), LT = 1 R (1), LT = 3 S (2), LT = 2

Page 9: MRP-CaseStudies2008 (1)

LT = 3, R (2) T(2), LT = 3 T(3), LT = 3 U (4), LT = 1

Fig. Product Structure

( Note : Lead times (LT) are in days.)

Based on the above, find out the time-schedule of the requirements of the various items involved if 50 units of the end product P are required to be shipped out on day 8. Specify as to when an item is required and when an order for its production/procurement is to be placed in what quantities.

Q.14 The lead time to procure Paracetamol from a supplier is four

weeks. At present, 54 kg of the drug is available with us. There is also a

scheduled receipt of 45 kg of it in four weeks. The production

requirements of paracetamol over the next nine weeks are as :

Week 1 2 3 4 5 6 7 8 9

Amount in kg 24 - 29 11 - 5 19 27 18

If we use an order quantity of 45 kg, when shall we release the orders for

Paracetamol?

Q.15 Given the following information, how many units are on hand at the end of week 9?

Which are the weeks in which the orders may be placed?

Order Quantity = 200

Lead Time = 2 weeks Week 1 2 3 4 5 6 7 8 9

Requirements

90

10

140

55

5

15

115

95

100

Scheduled Receipts

On Hand at the

End of the Period

110

Page 10: MRP-CaseStudies2008 (1)

Planned Order Release

Q.16. Geetha Industries uses MRP for its production materials planning. The table below

provides the information about a particular component X. The demand for this component

is somewhat uncertain and in order to take care of a sudden spurt in the demand, a safety

stock of 50 items is recommended.

Order Quantity = 250

Lead Time = 3 weeks Week

1 2 3 4 5 6 7 8 9

Requirements

40

100

70

150

20

20

50

100

70

Scheduled Receipts

250

On Hand at the

End of the Period

150

Planned Order

Release

During which week/weeks should the receipts be planned? When should the orders be

placed? What is the expected on hand position at the end of week 9?

Q.17. Jayanagar Chair Co., (JCC) makes office chairs mainly with a steel frame, plastic-thread work and two beautifully carved wooden arm-rests. The latter are procured from a wood-turning shop which supplies JCC with a lead time of five weeks and in a lotsize of 2000 arm-rests.

As per JCC's customers' requirements, the delivery schedule for completed chairs is: Week No. 1 2 3 4 5 6 7 8 9 No. of Chairs required 200 200 500 700 300 The wooden chair handles are almost the last item to go in to JCC's chairs and

Page 11: MRP-CaseStudies2008 (1)

the lead time for the final assembly of the chair can be taken as one week. There are 50completed chairs in stock in JCC's finished goods' warehouse and 800 wooden handles in the plant's store. Due to the orders placed earlier, 2000 wooden handles are scheduled to arrive in week 4. Draw a MRP for the wooden handles.

Q.18 What do you mean by Bill Of Material ?

The manufacture of product x, requires the assembly of modules a, b, and c. Two

modules, each of a and c and only one module of b is needed to make one unit of x.

Module a is made from the sub-assemblies d (2 needed), e(1 needed) and f(2 needed). d is

made from components i, j and k. To make one sub-assembly of d, two components each

of i and j are required and 1 of component k. Sub-assembly f needs components l and m

(one each) . Module c needs sub-modules of g and h in quantities of two units and one

unit, respectively.

Sub-module g is, in turn, assembled from five units each of components i and j. Item i is

made from 1 unit each of components n and o.

(1) Draw the product structure based on the above information.

(2) If 100 units of x are to be produced, what are the requirements at the various

levels of the product? Write an indented Bill of Materials and calculate the

requirement of materials at the various levels.

(3) Calculate the net requirements if the quantities on hand and/or on order are as

shown below. A safety stock of i of 400 is seen as essential as it is used

sometimes in another product y whose demand is not all that predictable.

Item On Hand On Order

d 70

e 100

f 50 100

i 500 500

Q.19 Discuss the importance of MRP.

Bhagyadeep Industries is a small scale unit which assembles decorative lamps. These are

available in two models, Lakshmi (L) and Saraswati (S). The lampbase assembly (A) consisting

of the base (B), the Holder (H) and Wirecoil (W) is common to both the models; however, the

shades or covers (C) for the two models of lamps are different. The lead times are as given in

Figure below.

Page 12: MRP-CaseStudies2008 (1)

L,LT = 1 S,LT = 1

CL (1), LT = 3 A (1), LT = 1 CS (1), LT = 1 A (1), LT = 1

B(1) H(1) W(1) B(1) H(1) W(1)

LT=2 LT=2 LT=1 LT=2 LT=2 LT=1

Product Structures for Lamps

At the beginning of week 1, the materials position is as :

On Hand Scheduled Receipts

Base : 25 Units Cover ( Saraswati ) : During Week 2,

Holders : 100 Units 50 Units

Wire-coil : (During week 3), 100 units.

If an order of 100 Lakshmi is and 50 Saraswati is to be filled by the sixth week, calculate

the materials requirement plan. Assume that the items are ordered as required (there is no fixed

lot size).

Q.20 What is MRP ?

Stick- fast Adhesive Ltd makes adhesive plasters, cellophane tapes, plastic-coated adhesive

tapes, etc all of which need the basic ingredients of a special rubber (Code; RB 342) and a resin

(Code: Rs 108) in addition to various other ingredients. The requirements as per the formula are

as follows:

(a) Adhesive Hospital Tape (AHT)

RB 342; 100 Kg per 1000 m

Rs 108: 90 Kg per 1000 m

(b) Cellotape (CT)

Transparent (CTT)

RB 342: 50 Kg per 1000 m

Rs 108: 60 Kg per 1000 m

Coloured (CTC)

RB 342; 60 Kg per 1000 m

Rs 108: 72 Kg per 1000 m

Page 13: MRP-CaseStudies2008 (1)

(c) Plastic-coated Tape (PCT)

RB 342; 40 Kg per 1000 m

Rs 108: 40 Kg per 1000 m

(d) Water-Proof Sticking Tape (WPT)

RB 342; 80 Kg per 1000 m

Rs 108: 75 Kg per 1000 m

The RB 342 needs to be masticated and cured before it can be incorporated into the tapes. The

mastication and curing time is roughly two weeks. There is no loss of rubber during the

mastication and curing process. RS 108 is procured from another plant of the same company

located elsewhere and usual notice needed by that plant is about 4 weeks. RB 342 (Raw) is

supplied in batches of 4000 Kg with a lead time of four weeks.

The process of manufacture of these tapes consists of:

(a) Masticating and curing the rubber

(b) Mixing the masticated rubber, resin (RS 108) and other ingredients with n-Hexane in a mixer

(c) Coating the solution , thus prepared, onto the cello-paper or clot (as the case may be) and

simultaneously curing the coated sheet in heated chambers.

(d) Slitting the tapes into standard sizes such as 1 inch, ½ inch, etc. and packing in containers.

The manufacturing time for all the tapes (inclusive of packaging) is approximately two weeks

before the product can be shipped out.

Orders committed and forecasted are as follows:

Week from Now 1 5 9 13 17 21 25

Orders in thousand

meters for

AHT

CTT

CTC

PCT

WPT

5

25

-

-

-

10

-

-

5

-

5

25

15

-

-

15

15

-

8

-

20

-

-

-

10

18

-

10

8

10

15

30

-

-

10

The resin is supplied in batches of 5000 Kg.

The inventory position at the plant, as of now, is

RB 342 (raw) : 4500 Kg

RB 342 (Masticated) : 1800 Kg

RS 108 : 3000 Kg

RS 108 is in order, with 5,000 kg expected to arrive in week 5.

Draw a materials Requirement Plan for the above example.

Q.21 What do you mean by MRP ?

Page 14: MRP-CaseStudies2008 (1)

Develop product structure for Item A and Item B based on following data:

To make one unit of A, it requires 1 unit of D ,1 unit of C and 2 units of E.

To make one unit of B, it requires 1 unit of E,1 unit of C and 2 units of F.

To make one unit of C, it requires 1 unit of D and 2 units of F.

To make one unit of D, it requires 1 unit of E and 1 unit of F.

Following information is given with respect to on hand inventory and lead time.

Item On-Hand-Inventory Lead-time(Weeks)

A 50 2

B 60 2

C 40 1

D 30 1

E 30 1

F 40 1

Gross requirement of Item A is 1250 units in the week 9 as well as Gross

requirement of Item B is 460 units in week 9 . Also there is independent requirement of 270 units

for Item D and 380 units for Item E in week9.

Prepare MRP schedule based on above information.

Section C

Q.22 The precedence diagram for assembly activities A to G is shown below. The element times

required for the activities are shown in the diagram in the minutes. The line operates for 7 hours

per day and an output of 550 units per day is desired.

(a) Calculate (i) The cycle time. And

(ii) The theoretical minimum number of workers

(b) Group the task into an appropriate number of workstations.

(c) Calculate the balance efficiency.

Q.23 A producer of electronic equipment needs to add a component sub-assembly operation that

can produce 80 units during 8 hours shift. The operation have been designed for 3 activities as

shown

Operation Activity Standard time (minutes)

A

B

Mechanical Assembly

Electric wiring

12

16

Page 15: MRP-CaseStudies2008 (1)

C

Testing 3

(a) How many workers will be required for each activity?

(b)Assuming that the workers at each station cannot be used for other activities in the plant,

what is the approximate percentage of idle time for this assembly operation?

(c) Compute the balance efficiency.

Q.24 Balance the line for the following

Only 4 workstation are available.

Find the idle time and efficiency of balancing.

Q.25 The sequence of manufacture for a product is as given below

Page 16: MRP-CaseStudies2008 (1)

a) What is the most efficient number of workstations to produce this product at a rate of 40 units

per day? How many workers are required?

b) What is the most efficient and best-balanced operations assignment for 10 workers? What is

the rate of production?

c) The total direct labour cost is Rs. 40 per hour. What is the idle time cost per unit? Assume 8

hours work per day.

Section D

Q.26 PQR company has kept records of break-downs of its machines for 300 day work year as

shown below:

No. of break-

down

Frequency in days

0 40

1 150

2 70

3 30

4 10

300

The firm estimates that each break-down costs Rs.650/- and is considering adopting a

preventive maintenance program which would cost Rs.200 per day and limit the number of

Page 17: MRP-CaseStudies2008 (1)

break-down to an average of one per day . What is the expected annual savings from

preventive maintenance programme?

Q. 27. In a simulated operation, a firm’s maintenance crew received requests for service and

provide service during an 8 hour period as shown below:

Request arrival (clock) time Service time (hours)

0.00 1.5

1.00 0.5

3.30 2.0

4.0 0.5

7.0 1.0

The maintenance labour cost is Rs.140 per hour and the delay time cost is Rs.450 per hour .

a) Find the idle time cost for the maintenance crew.

b) Find the delay time cost for the machinery .

Q.28 The breakdowns of equipment over the past 2 years is as below:

No. of break-downs No . of month this

occurred

0 3

1 7

2 9

3 3

4 2

Total 24

Each break down costs an average of Rs. 300/- . Preventive maintenance service can be hired

at a cost of Rs . 150 per month and it will limit the break downs to an average of one per month.

Which maintenance arrangement is preferable , the current break down maintenance policy or a

preventive maintenance service contract?

Q.29 Request for maintenance service made upon a centralized maintenance facility have been

simulated for a typical 8 hours shift with arrival and service pattern as shown below :

Request arrival (clock) time Repair service time

1:30 60 mins.

2:00 20 mins.

4:15 45 mins.

4:30 120 mins.

5:30 30 mins.

7:00 10 mins.

Page 18: MRP-CaseStudies2008 (1)

The labour charges of maintenance crew is Rs.40 per hour, whether working or idle . the waiting

time of operators and machinery that has broken down is costed at Rs. 70 per hour .

a) Find the idle time cost of maintenance facility.

b) Find the waiting time cost of operators and machinery (not including repair time).

c) Find the total facility idle time and machinery waiting time cost .

d) Assuming that for an additional cost of Rs.10 per hour , the maintenance center could add

another crew and decrease the repair time by one third , would the additional cost be

justified.

Q.30 The probabilities of failure after maintenance for a machine is given in the table below:

Years after

maintenance

1 2 3 4 5

Probabilities of

break downs

0.2 0.4 0.2 0.1 0.1

If there are 50 machines in the facility , what is the expected number of break-downs in the 3rd

year?

Q.31 It costs Rs.4,000 to perform preventive maintenance on a group of 10 machines . If one of

the machine breaks down between preventive maintenance inspection, the break-down

maintenance costs Rs.8,000/- . The break down history on the machines is given below:

Weeks between preventive maintenance

(n)

Probability of break-down

1 0.1

2 0.2

3 0.3

4 0.4

If only costs are considered, how often should preventive maintenance de performed to minimize

the total maintenance cost (i.e. ,cost of preventive maintenance + cost of break-down

maintenance).

Q.32 CCS company has 10 regional computer centers. A preventive maintenance inspection

and repair costs a total of Rs.7000 on the average in all 10 centres. If a break –down occurs at

any centre, and average cost of Rs.10,000 is incurred for break-down maintenance. The break –

down history is as below :

Weeks between preventive maintenance

(n)

Average no. of break-downs between

PM inspections

1 0.6

2 1.8

3 3.0

4 7.0

Page 19: MRP-CaseStudies2008 (1)

Recommend how often preventive maintenance should be performed for minimising the total

maintenance cost.

Q.33 Aworkshop has 20nos. of identical machines. The failure pattern of machines is given in

the following table:

Estimated time after maintenance

attention (in month)

1 2 3 4 5 6

Probability of failure 0.20 0.15 0.15 0.15 0.15 0.20

It costs Rs.150/- to attend a failed machine and rectify the same. Compute the yearly cost of

servicing the broken down machines.

Q.34 The probability of failure Pn of an equipment in the nth

period after maintenance has been

estimated as follows :

N 1 2 3 4

Pn 0.1 0.2 0.4 0.3

Cost of preventive maintenance =Rs.150/-

Cost of break-down maintenance =Rs.1000/-

Determine the optimum frequency of preventive maintenance .

Q.35 A work shop has 65 nos. of machines which are identical. The failure pattern of the

machine has been observed as follows over a year :

Elapsed

time after

last

maintenan

ce in

months

1 2 3 4 5 6 7 8 9 10 11 12

Probabilit

y of

failure

0.0

5

0.0

5

0.1

0

0.1

0

0.1

0

0.1

0

0.1

0

0.1

0

0.1

0

0.1

0

0.0

5

0.0

5

If the yearly cost of servicing the failed machine is Rs. 24,000. What is the average cost of

repairs per machine per occasion.

Q.36 The break-down probability of an equipment is given below:

Month 1 2 3 4 5

Probability 0.05 0.15 0.30 0.30 0.20

Page 20: MRP-CaseStudies2008 (1)

There are 50 equipments in the plant . The cost of individual preventive replacement is Rs. 15

per equipment and the cost of individual break-down replacement is Rs.30 per equipment. Find

out the average break-down maintenance cost per month.

Q.37 Product A has a mean time between failure (MTBF) of 30 hrs. and has a mean time to

repairs(MTTR) of 5hrs. Product B has an M.T.B.F. of 40 hrs and has at MTTR of 2 hrs.

a) Which product has the higher reliability?

b) Which product has greater maintainability ?

c) Which product has greater availability?

Q.38 An electrical circuit board in the main control panel of a machine has four components

A,B,C and D 200 Nos.of the circuit board were subjected to accelerated operation tests which

have been equivalent to 3000 hrs of normal operation. The following data is available from the

tests..

Components

No. of failures

A 3

B 2

C 24

D 5

a) Determine the reliability of the circuit board .

b) Calculate the MTBF for the four components.

Section E

Q. 39 Following is the manpower requirements for each activity in a software project.

Activity Normal time Manpower required

0-1 2 4

1-2 3 3

1-3 4 3

2-4 2 5

3-5 4 3

3-6 3 4

4-7 6 3

5-7 6 6

6-8 5 2

7-9 4 2

Page 21: MRP-CaseStudies2008 (1)

8-9 4 9

A) Draw the network diagram of the project activities.

B) Rearrange the activities suitably for reducing the existing total manpower

requirement.

C) If only 9 men are available for the execution of the project then rearrange the

activities suitably for leveling the manpower resource.

Q.40 Following the manpower requirements for each in a project.

Activity Normal time(days) Manpower Required / Day

1-2 10 2

1-3 11 3

2-4 13 4

2-6 14 3

3-4 10 1

4-5 7 3

4-6 17 3

5-7 13 5

6-7 9 8

7-8 1 11

a) Draw a network and find out total and free float for each activity.

b) The contractor stipulates that during the first 26 days only 4 to 5 men and

during remaining days 8 to 11 men only can be made available. Rearrange

activities suitably for levelling the manpower sources, satisfying the above

condition.

Section F

Q.41 The information regarding jobs to be scheduled through one machine is given below

Job A B C D E F G

Processing Time (

days)

4 12 2 11 10 3 6

Due date ( days ) 20 30 15 16 18 5 9

a. What is the First Cum First Served Schedule ( FCFS ) ?

b. What is the Shortest Processing Time ( SPT ) schedule ?

c. What is the Slack Time Remaining ( STR ) schedule ?

d. What is the Earliest Due Date ( EDD ) schedule ?

e. What are the Mean Flow Times for each of the above

Q.42 Eight jobs are to be processed on a single machine . The processing times, due dates and

importance weights of the jobs are as shown in the table.

Page 22: MRP-CaseStudies2008 (1)

Job 1 2 3 4 5 6 7 8

Processing Time (

days)

5 8 6 3 10 14 7 3

Due date ( days ) 15 10 15 25 20 40 45 50

Importance

Weights

1 2 3 1 2 3 2 1

Assuming no new jobs arrive thereafter, determine using SPT rule and WSPT rule

a. Optimal Sequence

b. Completion time of the jobs

c. Mean flow time as well as Weighted Mean flow time

d. Average in process inventory

e. Lateness, Mean lateness, and Maximum lateness

f. Number of jobs actually late

Q.43 The process times for the five jobs A, B, C, D and E and the due dates of the jobs are given in table below. Job Process Time Due Date (Days) (Days from now) A 9 16 B 7 20 C 5 25 D 11 15 E 6 40 The jobs may be sequenced according to any of the following rules:

a) Minimum Process Time ( MINPRT) b) First Come First Served (FCFS) c) Longest Process Time (LPT) d) Due Date (DD)

For the above set of jobs, compute the following resultant characteristics of he priority rules (sequencing rules):

i) Total completion time ii) Average completion time iii) Average number of jobs in the system iv) Average job lateness

Compare the above characteristics for the given four sequencing rules. Q.44 A machine operator has to perform two operations turning and threading, on a number of

different jobs. The time required to perform these operations for each job is known. Determine

Page 23: MRP-CaseStudies2008 (1)

the order in which the jobs should be processed in order to minimize the total time required to

turn out all the jobs.

Job Time for Turning Minutes Time for Threading Minutes

1 3 8

2 12 10

3 5 9

4 2 6

5 9 3

6 11 1

Also find the total processing time and idle time for turning and threading operations

Q.45 There are seven jobs, each of which has to go through the machines A and B in the order

AB. Processing time in hours is as given below.

Job 1 2 3 4 5 6 7

M/C A 3 12 15 6 10 11 9

M/C B 8 10 10 6 12 1 3

Determine a sequence of these jobs that will minimize the total elapsed time T. Also find T and

idle time for machine A and B.

Q.46 A refrigeration company has six plants located in different parts of a city. Every year it is

necessary for each plant to be completely overhauled. The overhauling is carried out in two

stages A and B, and each stage requires a crew of workmen with completely different skills. The

work on stage B can start only when stage A has been completed. The plant has to be closed for

the entire period of the overhauling. The company, at present is following the schedule of the

overhaul of the six plants as given below:

Time required by the crew in days

Plant P1 P2 P3 P4 P5 P6

Crew A 12 9 10 8 10 10

Crew B 10 7 9 14 6 8

a. Determine the optimal sequence

b. If downtime of any of the six plants costs Rs.5000/day, idle time for crew A costs Rs.

1500/day and idle time for crew B costs Rs.2500 / day, which of the two schedules, the

present one or the one determined in part (a), will be more economical? What are their

respective costs?

Q.47 Four jobs 1,2,3 and 4 are to be processed on each of the five m/cs A,B,C,D and E in the order of ABCDE. Find the minimum total elapsed time if no passing of jobs is permitted. Also determine idle time for each m/c

m/c A m/c B m/c C m/c D m/c E

Page 24: MRP-CaseStudies2008 (1)

Job 1 7 5 2 3 9

Job 2 6 6 4 5 10

Job 3 5 4 5 6 8

Job 4 8 3 3 2 6

Q.48 Four jobs 1,2,3 and 4 are to be processed on each of the four m/cs A,B,C, and D in the order of ABCD. Find the minimum total elapsed time if no passing of jobs is permitted. Also determine idle time for each m/c

m/c A m/c B m/c C m/c D

Job 1 58 14 14 48

Job 2 30 10 18 32

Job 3 28 12 16 44

Job 4 64 16 12 42