1.the MRP II Hierarchy

download 1.the MRP II Hierarchy

of 17

Transcript of 1.the MRP II Hierarchy

  • 8/2/2019 1.the MRP II Hierarchy

    1/17

    The MRP II Hierarchy

  • 8/2/2019 1.the MRP II Hierarchy

    2/17

  • 8/2/2019 1.the MRP II Hierarchy

    3/17

    Long-Range Planning

    At the top of the hierarchy we have long-range

    planning. This involves three functions: resource

    planning, aggregate planning, and forecasting. The

    length of the time horizon for long-range planningranges from around six months to five years. The

    frequency for replanning varies from once per month,

    to once per year, with two to four times per year

    being typical. The degree of detail is typically at thepart family level.

  • 8/2/2019 1.the MRP II Hierarchy

    4/17

    Forecasting

    The forecasting function seeks to predictdemands in the future. Long-range fore-casting is important to determining the

    capacity, tooling, and personnelrequirements. Short-term forecastingconverts a long-range forecast of partfamilies to short-term fore-casts of individual

    end items. Both kinds of forecasts are inputto-the intermediate-level function ofdemandmanagement.

  • 8/2/2019 1.the MRP II Hierarchy

    5/17

    Resource planning

    Resource planning is the process of determining

    capacity requirements over the long term. Decisions

    such as whether to build a new plant or to expand an

    existing one are part of the capacity planningfunction. An important output of resource planning is

    projected available capacity over the long-term

    planning horizon. This information is fed as a

    parameter to the aggregate planning function.

  • 8/2/2019 1.the MRP II Hierarchy

    6/17

    Aggregate planning

    Aggregate planning is used to determine levels ofproduction, staffing, inventory, overtime, and so onover the long term. The level of detail is typically bymonth and for part families. For instance, the

    aggregate planning function will determine whetherwe build up inventories in anticipation of increaseddemand (from the forecasting function), "chase" thedemand by varying capacity using overtime, or dosome combination of both. Optimization techniquessuch as linear programming are often used to assistthe aggregate planning process.

  • 8/2/2019 1.the MRP II Hierarchy

    7/17

    Intermediate Planning

    Included production planning functions:

    demand management

    rough-cut capacity planning

    master production scheduling

    material requirements planning

    capacity requirements planning

  • 8/2/2019 1.the MRP II Hierarchy

    8/17

    Demand management

    The process of converting the long-term

    aggregate forecast to a detailed forecast

    while tracking individual customer orders is

    the function ofdemand management. Theoutput of the demand management module is

    a set of actual customer orders plus a

    forecast of anticipated orders. As timeprogresses, the anticipated orders should be

    "consumed" by actual orders.

  • 8/2/2019 1.the MRP II Hierarchy

    9/17

    ATP

    Demand management is accomplished with a

    technique known as available to promise

    (ATP). This feature allows the planner to

    know which orders on the MPS are alreadycommitted and which are available to

    promise to new customers. ATP combined

    with a capacity-feasible MPS facilitatesnegotiation of realistic due dates.

  • 8/2/2019 1.the MRP II Hierarchy

    10/17

    ATP

    If more orders than expected are received, sothat quoted lead times become excessive,additional capacity (e.g., overtime) might be

    required. On the other hand, if fewer thanexpected orders arrive, sales might want tooffer discounts or some other incentives toincrease demand. In either case, the forecast

    and possibly the aggregate plan should berevised.

  • 8/2/2019 1.the MRP II Hierarchy

    11/17

    Master productionscheduling

    Master production scheduling takes the demandforecast along with the firm orders from the demandmanagement module and, using aggregate capacitylimits, generates an anticipated build schedule at the

    highest level of planning detail. These are the"demands" (i.e., part number, quantity, and due date)used by MRP. Thus, the master production schedulecontains an order quantity in each time bucket for

    every item with independent demand, for everyplanning date.

  • 8/2/2019 1.the MRP II Hierarchy

    12/17

    RCCP

    Rough-cut capacity planning (RCCP) is used to

    provide a quick capacity check of a few critical

    resources to ensure the feasibility of the master

    production schedule. Although more detailed thanaggregate planning, RCCP is less detailed than

    capacity requirements planning (CRP), which is

    another tool for performing capacity checks after the

    MRP processing. RCCP makes use of a bill of

    resources for each end item on the MPS. 1

  • 8/2/2019 1.the MRP II Hierarchy

    13/17

    CRP

    Capacity requirements planning (CRP) provides a

    more detailed capacity check on MRP-generated

    production plans than RCCP. Necessary inputs

    include all planned orderreleases, existing WIPpositions, routing data, as well as capacity and lead

    times for all process centers. In spite of its name,

    capacity requirements planning does notgenerate

    finite capacity analysis. Instead, CRP performs what

    is called infinite forward loading.2

  • 8/2/2019 1.the MRP II Hierarchy

    14/17

    Short-Term Control

    The plans generated in the long- and

    intermediate-term planning functions are

    imple-mented in the short-term control

    modules, ofjob release, job dispatching,and in-put/output control.

  • 8/2/2019 1.the MRP II Hierarchy

    15/17

    Job release

    Job release converts planned order releases

    to scheduled receipts. One of the impor-tant

    functions of job release is allocation. When

    there are several high-level items that use thesame lower-level part, a conflict can arise

    when there is an insufficient quantity on

    hand. By allocating parts to one job oranother, the job release function can

    rationalize these conflicts.

  • 8/2/2019 1.the MRP II Hierarchy

    16/17

    Job Dispatching

    The basic idea behind job dispatching is

    simple: Develop a rule for arranging the

    queue in front of each workstation that will

    maintain due date integrity while keepingmachine utilization high and manufacturing

    times low. Many rules have been proposed

    for doing this.

  • 8/2/2019 1.the MRP II Hierarchy

    17/17

    Input/Output Control

    1. Monitor the WIP level in each process center.

    2. If the WIP goes above a certain level, then the

    current release rate is too high, so reduce it.

    3. If it goes below a specified lower level, then thecurrent release rate is too low, so increase it.

    4. If it stays between these control levels, the

    release rate is correct for the current conditions.