Prepared By
SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS)
MONTHLY PROGRESS REPORT
SEPTEMBER, 2018
RAS OFFICERS’ INSTITUTE (CLUB HOUSE)
(2, institutional Area, Near Dainik Bhaskar, Jaipur)
Developers: M/S RAS Officers’ Institute
2, institutional Area, Near Dainik Bhaskar-Jaipur
Project Highlights
Total Built up Area: - 1, 20,000Sq.ft
Total Floor of Project: -2 Basement + 6 Floors
(Gym, Swimming pool, Banquet hall, Conference hall, Bar, Tennis& Squash)
Builders & Developers
M/S RAS Officers’ Institute,
Registered office at 2, institutional Area,
Near Dainik Bhaskar- Jaipur (Raj.)
Consultants & Management Team
Architectural Consultant Project Management Consultants
Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40, 4th Floor, Trinity Mall,
New Sanganer Road Sodala- Jaipur New Sanganer Road, Jaipur
Mr. Lokesh JoshiMob: 91-9680282624. Phone: 91-9314932438, 0141 5106606
Mr. Kulvinder Singh Mob: 91-9314480610
Structural Consultant MEP Consultant M/S SANRACHNA M/S Cube Consultant
S-41, AMBA BARI, JAIPUR A-8, Jamna Nagar Sodala- Jaipur
Mr. Sandeep Garg Mob: 91-9799496696 Mr. Sanjay Vajpayee Mob: 91-9214308430
Interior Designer Consultant M/S Sthapatya Architects A-58 Shanti path, Tilak Nagar, JAIPUR
Ms. Ritu Khandelwal Mob: 91-9829016773
Contractor Agencies
Civil Contractor Electrical Work Contractor
M/S H. R. Gwala M/S Vijay Electric service
F9/465, Chitrakoot, Vaishali Nagar-Jaipur VivekVihar, New Sanganer Road, Sodala.
Mr. H.R. Gwala Mob: 91-9783940001 Mr. Shyam Vijay Mob: 91-9783300501
Plumbing Contractor Waterproofing Contractor M/S Gayatri Plumbing M/S NS Solutions
B-50, Jawahar Nagar, Jaipur 3/77, Agarwal Farm, Mansarovar, Jaipur
Mr. Jeet Ram Mob: 91-9829008082 Mr. Shrikant Dandia Mob: 91-9214529486
Fire Fighting Contractor False Ceiling Contractor
M/S Men At Work M/s Shakuntalam Interiors Pvt. Ltd.
S-3, CD 304, Dadudayal Residency, 100-A, Civil Lines, Ajmer Road, Jaipur
Dadudayal Nagar, Mansarover, Jaipur. Mr. Sandeep Tholiya Mob: 91-9829059622
Mr. Ravi Kumawat Mob: 91-9928084922
Heating, ventilation, and air conditioning (HVAC)
Daikin Air conditioning India Pvt. Ltd (Higher Side)
S-10-11-12, Second Floor, Geejgarh Tower, Hawa Sadak
Jaipur,302006
M/s K.P. Airtech (Lower Side)
Yashoda Nikunj,BB-51, Jai Ambey Nagar, Tonk Road,
Jaipur – 203018, Rajasthan.
Mr. K.K. Sharma Mob: 91-9829063283
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
4 | P a g e
INDEX
S. No. Content Page. No.
(i) Executive Summary 5
(ii) Project View 5
(iii) Milestone Achieved: At Execution Level 6
(iv) Manpower & Material Status 6-8
(v) Proposed Schedule & Material Procurement Details 8-11
(vi) Drawing Status 12
(vii) Progress Photographs 13-19
(viii) Cube Test Report 19
(ix) Pending Decisions & Requirements 20
Distribution to:-
(i) RASO’I Members
(ii) Architect Design & Services (ADS)-Architectural Consultant
(iii) Sthapatya- Interior Designer
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
5 | P a g e
EXECUTIVE SUMMARY
Terrace floor columns and parapet shuttering,bar binding & casting 40% completed.
Upper basement ramp slab & driveway slab casting completed.
UGWT excavation work in progress.
Fourth & fifth floor brick masonry work in progress.
First Floor plastering work completed & fourth Floor Plastering work in progress.
First & second floor low-voltage wall conducting work in progress.
Ground & first floor electrical ceiling conducting work in progress.
Sprinkler line laying of fourth & ground floor.(scope of fire fighting work).
HVAC copper piping work in progress at ground floor & first floor ducting work in progress.
Fire Staircase fifth floor LVL. BB, Shuttring & Casting in progress.
Plumbing work in progress at fourth floor.LVL.
Earth filling in South & East Side areas of building.
PROJECT VIEW as on 30th
SEPTEMBER 2018
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
6 | P a g e
MILESTONES ACHIEVED
(i) At Execution Level:-
(i) Terrace floor Parapet wall & mumty slab concreting (casting) completed.
(ii) Casting of terrace floor columns concreting (casting) 40% completed.
(iii) North side Boundary wall Stone masonry work started.
(iv) Plastering work started at fourth floor.
(v) HVAC copper piping work Started at ground floor.
(vi) Electrical Wall conducting work Completed at fourth floor.
(vii) Building Front Side Plantation completed.
(viii) UGWT Excavation work started.
(ii) At Decision Level:-
(i) UG water tanks floor level redesigned from lower basement to upper basement floor level.
(ii) Astral PVC Material Finalized for Electrical Conducting work.
(iii) Italian Marble finalized for flooring from R.K. Marble.
(iv) SCM Engineering finalized for Swimming pool work.
(v) ThyssenKrupp finalized for elevator (lift).
MANPOWER DEPLOYED AT SITE STATUS
Total Manpower Deployed at Site by different Agencies / Vendors
Manpower Details Till 30th
September‘18
S. No. Name of Contractor Work Skilled Unskilled Total
1.0 H.R. Gwala Civil Work 60 210 270
1.1 SK Burman/ (H.R. Gwala) Shuttering 70 140 300
1.2 Govind/(H.R. Gwala) Bar Binding 90 150 240
1.3 Ashok/ (H.R. Gwala) Brick Work 210 230 440
1.4 Bharosi/ (H.R. Gwala) Plaster Work 150 160 310
2.0 Vijay Electrical Service Electrical 110 100 210
3.0 Gayatri Plumbing Plumbing 20 20 40
4.0 NS Solutions Waterproofing 0 0 0
5.0 Man At Work Fire Fighting 50 130 180
6.0 WhiteWash White Wash 30 40 70
7.0 K.P. Airtech HVAC 45 60 105
Total 835 1240 2075
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
7 | P a g e
MATERIAL STATUS
A. Steel Received & Consumed Details in September‘18
Diameter of Bar Received Till
Date (MT)
Received in
September
18 (MT)
Consumed in
September ’18
(MT)
Total
Consumed
till Date
(MT)
Balance at
Site as on
30.09.18 (MT)
8mm 85.68
- 1.00 82.68 3.00
10mm 206.97
- 5.00 203.97 3.00
12mm 94.43
- 1.50 94.43 0.00
16mm 55.09
- - 55.09 0.00
20mm 73.59
- 0.50 69.59 4.00
25mm 179.52
- 2.00 176.52 3.00
32mm 132.21
- - 132.21 0.00
Total (MT) 827.53
- 10.00 814.49 13.00
B. Cement Consumed & Received Details in month of September ’18
Location Received
Till Date
(Bags)
Received in
September
’18 (Bags)
Consumed
Till Date
(Bags)
Consumed in
September
’18 (Bags)
Balance at
Site as on
30.09.18
(Bags)
Remarks
At Site 33237 600 33177 1540 60
At RMC
Plant
5792-
372=5420
0 5420 0 0 372 Bags Amount
adjusted in Vendor’s
Bill
Total (Bags) 38657 600 38597 1540 60
C. Aggregate Consumed & Received Details in month of September’18
(i) 10mm Aggregate
Location Received
Till Date
(C.Ft)
Received in
September
’18 (C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
September
’18 (C.Ft)
Balance at Site
as on 30.09.18
(C.Ft)
Remarks
At Site 47539 - 47439 1400 100
At RMC
Plant
11506 - 12271 - 0 Excess 765 C.ft Amount
adjusted in Vendor’s Bill
Total (C.Ft) 59045 - 59710 1400 100
(i) 20mm Aggregate
Location Received
Till Date
(C.Ft)
Received in
September’18
(C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
September
’18 (C.Ft)
Balance at Site
as on 30.09.18
(C.Ft)
Remarks
At Site 77530 1520 76630 2020 900
At RMC
Plant
17911 - 18130 - 0 Excess 219 C.ft Amount
adjusted in Vendor’s Bill
Total (C.Ft) 95441 1520 94760 2020 900
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
8 | P a g e
D. Sand Consumed & Received Details in month of September ’18
Location Received
Till Date
(C.Ft)
Received in
September
’18 (C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
September
’18 (C.Ft)
Balance at Site
as on30.09.18
(C.Ft)
Remarks
At Site 95404 2160 94904 1677 500
At RMC
Plant
18112 - 18100 - 0 12 C.ft Amount adjusted
in Vendor’s Bill
Total (C.Ft) 113516 2160 113004 1677 500
E. Bricks Consumed & Received Details in month of September ’18
Location Received
Till Date
(Nos.)
Received in
September
’18 (Nos.)
Consumed Till
Date (Nos.)
Consumed in
September
(Nos.)
Balance at Site
as on 30.09.18
(Nos.)
At Site 381000 0 377000 15000 4000
Total (Nos.) 381000 0 377000 15000 4000
F. AAC Block Consumed & Received Details in month of September ’18
Location Received
Till Date
(Nos.)
Received in
September’18
(Nos.)
Consumed Till
Date (Nos.)
Consumed in
September
(Nos.)
Balance at Site
as on 30.09.18
(Nos.)
At Site 6222 3022 5422 3822 800
Total (Nos.) 6222 3022 5422 3822 1600
PROPOSED SCHEDULES FOR THE MONTH OF OCTOBER ‘18
Following activities are planned for the Month of October ‘18
(i) Completion of O.H. Tank R/W shuttering, bar binding & casting work.
(ii) Fire Staircase up-to Terrace Floor Level bar binding, shuttering & Casting work.
(iii) Fourth & Fifth Floor brick work.
(iv) Earth filling in surrounding areas of building.
(v) Lower Basement & Ground Floor Plumbing Drainage & fourth floor Toilets Internal Works.
(vi) U.G. Water tank shuttering, bar binding & concreting (casting) work.
(vii) Fourth & Third Floor Electrical Wall & Ceiling Conducting Works.
(viii) Ground Floor Fire Alarm wiring work. (Fire Fighting).
(ix) First Floor HVAC Duct making , Installation & copper Piping of ground floor.
(x) North & East Side Boundary wall foundation & brick work.
(xi) Second & Third Floor Plastering Work.
(xii) Lower & Upper Basement Trimix flooring work.
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
9 | P a g e
STEEL & CEMENT REQUIREMENT FOR THE MONTH OF OCTOBER ‘18
A. Steel Requirement Detail for the Month of October‘18
S. No. Location of Use Dia. Of Bars # Required
Quantity (MT)
Available at
Site (MT)
Net Required
Quantity (MT)
1.
U.G. water tanks, Fire
staircase Boundary wall
Beams & Columns.
8mm 3.00 3.00 -
10mm 8.00 3.00 5.00
12mm 12.00 - 12.00
16mm 5.00 - 5.00
20mm 4.00 4.00 -
25mm 5.00 3.00 2.00
32mm - - -
Total Qty Required (MT) 37.00 MT 13.00 MT 24 MT
B. Cement Requirement Detail for the Month of October‘18
(i) Cement (PPC) At site
S. No. Description of Work Qty. Unit Coefficient Quantity Reqd. (Bags)
1 PCC & RCC Work
(i) UGWT Casting including R/W 220 Cum 7.08 1558
(ii) Terrace Floor Water Tanks Top Slab
& R/W 80 Cum 7.08 566
(iii) O.H. water tank raft & Walls 50 Cum 7.08 354
(iv) Plaster Work 3020 Sqmtr 0.11 334
(v) Stone masonry for Boundary Wall 200 cum 0.84 168
Total Required Bags of Cement for the Month of October ’18 2980
Total Available Bags of Cement at Site 60
Net Required Bags of Cement for the Month of October’18 2920
Say 3000
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
10 | P a g e
C. Aggregate Requirement Detail for the Month of October‘18
(i) 10mm Aggregate
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) UGWT Casting including R/W 220 Cum 11.515 2534
(ii) Terrace Floor Water Tanks Top
Slab & R/W 80 Cum
11.515 912
(iii) O.H. water tank raft & Walls 50 Cum 11.515 576
Total Required Qty of 10mm Aggregates for the Month of October’18 4022
Total Available Qty of 10mm Aggregate at Site 100
Net Required Qty of 10mm Aggregate for the Month of October’18 3922
Say 4000
(ii) 20mm Aggregate
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) UGWT Casting including R/W 220 Cum 16.8 3696
(ii) Terrace Floor Water Tanks Top
Slab & R/W 80 Cum
16.8
1344
(iii) O.H. water tank raft & Walls 50 Cum 16.8 840
Total Required Qty of 20mm Aggregates for the Month of October’18 5880
Total Available Qty of 20mm Aggregate at Site 900
Net Required Qty of 20mm Aggregate for the Month of October’18 4980
Say 5000
A. Sand Requirement Detail for the Month of October ‘18
(i) Sand
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) UGWT Casting including R/W 220 Cum 17.30 3086
(ii) Terrace Floor Water Tanks Top
Slab & R/W 80 Cum
17.30 1384
(iii) O.H. water tank raft & Walls 50 Cum 17.30 865
(iv) Plaster Work 3020 Sqmtr 0.50 1510
(v) Stone masonry for Boundary Wall 200 Cum 14.82 2965
Total Required Qty of Sand for the Month of October’18 9810
Total Available Qty of Sand at Site 500
Net Required Qty of Sand for the Month of October’18 9310
Say 9500
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
11 | P a g e
A. Bricks Requirement Detail for the Month of October ‘18
S.No Description of Work Unit Qty Reqd.
(i) Fourth &Fifth Floor Brickwork. Nos. 5000
(ii) Boundary Wall Brickwork.(front Side) Nos. 26500
Total Required Qty. of Bricks for the Month of October ‘18 31500
Total Available Qty of Bricks at Site 4000
Net Required Qty of Bricks for the Month of October ‘18 27500
Say 27500
B. AAC Block (9”)Requirement Detail for the Month of October ‘18
S.No Description of Work Unit Qty Reqd.
(i) Fifth Floor Brick work. Nos. 1600
Total Required Qty. of Bricks for the Month of October ‘18 1600
Total Available Qty of Bricks at Site -
Net Required Qty of Bricks for the Month of October ‘18 1600
Say 1600
C. Weekly Material Procurement Schedule month of October ‘18
WEEKLY MATERIAL REQUIREMENT SCHEDULE FOR THE MONTH OF SEPTEMBER‘18
S.
NO.
MATERIAL
DESCRIPTION 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK
TOTAL
QUANTITY
Remarks
(if any)
1 Steel 16 9 - - 24 MT
2 Cement(PPC) 1500 600 600 300 3000 Bags
3 10mm Aggregate 2000 1400 600 - 4000 C.Ft
4 20mm Aggregate 2000 1500 800 700 5000C.Ft
5 Sand 4000 3000 1000 1500 9500C.Ft
6 Stone 7056 - - - 7056 cft
7 Bricks 15000 10000 2500 - 27500 Nos.
8 AAC Block 1600 - - - 1600 Nos.
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
12 | P a g e
DRAWING STATUS
Status of Drawings in the Month of September‘18
Following is the status of drawings in month of August from Architect Design & Services (ADS) by PMC
Engineer and issued to concerning Contractors at site.
S.No Date of
Received Drawing Title Drawing No.
Rev.
No. Remark
1 01.09.2018 First Floor Working Plan 176/RASC/FFW/10 03 Received
2 01.09.2018 Third Floor Working Plan 176/RASC/FFW/12 - Received
3 01.09.2018 Fourth Floor Working Plan 176/RASC/FFW/13 - Received
4 - Terrace Floor Working Plan - - Not Received
5 01.09.2018 Fifth Floor Working Plan 176/RASC/FFW/14 - Received
6 03.09.2018 O.H. Water Tank Detail - - Received
7 03.09.2018 Water Tank Covering Slab Detail - Received
8 03.09.2018 Shuttering plan Mumti Slab 176/RASC/TFA/WT/15B Received
9 03.09.2018 Water Tank Section Detail - Received
10 18.09.2018 Lower to fifth Floor Working Plan 176/RASC/FFW/07-14 Received
11 28.09.2018 U.G.Tank Section Detail - Received
12 28.09.2018 U.G.Tank Detail - Received
13 28.09.2018 Pump Room Floor Slab Detail - Received
14 28.09.2018 Puddle Flange Detail for UGT 176/RASC/U.G.Tank Detail Received
15 28.09.2018 Puddle Flange Detail for OGT 176/RASC/TFP/WTS/15B Received
16 28.09.2018 North Side Boundary Wall Section
176/EASC/Ground floor
plan
Received
17 28.09.2018 Swimming Pool Area Working Plan - Received
18 28.09.2018 Swimming Pool Area Section Details - Received
List of Drawings Required in October ’18
Following Drawings are required at site in the Month of October’18
S. No. Drawing Title Date of Requirement
on OR Before
1 Terrace Floor Column & Covering Details with Sections. 10.10.2018
2 STP & Rain water harvesting Pit Details With Sections. 10.10.2018
3 West Side Boundary Wall Plans With Sections. 10.10.2018
4 Final Building Elevation Details With Sections. 10.10.2018
5 Outer Development Details With Sections including All MEP Services. 10.10.2018
6 Fire Staircase Covering detail with Brick work & Railing Details. 10.10.2018
7 Main Gate MS Section Details & Guard Rooms Shuttering & Reinforcement Details.
10.10.2018
8 Revised Door-Window Schedule. 10.10.2018
9 Revised MEP Plan (HVAC, Fire Fighting System) 14.10.2018
10 False Ceiling Plans (Second to Fifth Floor) with Section & Sectional Details.
10.10.2018
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
13 | P a g e
PROGRESS PHOTOGRAPHS
Site View 30th
September ’18
Site visit by Structural consultant & Architect
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
14 | P a g e
Progress Review Meeting at DLB Office
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
15 | P a g e
Project Review Meeting at Site (06.09.2018)
Kishangarh Visit for Italian Marble Finalization of Flooring Material (12.09.2018)
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
16 | P a g e
Plastering Work in Progress at First & Fourth Floor
AAC Block Masonry Work In Progress at Fourth & Fifth Floor Outer Side
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
17 | P a g e
Fire Fighting Work In Progress at Ground Floor
UGWT Excavation Work In Progress
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
18 | P a g e
HVAC Work (Copper piping & Ducting) In Progress at Ground & First Floor
Electrical & Plumbing Work In Progress at Fourth Floor
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
19 | P a g e
Stone Masonry Work (North & East Side)
Cube Testing Report Month of October-2018
RAS Officers Institute (Club House) Monthly Progress Report September ‘18
20 | P a g e
MAJOR PENDING DECISIONS & REQUIREMENTS AT SITE
Some other decisions pending at site are as follows:-
(i) Electrical Accessories & Fixtures Vendors to be finalized.
(ii) STP Vendor to be finalized.
Signature Signature
Mr. Vipin Pachlangia Mr. Kulvinder Singh
(Project Head) (PMC Head)
Mobile: 91-9929312666 Mobile: 91-9314480610