Prepared By
SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS)
MONTHLY PROGRESS REPORT
OCTOBER, 2018
RAS OFFICERS’ INSTITUTE (CLUB HOUSE)
(2, institutional Area, Near Dainik Bhaskar, Jaipur)
Developers: M/S RAS Officers’ Institute
2, institutional Area, Near Dainik Bhaskar-Jaipur
![Page 2: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/2.jpg)
Project Highlights
Total Built up Area: - 1, 20,000Sq.ft
Total Floor of Project: -2 Basement + 6 Floors
(Gym, Swimming pool, Banquet hall, Conference hall, Bar, Tennis& Squash)
Builders & Developers
M/S RAS Officers’ Institute,
Registered office at 2, institutional Area,
Near Dainik Bhaskar- Jaipur (Raj.)
Consultants & Management Team
Architectural Consultant Project Management Consultants
Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40, 4th Floor, Trinity Mall,
New Sanganer Road Sodala- Jaipur New Sanganer Road, Jaipur
Mr. Lokesh JoshiMob: 91-9680282624. Phone: 91-9314932438, 0141 5106606
Mr. Kulvinder Singh Mob: 91-9314480610
Structural Consultant MEP Consultant M/S SANRACHNA M/S Cube Consultant
S-41, AMBA BARI, JAIPUR A-8, Jamna Nagar Sodala- Jaipur
Mr. Sandeep Garg Mob: 91-9799496696 Mr. Sanjay Vajpayee Mob: 91-9214308430
Interior Designer Consultant M/S Sthapatya Architects A-58 Shanti path, Tilak Nagar, JAIPUR
Ms. Ritu Khandelwal Mob: 91-9829016773
![Page 3: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/3.jpg)
Contractor Agencies
Civil Contractor Electrical Work Contractor
M/S H. R. Gwala M/S Vijay Electric service
F9/465, Chitrakoot, Vaishali Nagar-Jaipur VivekVihar, New Sanganer Road, Sodala.
Mr. H.R. Gwala Mob: 91-9783940001 Mr. Shyam Vijay Mob: 91-9783300501
Plumbing Contractor Waterproofing Contractor M/S Gayatri Plumbing M/S NS Solutions
B-50, Jawahar Nagar, Jaipur 3/77, Agarwal Farm, Mansarovar, Jaipur
Mr. Jeet Ram Mob: 91-9829008082 Mr. Shrikant Dandia Mob: 91-9214529486
Fire Fighting Contractor False Ceiling Contractor
M/S Men At Work M/s Shakuntalam Interiors Pvt. Ltd.
S-3, CD 304, Dadudayal Residency, 100-A, Civil Lines, Ajmer Road, Jaipur
Dadudayal Nagar, Mansarover, Jaipur. Mr. Sandeep Tholiya Mob: 91-9829059622
Mr. Ravi Kumawat Mob: 91-9928084922
Heating, ventilation, and air conditioning (HVAC)
Daikin Air conditioning India Pvt. Ltd (Higher Side)
S-10-11-12, Second Floor, Geejgarh Tower, Hawa Sadak
Jaipur,302006
M/s K.P. Airtech (Lower Side)
Yashoda Nikunj,BB-51, Jai Ambey Nagar, Tonk Road,
Jaipur – 203018, Rajasthan.
Mr. K.K. Sharma Mob: 91-9829063283
![Page 4: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/4.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
4 | P a g e
INDEX
S. No. Content Page. No.
(i) Executive Summary 5
(ii) Project View 5
(iii) Milestone Achieved: At Execution Level 6
(iv) Manpower & Material Status 6-8
(v) Proposed Schedule & Material Procurement Details 8-11
(vi) Drawing Status 12
(vii) Progress Photographs 13-17
(viii) Pending Decisions & Requirements 18
Distribution to:-
(i) RASO’I Members
(ii) Architect Design & Services (ADS)-Architectural Consultant
(iii) Sthapatya- Interior Designer
![Page 5: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/5.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
5 | P a g e
EXECUTIVE SUMMARY
Terrace floor OHWT R/W & Slab shuttering,bar binding & casting 90% completed.
UGWT Excavation work in completed.
UGWT Raft & R/W casting completed.
Fourth & fifth floor brick masonry work in 95% completed.
Fourth Floor Plastering work completed & Fifth Floor Plastering work in progress.
First & Second floor low-voltage wall conducting work in progress.
Ground & first floor electrical ceiling conducting work 90% completed as per Drawings.
HVAC copper piping work in progress at ground floor & first floor ducting work in progress.
Fire Staircase fifth floor LVL. BB, Shuttring & Casting Completed.
Plumbing work in progress at fourth floor.LVL.
West , North & South Side Boundary Wall in progress.
PROJECT VIEW as on 31st
OCTOBER 2018
![Page 6: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/6.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
6 | P a g e
MILESTONES ACHIEVED
(i) At Execution Level:-
(i) Terrace floor OHWT concreting (casting) completed.
(ii) Casting of terrace floor columns concreting (casting) completed.
(iii) West & South side Boundary wall Stone masonry work started.
(iv) Fifth Floor Plastering work 70% Completed.
(v) HVAC copper piping work 80% Completed as per Drawings.
(vi) Electrical Wall conducting work Completed at Third floor.
(vii) UGWT Excavation work Competed.
(viii) UGWT R/W work Competed.
(ii) At Decision Level:-
MANPOWER DEPLOYED AT SITE STATUS
Total Manpower Deployed at Site by different Agencies / Vendors
Manpower Details Till 31st
October‘18
S. No. Name of Contractor Work Skilled Unskilled Total
1.0 H.R. Gwala Civil Work 60 290 350
1.1 SK Burman/ (H.R. Gwala) Shuttering 90 150 240
1.2 Govind/(H.R. Gwala) Bar Binding 80 120 200
1.3 Ashok/ (H.R. Gwala) Brick Work 220 240 460
1.4 Bharosi/ (H.R. Gwala) Plaster Work 248 270 518
2.0 Vijay Electrical Service Electrical 105 100 205
3.0 Gayatri Plumbing Plumbing 55 100 155
4.0 NS Solutions Waterproofing 0 0 0
5.0 Man At Work Fire Fighting 50 130 180
6.0 WhiteWash White Wash 20 40 60
7.0 K.P. Airtech HVAC 70 90 160
Total 998 1530 2528
![Page 7: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/7.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
7 | P a g e
MATERIAL STATUS
A. Steel Received & Consumed Details in October‘18
Diameter of Bar Received Till
Date (MT)
Received in
October ’18
(MT)
Consumed in
October ’18
(MT)
Total
Consumed
till Date
(MT)
Balance at
Site as on
31.10.18 (MT)
8mm 85.68
- 2.00 84.68 1.00
10mm 210.02
3.057 2.05 206.02 4.00
12mm 107.16
8.393 7.73 102.16 5.00
16mm 55.09
- - 55.09 0.00
20mm 73.59
- 4.00 73.59 1.50
25mm 179.52
- 0.50 177.02 2.50
32mm 132.21
- - 132.21 0.00
Total (MT) 843.30
- 16.28 830.77 14.00
B. Cement Consumed & Received Details in month of October ’18
Location Received
Till Date
(Bags)
Received in
October ’18
(Bags)
Consumed
Till Date
(Bags)
Consumed in
October’18
(Bags)
Balance at
Site as on
31.10.18
(Bags)
Remarks
At Site 35357 1900 35257 2080 100
At RMC
Plant
5792-
372=5420
0 5420 0 0 372 Bags Amount
adjusted in Vendor’s
Bill
Total (Bags) 40777 1900 40677 2080 100
Aggregate Consumed & Received Details in month of October ’18
(i) 10mm Aggregate
Location Received
Till Date
(C.Ft)
Received in
October’18
(C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
October ’18
(C.Ft)
Balance at Site
as on 31.10.18
(C.Ft)
Remarks
At Site 49059 1520 48559 1120 500
At RMC
Plant
11506 - 12271 - 0 Excess 765 C.ft Amount
adjusted in Vendor’s Bill
Total (C.Ft) 60565 1520 60830 1120 500
(i) 20mm Aggregate
Location Received
Till Date
(C.Ft)
Received in
October’18
(C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
October ’18
(C.Ft)
Balance at Site
as on 31.10.18
(C.Ft)
Remarks
At Site 82090 4560 81290 4660 800
At RMC
Plant
17911 - 18130 - 0 Excess 219 C.ft Amount
adjusted in Vendor’s Bill
Total (C.Ft) 100001 4560 99420 4660 800
![Page 8: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/8.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
8 | P a g e
Sand Consumed & Received Details in month of October ’18
Location Received
Till Date
(C.Ft)
Received in
October’18
(C.Ft)
Consumed
Till Date
(C.Ft)
Consumed in
October ’18
(C.Ft)
Balance at Site
as on 31.10.18
(C.Ft)
Remarks
At Site 101373 5221 100773 5869 600
M.Sand
(Site)
37175 9357 36675 3800 500
At RMC
Plant
18112 - 18100 - 0 12 C.ft Amount adjusted
in Vendor’s Bill
Total (C.Ft) 156660 14578 155548 9669 1100
C. Bricks Consumed & Received Details in month of October ’18
Location Received
Till Date
(Nos.)
Received in
October’18
(Nos.)
Consumed Till
Date (Nos.)
Consumed in
October ’18
(Nos.)
Balance at Site
as on 31.10.18
(Nos.)
At Site 424000 43000 404000 27000 20000
Total (Nos.) 424000 43000 404000 27000 20000
D. AAC Block Consumed & Received Details in month of October ’18
Location Received
Till Date
(Nos.)
Received in
October’18
(Nos.)
Consumed Till
Date (Nos.)
Consumed in
October ’18
(Nos.)
Balance at Site
as on 31.10.18
(Nos.)
At Site 7182 960 6582 1160 600
Total (Nos.) 7182 960 6582 1160 600
PROPOSED SCHEDULES FOR THE MONTH OF NOVEMBER ‘18
Following activities are planned for the Month of November ‘18
(i) Completion of O.H. Water Tank shuttering, bar binding & casting work.
(ii) Completion of Fire Staircase Mummty Slab bar binding, shuttering & Casting work.
(iii) Completion of Fifth Floor brick work.
(iv) Earth filling in surrounding areas of building.
(v) Lower Basement & Ground Floor Plumbing Drainage & Toilets Internal Piping Works.
(vi) U.G. Water tank shuttering, bar binding & concreting (casting) work.
(vii) Ground Floor Electrical Wiring, Modular Box Fixing & Ceiling Conducting Works.
(viii) Ground Floor Fire Alarm wiring work. (Fire Fighting).
(ix) First Floor HVAC Duct making, Installation & copper Piping of ground floor.
(x) South & East Side Boundary wall foundation & brick work.
(xi) Fifth Floor & Staircase Plastering Work.
(xii) Lower & Upper Basement VDC (Trimix) flooring work.
(xiii) Ground Floor False Ceiling Frame Fixing Work.
![Page 9: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/9.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
9 | P a g e
STEEL & CEMENT REQUIREMENT FOR THE MONTH OF NOVEMBER ‘18
A. Steel Requirement Detail for the Month of November‘18
S. No. Location of Use Dia. Of Bars # Required
Quantity (MT)
Available at
Site (MT)
Net Required
Quantity (MT)
1.
Terrace Floor Beam for
Truss Structure
8mm 1.00 1.00 -
10mm 0.00 4.00 -
12mm 0.00 5.00 -
16mm 2.00 0.00 2.00
20mm 2.00 1.50 0.5
25mm 3.00 2.50 0.5
32mm - 0.00 -
Total Qty Required (MT) 8.0 MT 14.0 MT 3.0 MT
A. Cement Requirement Detail for the Month of November‘18
(i) Cement (PPC) At site
S. No. Description of Work Qty. Unit Coefficient Quantity Reqd. (Bags)
1 PCC & RCC Work
(i) UGWT R/W & Slab Casting 110 Cum 7.08 779
(ii) Terrace Floor Water Tanks Top Slab
& Column 80 Cum 7.08 566
(iii) VDC Flooring
(Upper & Lower Basement) 150 Cum 7.08 1062
(iv) Plaster Work 4020 Sqmtr 0.11 442
(v) Boundary Wall Masonry Work 250 cum 0.84 210
Total Required Bags of Cement for the Month of November‘18 3059
Total Available Bags of Cement at Site 100
Net Required Bags of Cement for the Month of November‘18 2959
Say 3500
![Page 10: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/10.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
10 | P a g e
A. Aggregate Requirement Detail for the Month of November‘18
(i) 10mm Aggregate
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) UGWT R/W & Slab Casting 110 Cum 11.515 1266
(ii) Terrace Floor Water Tanks Top
Slab & Column 80 Cum
11.515 921
(iii) VDC Flooring
(Upper & Lower Basement) 150 Cum
11.515 1727
Total Required Qty of 10mm Aggregates for the Month of November’18 3914
Total Available Qty of 10mm Aggregate at Site 500
Net Required Qty of 10mm Aggregate for the Month of November‘18 3414
Say 4000
(ii) 20mm Aggregate
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) UGWT R/W & Slab Casting 110 Cum 16.8 1848
(ii) Terrace Floor Water Tanks Top
Slab & Column 80 Cum
16.8
1344
(iii) VDC Flooring
(Upper & Lower Basement) 150 Cum
16.8 2520
Total Required Qty of 20mm Aggregates for the Month of November’18 5712
Total Available Qty of 20mm Aggregate at Site 800
Net Required Qty of 20mm Aggregate for the Month of November’18 4912
Say 5000
A. Sand Requirement Detail for the Month of November’18
(i) Sand
S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)
(i) UGWT R/W & Slab Casting 110 Cum 17.30 1903
(ii) Terrace Floor Water Tanks Top
Slab & Column 80 Cum
17.30 1384
(iii) VDC Flooring
(Upper & Lower Basement) 150 Cum
17.30 2595
(iv) Plaster Work 4020 Sqmtr 0.50 2010
(v) Boundary Wall Masonry Work 250 cum 14.82 3705
Total Required Qty of Sand for the Month of November’18 11597
Total Available Qty of Sand at Site 1100
Net Required Qty of Sand for the Month of November’18 10497
Say 10500
![Page 11: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/11.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
11 | P a g e
A. Bricks Requirement Detail for the Month of November’18
S.No Description of Work Unit Qty Reqd.
(i) Terrace Floor Brickwork. Nos. 15000
(ii) Boundary Wall Brickwork.(front Side & North Side) Nos. 20000
Total Required Qty. of Bricks for the Month of November’18 35000
Total Available Qty of Bricks at Site 20000
Net Required Qty of Bricks for the Month of November’18 15000
Say 15000
B. AAC Block (9”)Requirement Detail for the Month of November’18
S.No Description of Work Unit Qty Reqd.
(i) Terrace Floor Brick work. Nos. 1000
Total Required Qty. of Bricks for the Month of November’18 1000
Total Available Qty of Bricks at Site -
Net Required Qty of Bricks for the Month of November’18 400
Say 400
C. Weekly Material Procurement Schedule month of November ‘18
WEEKLY MATERIAL REQUIREMENT SCHEDULE FOR THE MONTH OF NOVEMBER‘18
S.
NO.
MATERIAL
DESCRIPTION 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK
TOTAL
QUANTITY
Remarks
(if any)
1 Steel - - - 3.0 3.0 MT
2 Cement(PPC) 1500 600 600 800 3500 Bags
3 10mm Aggregate 2000 1400 600 - 4000 C.Ft
4 20mm Aggregate 2000 1500 800 700 5000C.Ft
5 Sand 4000 3000 1000 2500 10500C.Ft
6 Italian Marble - - - 1200 12000 Sqft
7 Bricks - - 15000 - 15000 Nos.
8 AAC Block - - - 400 400 Nos.
![Page 12: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/12.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
12 | P a g e
DRAWING STATUS
Status of Drawings in the Month of October‘18
Following is the status of drawings in month of August from Architect Design & Services (ADS) by PMC
Engineer and issued to concerning Contractors at site.
S.No Date of
Received Drawing Title Drawing No.
Rev.
No. Remark
1 06.10.2018 Window Details First Floor 176/RASC/FFW/10 - Received
2 06.10.2018 Window Details Third Floor 176/RASC/TFW/12 - Received
3 06.10.2018 Window Details Fourth Floor 176/RASC/FFW/13 - Received
4 06.10.2018 Window Details Fifth Floor 176/RASC/FFW/14 - Received
5 06.10.2018 Fourth Floor Drainage Layout - - Received
6 06.10.2018 Fourth Floor Internal Plumbing Layout - - Received
7 06.10.2018 West Side Boundary Wall Section 176/RASC/GFP/BW Received
8 22.10.2018 Fire Staircase Roof & Beam Detail - Received
9 22.10.2018 Working Plan Terrace Floor 176/RASC/TP/15 Received
10 22.10.2018 Working Plan Ground Floor 176/RASC/GFP/09 Received
11 22.10.2018 Puddle Flange Details UGWT - Received
12 30.10.2018 Fourth Floor Internal Plumbing Layout - 03 Received
13 30.10.2018 Building Electrical Distribution - Received
14 30.10.2018 G.R.C. Jalli Detail 176/RASC/FFP/10 Received
15 30.10.2018 Truss Plan & Section - Received
16 30.10.2018 Trench Covering Jalli Detail 176/RASC/GFP/BWS/09 Received
17 30.10.2018 Lower Basement Drainage Plan - 01 Received
18 30.10.2018 S/E & N/E Corner Boundary 176/RASC/GFP/09 Received
List of Drawings Required in November ’18
Following Drawings are required at site in the Month of November’18
S. No. Drawing Title Date of Requirement
on OR Before
1 Terrace Floor Column & Covering Details with Sections. ASAP
2 STP & Rain water harvesting Pit Details With Sections. ASAP
3 Electrical Working & SLD & Plumbing SLD. ASAP
4 Ground Floor Flooring Detail with Section & Sectional Details.. ASAP
5 Outer Development Details with Sections including All MEP Services. ASAP
6 Fire Staircase Railing Details. ASAP
7 Main Gate MS Section Details & Guard Rooms Shuttering & Reinforcement Details.
ASAP
8 Porch Detail Section & Sectional Details. ASAP
9 Revised MEP Coordinated Plan upto first floor. ASAP
10 False Ceiling Plans (Second to Fifth Floor) with Section & Sectional Details.
ASAP
![Page 13: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/13.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
13 | P a g e
PROGRESS PHOTOGRAPHS
Site View 31th
October ’18
Site Meeting With Architect & MEP Consultant (20.10.2018)
![Page 14: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/14.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
14 | P a g e
Project Review Meeting at Site (24.10.2018)
Site Meeting for Finalization of Electrical Accessories
![Page 15: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/15.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
15 | P a g e
False Ceiling Work in Progress at Ground Floor
Boundary Wall Brick Masonry Work (North & East Side)
![Page 16: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/16.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
16 | P a g e
Project Views (Front Side)
(Back Side View)
![Page 17: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/17.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
17 | P a g e
HVAC Work (Copper piping & Ducting) In Progress at Ground & First Floor
Electrical & Plumbing Work In Progress at First & Third Floor
![Page 18: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,](https://reader033.fdocuments.net/reader033/viewer/2022042101/5e7db9c114aafa448606022d/html5/thumbnails/18.jpg)
RAS Officers Institute (Club House) Monthly Progress Report October ‘18
18 | P a g e
MAJOR PENDING DECISIONS & REQUIREMENTS AT SITE
Some other decisions pending at site are as follows:-
(i) STP Vendor to be finalized.
(ii) Swimming pool Waterproofing & Tile fixing Vendor to be finalized.
(iii) Terrace floor M.S. work Vendor to be finalized.
(iv) Flooring Contractor to be finalized.
(v) Exterior Stone Cladding Contractor to be finalized.
(vi) Elevation Structural Glazing Contractor to be finalized.
Signature Signature
Mr. Vipin Pachlangia Mr. Kulvinder Singh
(Project Head) (PMC Head)