Middle Harbor Redevelopment Project

13
Middle Harbor Redevelopment Project WEDA Conference November 5, 2009

description

Middle Harbor Redevelopment Project. WEDA Conference November 5, 2009. Existing Middle Harbor Terminals. California United Terminals (CUT) 170-acre break-bulk/container terminal at Piers D and E on the north - PowerPoint PPT Presentation

Transcript of Middle Harbor Redevelopment Project

Page 1: Middle Harbor Redevelopment Project

Middle Harbor Redevelopment Project

WEDA ConferenceNovember 5, 2009

Page 2: Middle Harbor Redevelopment Project

Existing Middle Harbor Terminals

● California United Terminals (CUT) 170-acre break-bulk/container terminal at Piers D and E on the north

● Long Beach Container Terminal (LBCT) 101-acre container terminal at Pier F on the south

Page 3: Middle Harbor Redevelopment Project

Proposed Middle Harbor Terminal

● Consolidate two older facilities into one efficient, 345-acre rectangular-shaped terminal

● Construction will occur in multiple stages over a 10-year period

Page 4: Middle Harbor Redevelopment Project

Dredging and Excavation

● Demolish existing Pier D & Pier E wharves

● Widen and deepen Slip 3

● Construct rock containment dike

● Excavate portion of Pier F

Page 5: Middle Harbor Redevelopment Project

Middle Harbor Fill Site

● Fill Pier E Extension, wedge fill, and portion of Slip 1

● Complete fill of Slip 1 and portion of East Basin

● Connect Pier E terminal to Pier F terminal with a fill

EAST BASIN

Page 6: Middle Harbor Redevelopment Project

Project Timing

● Estimated to start in Spring 2010

● Require approx. 4,800,000 cy of fill material

● Project will generate 2,200,000 cy

● Fills will accommodate an additional 2,600,000 cy from other Port and outside sources

● Window of opportunity for acceptance of third party fill material between late 2010 to mid 2012

Page 7: Middle Harbor Redevelopment Project

Sediment Management Plan

Goals● Illustrate Port’s decision process for sediment

management

● Define management priorities for contaminated and uncontaminated sediments

● Define procedures for the movement of sediment

● Guidance document for Port Engineering and Environmental Planning throughout the life of the project

● Living-document to be continually updated

Page 8: Middle Harbor Redevelopment Project

Sediment Management Plan

● Components include a description of the project, a fill plan, priority of acceptance of third party material, and environmental controls to protect water quality

Page 9: Middle Harbor Redevelopment Project

Nature of Fill Material

The Port will NOT accept material that:

1. Constitutes “hazardous waste” as termed by USEPA or CA DTSC

2. Deemed unsuitable for confined aquatic disposal by USEPA

3. Has or will have land use restrictions or other requirements imposed by DTSC or other regulatory agencies

Page 10: Middle Harbor Redevelopment Project

Third Party Fill Material Criteria

Acceptance of third party fill material based on four criteria:

1. Schedule– Delivery timing relative to fill construction progress

2. Fill Composition– Chemical and geotechnical nature

3. Documentation– Required permits, insurance, licenses, & agreements (MOA)

4. Fill Source– Geographic source of material

Page 11: Middle Harbor Redevelopment Project

Geographic Source Priority

1. From other elements of the project

2. From other POLB dredging projects

3. City of Long Beach material unsuitable for unconfined aquatic disposal

4. POLA remedial dredging projects material

5. City of Long Beach material suitable for unconfined aquatic disposal but cannot be beneficially re-used

6. POLA material unsuitable for unconfined aquatic disposal

Page 12: Middle Harbor Redevelopment Project

Geographic Source Priority

7. Western Anchorage Sediment Storage and Disposal Site

8. From dredging projects within Los Angeles County unsuitable for unconfined aquatic disposal

9. From dredging projects outside Los Angeles County unsuitable for unconfined aquatic disposal

10. POLA dredging projects suitable for unconfined aquatic disposal but cannot be beneficially re-used

11. Sand borrow from within the Port of Long Beach

Page 13: Middle Harbor Redevelopment Project

Tom BaldwinSr. Program Manager(562) [email protected]

Matt ArmsSr. Environmental Specialist(562) 590-4160 [email protected]

Thank You

For questions/comments please contact: