Microsoft Project User GroupSeptember 2002 - Chapter
MeetingResource Pooling
Presented by James Nuthall
Brentford Technologies, Inc
• © 2002 by Brentford Technologies, Inc.• ALL RIGHTS RESERVED. No part of this publication may be reproduced, stored in
a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the copyright holder
• All Brentford Technologies, Inc. copyrighted products are distributed exclusively by• Brentford Technologies, Inc.• Danville, California 94526 USA• TEL: (925) 831-9666
Resource Pooling
RESOURCE POOLING
• What is Resource Pool?• Why consider Resource Pool?• Initial Resource Pool Set-up• Sharer Project Schedule Set-up• Updating the Resource Pool• Reviewing the Resource Pool
What is it?
• Ability to see combined resource work load across projects
• Ability to manage resource information in a single repository
Resource on Multiple Projects
Project A
Time
Project D
Wo
rk
Project B
Project C
Project E
Project F
Work Week Hours
•Is Resource Over / Under Utilized ?•If so, where / when?•By how much?
Schematic of Projects across country / continents
.mpp .mpp.mpp.mpp .mpp .mpp.mpp
•How long do you need them?•When will you need them?•How much work will they be doing?
Why Consider it?
• Reduced work effort - Centralized Resource information & maintenance– Rates– Holidays– Vacations– Training classes– Un-Available time
Initial Set-up – Gantt View
Initial Set-up – Resources
Add a Schedule to Res. Pool
Add more Schedule(s)
Resource Pool – Gantt
Resource Pool - Resources
Auto filter Icon
Resource Pool–Resource Usage
Resource Usage view icon
Opening the Resource Pool
Opening Resource Pool (1)
Opening Resource Pool (2)
Opening Resource Pool (3)
Updating Sharer’s project
Saving Sharer’s Changes
Review Pool Information
Resource Pool–Code & Group
Some other Tips when using Resource Pooling
• Save Workspace…• Arrange All• Crtl+ F6 keys• Auto Filter – Custom filters
Do and Don'ts
• Set–up a weekly process for when PM’s will have their .mpp’s up to date and ready for you to review
• Communicate with your PM’s on any updates that effect their schedules
Last Word!!
• This is not a replacement for:– Project 2000 Central– Project 2002 Server
• However for 20+ project schedules and over 250 team members it worked for me!
RECAP
• What is Resource Pool?• Why consider Resource Pool?• Initial Resource Pool Set-up• Sharer Project Schedule Set-up• Updating the Resource Pool• Reviewing the Resource Pool