Microsoft Project 2003The Integrated Master Schedule Conundrum
MPA DC Metro Chapter MeetingSeptember 27, 2005
![Page 2: Microsoft Project 2003 The Integrated Master Schedule Conundrum MPA DC Metro Chapter Meeting September 27, 2005.](https://reader036.fdocuments.net/reader036/viewer/2022082510/5a4d1ae17f8b9ab0599773c8/html5/thumbnails/2.jpg)
Using Master Projects in Microsoft Project
What is the Conundrum?
Not a puzzle … a feature!
![Page 3: Microsoft Project 2003 The Integrated Master Schedule Conundrum MPA DC Metro Chapter Meeting September 27, 2005.](https://reader036.fdocuments.net/reader036/viewer/2022082510/5a4d1ae17f8b9ab0599773c8/html5/thumbnails/3.jpg)
What are Master Projects?
Small project schedules:– Increased computing
speed– File sharing less hassle– Faster printing
Large project schedules:– One file / schedule for
entire program– Master project schedules
can be multi-tiered
Consolidated related projectsConsolidated related projects
![Page 4: Microsoft Project 2003 The Integrated Master Schedule Conundrum MPA DC Metro Chapter Meeting September 27, 2005.](https://reader036.fdocuments.net/reader036/viewer/2022082510/5a4d1ae17f8b9ab0599773c8/html5/thumbnails/4.jpg)
How are master projects created?Two Methods:– Window … New Window
Open all the files to be included in the master project
– Insert … ProjectSelect files one at-a-timeto create a master schedule
Task Informationbecomes Inserted ProjectInformation …Advanced Tab
![Page 5: Microsoft Project 2003 The Integrated Master Schedule Conundrum MPA DC Metro Chapter Meeting September 27, 2005.](https://reader036.fdocuments.net/reader036/viewer/2022082510/5a4d1ae17f8b9ab0599773c8/html5/thumbnails/5.jpg)
Things to considerWho “owns” the master project / getting organized
Linked vs. unlinked
Read-only vs. Read-Write
Saving master schedule on Project Server vs. offline (e.g. laptop hard drive) … or not saving master schedules at all
Using master schedule to create task dependencies between projects
Using the Subproject Read Only, Subproject File, and External Task fields
![Page 6: Microsoft Project 2003 The Integrated Master Schedule Conundrum MPA DC Metro Chapter Meeting September 27, 2005.](https://reader036.fdocuments.net/reader036/viewer/2022082510/5a4d1ae17f8b9ab0599773c8/html5/thumbnails/6.jpg)
Saving and Publishing to Project Server
![Page 7: Microsoft Project 2003 The Integrated Master Schedule Conundrum MPA DC Metro Chapter Meeting September 27, 2005.](https://reader036.fdocuments.net/reader036/viewer/2022082510/5a4d1ae17f8b9ab0599773c8/html5/thumbnails/7.jpg)
Let’s take a quick look …
DemonstrationDemonstration1. Creating a master schedule (linked, not linked, R-O,
R-W)2. Publishing task assignments/reviewing resource
allocations3. Unlinking a schedule4. Creating task dependencies between schedules5. Using “master schedule” fields