MICE Prototype Coupling Coil Fabrication Update

22
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014

description

Allan DeMello Lawrence Berkeley National Laboratory. MICE Prototype Coupling Coil Fabrication Update. MICE CM38 - Napa California February 25, 2014. Outline. Cold mass Prototype vacuum vessel Prototype thermal shield Prototype cooling circuit. MICE Cooling Channel. - PowerPoint PPT Presentation

Transcript of MICE Prototype Coupling Coil Fabrication Update

Page 1: MICE Prototype Coupling Coil Fabrication  Update

MICE Prototype Coupling Coil Fabrication Update

Allan DeMelloLawrence Berkeley National Laboratory

MICE CM38 - Napa California February 25, 2014

Page 2: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 2Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Outline

•Cold mass•Prototype vacuum vessel•Prototype thermal shield•Prototype cooling circuit

Page 3: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 3Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

MICE Cooling ChannelTwo coupling coil magnets integrated into the RFCC modules

Spectrometer solenoid magnets

Focus magnets

Page 4: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 4Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Coupling Coil Sub-assemblies

Page 5: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 5Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Coupling Coil Cold Mass

•Preparation cold mass coil #1 finished at LBNL January 2013

•Preparation of cold mass coils #2, #3 and #4 at LBNL to begin when coils arrive from China

Strain Gauges

Cernox Sensor

Voltage TapsQuench

Protection

Superconductor Lead Stabilizers

Page 6: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 6Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Cold Mass Magnetic Test at Fermilab

The 1st cold mass is currently undergoing magnetic testing at Fermilab

Page 7: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 7Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Coupling Coil Vacuum Vessel•LBNL mechanical shop is in the process of fabricating the first cryostat vacuum vessel

•Estimated completion the end of March (vacuum vessel, tower, warm bore)

•Drawings will be updated to reflect the “as built” cryostat

Page 8: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 8Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Coupling CoilCoupling coil magnet integrated into the RFCC

RFCC Module

Page 9: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 9Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Coupling Coil Scallop ClearanceTight tolerance for vacuum vessel scallops• Because of the tight clearance

distance (2 mm) between the concave radius of the scallop and the O.D. of the RF coupler vacuum vessel spool a tight tolerance was placed on the final locations of the welded scallops.

• The tolerance is true position within 0.254 mm

Scallops

Page 10: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 10

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Coupling Coil Scallop Clearance

MLI superinsulation must also fit inside the 12.5 mm gap between the thermal shield and the inner surface of the scallop.

Limited space between inner surface of the scallop and the thermal shield

Page 11: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 11

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Coupling Coil Vacuum Vessel Tolerance

Tight tolerance on the final locations of the welded scallops.

Page 12: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 12

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Coupling Coil Scallop

Original Scallop Design• Original thin walled scallop

deformed during welding

Gap shows the distortion from welding the scallop to the vacuum vessel

Page 13: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 13

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Coupling Coil Scallop

New Scallop Design• New design has thicker walls

at location of welds to help minimize the distortion

Page 14: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 14

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Alignment Fixture for Welding ScallopsScallop alignment

fixture• LBNL shop developed a

go/no go alignment fixture to ease the welding process for the scallops

Scallop alignment fixture• Nominal and ± indicators

Page 15: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 15

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Vacuum Vessel Welding Complete

Next steps for vacuum vessel

• LBNL shop will machine the central bore and the tower flange

• Finish machine the tower• Complete the warm bore roll-up• Vacuum check the vessel, the

tower and the warm bore

Ports and bore shown covered due to the bead blasting process

Page 16: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 16

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Thermal Shield

Status• Initial thermal shield design and

drawings were completed• Reviewed by LBNL Superconductor

Magnet Group• Design is being revised for ease of

fabrication and assembly (see following slides)

Page 17: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 17

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

New Concept For The Thermal Shield• Design concept from Fermilab

shown• Thermal shield fabricated in two

symmetric halves• Eliminates welding of TS as final

assembly step• Removes the risk of damage to

the MLI wrapped around the cold mass

• New model and drawings will need to be generated

Page 18: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 18

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

New Concept For The Thermal Shield• Concept model of split thermal

shield with edge lip for fasteners

Lips joined by fasteners Half of assembly

Full assembly

Page 19: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 19

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Prototype Cooling Circuit Assembly

Status

• Initial design drawings have been finished and reviewed by the LBNL Superconducting Magnet group

• Revisions required before requesting quotes from outside vendors

• Also requires addition of fiducial target mount points

• LBNL will ship cooling circuit as two sub-assemblies, to be integrated at FNAL in final assembly

Page 20: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 20

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Cold Mass / Thermal Shield Mock-up

A wood mock-up of the cold mass/thermal shield is being planned to assist in defining the coupling coil magnet assembly procedure

Page 21: MICE Prototype Coupling Coil Fabrication  Update

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 21

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Projected Schedule

• Cryostat vacuum vessel components • Completed end of March, shipped to FNAL in April• Incorporation of red-lines into final drawings by ~mid-June

• Thermal shield• Redesign & drawings to be completed by end of March• Fabrication estimated complete by end of May

• Cooling circuit• Drawing revisions to be completed by mid-April• Fabrication estimated complete by July/August

• Cold mass mockup• Design complete by end of February• Fabrication complete by end of March

Page 22: MICE Prototype Coupling Coil Fabrication  Update

MICE RFCC Module – MICE Schedule Review at RAL, UK

Page 22Derun Li - Lawrence Berkeley National Lab – May 24, 2011

Prototype Coupling Coil Fabrication Update – MICE CM38 - Napa California

Page 22

Allan DeMello - Lawrence Berkeley National Lab – February 25, 2014

Summary of Prototype Coupling Coil• Cold Mass

• LBNL finished cold mass preparation work January 2013• Cold mass is currently being tested at Fermilab

• Cryostat Vacuum Vessel• LBNL mechanical shop is fabricating the first cryostat vacuum vessel• Scheduled to finish the end of March

• Thermal Shield• Initial design drawings have been finished and have been reviewed by the LBNL

superconducting magnet group• New thermal shield concept introduced by Fermilab• New model and drawings need to be generated prior to fabrication

• Cooling Circuit• Initial design drawings have been reviewed by the LBNL superconducting magnet group

• Revisions required before requesting fabrication quotes• LBNL will integrate components into two sub-assemblies to be shipped to FNAL this summer