METODE KERJA ARSITEKTUR
![Page 2: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/2.jpg)
METODE PELAKSANAANPEKERJAAN PLESTERAN
DINDINGA. PERALATAN YANG DIGUNAKAN :
1. METERAN2. JIDAR ALUMINIUM3. ROSKAM KAYU4. ROSKAM BESI5. KERTAS SEMEN6. BENANG
B. BAHAN YANG DIGUNAKAN :
1. TRIPLEK2. KAWAT AYAM ( JIKA PLESTERAN LEBIH DARI 3 CM )3. AIR4. SEMEN
![Page 3: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/3.jpg)
C. PELAKSANAAN :
1. PASANG HEBEL SESUAI SHOP DRAWING.
2. BASAHI PERMUKAAN PASANGAN HEBEL DENGAN AIR SAMPAI BASAH SECARA MERATA ( CURING ).
3. PASANG TARIKAN BENANG VERTIKAL DAN HORIZONTAL UNTUK CAPLAKAN KEPALAAN DAN CEK TARIKAN BENANG.
4. SETELAH KEPALAAN TERPASANG TENTUKAN HOLD POINT KE 1 :
ACCEPTANCE CRITERIA
a. INSTALASI M / E SESUAI SHOP DRAWING
KOORDINAT TITIK M / EHARUS TEPAT
b. KETEBALAN KEPALAAN SESUAI SPESIFIKASI
KETEBALAN 1,5 - 3 CM
![Page 4: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/4.jpg)
c. CEK VERTIKALNYA SHOP DRAWING
VERTIKAL & HORIZONTALLURUS DAN RATA
( HARUS LOT )
5. KEMUDIAN TENTUKAN HOLD POINT KE 2 :
ACCEPTANCE CRITERIA
a. KERATAAN PERMUKAAN PLESTERAN
DENGAN JIDAR ALUMINIUML = 2 M DEVIASI ± 1 MM
b. POSISI OUT LET M / E HARUS SESUAI SHOP -DRAWING
![Page 5: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/5.jpg)
PAS. HEBEL
TARIKAN BENANG
HORISONTAL
KEP
ALA
AN
KEP
ALA
AN
TARIKAN BENANG
HORISONTAL
TA
RIK
AN
B
EN
AN
G
VER
TIK
AL
TA
RIK
AN
B
EN
AN
G
VER
TIK
AL
KEP
ALA
AN
KEP
ALA
AN
PLESTER PLESTER PLESTER
TIDAK
PERBAIKI
HOLD POINT 1 SETELAH KEPALAAN TERPASANG
PERIKSA HOLDPOINT 1
YA
HOLD POINT 2
CEK KOORDINATTITIK M / E
CEK LOT
![Page 6: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/6.jpg)
TIDAK
PERBAIKI
HOLD POINT 2 SETELAH MERATAKAN PLESTERAN
PAS. BATA
TARIKAN BENANG
HORISONTAL
KEP
ALA
AN
KEP
ALA
AN
TARIKAN BENANG
HORISONTAL
TA
RIK
AN
B
EN
AN
G
VER
TIK
AL
TA
RIK
AN
B
EN
AN
G
VER
TIK
AL
KEP
ALA
AN
KEP
ALA
AN PLESTER PLESTER PLASTE
R
CEK KERATAANPLESTERAN
PERIKSA HOLDPOINT 2
![Page 7: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/7.jpg)
TIDAK
PERBAIKI
HOLD POINT 2 SETELAH MERATAKAN PLESTERAN
PAS. BATA
TARIKAN BENANG
HORISONTAL
KEP
ALA
AN
KEP
ALA
AN
TARIKAN BENANG
HORISONTAL
TA
RIK
AN
B
EN
AN
G
VER
TIK
AL
TA
RIK
AN
B
EN
AN
G
VER
TIK
AL
KEP
ALA
AN
KEP
ALA
AN PLESTER PLESTER PLASTE
R
CEK KERATAANPLESTERAN
PERIKSA HOLDPOINT 2
PENGACIAN
YA
FINISH ACIAN
![Page 8: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/8.jpg)
• PEKERJAAN PLAFOND GYPSUM
![Page 9: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/9.jpg)
1. TENTUKAN / MARKING ELEVASI PLAFOND DAN BUAT GARIS SIPATAN PADA DINDING & AS SUMBU RUANG - AN SERTA TITIK - TITIK PAKU KAIT PADA LANGIT - LANGIT DENGAN JARAK SESUAI SHOP DRAWING.
2. PASANG PAKU KAIT. TEMBAKAN PAKU - PAKU KAIT PADA MARKING TITIK - TITIK YANG TELAH ADA 600 x 1200 MM.
![Page 10: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/10.jpg)
3. PASANG PENGGANTUNG RANGKA PLAFOND ( ROD ) YANG TERDIRI DARI HANGER DAN CLIP ADJUSTER ( ex. BORAL TYPE 223 ), DENGAN POSISI TEGAK - LURUS.
4. PASANG RANGKA TEPI ( STEEL HOLLOW ) & WALL ANGLE PROFIL L 20 x 20 MM ATAU MOULDING PROFIL W SEBAGAI LIST TEPI TEPAT PADA SIPATAN MARKING ELEVASI PLAFOND.
![Page 11: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/11.jpg)
7. PASANG RANGKA UTAMA / TOP CROSS RAIL ( ex. BORAL TYPE 201 ) DENGAN JARAK 1200 MM.
8. PASANG RANGKA PEMBAGI / FURING CHANEL ( ex. BORAL TYPE 204 ) DENGAN JARAK 600 MM MENG - GUNAKAN LOCKING CLIP ( ex. BORAL TYPE 210 ).
- CEK ELEVASI DAN JARAK RANGKA PLAFOND.- CEK SPARING, DUCTING DAN PERLENGKAPAN MEKANIKAL ELEKTRIKAL LAINNYA.
![Page 12: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/12.jpg)
9. PASANG DAN KENCANGKAN CLIP / ROD.
10. PASANG PANEL GYPSUM PADA RANGKA DENGAN SEKRUP CEILING MENGGUNAKAN SCREW DRIVER DENGAN JARAK 60 CM DAN SETIAP SAMBUNGAN HARUS TEPAT PADA RANGKA.
![Page 13: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/13.jpg)
11. CEK KERAPIHAN DAN KERATAAN BIDANG PLAFOND DENGAN MENGGUNAKAN WATERPASS.
12. PERATAAN SAMBUNGAN PLAFOND DENGAN MENG - GUNAKAN CEILING NET / LAKBAN.
13. KEMUDIAN DITUTUP DENGAN PAPER TAPE DAN COMPOUND CEILING.
14. SETELAH ITU DIAMPLAS.
15. FINISH PERMUKAAN PLAFOND GYPSUM TERSEBUT DENGAN CAT.
a. RATAKAN PERMUKAAN PLAFON GYPSUM MENG - GUNAKAN PLAMUR SAMPAI TERLIHAT RATA DAN LURUS. b. HALUSKAN DENGAN AMPLAS SAMPAI RATA DAN BENAR - BENAR HALUS.
c. CAT SELURUH PERMUKAAN PLAFOND SECARA MERATA DENGAN KUAS UNTUK BAGIAN TEPI DAN SUDUT, SERTA ROL CAT UNTUK BIDANG LUAS.
![Page 14: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/14.jpg)
PERTEMUAN ANTAR PANEL GYPSUM
![Page 15: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/15.jpg)
METODE PEMASANGAN COMPOUND
1. LAKUKAN PELAPISAN PADA PERTEMUAN BIDANG PANEL DENGAN COMPOUND.
2. LANJUTKAN DENGAN PENEMPELAN PAPER TAPE PADA LAPISAN COMPOUND.
3. LAPISKAN KEMBALI COMPOUND MENIMPA PAPER TAPE.
4. TUNGGU SAMPAI KERING.
5. KEMUDIAN HALUSKAN PERMUKAAN DENGAN HAND SANDER DAN GRIT PAPER 150 / 120.
![Page 16: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/16.jpg)
METODE PELAKSANAANPEKERJAAN PEMASANGAN KUSEN
PINTU / JENDELA ALUMINIUM
A. PERALATAN YANG DIGUNAKAN :
1. BAJI KARET / KAYU2. BOR 3. OBENG
B. BAHAN YANG DIGUNAKAN :
1. KUSEN ALUMINIUM2. DAUN PINTU / JENDELA (SETELAH DIPASANG KACA )
3. FISCHER4. SKRUP
5. MORTAR / SEMEN / SEALANT6. VASELINE / ISOLASI KERTAS / PLASTIK-
![Page 17: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/17.jpg)
C. PELAKSANAAN :
1. PASANG KUSEN PINTU / JENDELA ALUMINIUM PADA LOKASI YANG DITENTUKAN ( SESUAI TYPE YANG ADA ),SESUAIKAN LUBANG KUSEN DENGAN UKURAN KUSEN ( SELISIH LUBANG 1 CM ).
2. MASUKKAN KUSEN YANG SIAP DIPASANG KE LUBANG TEMBOK DENGAN BANTUAN BAJI KARET / KAYU.
![Page 18: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/18.jpg)
3. ATUR KEDUDUKAN KUSEN DENGAN BAJI KARET / KAYU.
4. STEL KELURUSAN / KEDUDUKAN KUSEN TERHADAP TEMBOK/ DINDING.
![Page 19: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/19.jpg)
5. LUBANGI TEMBOK / DIN DING MELALUI LUBANG KUSEN DENGAN BOR , UNTUK TEMPAT SKRUP.
6. MASUKKAN FISCHER KE DALAM LUBANG BOR.
![Page 20: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/20.jpg)
7. FISCHER DIKENCANGKAN DENGAN OBENG.
8. PASANG DAUN PINTU / JENDELA ( SETELAH - DIPASANG KACA ) KE - DALAM KUSEN.
9. STEL PERLENGKAPAN SERTA ASESSORISNYA ( RODA / REL , ENGSEL , KUNCI DLL ).
![Page 21: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/21.jpg)
9. FINISH TEMBOK / DINDING DENGAN MORTAR / SEMEN / SEALANT.
( PENGISIAN PADA CELAHANTARA KUSEN DAN TEMBOK / DINDING ).
10. UNTUK MENGHINDARI CACAT PADA PROFIL - PROFIL ALUMINIUM YANG TELAH TERPASANG, MAKA BERI PELINDUNG : SEJENIS VASELINE / ISOLASI KERTAS / PLASTIK PADA TEMPAT YANG RAWAN GORESAN.
![Page 22: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/22.jpg)
I. SHOP DRAWING :
METODE PELAKSANAANPEKERJAAN LANTAI KERAMIK
A. PLANNING
a. MENENTUKAN SISA POTONGAN KERAMIK HARUS > ½ BADAN KERAMIK.
b. MENENTUKAN NAD KERAMIK DINDING & LANTAI AGAR BERTEMU & NAD KERAMIK SERAGAM.c. MENENTUKAN SUPAYA PEREMPATAN KERAMIK BERTEMU.
d. MENENTUKAN TATA LETAK SANITAIR & FIXTURE : HARUS DIPEREMPATAN / TENGAH BADAN KERAMIK.
e. MENENTUKAN TITIK AWAL PEMASANGAN KERAMIK.
f. MENENTUKAN EXPANTION JOINT MINIMAL SETIAP LUAS - AN 12 M² - 16 M².
![Page 23: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/23.jpg)
a. BAHAN YANG DIGUNAKAN :
II. PERHITUNGAN RESOURCES ( SUMBER DAYA ) :
- KERAMIK.
- SEMEN PC.
1. JIDAR ALUMINIUM.
2. BAK AIR ( EMBER ).
b. ALAT YANG DIGUNAKAN :
- AIR.
- ADDITIVE.
3. TEMPAT DUDUKAN / TATAKAN KERAMIK.
4. BENANG ATAU SENAR.
![Page 24: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/24.jpg)
MENENTUKAN TENAGA KERJA YANG DIBUTUHKAN
SESUAI SKEJUL DAN VOLUME PEKERJAAN.
c. TENAGA KERJA :
5. PALU KARET.
6. SENDOK SPESI.
7. WATERPASS.
8. SEKOP.
9. BUSA / SPON
10. KAIN / LAP BASAH.
![Page 25: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/25.jpg)
B. PELAKSANAAN :
1. SIAPKAN PERALATAN DAN BAHAN - BAHAN YANG AKAN DIGUNAKAN.
2. PAHAMI GAMBAR KERJA, POLA PEMASANGAN DAN LAIN - LAIN.
3. SORTIR KERAMIK AGAR MENGHASILKAN KESERAGAMAN : :
- UKURAN / DIMENSI.
- PRESISI.
- WARNA.Jidar Aluminium
OK
OK
![Page 26: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/26.jpg)
4. RENDAM KERAMIK YANG AKAN DIPASANG KEDALAM BAK AIR ( EMBER ) SELAMA 1 JAM.
CONTOH : BAK AIR
OUT
IN
![Page 27: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/27.jpg)
5. KERAMIK DIANGINKAN DENGAN CARA DILETAKAN PADA TEMPAT DUDUKAN / TATAKAN KERAMIK, SETELAH PRO -
SES PERENDAMAN.
TEMPAT DUDUKAN / TATAKAN KERAMIK
![Page 28: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/28.jpg)
6. TENTUKAN GARIS DASAR PASANGAN SERTA PEIL DARI LANTAI.
PENENTUAN PEIL INI UNTUK SELURUH KESATUAN.
7. PASANG BENANG ARAH HORIZONTAL DAN VERTIKAL PADA LANTAI SESUAI ELEVASI PADA SHOP
DRAWING.
BENANG HORIZONTAL
BENANGVERTIKAL
KEDUDUKAN BENANG HARUS DATAR DAN SIKU ,APABILA DINDING YANG ADA ADALAH DINDINGKERAMIK, MAKA KEDUDUKAN NAD LANTAI HARUSDISESUAIKAN DENGAN YANG ADA PADA DINDING.
![Page 29: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/29.jpg)
8. PASANG KERAMIK SEBAGAI PASANGAN KEPALAAN , SEPANJANG GARIS DASAR YANG TELAH TERPASANG.
BENANG HORIZONTAL
BENANGVERTIKAL
KEPALAAN HORIZONTAL
KEPALAAN VERTIKAL
9. CEK KESIKUAN KERAMIK DENGAN BESI SIKU DAN
KERATAAN ELEVASI KERAMIK DENGAN WATERPASS.
![Page 30: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/30.jpg)
BENANG HORIZONTAL
BENANGVERTIKAL
KEPALAAN HORIZONTAL
KEPALAAN VERTIKAL
WATERPASS
10. ISI BAGIAN / DAERAH PERMUKAAN LANTAI YANG LAIN - NYA DENGAN ADUKAN / SPESI.
ADUKAN / SPESI
11. SETELAH ITU PASANG KERAMIK BERIKUTNYA SESUAI POSISINYA SAMPAI SELESAI, USAHAKAN SUPAYA TIDAK ADA LAS - LASAN.
![Page 31: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/31.jpg)
12. JIKA KERAMIK SUDAH TERPASANG SEMUA, KETUK PER - MUKAAN KERAMIK DENGAN PALU KARET UNTUK MENDA -
TARKAN / MERATAKAN PERMUKAAN KERAMIK SUPAYA
TIDAK RUSAK / CACAT.
13. SETELAH ITU CEK KERATAAN ELEVASI KERAMIK DENGAN WATERPASS.
14. BERSIHKAN PERMUKAAN PASANGAN KERAMIK YANG TELAH TERPASANG DENGAN KAIN / LAP BASAH SAM -
PAI BERSIH.
PASANGAN KERAMIK
KAIN / LAPBASAH
![Page 32: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/32.jpg)
15. UNTUK MENGHINDARI NAIKNYA LANTAI ( MENGGELEM - BUNGNYA LANTAI ) MAKA BUATLAH DELATASI.
PAS. KERAMIK LANTAI
30 X 30 CM
DELATASI PER
AS KOLOM
DELATASI PERAS KOLOM
7200
3600
3600
36
00
36
00
72
00
A A
![Page 33: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/33.jpg)
POTONGAN A - A
PLAT BETON
SCREED
DELATASI STEREFORM( 10 MM )
KERAMIK 30 x 30 CM
NAD SEALANT ( 0,5MM )
16. KEMUDIAN SIAPKAN ISIAN / BAHAN COR NAD PADA BAK AIR ( EMBER ) DAN ADUKLAH HINGGA RATA.
![Page 34: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/34.jpg)
17. SETELAH ADUKAN RATA , ISI SELA - SELA NAD DENGAN BAHAN COR NAD DENGAN MENGGUNAKAN SENDOK
SPESI ( SEKOP ).
PENGISIAN NAD DILAKUKAN APABILA KEDUDUKANKERAMIK TELAH KUAT ATAU SPESI TELAH KERING.
18. KEMUDIAN RAPIKAN NAD TERSEBUT DENGAN CAPE.
PASANGAN KERAMIK
NAD KERAMIK
CAPE
![Page 35: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/35.jpg)
19. DIAMKAN DAN TUNGGU SAMPAI NAD TERSEBUT BENAR - BENAR KERING.
20. SETELAH KERING, BERSIHKAN PERMUKAAN PASANGAN KERAMIK YANG SUDAH DIPASANG NAD DARI SISA - SISA
BAHAN COR NAD DENGAN MENGGUNAKAN KAIN / LAP BASAH SAMPAI BERSIH.
PASANGAN KERAMIK
KAIN / LAPBASAH
![Page 36: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/36.jpg)
METODE PELAKSANAANPENGECATAN DINDING
A. PERALATAN YANG DIGUNAKAN :
1. KERTAS SEMEN / KORAN 2. LAKBAN 3. AMPLAS 4. ROL 5. KWAS 6. SKRAP 7. KAIN LAP
B. BAHAN YANG DIGUNAKAN :
1. PLAMIR 2. CAT DINDING
![Page 37: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/37.jpg)
C. PELAKSANAAN :
1. BERSIHKAN PERMUKAAN DINDING DARI DEBU ,
KOTORAN DAN BEKAS PERCIKAN PLESTERAN
DENGAN KAIN LAP.2. LINDUNGI BAHAN - BAHAN / PEKERJAAN LAIN YANG
BERBATASAN DENGAN DINDING YANG AKAN DICAT
DENGAN KERTAS SEMEN / KORAN DAN LAKBAN.
3. GUNAKAN SKRAP UNTUK MEMPERBAIKI BAGIAN -
BAGIAN DINDING YANG RETAK & KURANG RATA
DENGAN PLAMIR, KEMUDIAN TUNGGU SAMPAI
KERING.4. HALUSKAN PLAMIR YANG TELAH KERING DENGAN
AMPLAS HINGGA RATA.
5. C E K , APAKAH PERMUKAAN DINDING SUDAH
RATA ?
![Page 38: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/38.jpg)
6. JIKA PERMUKAAN SUDAH RATA, MAKA LAKUKAN
PENGECATAN DASAR DENGAN ALAT ROL PADA
BIDANG YANG LUAS & DENGAN KWAS UNTUK
BIDANG YANG SEMPIT ( SULIT ).7. JIKA CAT DASAR TERSEBUT SUDAH KERING, LAKU -
KAN PENGECATAN FINISH YANG PERTAMA.
8. JIKA CAT FINISH YANG PERTAMA SUDAH KERING, LA -
LAKUKAN PENGECATAN FINISH YANG KEDUA / TER -
AKHIR ( JUMLAH PELAPISAN CAT SESUAI DENGAN
SPESIFIKASI ).
9. C E K , APAKAH PENGECATAN FINISH YANG KEDUA /
TERAKHIR ITU SUDAH RATA ?
10. APABILA SUDAH RATA, BERSIHKAN CAT - CAT YANG
MENGOTORI BAHAN - BAHAN / PEKERJAAN LAIN YANG
SEHARUSNYA TIDAK TERKENA CAT DENGAN KAIN LAP.
![Page 39: Metode Kerja Arsitektur](https://reader034.fdocuments.net/reader034/viewer/2022050618/5534c6274a79593c508b4ca0/html5/thumbnails/39.jpg)
DINDING
LANTAI
PERLINDUNGAN KERTAS KORAN
TEPI KUSEN DIBERI LAKBAN
TEMPAT CAT
DINDING YANG DICAT