Metallurgylab Presentation

68
Metallurgical Aspects of Boiler Tube Failures – A Few Case Studies B.G.Setty Sr. Manager R&D Centre, Noida

description

power plant

Transcript of Metallurgylab Presentation

Page 1: Metallurgylab Presentation

Metallurgical Aspects of Boiler Tube Failures – A Few Case Studies

B.G.SettySr. Manager R&D Centre, Noida

Page 2: Metallurgylab Presentation

Metallurgical analysis

– Failure analysis– Health/ Condition Assessment – Residual Life Assessment– Indegenisation / Material Development

Page 3: Metallurgylab Presentation

Components

– Boiler tubes– Turbine components– High Energy Piping– CHP Components– Grinding elements– Gas Turbine Components

Page 4: Metallurgylab Presentation

Failure Mechanisms(Water Touched Tubes)

Corrosion FatigueFlyash ErosionHydrogen DamageAcid Phosphate corrosionCaustic GougingFireside CorrosionThermal FatigueErosion CorrosionSootblower Erosion

Short Term Overheating Low Temperature CreepChemical Cleaning DamageFatigue PittingCoal Particle ErosionFalling Slag DamageAcid Dew Point Corrosion

Page 5: Metallurgylab Presentation

Failure Mechanisms(Steam Touched Tubes)

Long Term Overheating / CreepFire Side CorrosionDissimilar Metal Weld Short Term OverheatingStress Corrosion CrackingSH/RH Sootblower Erosion

FatigueRubbing Tubes / FrettingPittingGraphitisationSH /RH Chemical Cleaning

Page 6: Metallurgylab Presentation

Stages in Failure Analysis

Visual Examination.Collection of background data.Identification of sampling locations.Laboratory investigationsAnalysis of data

Page 7: Metallurgylab Presentation

Visual examination of damaged parts is the first and most critical step in failure investigation

Page 8: Metallurgylab Presentation

Case Studies in Failure Investigation

Page 9: Metallurgylab Presentation

Singarauli STPS

Boiler No.3Date of Failure: 05/04/2004Zone: Economiser Lower BankLocation: Coil No.02Material: SA210 A1R&D Ref: 2210

Page 10: Metallurgylab Presentation
Page 11: Metallurgylab Presentation
Page 12: Metallurgylab Presentation

Kahalgaon STPS

Boiler No.2Date of Failure: 28/03/2004Zone: Convection Pass Wall (RHS)Location: Front Tube-01 (from RHS)Material: C20R&D Ref: 2209

Page 13: Metallurgylab Presentation
Page 14: Metallurgylab Presentation
Page 15: Metallurgylab Presentation
Page 16: Metallurgylab Presentation

Ramagundam STPS

Boiler No.1Date of Failure: 01/03/2004Zone: Economiser LHS wallLocation: Bank no.03 (from rear)Material: SA210 A1R&D Ref: 2198

Page 17: Metallurgylab Presentation
Page 18: Metallurgylab Presentation
Page 19: Metallurgylab Presentation

Corrosion Fatigue

Page 20: Metallurgylab Presentation
Page 21: Metallurgylab Presentation

Ramagundam STPS

Boiler No.2Date of Failure: 27/02/2004Zone: ReheaterLocation: Bank-05, Coil-22, Tube-07Material: SA213 T22R&D Ref: 2199

Page 22: Metallurgylab Presentation
Page 23: Metallurgylab Presentation
Page 24: Metallurgylab Presentation

Korba STPS

Boiler No.1Date of Failure: 09/01/2004Zone: ReheaterLocation: Panel-31, 3rd Bend, 2nd BunchMaterial: SA213 T11R&D Ref: 2132

Page 25: Metallurgylab Presentation
Page 26: Metallurgylab Presentation
Page 27: Metallurgylab Presentation

Long Term Overheating

Page 28: Metallurgylab Presentation

Talcher #2, Stage –I

S-Panel Water Wall Tube Failure

Dated 09/01/2004

Report: R&D/MET/2130

Page 29: Metallurgylab Presentation

Pinhole on weld

Page 30: Metallurgylab Presentation
Page 31: Metallurgylab Presentation
Page 32: Metallurgylab Presentation
Page 33: Metallurgylab Presentation
Page 34: Metallurgylab Presentation
Page 35: Metallurgylab Presentation
Page 36: Metallurgylab Presentation
Page 37: Metallurgylab Presentation
Page 38: Metallurgylab Presentation

Vindhyachal #8

S-Panel Water Wall Tube Failure

Dated 06/12/2003

Report No R&D/MET/2073

Page 39: Metallurgylab Presentation
Page 40: Metallurgylab Presentation
Page 41: Metallurgylab Presentation

2073

Origin of Leak

Page 42: Metallurgylab Presentation

Origin of Leak

Page 43: Metallurgylab Presentation
Page 44: Metallurgylab Presentation
Page 45: Metallurgylab Presentation
Page 46: Metallurgylab Presentation

NCPP Dadri #2

S-Panel Water Wall Tube Failure

Dated 05/11/2003

Report No. R&D/MET/R-2118

Page 47: Metallurgylab Presentation
Page 48: Metallurgylab Presentation
Page 49: Metallurgylab Presentation
Page 50: Metallurgylab Presentation
Page 51: Metallurgylab Presentation
Page 52: Metallurgylab Presentation

TANDA Unit #2

Hydrogen Damage Failure in Water Wall

Page 53: Metallurgylab Presentation
Page 54: Metallurgylab Presentation
Page 55: Metallurgylab Presentation
Page 56: Metallurgylab Presentation

NCPP Dadri Unit #2

Weld Porosity in Economiser Tube

Page 57: Metallurgylab Presentation
Page 58: Metallurgylab Presentation
Page 59: Metallurgylab Presentation
Page 60: Metallurgylab Presentation

Talcher Thermal Unit #6

Weld Defects in Economiser Tube

Page 61: Metallurgylab Presentation
Page 62: Metallurgylab Presentation
Page 63: Metallurgylab Presentation
Page 64: Metallurgylab Presentation

Water wall Tube (near Man hole)Material: SA210 GrA1

Thermal Fatigue

Page 65: Metallurgylab Presentation

Hydrogen Damage

Page 66: Metallurgylab Presentation

Usefulness of Failure Analysis

Establishing the main reason of failureEstablishing the main reason of failureTaking remedial action to prevent further Taking remedial action to prevent further

failuresfailuresReduces forced outagesReduces forced outagesHelps in taking decisions for making design Helps in taking decisions for making design

modifications, if necessarymodifications, if necessary

Page 67: Metallurgylab Presentation

Water wall (Rear Side- tube no. 139 - S-Panel bend)Water wall (Rear Side- tube no. 139 - S-Panel bend)

Short Term Overheating

Page 68: Metallurgylab Presentation