MAY 02, 2012 | HOLYOKE, MA

45
MAY 02, 2012 | HOLYOKE, MA Matthew Gdula SENIOR BUSINESS ANALYST MARKET OPERATIONS SUPPORT SERVICE Compensation and Cost Allocation Transitional Demand Response

description

MAY 02, 2012 | HOLYOKE, MA. Matthew Gdula. SENIOR BUSINESS ANALYST MARKET OPERATIONS SUPPORT SERVICE. Compensation and Cost Allocation. Transitional Demand Response. Objectives. At the completion of this training you will know: How payments and charges are determined - PowerPoint PPT Presentation

Transcript of MAY 02, 2012 | HOLYOKE, MA

Page 1: MAY 02, 2012 | HOLYOKE, MA

MAY 02, 2012 | HOLYOKE, MA

Matthew GdulaSENIOR BUSINESS ANALYST

MARKET OPERATIONS SUPPORT SERVICE

Compensation and Cost Allocation

Transitional Demand Response

Page 2: MAY 02, 2012 | HOLYOKE, MA

2

Page 3: MAY 02, 2012 | HOLYOKE, MA

Objectives

• At the completion of this training you will know:– How payments and charges are determined– Settlement changes related to the FCM Market– Cost allocation– Report Changes

3

Page 4: MAY 02, 2012 | HOLYOKE, MA

Governing Documents

• Market Rule 1, Appendix E– Section III.E.9

• Market Rule 1, Section 13– III.13.7.2.5.3– III.13.7.2.5.4

4

Page 5: MAY 02, 2012 | HOLYOKE, MA

TRANSITIONAL DEMAND RESPONSEPayments and Charges

Page 6: MAY 02, 2012 | HOLYOKE, MA

Payments and Charges

• Day-Ahead– Paid for any MW cleared

• Real-Time– Paid or Charged dependent

on Real-Time Conditions

6

Page 7: MAY 02, 2012 | HOLYOKE, MA

Calculate Asset Day-Ahead Payment

7

Day-Ahead Demand Reduction PaymentDay-Ahead Demand Reduction Payment

Day-Ahead Demand Reduction ObligationDay-Ahead Demand Reduction Obligation Day-Ahead LMPDay-Ahead LMPX

Cleared Demand Reduction OfferCleared Demand Reduction Offer X ( 1 + Average Avoided Peak

Distribution LossesAverage Avoided Peak

Distribution Losses )

• Note– Day-Ahead LMP applicable to the Load Zone the asset is located

Page 8: MAY 02, 2012 | HOLYOKE, MA

Average Avoided Peak Distribution Losses

• Section III.E.10– The average avoided peak transmission and distribution losses used for the

associated Capacity Commitment Period in the FCMless

The percent average avoided peak transmission system losses

• Section III.13.7.1.5.1.– The percent average avoided peak transmission and distribution losses used by

the ISO in its calculations of the Installed Capacity Requirement (ICR) for the Forward Capacity Auction immediately preceding the Forward Capacity Auction

• The ICR report states the Transmission and Distribution Gross-up as 8%

• Average avoided peak transmission system losses– Calculated to be 1.5%

• Average Avoided Peak Distribution Losses– 8% - 1.5% = 6.5%

8

Page 9: MAY 02, 2012 | HOLYOKE, MA

9

Asset Day-Ahead Offer ExampleDemand Reduction Offer - 123

MW 5

Price $30

Minimum interruption duration 1 hour

Curtailment Initiation Price $0

Demand Reduction Offer Cost $30

Demand Reduction Offer - 456MW 2

Price $50

Minimum interruption duration 1 hour

Curtailment Initiation Price $400

Demand Reduction Offer Cost $250

Offer Price + [Curtailment Initiation Price/(Minimum interruption duration x bid amount)]:

$30 + [0/(1 x 5)] = $30

Page 10: MAY 02, 2012 | HOLYOKE, MA

10

Asset Day-Ahead Offer ExampleDemand Reduction Offer - 123

MW 5

Price $30

Minimum interruption duration 1 hour

Curtailment Initiation Price $0

Demand Reduction Offer Cost $30

Demand Reduction Offer - 456MW 2

Price $50

Minimum interruption duration 1 hour

Curtailment Initiation Price $400

Demand Reduction Offer Cost $250

Offer Price + [Curtailment Initiation Price/(Minimum interruption duration x bid amount)]:

$50 + [400/(1 x 2)] = $250

Page 11: MAY 02, 2012 | HOLYOKE, MA

11

Asset Day-Ahead Payment ExampleDemand Reduction Offer - 123

MW 5

Price $30

Minimum interruption duration 1 hour

Curtailment Initiation Price $0

Demand Reduction Offer Cost $30

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

Hour Asset Load Zone

DA Cleared (MWh)

DA Demand Reduction Obligation (MWh)

DA LMP ($/MWh)

DA Payment($)

16 123 ABC 5 5.325 320 1704.00

Demand Reduction Offer - 456MW 2

Price $50

Minimum interruption duration 1 hour

Curtailment Initiation Price $400

Demand Reduction Offer Cost $250

5.325 x 320$320 ≥ $30

5 x (1 + 0.065)

Page 12: MAY 02, 2012 | HOLYOKE, MA

12

Asset Day-Ahead Payment ExampleDemand Reduction Offer - 123

MW 5

Price $30

Minimum interruption duration 1 hour

Curtailment Initiation Price $0

Demand Reduction Offer Cost $30

Hour Asset Load Zone

DA Cleared (MWh)

DA Demand Reduction Obligation (MWh)

DA LMP ($/MWh)

DA Payment($)

16 123 ABC 5 5.325 320 1704.00

16 456 XYZ 2 2.13 500 1065.00

Demand Reduction Offer - 456MW 2

Price $50

Minimum interruption duration 1 hour

Curtailment Initiation Price $400

Demand Reduction Offer Cost $250

$500 ≥ $250

2 x (1 + 0.065)

2.13 x 500

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

Page 13: MAY 02, 2012 | HOLYOKE, MA

13

Asset Day-Ahead Payment ExampleDemand Reduction Offer - 123

MW 5

Price $30

Minimum interruption duration 1 hour

Curtailment Initiation Price $0

Demand Reduction Offer Cost $30

Hour Asset Load Zone

DA Cleared (MWh)

DA Demand Reduction Obligation (MWh)

DA LMP ($/MWh)

DA Payment($)

16 123 ABC 5 5.325 320 1704.00

16 456 XYZ 2 2.13 500 1065.00

Demand Reduction Offer - 456MW 2

Price $50

Minimum interruption duration 1 hour

Curtailment Initiation Price $400

Demand Reduction Offer Cost $250

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

Page 14: MAY 02, 2012 | HOLYOKE, MA

Asset Real-Time Payments and Charges

• An asset is eligible for Real-Time Payments and Charges when– The asset clears in Day-Ahead, or– The hourly provisional Real-Time LMP is greater than or equal to the

Demand Reduction Offer price

14

Page 15: MAY 02, 2012 | HOLYOKE, MA

Calculate Asset Real-Time Payments or Charges

Asset clears Day-Ahead

15

Real-Time Payments or Charges

Real-Time Payments or Charges

Real-Time Demand Reduction Obligation

Real-Time Demand Reduction Obligation Final Real-Time LMPFinal Real-Time LMPX

Real-Time demand reduction adjusted for net supply

Real-Time demand reduction adjusted for net supplyMIN ( ,

Demand Reduction Offer

Demand Reduction Offer X 2) X( 1+ Average Avoided Peak

Distribution LossesAverage Avoided Peak

Distribution Losses )

Day-Ahead Demand Reduction ObligationDay-Ahead Demand Reduction Obligation-( )

• Note– Real-Time LMP applicable to the Load Zone the asset is located

• Exception– Real-Time Demand Reduction Obligation is capped to the Day-Ahead

Demand Reduction Obligation when the provisional Real-Time LMP < Demand Response Threshold Price

Page 16: MAY 02, 2012 | HOLYOKE, MA

16

Real-Time Payments or Charges

Real-Time Payments or Charges

Real-Time Demand Reduction Obligation

Real-Time Demand Reduction Obligation Final Real-Time LMPFinal Real-Time LMPX

Calculate Asset Real-Time Payments or Charges

Asset does not clear Day-Ahead

Real-Time demand reduction adjusted for net supply

Real-Time demand reduction adjusted for net supplyMIN ( ,

Demand Reduction Offer

Demand Reduction Offer X 2) X( 1+ Average Avoided Peak

Distribution LossesAverage Avoided Peak

Distribution Losses )

• Note– Real-Time LMP applicable to the Load Zone the asset is located

• Exception– Will not be charged if Real-Time demand reduction adjusted for net

supply is negative

Page 17: MAY 02, 2012 | HOLYOKE, MA

17

Asset Real-Time Payment or Charges ExampleDemand Reduction Offer - 123

MW 5

Price $30

Minimum interruption duration 1 hour

Curtailment Initiation Price $0

Demand Reduction Offer Cost $30

Demand Reduction Offer - 456MW 2

Price $50

Minimum interruption duration 1 hour

Curtailment Initiation Price $400

Demand Reduction Offer Cost $250

Page 18: MAY 02, 2012 | HOLYOKE, MA

18

Asset Real-Time Payment or Charges Example

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

Real-Time LMP >

Offer Price

Real-Time LMP > DRTP

RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 8 8.52 N N 20 0

Demand Reduction Offer - 123MW 5

Price $30

Demand Reduction Offer - 456MW 2

Price $50

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

8 x (1 + 0.065)8.52 – 5.325 is set to 0

Page 19: MAY 02, 2012 | HOLYOKE, MA

19

Asset Real-Time Payment or Charges Example

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

Real-Time LMP >

Offer Price

Real-Time LMP > DRTP

RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 8 8.52 N N 20 0

16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8

Demand Reduction Offer - 123MW 5

Price $30

Demand Reduction Offer - 456MW 2

Price $50

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

-3 x (1 + 0.065)(-3.195 – 2.13) x 24

Page 20: MAY 02, 2012 | HOLYOKE, MA

20

Asset Real-Time Payment or Charges Example

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

Real-Time LMP >

Offer Price

Real-Time LMP > DRTP

RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 8 8.52 N N 20 0

16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8

17 123 ABC 0 0 12 10.65 Y Y 35 372.75

Demand Reduction Offer - 123MW 5

Price $30

Demand Reduction Offer - 456MW 2

Price $50

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

MIN (12, 5 x 2) x (1 +0.065) 10.65 x 35

Page 21: MAY 02, 2012 | HOLYOKE, MA

21

Asset Real-Time Payment or Charges Example

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

Real-Time LMP >

Offer Price

Real-Time LMP > DRTP

RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 8 8.52 N N 20 0

16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8

17 123 ABC 0 0 12 10.65 Y Y 35 372.75

17 456 XYZ 0 0 -1.5 0 Y Y 55 0

Demand Reduction Offer - 123MW 5

Price $30

Demand Reduction Offer - 456MW 2

Price $50

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

Set to 0 due to DA being 0 0 x 55

Page 22: MAY 02, 2012 | HOLYOKE, MA

22

Asset Real-Time Payment or Charges Example

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

Real-Time LMP >

Offer Price

Real-Time LMP > DRTP

RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 8 8.52 N N 20 0

16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8

17 123 ABC 0 0 12 10.65 Y Y 35 372.75

17 456 XYZ 0 0 -1.5 0 Y Y 55 0

Demand Reduction Offer - 123MW 5

Price $30

Demand Reduction Offer - 456MW 2

Price $50

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

Page 23: MAY 02, 2012 | HOLYOKE, MA

Demand Reductions of 5 MW and Above

23

• Assets intending to reduce ≥ 5 MW of load during a 60 minute period must contact the Control Room between 15 to 60 minutes prior to initiating the reduction

• When a request to interrupt is denied by the control room– If the asset cleared Day-Ahead, the asset will not be charged for the

difference between its Real-Time Demand Reduction Obligation and Day-Ahead Demand Reduction

– If the asset did not clear Day-Ahead, the asset will not be paid

Page 24: MAY 02, 2012 | HOLYOKE, MA

TRANSITIONAL DEMAND RESPONSEFCM Conforming Changes

Page 25: MAY 02, 2012 | HOLYOKE, MA

FCM Conforming Changes

• Energy Compensation at the Final Real-Time LMP for– Real-Time Demand Response (“RTDR”) resource with a Capacity

Supply Obligation – Real-Time Emergency Generation (“RTEG”) resource with a Capacity

Supply Obligation

• Energy Compensation at the Final Real-Time LMP during– ISO Dispatch for OP4– ISO Dispatch for an Audit

25

Page 26: MAY 02, 2012 | HOLYOKE, MA

Calculate Asset Energy Payments or Charges - FCM Event RTDR Asset that cleared Day-Ahead

2626

Real-Time Payments or Charges – FCM Event

Real-Time Payments or Charges – FCM Event

Final Real-Time LMPFinal Real-Time LMPXReal-Time demand reduction adjusted

for net supply

Real-Time demand reduction adjusted

for net supplyX(1+

Average Avoided Peak Distribution

Losses

Average Avoided Peak Distribution

Losses) Day-Ahead Demand

Reduction ObligationDay-Ahead Demand Reduction Obligation-( )

• Note– No cap on Real-Time demand reduction adjusted for net supply– Final Real-Time LMP applicable to the Load Zone the asset is located– Average Distribution Losses has been estimated to be 6.5%

Page 27: MAY 02, 2012 | HOLYOKE, MA

Calculate Asset Energy Payments or Charges - FCM Event RTDR and RTEG Assets - Real-Time only

2727

Real-Time Payments or Charges – FCM Event

Real-Time Payments or Charges – FCM Event

Final Real-Time LMPFinal Real-Time LMPXReal-Time demand reduction adjusted

for net supply

Real-Time demand reduction adjusted

for net supplyX(1+

Average Avoided Peak Distribution

Losses

Average Avoided Peak Distribution

Losses)

• Note– No cap on Real-Time demand reduction adjusted for net supply– Final Real-Time LMP applicable to the Load Zone the asset is located– Average Distribution Losses has been estimated to be 6.5%

Page 28: MAY 02, 2012 | HOLYOKE, MA

Demand Response Performance in FCM Events

• When Interrupted MW are calculated for the FCM Settlement only intervals that are part of the FCM Event in the hour are used

• When Demand Reduction MWh are calculated for the Energy Settlement all intervals in the hour are used

28

Page 29: MAY 02, 2012 | HOLYOKE, MA

Demand Response Performance in FCM Events

29

Interval FCM Event MW

16:00 N 0

16:05 N 0

16:10 N 0

16:15 N 0

16:20 N 0

16:25 N 0

16:30 N 0

16:35 N 0

16:40 N 0

16:45 Y 10

16:50 Y 10

16:55 Y 10

• Performance for FCM Settlement 10 MW

• Performance for Energy Settlement 2.5 MWh

Page 30: MAY 02, 2012 | HOLYOKE, MA

30

Asset Energy Payments or Charges - FCM Event

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

FCM Event RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 15 15.975 Y 500 5325

16 789 ABC N/A N/A -0.5 -0.5325 Y 500 -266.25

Demand Reduction Offer - 123Asset Type RTDR

MW 5

Price $30

Asset 789Asset Type RTEG

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

(15.975 – 5.325) x 500No Cap:

15 x (1 + 0.065)

Page 31: MAY 02, 2012 | HOLYOKE, MA

31

Asset Energy Payments or Charges - FCM Event

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

FCM Event RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 15 15.975 Y 500 5325

16 789 ABC N/A N/A -0.5 -0.5325 Y 500 -266.25

Demand Reduction Offer - 123Asset Type RTDR

MW 5

Price $30

Asset 789Asset Type RTEG

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

-0.5325 x 500

Page 32: MAY 02, 2012 | HOLYOKE, MA

32

Asset Energy Payments or Charges - FCM Event

HE Asset Load Zone

DA Demand Reduction Obligation

(MWh)

DA Payment

($)

Real-Time Demand

Reduction(MWh)

Real-Time Demand

Reduction Obligation

(MWh)

FCM Event RT LMP($/MWh)

RT Payment

($)

16 123 ABC 5.325 1704 15 15.975 Y 500 5325

16 789 ABC N/A N/A -0.5 -0.5325 Y 500 -266.25

Demand Reduction Offer - 123Asset Type RTDR

MW 5

Price $30

Asset 789Asset Type RTEG

Demand Reduction Threshold Price $25

Average Distribution Losses 6.5%

Page 33: MAY 02, 2012 | HOLYOKE, MA

TRANSITIONAL DEMAND RESPONSECost Allocation

Page 34: MAY 02, 2012 | HOLYOKE, MA

Cost Allocation

• Payments and charges will be allocated proportionally on an hourly basis to system-wide Real-Time Load Obligation (RTLO), excluding RTLO at external nodes and RTLO incurred by Dispatchable Asset Related Demand Postured by the ISO.

34

Monthly Demand Reduction Cost Allocation

Monthly Demand Reduction Cost Allocation

Hourly Pool PaymentHourly Pool Payment Pool Real-Time Load Obligation

Pool Real-Time Load ObligationX ( Customer Real-Time

Load ObligationCustomer Real-Time

Load Obligation / )SUM [ ]

Page 35: MAY 02, 2012 | HOLYOKE, MA

TRANSITIONAL DEMAND RESPONSEReports and Billing

Page 36: MAY 02, 2012 | HOLYOKE, MA

New Reports

• Demand Response Settlement Detail Report– SD_DRSTLDETAIL – Hourly values for Real-Time Demand Response Assets and Real-Time

Emergency Generation Assets for the specified month.– RTDR Asset Tab:

36

Page 37: MAY 02, 2012 | HOLYOKE, MA

New Reports

• Demand Response Settlement Detail Report– SD_DRSTLDETAIL – Hourly values for Real-Time Demand Response Assets and Real-Time

Emergency Generation Assets for the specified month.– RTEG Asset Tab:

37

Page 38: MAY 02, 2012 | HOLYOKE, MA

New Reports

• Demand Response Settlement Charges Report– SD_DRCHGDETAIL – Hourly cost allocation of the Demand Response settlement for the

specified month.– Hourly Tab:

38

Page 39: MAY 02, 2012 | HOLYOKE, MA

New Reports

• Demand Response Settlement Summary Report– SR_DRSTLSUM– Hourly summary of Pool and Customer payments of the Demand

Response settlement for the specified month. – Monthly summary of Pool payments and Customer payments and

charges of the Demand Response settlement for the specified month.– Hourly Tab:

39

Page 40: MAY 02, 2012 | HOLYOKE, MA

New Reports

• Demand Response Settlement Summary Report– SR_DRSTLSUM– Hourly summary of Pool and Customer payments of the Demand

Response settlement for the specified month. – Monthly summary of Pool payments and Customer payments and

charges of the Demand Response settlement for the specified month.– Monthly Tab:

40

Page 41: MAY 02, 2012 | HOLYOKE, MA

Updated Reports

• Daily Financial Position Report – BL_DAILYPOSITION – Transitional Demand Response line item added.

• FERC Electric Quarterly Reporting – Transitional Demand Response line item added.

• Load Cost Report – Transitional Demand Response column added

41

Page 42: MAY 02, 2012 | HOLYOKE, MA

Billing

• New Line Item– Transitional Demand Response

• Two Line Items on July 16, 2012 Bill– Current Demand Response Programs are allocated to Regional

Network Load which causes a month lag (May 2012)– Transitional Demand Response Cost allocated to Real-Time Load

Obligation (June 2012)

• Data Reconciliation Process (DRP) resettlement billing will not have the same overlap as the July 2012 bill– May 2012 DRP will be included in bill issued on October 15, 2012– June 2012 DRP will be included in bill issued on November 13, 2012

42

Page 43: MAY 02, 2012 | HOLYOKE, MA

43

Page 44: MAY 02, 2012 | HOLYOKE, MA

TRANSITIONAL DEMAND RESPONSEAppendix

Page 45: MAY 02, 2012 | HOLYOKE, MA

Possible Clearing Scenarios

45

*Capped = 200% Enforced