MAY 02, 2012 | HOLYOKE, MA
-
Upload
joelle-beasley -
Category
Documents
-
view
41 -
download
4
description
Transcript of MAY 02, 2012 | HOLYOKE, MA
MAY 02, 2012 | HOLYOKE, MA
Matthew GdulaSENIOR BUSINESS ANALYST
MARKET OPERATIONS SUPPORT SERVICE
Compensation and Cost Allocation
Transitional Demand Response
2
Objectives
• At the completion of this training you will know:– How payments and charges are determined– Settlement changes related to the FCM Market– Cost allocation– Report Changes
3
Governing Documents
• Market Rule 1, Appendix E– Section III.E.9
• Market Rule 1, Section 13– III.13.7.2.5.3– III.13.7.2.5.4
4
TRANSITIONAL DEMAND RESPONSEPayments and Charges
Payments and Charges
• Day-Ahead– Paid for any MW cleared
• Real-Time– Paid or Charged dependent
on Real-Time Conditions
6
Calculate Asset Day-Ahead Payment
7
Day-Ahead Demand Reduction PaymentDay-Ahead Demand Reduction Payment
Day-Ahead Demand Reduction ObligationDay-Ahead Demand Reduction Obligation Day-Ahead LMPDay-Ahead LMPX
Cleared Demand Reduction OfferCleared Demand Reduction Offer X ( 1 + Average Avoided Peak
Distribution LossesAverage Avoided Peak
Distribution Losses )
• Note– Day-Ahead LMP applicable to the Load Zone the asset is located
Average Avoided Peak Distribution Losses
• Section III.E.10– The average avoided peak transmission and distribution losses used for the
associated Capacity Commitment Period in the FCMless
The percent average avoided peak transmission system losses
• Section III.13.7.1.5.1.– The percent average avoided peak transmission and distribution losses used by
the ISO in its calculations of the Installed Capacity Requirement (ICR) for the Forward Capacity Auction immediately preceding the Forward Capacity Auction
• The ICR report states the Transmission and Distribution Gross-up as 8%
• Average avoided peak transmission system losses– Calculated to be 1.5%
• Average Avoided Peak Distribution Losses– 8% - 1.5% = 6.5%
8
9
Asset Day-Ahead Offer ExampleDemand Reduction Offer - 123
MW 5
Price $30
Minimum interruption duration 1 hour
Curtailment Initiation Price $0
Demand Reduction Offer Cost $30
Demand Reduction Offer - 456MW 2
Price $50
Minimum interruption duration 1 hour
Curtailment Initiation Price $400
Demand Reduction Offer Cost $250
Offer Price + [Curtailment Initiation Price/(Minimum interruption duration x bid amount)]:
$30 + [0/(1 x 5)] = $30
10
Asset Day-Ahead Offer ExampleDemand Reduction Offer - 123
MW 5
Price $30
Minimum interruption duration 1 hour
Curtailment Initiation Price $0
Demand Reduction Offer Cost $30
Demand Reduction Offer - 456MW 2
Price $50
Minimum interruption duration 1 hour
Curtailment Initiation Price $400
Demand Reduction Offer Cost $250
Offer Price + [Curtailment Initiation Price/(Minimum interruption duration x bid amount)]:
$50 + [400/(1 x 2)] = $250
11
Asset Day-Ahead Payment ExampleDemand Reduction Offer - 123
MW 5
Price $30
Minimum interruption duration 1 hour
Curtailment Initiation Price $0
Demand Reduction Offer Cost $30
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
Hour Asset Load Zone
DA Cleared (MWh)
DA Demand Reduction Obligation (MWh)
DA LMP ($/MWh)
DA Payment($)
16 123 ABC 5 5.325 320 1704.00
Demand Reduction Offer - 456MW 2
Price $50
Minimum interruption duration 1 hour
Curtailment Initiation Price $400
Demand Reduction Offer Cost $250
5.325 x 320$320 ≥ $30
5 x (1 + 0.065)
12
Asset Day-Ahead Payment ExampleDemand Reduction Offer - 123
MW 5
Price $30
Minimum interruption duration 1 hour
Curtailment Initiation Price $0
Demand Reduction Offer Cost $30
Hour Asset Load Zone
DA Cleared (MWh)
DA Demand Reduction Obligation (MWh)
DA LMP ($/MWh)
DA Payment($)
16 123 ABC 5 5.325 320 1704.00
16 456 XYZ 2 2.13 500 1065.00
Demand Reduction Offer - 456MW 2
Price $50
Minimum interruption duration 1 hour
Curtailment Initiation Price $400
Demand Reduction Offer Cost $250
$500 ≥ $250
2 x (1 + 0.065)
2.13 x 500
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
13
Asset Day-Ahead Payment ExampleDemand Reduction Offer - 123
MW 5
Price $30
Minimum interruption duration 1 hour
Curtailment Initiation Price $0
Demand Reduction Offer Cost $30
Hour Asset Load Zone
DA Cleared (MWh)
DA Demand Reduction Obligation (MWh)
DA LMP ($/MWh)
DA Payment($)
16 123 ABC 5 5.325 320 1704.00
16 456 XYZ 2 2.13 500 1065.00
Demand Reduction Offer - 456MW 2
Price $50
Minimum interruption duration 1 hour
Curtailment Initiation Price $400
Demand Reduction Offer Cost $250
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
Asset Real-Time Payments and Charges
• An asset is eligible for Real-Time Payments and Charges when– The asset clears in Day-Ahead, or– The hourly provisional Real-Time LMP is greater than or equal to the
Demand Reduction Offer price
14
Calculate Asset Real-Time Payments or Charges
Asset clears Day-Ahead
15
Real-Time Payments or Charges
Real-Time Payments or Charges
Real-Time Demand Reduction Obligation
Real-Time Demand Reduction Obligation Final Real-Time LMPFinal Real-Time LMPX
Real-Time demand reduction adjusted for net supply
Real-Time demand reduction adjusted for net supplyMIN ( ,
Demand Reduction Offer
Demand Reduction Offer X 2) X( 1+ Average Avoided Peak
Distribution LossesAverage Avoided Peak
Distribution Losses )
Day-Ahead Demand Reduction ObligationDay-Ahead Demand Reduction Obligation-( )
• Note– Real-Time LMP applicable to the Load Zone the asset is located
• Exception– Real-Time Demand Reduction Obligation is capped to the Day-Ahead
Demand Reduction Obligation when the provisional Real-Time LMP < Demand Response Threshold Price
16
Real-Time Payments or Charges
Real-Time Payments or Charges
Real-Time Demand Reduction Obligation
Real-Time Demand Reduction Obligation Final Real-Time LMPFinal Real-Time LMPX
Calculate Asset Real-Time Payments or Charges
Asset does not clear Day-Ahead
Real-Time demand reduction adjusted for net supply
Real-Time demand reduction adjusted for net supplyMIN ( ,
Demand Reduction Offer
Demand Reduction Offer X 2) X( 1+ Average Avoided Peak
Distribution LossesAverage Avoided Peak
Distribution Losses )
• Note– Real-Time LMP applicable to the Load Zone the asset is located
• Exception– Will not be charged if Real-Time demand reduction adjusted for net
supply is negative
17
Asset Real-Time Payment or Charges ExampleDemand Reduction Offer - 123
MW 5
Price $30
Minimum interruption duration 1 hour
Curtailment Initiation Price $0
Demand Reduction Offer Cost $30
Demand Reduction Offer - 456MW 2
Price $50
Minimum interruption duration 1 hour
Curtailment Initiation Price $400
Demand Reduction Offer Cost $250
18
Asset Real-Time Payment or Charges Example
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
Real-Time LMP >
Offer Price
Real-Time LMP > DRTP
RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 8 8.52 N N 20 0
Demand Reduction Offer - 123MW 5
Price $30
Demand Reduction Offer - 456MW 2
Price $50
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
8 x (1 + 0.065)8.52 – 5.325 is set to 0
19
Asset Real-Time Payment or Charges Example
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
Real-Time LMP >
Offer Price
Real-Time LMP > DRTP
RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 8 8.52 N N 20 0
16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8
Demand Reduction Offer - 123MW 5
Price $30
Demand Reduction Offer - 456MW 2
Price $50
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
-3 x (1 + 0.065)(-3.195 – 2.13) x 24
20
Asset Real-Time Payment or Charges Example
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
Real-Time LMP >
Offer Price
Real-Time LMP > DRTP
RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 8 8.52 N N 20 0
16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8
17 123 ABC 0 0 12 10.65 Y Y 35 372.75
Demand Reduction Offer - 123MW 5
Price $30
Demand Reduction Offer - 456MW 2
Price $50
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
MIN (12, 5 x 2) x (1 +0.065) 10.65 x 35
21
Asset Real-Time Payment or Charges Example
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
Real-Time LMP >
Offer Price
Real-Time LMP > DRTP
RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 8 8.52 N N 20 0
16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8
17 123 ABC 0 0 12 10.65 Y Y 35 372.75
17 456 XYZ 0 0 -1.5 0 Y Y 55 0
Demand Reduction Offer - 123MW 5
Price $30
Demand Reduction Offer - 456MW 2
Price $50
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
Set to 0 due to DA being 0 0 x 55
22
Asset Real-Time Payment or Charges Example
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
Real-Time LMP >
Offer Price
Real-Time LMP > DRTP
RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 8 8.52 N N 20 0
16 456 XYZ 2.13 1065 -3.00 -3.195 N N 24 -127.8
17 123 ABC 0 0 12 10.65 Y Y 35 372.75
17 456 XYZ 0 0 -1.5 0 Y Y 55 0
Demand Reduction Offer - 123MW 5
Price $30
Demand Reduction Offer - 456MW 2
Price $50
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
Demand Reductions of 5 MW and Above
23
• Assets intending to reduce ≥ 5 MW of load during a 60 minute period must contact the Control Room between 15 to 60 minutes prior to initiating the reduction
• When a request to interrupt is denied by the control room– If the asset cleared Day-Ahead, the asset will not be charged for the
difference between its Real-Time Demand Reduction Obligation and Day-Ahead Demand Reduction
– If the asset did not clear Day-Ahead, the asset will not be paid
TRANSITIONAL DEMAND RESPONSEFCM Conforming Changes
FCM Conforming Changes
• Energy Compensation at the Final Real-Time LMP for– Real-Time Demand Response (“RTDR”) resource with a Capacity
Supply Obligation – Real-Time Emergency Generation (“RTEG”) resource with a Capacity
Supply Obligation
• Energy Compensation at the Final Real-Time LMP during– ISO Dispatch for OP4– ISO Dispatch for an Audit
25
Calculate Asset Energy Payments or Charges - FCM Event RTDR Asset that cleared Day-Ahead
2626
Real-Time Payments or Charges – FCM Event
Real-Time Payments or Charges – FCM Event
Final Real-Time LMPFinal Real-Time LMPXReal-Time demand reduction adjusted
for net supply
Real-Time demand reduction adjusted
for net supplyX(1+
Average Avoided Peak Distribution
Losses
Average Avoided Peak Distribution
Losses) Day-Ahead Demand
Reduction ObligationDay-Ahead Demand Reduction Obligation-( )
• Note– No cap on Real-Time demand reduction adjusted for net supply– Final Real-Time LMP applicable to the Load Zone the asset is located– Average Distribution Losses has been estimated to be 6.5%
Calculate Asset Energy Payments or Charges - FCM Event RTDR and RTEG Assets - Real-Time only
2727
Real-Time Payments or Charges – FCM Event
Real-Time Payments or Charges – FCM Event
Final Real-Time LMPFinal Real-Time LMPXReal-Time demand reduction adjusted
for net supply
Real-Time demand reduction adjusted
for net supplyX(1+
Average Avoided Peak Distribution
Losses
Average Avoided Peak Distribution
Losses)
• Note– No cap on Real-Time demand reduction adjusted for net supply– Final Real-Time LMP applicable to the Load Zone the asset is located– Average Distribution Losses has been estimated to be 6.5%
Demand Response Performance in FCM Events
• When Interrupted MW are calculated for the FCM Settlement only intervals that are part of the FCM Event in the hour are used
• When Demand Reduction MWh are calculated for the Energy Settlement all intervals in the hour are used
28
Demand Response Performance in FCM Events
29
Interval FCM Event MW
16:00 N 0
16:05 N 0
16:10 N 0
16:15 N 0
16:20 N 0
16:25 N 0
16:30 N 0
16:35 N 0
16:40 N 0
16:45 Y 10
16:50 Y 10
16:55 Y 10
• Performance for FCM Settlement 10 MW
• Performance for Energy Settlement 2.5 MWh
30
Asset Energy Payments or Charges - FCM Event
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
FCM Event RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 15 15.975 Y 500 5325
16 789 ABC N/A N/A -0.5 -0.5325 Y 500 -266.25
Demand Reduction Offer - 123Asset Type RTDR
MW 5
Price $30
Asset 789Asset Type RTEG
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
(15.975 – 5.325) x 500No Cap:
15 x (1 + 0.065)
31
Asset Energy Payments or Charges - FCM Event
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
FCM Event RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 15 15.975 Y 500 5325
16 789 ABC N/A N/A -0.5 -0.5325 Y 500 -266.25
Demand Reduction Offer - 123Asset Type RTDR
MW 5
Price $30
Asset 789Asset Type RTEG
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
-0.5325 x 500
32
Asset Energy Payments or Charges - FCM Event
HE Asset Load Zone
DA Demand Reduction Obligation
(MWh)
DA Payment
($)
Real-Time Demand
Reduction(MWh)
Real-Time Demand
Reduction Obligation
(MWh)
FCM Event RT LMP($/MWh)
RT Payment
($)
16 123 ABC 5.325 1704 15 15.975 Y 500 5325
16 789 ABC N/A N/A -0.5 -0.5325 Y 500 -266.25
Demand Reduction Offer - 123Asset Type RTDR
MW 5
Price $30
Asset 789Asset Type RTEG
Demand Reduction Threshold Price $25
Average Distribution Losses 6.5%
TRANSITIONAL DEMAND RESPONSECost Allocation
Cost Allocation
• Payments and charges will be allocated proportionally on an hourly basis to system-wide Real-Time Load Obligation (RTLO), excluding RTLO at external nodes and RTLO incurred by Dispatchable Asset Related Demand Postured by the ISO.
34
Monthly Demand Reduction Cost Allocation
Monthly Demand Reduction Cost Allocation
Hourly Pool PaymentHourly Pool Payment Pool Real-Time Load Obligation
Pool Real-Time Load ObligationX ( Customer Real-Time
Load ObligationCustomer Real-Time
Load Obligation / )SUM [ ]
TRANSITIONAL DEMAND RESPONSEReports and Billing
New Reports
• Demand Response Settlement Detail Report– SD_DRSTLDETAIL – Hourly values for Real-Time Demand Response Assets and Real-Time
Emergency Generation Assets for the specified month.– RTDR Asset Tab:
36
New Reports
• Demand Response Settlement Detail Report– SD_DRSTLDETAIL – Hourly values for Real-Time Demand Response Assets and Real-Time
Emergency Generation Assets for the specified month.– RTEG Asset Tab:
37
New Reports
• Demand Response Settlement Charges Report– SD_DRCHGDETAIL – Hourly cost allocation of the Demand Response settlement for the
specified month.– Hourly Tab:
38
New Reports
• Demand Response Settlement Summary Report– SR_DRSTLSUM– Hourly summary of Pool and Customer payments of the Demand
Response settlement for the specified month. – Monthly summary of Pool payments and Customer payments and
charges of the Demand Response settlement for the specified month.– Hourly Tab:
39
New Reports
• Demand Response Settlement Summary Report– SR_DRSTLSUM– Hourly summary of Pool and Customer payments of the Demand
Response settlement for the specified month. – Monthly summary of Pool payments and Customer payments and
charges of the Demand Response settlement for the specified month.– Monthly Tab:
40
Updated Reports
• Daily Financial Position Report – BL_DAILYPOSITION – Transitional Demand Response line item added.
• FERC Electric Quarterly Reporting – Transitional Demand Response line item added.
• Load Cost Report – Transitional Demand Response column added
41
Billing
• New Line Item– Transitional Demand Response
• Two Line Items on July 16, 2012 Bill– Current Demand Response Programs are allocated to Regional
Network Load which causes a month lag (May 2012)– Transitional Demand Response Cost allocated to Real-Time Load
Obligation (June 2012)
• Data Reconciliation Process (DRP) resettlement billing will not have the same overlap as the July 2012 bill– May 2012 DRP will be included in bill issued on October 15, 2012– June 2012 DRP will be included in bill issued on November 13, 2012
42
43
TRANSITIONAL DEMAND RESPONSEAppendix
Possible Clearing Scenarios
45
*Capped = 200% Enforced