Materials and Inventory Cost Control

8
Materials and Inventory Cost Control Maximum Level or Maximum Limit of Stock: Learning Objective: 1. Definite and explain maximum limit or maximum level of stock. 2. How is maximum limit or maximum level calculated? Definition and Explanation: The maximum stock limit is upper level of the inventory and the quantity that must not be exceeded without specific authority from management. In other words, the maximum stock level is that quantity of material above which the stock of any item should not normally be allowed to go. This level is fixed after taking into account such factors as: capital, rate of consumption of materials, storage space available, insurance cost, risk of deterioration and obsolescence and economic order quantity. Formula: MAXIMUM LEVEL OR MAXIMUM LIMIT can be calculated by the help of following formula: [Maximum limit or level = Re-order level or ordering point – Minimum usage × Minimum re-order period + Economic order quantity]

description

Materials and Inventory Cost Control,minimum level, maximum level,EOQ level

Transcript of Materials and Inventory Cost Control

Page 1: Materials and Inventory Cost Control

Materials and Inventory Cost

Control

Maximum Level or Maximum Limit of

Stock:

Learning Objective:

1. Definite and explain maximum limit or maximum level of stock. 2. How is maximum limit or maximum level calculated?

Definition and Explanation:

The maximum stock limit is upper level of the inventory and the quantity that must not be exceeded without specific authority from management. In other words, the maximum stock level is that quantity of material above which the stock of any item should not normally be allowed to go. This level is fixed after taking into account such factors as: capital, rate of consumption of materials, storage space available, insurance cost, risk of deterioration and obsolescence and economic order quantity.

Formula:

MAXIMUM LEVEL OR MAXIMUM LIMIT can be calculated by the help of following formula:

[Maximum limit or level = Re-order level or ordering point – Minimum usage × Minimum re-order period + Economic order quantity]

Page 2: Materials and Inventory Cost Control

Example:

Normal usage 100 units per

day

Maximum usage 130 units per

day

Minimum usage 70 units per

day

Re-order period 25 to 30 days

Economic order quantity 5,000 units

Calculate maximum limit or level.

In order to calculate maximum limit of stock we must calculate re-order point or re-order level first.

Ordering point or re-order level = Maximum daily or weekly or monthly usage × Maximum re-order

= 130 × 30

= 39,000 units

Calculation:

Maximum limit or level = Re-order level or ordering point – Minimum quantity used in re-order period usage + Economic order quantity

= 3900 – (70 × 25) + 5,000

= 7150 units

Page 3: Materials and Inventory Cost Control

Minimum Limit or Minimum Level of

Stock:

Learning Objective:

1. Definite and explain minimum limit or minimum level of stock. 2. How is minimum limit or minimum level calculated?

Definition and Explanation:

The minimum level or minimum stock is that level of stock below which stock

should not be allowed to fall. In case of any item falling below this level, there is danger of stopping of production and, therefore, the management should give top priority to the acquisition of new supplies.

Formula:

Minimum level or minimum limit can be calculated by the following formula:

[ MINIMUM LIMIT OR LEVEL = RE-ORDER LEVEL OR ORDERING POINT – AVERAGE OR NORMAL USAGE × NORMAL RE-ORDER PERIOD ]

OR THE FORMULA CAN BE WRITTEN AS:

[ MINIMUM LIMIT OR LEVEL = RE-ORDER LEVEL OR ORDERING POINT – AVERAGE USAGE FOR NORMAL PERIOD ]

Example:

Normal usage 100 units per day

Maximum usage 130 units per day

Minimum usage 70 units per day

Re-order period 25 to 30 days

Calculate: minimum limit or level

To calculate minimum limit of materials we must calculate re-order point or re-order level first.

Calculation:

Ordering point or re-order level = Maximum daily or weekly or monthly usage × Maximum re-order

= 130 × 30

= 3,900 units

Page 4: Materials and Inventory Cost Control

Minimum limit or level = Re-order level or ordering point – Average or normal usage × Normal re-order period

= 3900 – (100 × 27.5*)

1150 units

*(25 + 30 ) / 2

(By Sanjit Patel)

Page 5: Materials and Inventory Cost Control

Economic Order Quantity (EOQ):

Learning Objective:

1. Definite and explain economic order quantity (EOQ). 2. How is economic order quantity (EOQ) calculated?

1. Definition of EOQ

2. Formula

3. Example:

Definition and Explanation:

Economic order quantity (EOQ) is that size of the order which gives maximum economy in purchasing any material and ultimately contributes towards maintaining the materials at the optimum level and at the minimum cost.

In other words, the economic order quantity (EOQ) is the amount of inventory to be ordered at one time for purposes of minimizing annual inventory cost.

The quantity to order at a given time must be determined by balancing two factors: (1) the cost of possessing or carrying materials and (2) the cost of acquiring or ordering materials. Purchasing larger quantities may decrease the unit cost of acquisition, but this saving may not be more than offset by the cost of carrying materials in stock for a longer period of time.

The carrying cost of inventory may include:

• Interest on investment of working capital • Property tax and insurance

• Storage cost, handling cost • Deterioration and shrinkage of stocks

• Obsolescence of stocks.

Formula of Economic Order Quantity (EOQ):

The different formulas have been developed for the calculation of economic order quantity (EOQ). The following formula is usually used for the calculation of EOQ.

Page 6: Materials and Inventory Cost Control

• A = Demand for the year

• Cp = Cost to place a single order

• Ch = Cost to hold one unit inventory for a year

• * = ×

Example:

Pam runs a mail-order business for gym equipment. Annual demand for the TricoFlexers is 16,000. The annual holding cost per unit is $2.50 and the cost to place an order is $50.

Calculate economic order quantity (EOQ)

Calculation:

Underlying Assumptions of Economic Order Quantity:

1. The ordering cost is constant. 2. The rate of demand is constant 3. The lead time is fixed 4. The purchase price of the item is constant i.e no discount is available

5. The replenishment is made instantaneously, the whole batch is delivered at once.

Page 7: Materials and Inventory Cost Control

Re-order Level or Ordering Point or

Ordering Level:

1. Definition and explanation of re-order point 2. Formula of re-order level or ordering point 3. Examples

Definition and explanation:

This is that level of materials at which a new order for supply of materials is to

be placed. In other words, at this level a purchase requisition is made out. This level is fixed somewhere between maximum and minimum levels. Order points are based on usage during time necessary to requisition order, and receive materials, plus an allowance for protection against stock out.

The order point is reached when inventory on hand and quantities due in are equal to the lead time usage quantity plus the safety stock quantity.

Formula of Re-order Level or Ordering Point:

The following two formulas are used for the calculation of reorder level or point.

[ ORDERING POINT OR RE-ORDER LEVEL = MAXIMUM DAILY OR WEEKLY OR MONTHLY USAGE × LEAD TIME ]

The above formula is used when usage and lead time are known with certainty; therefore, no safety stock is provided. When safety stock is provided then the following formula will be applicable:

[ ORDERING POINT OR RE-ORDER LEVEL = MAXIMUM DAILY OR WEEKLY OR MONTHLY USAGE × LEAD TIME + SAFETY STOCK ]

Examples:

Example 1:

Minimum daily requirement 800 units

Time required to receive emergency supplies 4 days

Average daily requirement 700 units

Minimum daily requirement 600 units

Time required for refresh supplies One month (30 days)

Calculate ordering point or re-order level

Page 8: Materials and Inventory Cost Control

Calculation:

Ordering point = Ordering point or re-order level = Maximum daily or weekly or monthly usage × Lead time

= 800 × 30

= 24,000 units

Example 2:

Tow types of materials are used as follows:

Minimum usage

20 units per week each

Maximum usage 40 units per week each

Normal usage 60 units per week each

Re-order period or Lead time

Material A:

Material B

3 to 5 weeks

2 to 4 weeks

Calculate re order point for two types of materials

Calculation:

Ordering point or re-order level = Maximum daily or weekly or monthly usage × Maximum re-order period

A: 60 × 5 = 300 units

B: 60 × 4 = 240 units

Thanks For Reading,If Any Quiery Mail Me at

[email protected]