Major Power Grid Blackouts in North America and Europe

download Major Power Grid Blackouts in North America and Europe

of 32

Transcript of Major Power Grid Blackouts in North America and Europe

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    1/32

    1539pk

    Copyright P. Kundur

    This material should not be used without the author's consent

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    2/32

    1539pkMPB- 1

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    3/32

    1539pkMPB- 2

    ! Approximately 50 million peoplein 8 states in theUS and 2 Canadian provinces affected

    " 63 GW of load interrupted (11% of total loadsupplied by Eastern North AmericanInterconnected System)

    ! During this disturbance, over 400 transmission linesand 531 generatingunits at 261 power plants tripped

    ! For details refer to: "Final Report of Aug 14, 2003Blackout in the US and Canada: Causes and

    Recommendations", US-Canada Power System

    Outage Task Force, April 5, 2004. www.NERC.com

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    4/32

    1539pkMPB- 3

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    5/32

    1539pkMPB- 4

    ! Electricity demand high but not unusually high! Power transfer levels high, but within established

    limits and previous operating conditions

    ! Planned outages of generating units in the affectedarea: Cook 2, Davis Bess plant, East Lake 4, Sammis

    3 and Monroe 1

    ! Reactive power supply problems in the regions ofIndiana and Ohio prior to noon

    ! Operators took actions to boost voltages" voltages within limits

    ! System operating in compliance with NERCoperating policies prior to 15:05 Eastern Daylight

    Time

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    6/32

    1539pkMPB- 5

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    7/32

    1539pkMPB- 6

    ! The Midwest ISO (MISO) state estimator and real-time contingency analysis (RTCA) software not

    functioning properly from 12:15 to 16:04

    " prevented MISO from performing proper "earlywarning" assessments as the events wereunfolding

    ! At the First Energy (FE) Control Center, a number ofcomputer software problems occurred on the

    Energy Management System (EMS) starting at 14:14

    " contributed to inadequate situation awarenessat FE until 15:45

    ! The first significant event was the outage of EastLake generating unit #5 in the FE system at 13:31:34

    " producing high reactive power output" voltage regulator tripped to manual on

    overexcitation

    " unit tripped when operator tried to restore AVRcont'd

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    8/32

    1539pkMPB- 7

    ONTARIO

    2

    1

    ONTARIO

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    9/32

    1539pkMPB- 8

    ! Initial line trips in Ohio, all due to tree contact:" Chamberlin-Harding 345 kV line at 15:05:41" Hanna-Juniper 345 kV line at 15:32:03" Star-South Canton 345 kV line at 15:41:35

    ! Due to EMS failures at FE and MISO control centers,no proper actions (such as load shedding) taken

    ! Critical event leading to widespread cascadingoutages in Ohio and beyond was tripping of

    Sammis-Star 345 kV line at 16:05:57

    " Zone 3 relay operation due to low voltage andhigh power flow! Load shedding in northeast Ohio at this stage could

    have prevented cascading outages that following

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    10/32

    1539pkMPB- 9

    (3:05:41)(3:32:03)

    Star- S. Canton (3:41:35)

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    11/32

    1539pkMPB- 10

    Sammis-Star(4:05:57.5)

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    12/32

    1539pkMPB- 11

    ! Tripping of many additional 345 kV lines in Ohio andMichigan by Zone 3 (or Zone 2 set similar to Zone 3)

    relays

    ! Tripping of several generators in Ohio and Michigan! At 16:10:38, due to cascading loss of major lines in

    Ohio and Michigan, power transfer from Canada

    (Ontario) to the US on the Michigan border shifted

    " power started flowing counter clockwise fromPennsylvania through New York and Ontario

    into Michigan

    " 3700 MW of reverse power flow to serve loadsin Michigan and Ohio, which were severedfrom rest of interconnected system except

    Ontario

    ! Voltage collapsed due to extremely heavy loadingson transmission lines

    ! Cascading outages of several hundred lines andgenerators leading to blackout of the region

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    13/32

    1539pkMPB- 12

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    14/32

    1539pkMPB- 13

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    15/32

    1539pkMPB- 14

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    16/32

    1539pkMPB- 15

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    17/32

    1539pkMPB- 16

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    18/32

    1539pkMPB- 17

    Areas Affected by the Blackout

    Service maintained

    in some area

    Some Local Load

    Interrupted

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    19/32

    1539pkMPB- 18

    1. Inadequate understanding of the power systemrequirements:

    # First Energy (FE) failed to conduct rigorouslong-term planning studies and sufficient

    voltage stability analyses of Ohio control area

    # FE used operational criteria that did not reflectactual system behaviour and needs

    # ECAR (East Central Area Reliability Council)did not conduct an independent review or

    analysis of FE's voltage criteria and operatingneeds

    # Some NERC planning standards weresufficiently ambiguous that FE could interpret

    them in a way that resulted in inadequate

    reliability for system operation

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    20/32

    1539pkMPB- 19

    2. Inadequate level of situation awareness:

    # FE failed to ensure security of its system aftersignificant unforeseen contingencies

    #FE lacked procedures to ensure that itsoperators were continually aware of the

    functional state of their critical monitoring

    tools

    # FE did not have adequate backup tools forsystem monitoring

    3. Inadequate level of vegetation management (treetrimming)

    # FE failed to adequately manage tree growthinto transmission rights-of-way

    $ resulted in the outage of three 345 kVlines and one 138 kV line

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    21/32

    1539pkMPB- 20

    4. Inadequate level of support from the ReliabilityCoordinator

    # due to failure of state estimator, MISO did notbecome aware of FE's system problems early

    enough

    $ did not provide assistance to FE# MISO and PJM (Regional Transmission

    operator) did not have in place an adequate

    level of procedures and guidelines for dealing

    with security limit violations due to a

    contingency near their common boundary

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    22/32

    1539pkMPB- 21

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    23/32

    1539pkMPB- 22

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    24/32

    1539pkMPB- 23

    ! Pre-disturbance conditions:" system moderately loaded" facilities out of services for maintenance:

    $400 kV lines in South Sweden$4 nuclear units in South Sweden$3 HVDC links to Germany and Poland

    ! The first contingency was loss of a 1200 MW nuclear unitin South Sweden at 12:30 due to problems with steam

    valves

    " increase of power transfer from the north" system security still acceptable

    ! Five minutes later (at 12:35) a disconnector damagecaused a double busbar fault at a location 300 km away

    from the first contingency

    " resulted in loss of a number of lines in thesouthwestern grid and two 900 MW nuclear units

    ! At 12:37, voltage collapse in the eastern grid sectionsouth of Stockholm area

    " isolated southern Sweden and eastern Denmarksystem from northern and central grid

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    25/32

    1539pkMPB- 24

    At 12.30: Loss of a 1200 MWNuclear Unit

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    26/32

    1539pkMPB- 25

    At 12.35: Double bus-bar fault leading to-Loss of two 900 MW Nuclear Units-Disrupture of the south-western grid

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    27/32

    1539pkMPB- 26

    Voltage Collapse

    IsolatedSubsystem

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    28/32

    1539pkMPB- 27

    The blacked-out area after the grid separation at 12.37

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    29/32

    1539pkMPB- 28

    ! The isolated system had enough generation to coveronly about 30% of its demand

    " voltage and frequency collapsed within a fewseconds, blacking out the area

    ! Impact of the blackout:" loss of 4700 MW load in south Sweden

    $1.6 million people affected$City of Malmo and regional airports and rail

    transportation without power

    " loss of 1850 MW in eastern Denmark$2.4 million people affected$City of Copenhagen, airport and rail

    transportation without power

    ! Result of an (n-3) contingency, well beyond "designcontingencies"

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    30/32

    1539pkMPB- 29

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    31/32

    1539pkMPB- 30

    ! Predisturbance conditions (Sunday, 3:00 am):" total load in Italy was 27,700 MW, with 3638 MW

    pump load

    " total import from rest of Europe was 6651 MW! Sequence of events:

    " a tree flashover caused tripping of a major tie-linebetween Italy and Switzerland (Mettlen-Lavorgo

    380 kV line) at 03:01:22

    " Sychro-check relay prevented automatic and manualreclosure of line due to the large angle (42) across

    the breaker" resulted in an overload on a parallel path" attempts to reduce the overload by Swiss

    transmission operators by network change was not

    successful

    " at 03:21 import by Italy was reduced by 300 MW butwas not sufficient to mitigate the overload of a

    second 380 kV line (Sils-Soazza), which tripped at03:25:22 due to sag and tree contact

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    32/32

    " the cascading trend continued and the powerdeficit in Italy was such that the ties to France,

    Austria and Slovania were tripped

    " the outages left the Italian system with a powershortage of 6400 MW

    " the frequency decay could not be controlledadequately by under-frequency load shedding

    " over the course of several minutes, the entireItalian System collapsed at 3:28:00

    ! The blackout affected about 60 million people" total energy not delivered 180 GWh" worst blackout in the history of Italy" power was restored after 3 hours in the

    northern area and during the same day for

    most of Italy