MAHARASHTRA FISHERIES DEVELOPMENT...

123
MAHARASHTRA FISHERIES DEVELOPMENT CORPORATION, LTD, MUMBAI Modernization of Sassoon Dock TENDER DOCUMENT TENDER FOR CONSTRUCTION OF AUCTION HALL AND ALLIED INFRASTRUCTURE WORKS VOL. I / V - CONTRACT INFORMATION

Transcript of MAHARASHTRA FISHERIES DEVELOPMENT...

Page 1: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHERIES DEVELOPMENT

CORPORATION, LTD, MUMBAI

Modernization of Sassoon Dock

TENDER DOCUMENT

TENDER FOR CONSTRUCTION OF AUCTION HALL AND

ALLIED INFRASTRUCTURE WORKS

VOL. I / V - CONTRACT INFORMATION

Page 2: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHERIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd; Pune.

Volume-I Contract Information RF

INDEX

VOLUME-I – CONTRACT INFORMATION

� TENDER CALL NOTICE (TCN)

� INSTRUCTIONS TO BIDDERS (ITB)

� GENERAL CONDITIONS OF CONTRACT (GCC)

� SPECIAL CONDITIONS OF CONTRACT (SCC)

� ANNEXURES

� APPENDIX TO TENDER

� CHECKLIST

Page 3: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

TENDER CALL NOTICE (TCN)

To,

---------------------------------- ---------------------------------- ----------------------------------

Sub: Construction of Auction Hall & other allied Buildings and infrastructure facilities

Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017

Dear Sir(s)

Maharashtra Fisheries Development Corporation (MFDC) has been mandated by Government of Maharashtra for renovation and modernization of Sassoon Dock Mumbai. MFDC therefore invites the tenders from eligible bidders for: Construction of Civil and Structural works (including design wherever required) for proposed Auction Hall and allied buildings with necessary infra-structure facilities:

Your proposal duly filled in as per tender Document enclosed herewith should

reach to:

-------------

On or before--------------------by 15.00 hrs.

While quoting please mention the code referred above.

Please confirm your participation in above.

Construction of Auction Hall and Allied infrastructure works

Unison Project Management Pvt .Ltd Page: 1/1 Volume-I Contract Information–Tender Call Notice RF

Page 4: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 1/2 Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Instructions to Bidders RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

INSTRUCTIONS TO BIDDERS

1.0 INTRODUCTION

1.1 Broad Scope of Work

1.2 Key Dates

2.0 PROPOSAL REQUIREMENTS

2.1 General

2.2 Instructions for Filling Bids

2.3 Pricing of Bid

3.0 BID DOCUMENTS

3.1 Contents of Bid Documents

4.0 INFORMATION REQUIRED

4.1 Part I (Technical bid)

4.2 Part II (The Price Bid)

INDEX

5.0 AMENDMENT OF BID DOCUMENTS

6.0 FORMAT AND SIGNING OF BID

7.0 SEALING, MARKING & SUBMISSION OF BID (PART I AND PART II)

8.0 DEADLINE FOR SUBMISSION OF BIDS

9.0 LATE BIDS

10.0 MODIFICATION AND WITHDRAWAL OF BIDS

Page 5: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 2/2 Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Instructions to Bidders RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

11.0 EVALUATION AND COMPARISON OF BIDS

11.1 General

11.2 Evaluation Criteria

11.3 Correction of Errors

11.4 Clarification of Tenders

11.5 Process to be Confidential

11.6 Award Criteria

12.0 B BID OPENING

12.3 Part II (Price id)

12.4 Acceptance of Offer / Notification of Award

13.0 PERFORMANCE SECURITY

14.0 SIGNING OF THE CONTRACT

Page 6: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 1/15 Volume-I Contract Information – Instructions to Bidders RF

INSTRUCTIONS TO BIDDERS

1.0 INTRODUCTION

With the increasing imposition of international EU standards, cleanliness and hygiene of fish landing & handling places becomes an essence and pre-requisite to meet the quality standards of seafood. Unhygienic condition results in reduction in export potential, sometime may be total rejection. This will have negative impact on this labour intensive industry. Sassoon Dock is one of the busiest fishing harbours in the country and has won a major position on the marine export market, with 25% to 30 % of the total fish landings sold for export. At present the capacity of the fishing dock is too inadequate hence results in congestion, overcrowding and inconvenience to both fishing boat operators, auctioneers and harbour authorities giving rise to fish hygiene and poor harbour services. On this background, Government of Maharashtra has mandated “Maharashtra Fisheries Development Corporation (MFDC) a company incorporated under the Companies Act, 1956 to renovate and modernize the existing facilities at Sassoon Dock with the following objectives: 1) To improve the fish hygienic conditions for better health and enhancing export

potential. 2) De-congestion of the Traffic 3) Making it Stakeholders friendly by creating basic infrastructure facilities and

working environment. 4) Creating tourist potential. MFDC charged with the responsibilities of development, operation and maintenance of the Sassoon Dock, hereby invites the tenders on item rate basis, in the prescribed proforma from eligible bidders, for the construction of Civil & Structural works for auction hall and allied infrastructure as mentioned below:

1.1 Scope of Work

The scope of the work under this contract shall include, but not limited to construction of Auction Hall and other allied buildings and supporting infrastructure works.

The proposed auction halls shall be provided with RCC bored cast-in situ pile foundation with M.S. casing while other allied building shall be with open foundation system..

The scope includes providing all materials (unless otherwise specified), labours, temporary and enabling works, contractor’s equipments, superintendence and co-ordination of nominated-sub-contractors (appointed if any) for the completion of above works, as required in accordance to Contract Provisions and good engineering practice.

Page 7: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 2/15 Volume-I Contract Information – Instructions to Bidders RF

The work shall be carried out as per the FIT FOR CONSTRUCTION drawings and revisions thereof, issued to contractors from time to time. The work actually carried out shall be measured and paid as per the Contract Provisions as elaborated hereunder.

All bids are to be completed and submitted to the Employer in accordance with these instructions to bidders (ITB).

1.2 Key Dates & EMD

The key Dates and other pertinent information is given below

a) Cost of Bid Documents (non refundable) Rs.10, 000/- INR

(Payment shall be on line through e-procurement portal in the form of e- payments, using any of the following payment modes i.e. Credit Card, Direct Debit, National Electronic Fund Transfer (NEFT) or RTGS as per the procedure mentioned hereafter.)

b) Period of contract including mobilization & Monsoon 18 months

c) EMD (in Indian Rupees) Rs. 20 Lakhs.

d) Pre bid meeting 11.30 hrs on 24/11/2017

e) Tender download & Preparation up to 17.00 hrs on 07/12/2017

f) Last date and time of submission of bid. 17.00 hrs on 12/12/2017 __________

f) Date & Time of opening of Technical bid. 11.00 hrs on 13/12/2017

g) Technical presentation by short listed Bidders. To be decided later

1.3 Procedure for Submission of e-procurement Tender:

1. The bidders shall participate through the website:

https://maharashtra.etenders.in

2. The BID DOCUMENT shall be signed only by Proprietor if it is a Proprietary

concern. In support of which an affidavit of ownership, a copy of certificate of

registration has to be submitted.

3. One of the Partners or a person authorized by the partners shall sign the BID

DOCUMENT if it is a partnership firm. Copy of the Partnership deed shall be

submitted under signature and seal of the authorized person.

4. The Chief Executive of the company or a person authorized shall sign the

tender, if it is a public or private limited company. In support of which necessary

authorization of CEO letter with seal and signature, shall be submitted along

with the copy of Certificate of Registration of the company.

5. Corrigendum / modifications / corrections (if any) will be published in the e-

Procurement portal only.

1.4 Payment Process:

All the payments e.g. tender document cost/ EMD etc shall only be paid online through e-procurement portal in the form of e- payments, using any of the following payment modes i.e. Credit Card, Direct Debit, National Electronic Fund Transfer (NEFT) or RTGS The detailed procedure for paying ‘Processing Fees” is laid

Page 8: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 3/15 Volume-I Contract Information – Instructions to Bidders RF

down below. (The procedure given below is a general concept, tenderer have to proceed according to the system available in e- tendering process)

Credit Card Payment Method:

To pay the registration fee through your credit card, click on the “Credit Card

(Online Payment)” option. If you choose to pay the fees later click on “Close”

button, Click Pay after verifying details on the screen that appears.

Click on “Pay” button to proceed with payment process. Click “Back” if you wish to.

Choose a different payment method, Click on “OK” button on the payment method.

Confirmation window is displayed. Choose your card type (VISA, master card).

Enter your credit card details. Card Details should be completely filled.

Click on “PAY NOW” button to effect the payment. Your card details are verified by

the payment gateway service and you will receive confirmation of payment debited

to your card account if the card is valid. If the card is not valid you will receive

alter about it and system will wait for you to correct any errors in the card details

provided by you.

A successful transaction message will be displayed.

Direct Debit Method:

Click on “Direct Debit Using Internet Banking (Online Payment) option to pay from

your bank account through Internet Banking facility.

Click on “Pay” to proceed or “Back” to change the payment method on the Payment

details screen.

Click on “OK” on the confirmation window to effect the payment. Click on “Cancel”

and then on “Back” to change the payment method.

NEFT/ RTGS Payment Procedure:

If a bidder chooses to make payment of processing fees using Reserve Bank of

India’s (RBI) National Electronic Fund Transfer (NEFT) system, the supplier will

need to log into e-Procurement system, access the application for which bid is being

created and then select the NEFT option under the payment section and print the

Challan shown in that section. The printed challan will have the unique bid

reference number, account details of Government of Maharashtra and the amount to

be remitted. The bidder has to submit the printed challan to its bank-branch (NEFT-

enabled) and request for an account-to account transfer, wherein the money will get

transferred from the tenderer’ bank account to GOM’s bank account.

The bidder should ensure the NEFT transfer instructions are executed and the funds

are wired to the Government of Maharashtra’s principal account before the last date

for bid submission and preferably, 24 hours before the last date for bid submission.

If the bidder’s bank transfers / wire the money after the last date for BID

DOCUMENT submission, the bidders BID DOCUMENT will be liable for rejection.

Upon executing the transfer, the bidder’s bank will provide a reference number

generated by NEFT software as confirmation of transfer, which has to be entered by

Page 9: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 4/15 Volume-I Contract Information – Instructions to Bidders RF

tenderer in the payment section of its bid as payment confirmation before the bid is

submitted (i.e.) as a pre-requisite for bid submission. Also the account number from

which the fund was transferred has to be entered in the e-Procurement system as

part of its bid. The bidders BID DOCUMENT will be evaluated only on confirmation

of receipt of the payment in the Government of Maharashtra central pooling

Account.

For details on e-Payment services, refer to e-procurement portal for more

details on the process.

Help Desk: 020- 253 155 55 or e-mail: [email protected]

(Timings: 10.00 am to 9.00 pm).

2.0 PROPOSAL REQUIREMENTS

2.1 General

2.1.1 The Bid Documents issued to the Bidders are non-transferable.

2.1.2 Bid Documents shall remain the property of the EMPLOYER 2.1.3 EMPLOYER will not be responsible for any costs or expenses incurred by the bidder in

connection with preparation and delivery of this bid or for any other expenses incurred in connection with such bidding.

2.1.4 The work to be done is described in the Bid document (and in particular in the Technical Specifications, Bill of Quantities and Drawings) and in general includes, but is not limited to supply of all equipments, craft, materials including consumables necessary to carry out the works. Quantities, drawings and specifications given in the Bid Document are for the sole purpose of indicating to bidders the order of magnitude of work and are not in any way guaranteed to remain unchanged. Time is of the essence of the Contract and the work shall be completed in all respects within the period stated in Appendix to Tender.

2.1.5 Bidders are encouraged to visit the site of the work, review the drawings,

and acquaint themselves of all site conditions prior to submission of their bid. Not visiting the site will in no way relieve the successful bidder of any of the obligations in performing the work in accordance with this Bid Document within the quoted price.

The bidder and any of his authorized personnel or agents will be granted permission by the employer to enter upon its premises and lands for the purpose of such inspection but only upon the express condition that the bidder, his personnel or agents, will release and Indemnify the employer and it’s personnel from and against all liability in respect thereof and will be responsible for personal injury (whether title or otherwise), loss of or damage to property, any other loss, damage, costs and expenses however caused, which but for the exercise of such permission would have arisen.

It is proposed to hold a pre-bid meeting with all the bidders or its official representative(s) at the place and on the date and time as indicated in Appendix to Tender

Page 10: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 5/15 Volume-I Contract Information – Instructions to Bidders RF

The bidders who need clarifications on any specific issue shall inform the EMPLOYER in writing 24 hours before the pre-bid meeting. No queries /clarifications s ha l l be entertained after the pre-bid meeting.

2.1.6 If the bidders find discrepancies in or omission from the drawings, specifications, or other documents, or have any doubts as to the meaning or intent of any part thereof, they shall at once inform the EMPLOYER who may send a written instruction o r explanation to all bidders.

No oral communications shall be made by any bidder in this regard. Every request for an interpretation shall be in writing addressed and forwarded to the EMPLOYER at the address mentioned in Appendix to Tender and shall be four days before the pre-bid meeting and in any case not beyond pre-bid meeting.

2.1.7 In formulating their bid, bidders shall have full regard to the contents of the Bid Documents since all bids will be deemed to have been made after taking into account all the provisions thereof. The agreement as finally executed will include the Employer’s Bid Documents and the Bidder’s offer as finally accepted by the EMPLOYER together with Addenda, bid clarification and all correspondences exchanged between EMPLOYER and the bidder, if any.

2.1.8 The EMPLOYER will not entertain any correspondence or queries on the status of the offers received against this Bid. Should t h e EMPLOYER find it necessary to seek any clarifications, technical o r otherwise the EMPLOYER will duly contact the bidder concerned.

2.1.9 Canvassing in any form by the bidder or by any other agency acting on behalf of the bidder after submission of the bid may disqualify the said bidder. The Employer’s decision in this regard shall be final and binding on the bidder.

2.1.10 The EMPLOYER may reject, accept or prefer any bid without assigning any reason whatsoever. The EMPLOYER also reserves to himself the right to accept any bid in part or parts only with such conditions as he may prescribe.

2.1.11 The successful bidder shall furnish the required Performance Security in the form of Bank Guarantee from a Nationalized / Scheduled Bank (except Co-operative Banks) acceptable to the EMPLOYER on the Performa enclosed at Annexure -3 to the bid for the amount indicated in the Appendix to Tender.

2.1.12 EMPLOYER will not be liable for any financial obligation in connection with the work until such time the EMPLOYER has communicated to the successful bidder in writing his decision to entrust the Work (covered by the bid document issued to him).

2.1.13 Fax/Telegraphic/ Electronic transmitted offers will not be considered. Bidders

should prepare their bid themselves. Bids submitted by agents will not be recognized.

2.1.14 Bids received after the due date and time and any change in quotation after the

specified date will not be considered.

Page 11: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 6/15 Volume-I Contract Information – Instructions to Bidders RF

2.1.15 In case of an unscheduled holiday on the prescribed closing/opening day of the bid, the next working day will be treated as the scheduled prescribed day of closing/opening of the bid.

2.1.16 All bidders shall provide in their Technical and Commercial Bid a Statement that

the Bidder is not associated, nor has been associated in the past, directly or indirectly with the consultant or any other entity that has prepared the design, specifications and other documents for this project.

A firm that has been engaged by the Employer to provide consultancy services for the preparation of the design, specifications and other documents for the Project or for the supervision of the works and any of its affiliates shall not be eligible to bid.

2.2 Instructions for Filling Bids

2.2.1 The bids can only be submitted in the name of the bidder in whose name the bid documents are issued by the EMPLOYER

2.2.2 The bid and any annotations or accompanying documentation shall be in

English language only and in metric system.

2.2.3 Bidders shall sign their proposal with the exact name of the firm to whom the bid document has been issued. The bid shall be duly signed and sealed by an authorized executive officer of the bidder's organisation in all the pages.

2.2.4 Bidders shall clearly indicate their legal constitution and the person signing the bid shall state his capacity and also the source of his ability to bind the bidder. The power of attorney or authorization or any other document constituting adequate proof of the ability of the signatory to bind the bidder shall be annexed to the bid.

2.2.5 If the space in the bid form or in the Appendices thereto is insufficient, additional pages shall be separately added. These pages shall be consecutively numbered and shall also be signed by the Bidder.

2.2.6 Bidders should indicate at the time of quoting against this bid their full postal and e-mail addresses and Fax and Telephone numbers /Mobile number.

2.2.7 Bidder shall set their quotations in firm figures and without qualification. Each figure stated should also be repeated in words and in the event of a discrepancy between the amounts stated in figures and words, the amount quoted in words shall be deemed to be the correct amount. Conditional bids are liable for rejection.

2.2.8 Bidders shall submit along with their offer Earnest Money Deposit / Bid security (EMD) of the amount mentioned in the Appendix to Tender.

The EMD which shall be in the form of Bank Guarantee / demand draft / Banker’s Cheque for the said amount shall specifically bind the Bidder to keep his offer valid for acceptance and to abide by all the conditions of the EMPLOYER. The Employer shall have an unqualified option under the said EMD to claim the amount there under in the event the bidder withdraw his bid before expiry of bid validity or refuse to accept the work.

Page 12: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 7/15 Volume-I Contract Information – Instructions to Bidders RF

EMD in the form of Bank guarantee shall be from any Nationalised / Scheduled Bank (Except Co-operative Banks) which shall be as acceptable to the employer, as per the Proforma in Annexure -2.

The EMD shall be valid for 90 days beyond the validity of the bid. The EMD of unsuccessful bidders shall be returned on issue of the Letter of Award LOA to the successful b idder or 120 days whichever is earlier. The successful bidders EMD will be returned upon the bidder furnishing performance security and entering into contract agreement.

2.3 Pricing of Bid

2.3.1 General

The Bid shall be on Item-Rate basis. The offer shall include planning, mobilization and demobilization of suitable plant, equipment and machinery for construction of Auction Hall and allied works, including all items/materials, labour, tools, fabrication, transportation, insurance, taxes, duties, consumables, overhead, profit etc. necessary for execution of contract as described in the Bid Document.

Tenderers shall fill in the rate for each item of the Bill of Quantities in the "rate" column in figures. For each item, the quantity given in the "quantity" column shall be multiplied by the rate and the result entered in the "total" column. In any case of discrepancy between the rate and amount, the rate will be taken as correct and the amount adjusted accordingly. Where in the "unit" column the letters "L.S." are stated, the lump sum amount shall be entered in the "total" column by the Tenderer. Tender prices shall be submitted for those items in the Bill of Quantities where a quantity is indicated in the "quantity" column, or letters "L.S." are indicated in the "unit" column. Any item against which no rate or lump sum is quoted will not be paid for by the Employer when the work described therein is executed, and it shall be deemed to be covered by other rates and lump sums in the Bill of Quantities. All pages of the bill of quantities shall be initialed.

2.3.2 Currencies of Quotation The Bidder shall indicate the prices in Indian Rupees. The Bidder shall not quote in

any currency other than Indian Rupees.

2.3.3 Validity

The bid shall be valid for acceptance for a period of 90 days from the last date of submission. The Bid valid for a shorter period shall be rejected by the employer as non- responsive. In exceptional circumstances, prior to expiry of the original time limit, the Employer may request that the bidders may extend the period of validity for as specified additional period. The request and the bidders’ responses shall be made in writing. A bidder may refuse the request without forfeiting his bid security/ EMD. A bidder agreeing to the request will not be permitted to modify his bid and also shall submit an extension for EMD, if it is in the form of Bank Guarantee.

2.3.4 Duties and Taxes

Indian Custom duties, if any, levied upon the work, equipments etc. are to be borne by the bidders and to be incorporated in the item rates and this will not be separately paid for. The Contractor shall bear all Taxes both corporate and personal, including but not limited to taxes on income levied on the Contractor or on

Page 13: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 8/15 Volume-I Contract Information – Instructions to Bidders RF

their affiliated companies on account of payments received by them from the EMPLOYER for the works done under the Contract.

All duties, taxes and other levies payable by the Contractor under the Contract, or for any other cause shall be as applicable on base date except of GST. The incidence of GST shall be mentioned separately..

It shall be the responsibility of the Contractor to submit to the concerned Indian Statutory Authorities the returns and all connected documents required for this purpose. The Contractor shall also provide the EMPLOYER such information as they may require in regard to the Contractor's income and expenditure for this purpose.

3.0 BID DOCUMENTS The tender shall be uploaded in two parts namely:

a) Technical Envelope and

b) Financial Envelope

The tender shall be uploaded in following manner

STAGE I – Payments against EMD in the form of DD/BG/Online as applicable.

STAGE II – Technical and commercial Envolaps will be as per clause no.4.1 & 4.2.

3.1 Contents of Bid Documents

The bid documents, for the purpose of bidding shall include the following, together with any amendments issued, in accordance with clause 5.0 of these Instructions to Bidders.

Volume-1: Contract information

• Tender Call Notice

• Instructions to Bidders

• General Conditions of Contract

• Special Conditions of Contract

• All Annexure as indicated in Bid Document

Volume-2: Technical Specification

• Technical Specifications

Volume-3: Tender Drawings

• Drawings

Volume-4: Preamble & Bill of Quantity

• Preamble

• Bill of Quantities

• Tender form

• Appendix to Tender

Volume - 5: Soil Investigation Report

Page 14: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 9/15 Volume-I Contract Information – Instructions to Bidders RF

3.2 The bidder is expected to examine carefully all instructions, conditions, forms, terms, specifications and drawings in the Bid Documents. Failure to comply with the requirements of Bid submission will be at the Bidder’s own risk. Bids, which are not substantially responsive to the requirements of the Bid Documents, shall be liable for rejection.

3.3 Although the details presented in the Bid Documents have been compiled with all reasonable care, it is the Bidder’s responsibility to ensure that the information provided is adequate, clearly understood and that it includes all the documents listed above.

4.0 INFORMATION REQUIRED

The information required under specific parts of the submission is as under:

4.1 Part I (Technical bid)

4.1.1 Detailed Approach and methodology for the execution of the work comprising of following

a) Project scope understanding

b) Site appreciation

c) Organization chart furnishing the names of key personnel, their deployment schedule and their Bio data, bidder intends to deploy for the Project as required under Annexure 7

d) List of major equipment proposed to be deployed for this work giving the

schedule of deployment and the details such as capacity of equipment, trade name, year of built, etc as stated in Annexure 6.

e) Resource based activity linked project schedule in the form of CPM/PERT network and financial progress in the form of “S” Curve. The Bidder s h a l l indicate t h e project key-dates/milestones for all activities.

f) The Bidder in his bid shall indicate how he would execute the work within

the time specified by submitting a description of equipment and work method to be employed and the limiting weather condition for the proposed equipments. The shall also include a description of major procedures or any special technique to be employed in setting up the Works. (If necessary the Contractor may have to mobilise additional resources at his own cost for proper and timely completion of the work.)

g) Indicative Safety, Health and Environment Plan (SHE plan) as applicable for the

works. h) Indicative Project Quality Assurance Plan as applicable for the works.

4.1.2.1 Letter of Authority as per Proforma enclosed as Annexure 1 to the bid. 4.1.2.2 Form of Bank Gurantee for Tender Security/ Bid Security as Annexure 2 to the bid.

Page 15: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 10/15 Volume-I Contract Information – Instructions to Bidders RF

4.1.2.3 Annexure 5 to the bid giving the information related to Annual turnover, duly verified by the Chartered Accountant, copies of acknowledgment issued by Income Tax department Govt. of India of the return filed for last three assessment year.

4.1.2.4 Annexure 6 List of major equipment proposed

4.1.2.5 Annexure 7 Organization Chart 4.1.3 Any other information required in terms of this Bid Document. 4.1.4 Annexure 9

4.2 Part II (The Price Bid)

The price bid shall contain only duly completed document in Volume - 4 without any conditions whatsoever.

5.0 AMENDMENT OF BID DOCUMENTS

5.1 At any time prior to the deadline for submission of the Bid, the Employer may, for any reason, whether at his own initiative or in response to a clarification requested by a prospective Bidder, modify the Bid Documents by amendments.

5.2 The amendment in writing will be sent to all prospective Bidders who have been issued the Bid Documents, in writing or by fax or e-mail and will be binding upon them. Prospective bidders should promptly acknowledge receipt thereof by fax or e-mail to the Employer.

5.3 In order to afford prospective bidders reasonable time in which to take the amendment in to account in preparing their Bids, the Employer may, at its discretion, extend the deadline for the submission of the Bids.

5.4 All documents issued for the purpose of bidding and amendments issued in accordance with this clause shall be deemed to be incorporated in the bid.

6.0 FORMAT AND SIGNING OF BID

6.1 The Bid shall be filled-in and signed only by the firm in whose name the Bid documents have been issued.

7.0 SEALING, MARKING & SUBMISSION OF BID (PART I AND PART II)

7.1 The Bid shall be submitted in two parts viz;

Part I – Technical Bid and

Part II - Price Bid.

7.2 Part I of the Bid shall not refer directly or indirectly to the quoted prices. Part II of the

Bid shall not have any counter/commercial conditions whatsoever.

7.3 Part I – Technical Bid shall mention:

Page 16: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 11/15 Volume-I Contract Information – Instructions to Bidders RF

a) Proof of Payment of EMD as specified

b) Information required as per Sub Clause 4.1 of these instructions to Bidders.

c) Tender volumes as issued (Volumes 1, 2, 3, 4(un-priced) & 5) and common set of deviations/amendments issued by employer if any, all duly signed and stamped on each page as a token of acceptance.

7.4 Part II - Price Bid shall contain Volume 4 duly filled in containing:

a) Tender Form with Appendix to Tender

b) Preamble and Price Bill of Quantities

7.5 All recipients for the purpose of submitting a Bid shall treat the contents of the

documents as private and confidential. 8.0 DEADLINE FOR SUBMISSION OF BIDS

8.1 Bids must be received by the Employer not later than the time and date indicated in Appendix to Tender.

8.2 The Employer may, at its discretion, extend the deadline for submission of Bids through the issuance of an amendment in accordance with Sub Clause 5.0 in which case all rights and obligations of the Employer and the Bidders previously subject to the original deadline shall thereafter be subject to the new deadline as extended.

9.0 LATE BIDS

Any Bid received by the Employer after the prescribed deadline as per clause 8.1 or extended as per Clause 8.2 for submission shall be liable for rejection.

10.0 MODIFICATION AND WITHDRAWAL OF BIDS

10.1 Bidders may modify or withdraw their bids by giving notice in writing before the last date and the time as prescribed for the submission of the bids.

10.2 Bidder’s modification or withdrawal is permitted before the last date and time of

submission, In e-Procurement Portal, tenderer has the option of modifying /

withdrawing the Bid by digitally signing to withdraw/cancel bid before the bid

submission time / date.

10.3 No Bid can be modified after the last date and time as prescribed for the

submission of the Bids.

10.4 Withdrawal or modification of a Bid between the last date prescribed for the submission of the bids and the expiration of the original period of bid validity or an extension thereof by the Employer may result in the forfeiture of the EMD.

11.0 ELIGIBILITY, EVALUATION AND COMPARISON OF BIDS

Page 17: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 12/15 Volume-I Contract Information – Instructions to Bidders RF

11.1 Minimum Eligibility Criteria

1. Average Annual financial turnover during the last 3 years, ending 31st March

2017, should not be less than 15 Crores.

2. Experience of having successfully completed similar works during last 7 years

ending 31 march 2017, as under:

a) Three similar works completed costing not less than 6 Crores OR

b) Two similar works completed costing not less than 7.5 Crores OR

c) One similar work completed costing not less than 12 Crores.

3. The company should be minimum 5 years in continuous operations on the date of submission. (Copy of certification of incorporation or supporting documents to be attached)

4. Joint Ventures/ Consortium of not more than two parties are allowed. While evaluation of the bid by JV the aggregate experience and turn over shall be considered. While evaluation of Consortium offers, the turn-over of lead partner shall be considered. The experience of other consortium shall only be considered.

Similar Work means the construction of industrial sheds, residential, commercial and public buildings with all allied infrastructure works like water supply, road works, plumbing and electrical works.

11.2 Evaluation Criteria

11.2.1 The Evaluation Committee of Employer will examine the Bids to determine whether they are complete, whether the requisite Earnest Money Deposit has been furnished, whether the Documents have been properly signed, and whether the Bids are generally in order.

The Bids received and opened will be evaluated by Evaluation Committee of Employer, based on the following criteria: Technical Marking

SN Particulars Marks Allowed Max Marks

1 Company Structure Proprietary Firms Partnership Firms Joint Ventures*** Private Limited Public Limited.

1 2 3 4 5

5

2 Establishment of Company or firm. 7 years 7 to 10 years 10 to 15 years 15 to 20 years Above 20 years

1 2 3 4 5

5

3 Average Annual Turnover of company or firm during last 3 years ending on

20

Page 18: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 13/15 Volume-I Contract Information – Instructions to Bidders RF

31 march 17 INR 15 Crores INR 15 to 25 Crores INR 25 to 50 Crores INR 50 Crores and above

05 10 15 20

Page 19: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 14/15 Volume-I Contract Information – Instructions to Bidders RF

4 Ownership of Plant and Machinery. Piling Rigs- (2 nos. ) /Piling Machines – 4 (nos.) Crane of capacity not less than 25 Mt.- 1 no RMC Plant of 30 min. Cum/hr. – 1 no

1 2 2

05

5 Jobs of similar nature Min marks for qualifying criteria 5 additional marks for each of completed additional job of similar nature of value INR 6.0 Cr or more. Max 3 jobs

20

35

6 Approach & Methodology Scope understanding Site Appreciation SHE Plan Project quality plan Qualification of Project Manager**

05 05 05 05 10

30

** Evaluation of Project Manager CV BE + 10 years experience / DCE + 15 years experience : 4 marks Experience as Project Manager of similar assignments : 6 marks 2marks/Project Maximum 3 Projects

*** Evaluation of Joint Ventures/ Consortium offers While evaluation of the bid by JV the aggregate experience and turn over shall be considered. While evaluation of Consortium offers, the turn-over of lead partner shall be considered. The experience of other consortium shall only be considered.

The bidder securing more than 70 marks on evaluation of technical bids shall only be considered for opening the financial bid. The technical Evaluation committee will be as follows: a) Managing Director, MFDC, Mumbai – Chairperson b) Commissioner Of Fisheries , Mumbai – Member c) Superintending Engineer, BPT, Mumbai – Member d) Deputy Secretary, ADF Department – Member e) Unison Project Management Pvt. Ltd.- Member

The financial bids of the qualified bidder shall only be opened and unconditional lowest bid shall be considered for award of the work subject to fulfillment of all contract conditions.

11.2.2 The bids submitted in any other form than specified shall be treated as defective, invalid and rejected. Only detailed complete offers received prior to the closing time and date of the Bids will be considered as valid. Bids not complying with any of the Instructions contained herein may not be considered.

11.2.3 After the receipt of bids, if required, the EMPLOYER/ENGINEER may decide to inspect the facilities available with the bidder to ensure suitability and satisfactory working conditions of the equipment listed to be used by the bidder for the work. The bidder shall provide necessary assistance to the visiting team.

EMPLOYER reserves the right to open price part of the bid (Part II) of only such bidders whose technical aspects of the bid (Part I ) are acceptable and complete.

Page 20: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 15/15 Volume-I Contract Information – Instructions to Bidders RF

The Employer’s decision in this regard shall be final and binding on the bidder. The EMPLOYER may not open price part of the offer (Part II) of the bidders who do not satisfy the technical marking criteria stated above.

11.3 Correction of Errors

11.3.1 Bids will be checked by the Evaluation Committee of Employer for any arithmetical errors. Any errors will be corrected by the Employers as follows:

a) Where there is a discrepancy between the rates in figures and words, the rate in words will govern.

b) Where there is a discrepancy between the multiplication of unit rates and the quantity shown against any item the unit rate as quoted will govern.

c)

11.3.2 The amount stated in the Bid will be adjusted by the Evaluation Committee of Employer in accordance with the above procedure for the correction of errors and, with the concurrence of the Bidder, shall be considered as binding upon the Bidder. If the Bidder does not accept the corrected amount, the Bid will be rejected and the EMD may be forfeited.

11.4 Clarification of Tenders

11.4.1 To assist in the examination, evaluation and comparison of Bids, the Evaluation Committee of Employer may ask Bidders individually for clarification of their Bids, including breakdowns of prices. Requests for clarification and the response shall be in writing or by fax or e-mail.

11.5 Process to be Confidential

11.5.1 Information relating to the examination, clarification, evaluation, and comparison of Bids and recommendations concerning the award of Contract shall be uploaded on the e-portal at appropriate time.

11.5.2 Any effort by a Bidder to influence the Evaluation Committee of Employer in the process of examination, clarification, evaluation and comparison of the Bids or in decisions concerning the award of Contract may result in the summary rejection of the Bidder’s Bid including forfeiting of his EMD.

11.6 Award Criteria

11.6.1 Subject to Sub Clause 11.6.2 the Employer will award the Contract to the Bidder whose Bid has been determined to be eligible and responsive to the Bid documents and in the best interest of project.

11.6.2 Notwithstanding Sub Clause 11.6.1 the Employer reserves the right to accept or

reject any Bid and to annul the Bidding Process and reject all bids, at any time prior to Award of Contract, without thereby incurring any liability to the affected Bidder or Bidders or any obligation to inform the affected bidder or Bidders on the grounds for the Employer’s action.

11.6.3 In the event of annul of bidding process the EMD shall be returned to the respective bidder.

Page 21: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 16/15 Volume-I Contract Information – Instructions to Bidders RF

12.0 BID OPENING

12.1 The Technical Bid shall be opened on the date and time as indicated in Appendix to Tender.

12.2 At the time of Technical Bid opening the EMPLOYER will permit one authorized representative of each Bidder to be present provided such representative presents to the EMPLOYER at that time, a letter duly signed by the Bidder authorizing him to be present on behalf of the Bidder.

12.3 Part II (Price Bid)

Price Bids of Technically qualified bidders shall be opened subsequently and the prospective bidder(s) shall be called for negotiation

12.4 Acceptance of Offer / Notification of Award

Prior to expiration of the prescribed per i od or extended period of bid validity, the employer will notify the successful bidder by fax and confirm in writing by post that his bid has been accepted. The notification of award will constitute the formation of the contract.

13.0 PERFORMANCE SECURITY

The successful bidder, to whom the letter of acceptance is issued shall obtain and submit a Performance Security for proper performance, in the amount, currencies and mode stated in the Appendix to Tender and clause No.4.2 of G.C.C. Failure of the successful bidder to lodge the required Performance Security shall constitute sufficient grounds for the annulment of the award and forfeiture of the bid security/ EMD.

14.0 SIGNING OF THE CONTRACT

The successful Bidder shall be required to execute a Formal Contract in accordance with the requirement of the EMPLOYER within the time limit as specified in Appendix to the tender or within such extended time as may be permitted by the EMPLOYER in this behalf. This agreement shall be in the Proforma indicated at Annexure 4 of the bid. The stamp duty/ registration fees on the contract agreement shall be borne by the contractor.

Page 22: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 1/6

Volume-I Contract Information – General Conditions of Contract RF

GENERAL CONDITIONS OF CONTRACT

INDEX

1.0 GENERAL PROVISIONS

1.1 Definitions

1.2 Interpretation

1.3 Communications

1.4 Law and Language

1.5 Priority of Documents

1.6 Contract Agreement

1.7 Assignment

1.8 Care and Supply of Documents

1.9 Delayed Drawings or Instructions

1.10 Employer's Use of Contractor’s Documents

1.11 Contractor’s use of Employer's Documents

1.12 Confidential Details

1.13 Compliance with Laws

1.14 Joint and Several Liability

1.15 Details to be Confidential

2.0 THE EMPLOYER

2.1 Permission of Access to the Site

2.2 Permits, Licenses or Approvals

2.4 Employer's Claims

3.0 ENGINEER

3.1 Engineer’s Duties and Authority

3.2 Delegation by the Engineer

3.3 Instructions of the Engineer

3.4 Determinations

3.5 Management Meetings

4.0 THE CONTRACTOR

4.1 Contractor’s General Obligations

4.2 Performance Security

4.3 Contractor’s Representative

4.4 Sub-Contractors

4.5 Assignment of Benefit of Sub-Contract

4.6 Co-operation

Page 23: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 2/6

Volume-I Contract Information – General Conditions of Contract RF

4.7 Setting Out

4.8 Safety Procedures

4.10 Site Data

4.11 Sufficiency of the Accepted Contract amount

4.12 Unforeseeable Physical Conditions

4.15 Access Route

4.16 Transport of Goods

4.17 Contractor’s equipment

4.18 Protection of the Environment

4.19 Site Facilities

4.20 Progress Reports

4.21 Security of the Site

4.22 Contractor’s Operations on Site

4.23 Fossils

5.0 STAFF AND LABOUR

5.1 Engagement of Staff and Labour

5.2 Rates of Wages and Conditions of Labour

5.3 Persons in the Service of Employer/Engineer

5.4 Labour Laws

5.5 Working Hours

5.6 Facilities for Staff and Labour

5.7 Health and Safety

5.8 Contractor’s Superintendence

5.9 Contractor’s Personnel

5.10 Records of Contractor’s Personnel and Equipment

5.11 Disorderly Conduct

6.0 PLANT, MATERIALS AND WORKMANSHIP

6.1 Manner of Execution

6.2 Samples

6.3 Inspection

6.4 Testing

6.5 Rejection

6.6 Remedial Work

6.8 Royalties

7.0 COMMENCEMENT, DELAYS AND SUSPENSION

7.1 Commencement of Work

7.2 Time of Completion, Compensation for Delay due to Contractor’s Negligence

(Liquidated damages)

Page 24: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 3/6

Volume-I Contract Information – General Conditions of Contract RF

7.3 Programme

7.4 Extension of Time for Completion

7.5 Delays Caused by Authorities

7.6 Rate of Progress

7.7 Contractor’s Responsibility

7.8 Suspension of Work

7.9 Consequences of Suspension

7.10 Payment for Plant and Materials in event of Suspension

7.11 Prolonged Suspension

7.12 Resumption of Work

8.0 TESTS ON COMPLETION

8.1 Contractor’s Obligations

8.2 Delayed Tests

8.3 Retesting

8.4 Failure to Pass Tests on Completion

9.0 EMPLOYER'S TAKING OVER

9.1 Taking over of the Works and Sections

9.2 Taking Over of Parts of the Works

9.3 Interference with Tests on Completion

9.4 Surfaces Requiring Reinstatement

10.0 DEFECTS LIABILITY

10.1 Completion of Outstanding Work and Remedying Defects

10.2 Cost of Remedying Defects

10.3 Extension of Defects Liability Period

10.4 Failure to Remedy Defects

10.5 Removal of Defective Work

10.6 Further Tests

10.7 Right of Access

10.8 Contractor to Search

10.9 Performance Certificate

10.10 Unfulfilled Obligations

10.11 Clearance of Site

11.0 MEASUREMENT AND EVALUATION

11.1 Works to be Measured

11.2 Method of Measurement

11.3 Evaluation

11.4 Omissions

Page 25: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 4/6

Volume-I Contract Information – General Conditions of Contract RF

12.0 VARIATIONS AND ADJUSTMENTS

12.1 Right to Vary

12.2 Valuation Procedure

12.3 Payment in Applicable Currencies

12.4 Provisional Sums

12.5 Adjustments for Changes in Legislation

13.0 CONTRACT PRICE AND PAYMENT

13.1 The Contract Price

13.2 Advance payment

13.3 Escalation / Price Variation – No escalation will be allowed.

13.4 Application for Interim Payment Certificates

13.5 Schedule of Payments

13.6 Issue of Interim Payment Certificates

13.7 Payment

13.8 Delayed Payment

13.9 Retention Money

13.10 Statement at Completion

13.11 Application for Final Payment Certificate

13.12 Discharge

13.13 Issue of Final Payment Certificate

13.14 Cessation of Employer's Liability

13.15 Currencies of Payment

14.0 TERMINATION BY EMPLOYER

14.1 Notice to Correct

14.2 Termination by Employer

14.3 Valuation at Date of Termination

14.4 Payment after Termination

14.5 Employer’s Entitlement to Termination

15.0 SUSPENSION AND TERMINATION BY CONTRACTOR

15.1 Contractor’s Entitlement to Suspend Work

15.2 Termination by Contractor

15.3 Cessation of Work and Removal of Contractor’s Equipment

15.4 Payment on Termination

16.0 RISK AND RESPONSIBILITY

16.1 Indemnities

16.2 Contractor’s Care of the Works

Page 26: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 5/6

Volume-I Contract Information – General Conditions of Contract RF

16.3 Employer's Risks

16.4 Consequences of Employer's Risks

16.5 Intellectual and Industrial Property Rights

16.6 Limitation of Liability

17.0 INSURANCE

17.1 Insurance

17.2 Scope of cover

17.3 Insurances by the Contractor

17.4 Responsibility for amount not recovered

17.5 Indemnity by Contractor

17.6 Cross Liabilities

17.7 Evidence and Terms of Insurances

17.8 Adequacy of Insurances

17.9 Remedy on Contractor’s Failure to Insure

17.10 Compliance with Policy Conditions

18.0 FORCE MAJEURE

18.1 Definition of Force Majeure

18.2 Notice of Force Majeure

18.3 Duty to Minimize Delay

18.4 Consequences of Force Majeure

18.5 Force Majeure Affecting Sub-Contractor

18.6 Optional Termination, Payment and Release

18.7 Releases from Performance under the Law

19.0 CLAIM, DISPUTES AND ARBITRATION

19.1 Contractor’s Claims

19.2 Amicable Settlement

19.3 Arbitration

20.0 USE OF EXPLOSIVES

21.0 PROPERTY IN EXCAVATED MATERIALS

22.0 DRAWINGS & DESIGNS

23.0 FILLING IN HOLES AND TRENCHES

24.0 CONTRACT SUPERSEDES PREVIOUS DOCUMENTS

25.0 BRIBES AND COMMISSION

26.0 SERVICE TAX

Page 27: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 6/6

Volume-I Contract Information – General Conditions of Contract RF

27.0 SECURITY CLEARANCE 28.0 LIFE SAVING APPLIANCES AND FIRST AID EQUIPMENT

29.0 DRAWINGS AND PHOTOGRAPHS OF THE WORKS

30.0 TAXATION

30.1 General

30.2 Customs Duty

31.0 NOISE AND DISTURBANCE

32.0 SECURITY REQUIREMENTS 33.0 REMOVAL OF CRAFT OR PLANT THAT HAS SUNK

34.0 CONTRACTOR’S TEMPORARY MOORINGS

34.1 Anchoring

34.2 Midstream Transshipments

34.3 Submission of List of Plant and Equipment

35.0 POLLUTION

36.0 DIVING WORK

37.0 ADVERTISING

Page 28: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 1/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

GENERAL CONDITIONS OF CONTRACT 1.0 GENERAL PROVISIONS 1.1 Definitions

In the Conditions of Contract ("these Conditions"), which include Special Conditions and these General Conditions, the following words and expressions shall have the meanings stated. Words indicating persons or parties include corporations and other legal entities, except where the context requires otherwise.

1.1.1.1 The Contract 1.1.1.1 "Contract" means the Contract Agreement, the Letter of Acceptance, the Letter of

Tender, these Conditions, the Specifications, the Drawings, the Schedules, and the further documents (if any) which are listed in the Contract Agreement or in the Letter of Acceptance.

1.1.1.2 “Contract Agreement" means the Contract agreement (if any) referred to in Sub-Clause

1.6 [Contract Agreement]. 1.1.1.3 "Letter of Acceptance," means the letter of formal acceptance signed by the Employer, of

The Tender submitted by the tenderer including any annexed documents. 1.1.1.4 "Letter of Tender" means the document entitled letter of tender, which was completed by The

Contractor and includes the signed offer to the Employer for the Works. 1.1.1.5 "Specification" means the document entitled specification, (as included in the Contract),

and any additions and modifications to the specification in accordance with the Contract. Such document specifies the works.

1.1.1.6 "Drawings" means the drawings of the Works, as included in the Contract, and

any additional and modified drawings issued by (or on behalf of) the Employer in accordance with the Contract.

1.1.1.7 "Schedules" means the document(s) entitled schedules, completed by the Contractor

and submitted with the Letter of Tender, as included in the Contract. Such document may include the Bill of Quantities, data, lists, and schedules of rates and/or prices.

1.1.1.8 "Tender" means the Letter of Tender and all other documents, which the Contractor

submitted with the Letter of Tender, as included in the Contract. The Word "Tender" is synonymous with the word `Bid’.

1.1.1.9 "Appendix to Tender" means the completed pages entitled appendix to tender, which are

appended, to form part of the Letter of Tender.

1.1.1.10 "Bill of Quantities" and “Day work schedule” means the documents so named (if any)

which are comprised in the Schedules.

Page 29: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 2/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

1.1.2 Parties and Persons 1.1.2.1 "Party" means the Employer or the Contractor, as the context requires. 1.1.2.2 "Employer" means the person named as Employer in the Appendix to Tender and the

legal successors in title to this person. 1.1.2.3 "Contractor" means the person(s) named as Contractor in the Letter of Tender accepted

by the Employer and the legal successors in title to this person(s). 1.1.2.4 "Engineer" means the Consultants appointed by the Employer to act as the Engineer

for the purposes of the Contract and named in the Appendix to Tender or any other person nominated by the Employer from time to time to act as an Engineer.

1.1.2.5 "Contractor’s Representative" means the person named by the Contractor in the Contract or appointed from time to time by the Contractor under Sub- Clause 4.3 [Contractor’s Representative], who acts on behalf of the Contractor.

1.1.2.6 "Employer's Personnel" means the Engineer, the assistants referred to in Sub- Clause 3.2 [Delegation by the Engineer] and all other staff, labour and other Employees of the Engineer and of t h e E m p l o y e r ; and any other personnel notified to the Contractor, by the Employer or the Engineer, as Employer's Personnel.

1.1.2.7 "Contractor’s Personnel" means the Contractor’s Representative and all personnel whom the Contractor utilizes on Site, who may include the staff, labour and other employees of the Contractor and of each Sub-Contractor; and any other personnel assisting the Contractor in the execution of the works.

1.1.2.8 "Sub-Contractor" means any person named in the Contract as a Sub-contractor, or any person appointed as a Sub-contractor and/or the Nominated Sub-Contractor, for a part of the Works; and the legal successors in title to each of these persons.

1.1.3 Dates, Tests, Periods and Completion 1.1.3.1 "Base Date" means the 1st October 2017 if applicable anywhere in Contract. 1.1.3.2 "Commencement Date “means the date notified under Sub-Clause 7.1 Commencement Of Works]. 1.1.3.3 "Time for Completion" means the time for completing the Works or a Section (as the

case may be) under Sub-Clause 7.2 [Time for Completion], as stated in the Appendix to Tender (with any extension under Sub-Clause 7.4 [Extension of Time for Completion]), calculated from the Commencement Date.

1.1.3.4 "Tests on Completion" means the tests which are specified in the Contract or agreed by both Parties or instructed as a Variation, and which are carried out under Clause 8 [Tests on Completion] before the Works or a Section (as the case may be) are taken over by the Employer.

1.1.3.5 "Taking-Over Certificate" means a certificate issued under Clause 9 [Employer's Taking Over]. 1.1.3.6 "Tests after Completion" means the tests (if any), which are specified in the Contract,

and which are carried out in accordance with the provisions of the Particular Conditions after the Works or a Section (as the case may be) are taken over by the Employer.

1.1.3.7 "Defects Liability Period" means the period for notifying defects in the Works or a Section (as the case may be) under Sub-Clause 10.1[Completion of Outstanding Work and Remedying Defects], as stated in the Appendix to Tender (with any extension under Sub-Clause 10.3 [Extension of Defects Liability Period]), calculated from the date on which the Works or Section is completed as certified under Sub-Clause 9.1 [Taking Over of the Works and Sections].

1.1.3.8 "Performance Certificate" means the certificate issued under Sub-Clause 10.9 [Performance Certificate]. 1.1.3.9 "Day" means a calendar day and "Year" means 365 days.

Page 30: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 3/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

1.1.4 Money and Payments

1.1.4.1 "Accepted Contract Amount" means the amount accepted in the Letter of Acceptance for the execution and completion of the Works and the remedying of any defects.

1.4.2 "Contract Price" means the price defined in Sub-Clause 13.1 [The Contract Price], and includes adjustments in accordance with the Contract. 1.1.4.3 "Cost" means all expenditure reasonably incurred (or to be incurred) by the

Contractor, whether on or off the Site, including overhead and similar charges, but does not include profit.

1.1.4.4 "Final Payment Certificate" means the payment certificate issued under Sub-Clause 13.13 [Issue of Final Payment Certificate].

1.1.4.5 "Final Statement" means the statement defined in Sub-Clause 13.11 [Application for Final Payment Certificate].

1.1.4.6 "Currency" means Indian Rupees in which all of the Contract Price is payable. 1.1.4.7 "Interim Payment Certificate" means a payment certificate issued under Clause

13 [Contract Price and Payment], other than the Final Payment Certificate. 1.1.4.8 "Payment Certificate" means a payment certificate issued under Clause 13 [Contract

Price and Payment]. 1.1.4.9 "Provisional Sum" means a sum (if any), which is specified in the Contract as a

provisional sum, for the execution of any part of the Works or for the supply of Plant, Materials or services under Sub-Clause 12.4 [Provisional Sums].

1.1.4.10 "Retention Money" means the accumulated retention moneys, which the Employer retains under Sub-Clause 13.4 [Application for Interim Payment Certificates] and pays under Sub- Clause 13.9 [Retention Money].

1.1.4.11 "Statement" means a statement submitted by the Contractor as part of an application for payment, under Clause 13 [Contract Price and Payment].

1.1.5 Works and Goods 1.1.5.1 "Contractor’s Equipment" means all apparatus, machinery, vehicles and other things

required for the execution and completion of the works and the remedying of any defects. However, Contractor’s Equipment excludes Temporary Works, Employer's Equipment (if any), Plant, Materials and any other things intended to form or forming part of the Permanent Works.

1.1.5.2 "Goods" means Contractor’s Equipment, Materials, Plant and Temporary Works, or any of them as appropriate.

1.1.5.3 "Materials" means things of all kinds (other than Plant) intended to form or forming part of the Permanent Works, including the supply-only materials (if any) to be supplied by the Contractor under the Contract.

1.1.5.4 "Permanent Works" means the permanent works to be executed by the Contractor under The Contract in accordance with the scope of work mentioned in Instructions to Bidders. 1.1.5.5 "Plant" means the apparatus, machinery and vehicles intended to form or forming part of The Permanent Works. 1.1.5.6 "Section" means a part of the Works specified in the Appendix to Tender as a Section

(if any). 1.1.5.7 "Temporary Works" means all temporary works of every kind (other than Contractor’s

Equipment) required on Site for the execution and completion of the Permanent Works and the remedying of any defects.

1.1.5.8 "Works" mean the Permanent Works and the Temporary Works, or either of them as appropriate in accordance with the scope of work mentioned in Instructions to Bidders.

Page 31: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 4/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

1.1.5.9 “Mile Stone” means the specified event t o be completed as mandatory requirement in

the project as stated in Appendix to the Tender. 1.1.6 Other Definitions 1.1.6.1 "Contractor’s Documents" means the calculations, computer programs and other software,

drawings, manuals, models and other documents of a technical nature (if any) supplied by the Contractor under the Contract.

1.1.6.2 "Country" means the country India in which the Site (or most of it) is located, where The Permanent Works are to be executed. 1.1.6.3 "Employer's Equipment" means the apparatus, machinery and vehicles (if any)

made available by the Employer for the use of the Contractor in the execution of the Works, as stated in the specification.

1.1.6.4 "Force Majeure" is defined in Clause 18 [Force Majeure]. 1.1.6.5 "Laws" means all national (or state) legislation, statutes, ordinances and other laws, and

regulations and by-laws of any legally constituted public authority. 1.1.6.6 "Performance Security" means the security (or securities, if any) under Sub-Clause 4.2

[Performance Security]. 1.6.7 "Site" means the places where the Permanent Works are to be executed and to which Plant and materials are to be delivered, and any other places as may be specified in the Contract as forming part of the Site. 1.1.6.8 "Unforeseeable" means not reasonably foreseeable by an experienced Contractor by the

date for submission of the Tender. 1.1.6.9 "Variation" means any change to the Works, which is instructed or approved as a

variation under Clause 12 [Variations and Adjustments].

1.2 Interpretation

In the Contract, except where the context requires otherwise:

(a) Words indicating one gender include all genders;

(b) Words indicating the singular also include the plural and words indicating the plural also include the singular;

(c) Provisions including the word "agree", "agreed" or "agreement" require the agreement to be recorded in writing, and

(d) "Written” or "in wr i t i n g " means hand-written, type-written, printed or electronically

made, and resulting in a permanent record.

The marginal words and other headings shall not be taken into consideration in the interpretation of these Conditions.

1.3 Communications

Wherever these Conditions provide for the giving or issuing of approvals, certificates, consents, determinations, notices and requests, these communications shall be: (a) In writing and delivered by hand (against receipt), sent by mail or courier, or

transmitted using any of the agreed systems of electronic transmission as stated in the Appendix to Tender; and

(b) Delivered, sent or transmitted to the address for the recipient's communications as

stated in the Appendix to Tender. However:

Page 32: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 5/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

(i) If the recipient gives notice of another address, communications shall thereafter be

delivered accordingly; and

(ii) If the recipient has not stated otherwise when requesting an approval or consent, it may be sent to the address from which the request was issued.

Approvals, certificates, consents and determinations shall not be unreasonably withheld or delayed. When a certificate is issued to a Party, the certifier shall send a copy to the other Party. When a notice is issued to a Party, by the other Party or the Engineer, a copy shall be sent to the Engineer or the other Party, as the case may be.

1.4 Law and Language

The Contract shall be governed by the laws of India, if there are versions of any part of the Contract, which are written in more than one language, the version, which is in the ruling language stated in the Appendix to tender, shall prevail.

The language for communications shall be that stated in the Appendix to Tender. If no language is stated there, the language for communications shall be the language in which the Contract (or most of it) is written.

1.5 Priority of Documents

The documents forming the Contract are to be taken as mutually explanatory of one another. For the purposes of interpretation, the priority of the documents shall be in accordance with the following sequence:

(a) The Contract Agreement (if completed),

(b) The Letter of Acceptance

(c) Bid Clarifications issued in writing by the Employer

(d) The Form of Tender and Appendix to the Tender along with Instructions to Bidder

(e) The Special Conditions of Contract

(f) The General Conditions of Contract

(g) The Technical Specifications

(h) The Tender Drawings

(i) The Priced Bill of Quantities,

(j) Schedules and any other document forming part of Contract

If any ambiguity or discrepancy is found in the documents, the Engineer shall issue any necessary clarification or instruction.

Page 33: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 6/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

1.6 Contract Agreement

The Parties shall enter into a Contract Agreement within the time stated in Appendix to the tender, unless it is agreed otherwise. The Contract Agreement shall be in the format annexed to the bid (Annexure 4). The costs of stamp duties and similar charges (if any) imposed by law in connection with entry into the Contract Agreement shall be borne by the Contractor.

1.7 Assignment

The Contractor shall not assign the Contract or any part thereof or any benefit or interest therein or there under (otherwise than by a charge in favour of the Contractor’s Banker of any money due to or to become due under this Contract) without the prior Written consent of the Employer.

1.8 Care and Supply of Documents

The Specification and Drawings shall be in the custody and care of the Employer. Unless otherwise stated in the Contract, two copies of the Contract and of each subsequent Drawing shall be supplied to the Contractor, who may make or request further copies at the cost of the Contractor.

Each of the Contractor’s Documents shall be in the custody and care of the Contractor, unless and until taken over by the Employer. Unless otherwise stated in the Contract, the Contractor shall supply to the Engineer six copies of each of the Contractor’s Documents.

The Contractor shall keep, on the Site, a copy of the Contract, publications named in the Specification, the Contractor’s Documents (if any), the Drawings and Variations and other communications given under the Contract. The Employer's Personnel shall have the right of access to all these documents at all reasonable times.

If a Party becomes aware of an error or defect of a technical nature in a document, which was prepared for use in executing the Works, the Party shall promptly give notice to the other Party of such error or defect.

1.9 Delayed Drawings or Instructions

The Contractor shall give notice to the Engineer whenever the works are likely to be delayed or disrupted if any necessary drawing or instruction is not issued to the Contractor within a particular time, which shall be reasonable. The notice shall include details of the necessary drawing or instruction, details of why and by when it should be issued, and details of the nature and amount of the delay or disruption likely to be suffered if it is late.

If the Contractor suffers delay and/or incurs Cost as a result of a failure of the Engineer to issue the notified drawing or instruction within a time which is reasonable a n d is specified in the notice with supporting details, the Contractor shall give a further notice to the Engineer and shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to:

Page 34: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 7/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

(a) An extension of time for any such delay, if completion is or will be delayed, under

Sub-Clause 7.4 [Extension of Time for Completion], and

(b) Payment of any such Cost, which shall be included in the Contract Price.

After receiving this further notice, the Engineer shall proceed in accordance with Sub-Clause 3.4 [Determinations] to agree or determine these matters. However, if and to the extent that the Engineer’s failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor’s Documents, the Contractor shall not be entitled to such extension of time or cost.

1.10 Employer's Use of Contractor’s Documents

As between the Parties, the Contractor shall retain the copyright and other intellectual property rights in the Contractor’s Documents and other design documents made by (or on behalf of) the Contractor.

The Contractor shall be deemed (by signing the Contract) to give to the Employer a non- terminable transferable non-exclusive royalty-free Licence to copy, use and Communicate the Contractor’s Documents, including making and using modifications of them. This Licence shall: (a) Apply throughout the actual or intended working life (whichever is longer) of the relevant

parts of the Works,

(b) Entitle any person in proper possession of the relevant part of the Works to copy, use and communicate the Contractor’s Documents for the purposes of completing, Operating, maintaining, altering, adjusting, repairing and demolishing the Works, and

(c) In the case of Contractor’s Documents, which are in the form of computer programs and other software, permit their use on any computer on the Site and other places as

envisaged by the Contract, including replacements o f any computers supplied by

the Contractor. The Contractor’s Documents and other design documents made by (or on behalf of) the Contractor shall not, without the Contractor’s consent, be used, copied or communicated to a third party by (or on behalf of) the Employer for purposes other than those permitted under this Sub-Clause. Any modifications/ changes in the Contractor’s Documents and/or the design after the same are approved by the Employer shall be made only with prior written approval of the Employer.

1.11 Contractor’s use of Employer's Documents

As between the Parties, the Employer shall retain the copyright and other intellectual property rights in the Specification, the Drawings and other documents made by (or on behalf of) the Employer. The Contractor may, at his cost, copy, use, and obtain communication of these documents for the purposes of the Contract. They shall not, without the Employer's consent, be copied, used or communicated to a third party by the Contractor, except as necessary for the purposes of the Contract.

Page 35: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 8/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

1.12 Confidential Details

The Contractor shall disclose all such confidential and other information as the Engineer may reasonably require in order to verify the Contractor’s compliance with the Contract.

1.13 Compliance with Laws

The Contractor shall, in performing the Contract, comply with applicable Laws.] Unless otherwise: (a) The Employer shall have obtained (or shall obtain) the planning, zoning or

Similar permission for the Permanent works, and any other permissions described in the Specification as having been (or being) obtained by the Employer; and the Employer shall indemnify and hold the Contractor harmless against and from the consequences of any failure to do so; and

(b) The Contractor at his cost shall give all notices, pay all taxes, duties and fees,

and obtain all permits, licenses and approvals, as required by the Laws in relation to the execution and completion of the Works and the remedying of any defects; and the Contractor shall indemnify and hold the Employer harmless against and from the consequences of any failure to do so.

(c) The Contractor shall be responsible for all procedural compliances related to

the payment of taxes, duties and fees under the Contract and shall solely be responsible for any proceedings initiated by any relevant authority, in respect of any non payment, short payment, non compliance, penalty, interest or other such issues, and for all liabilities and expenses related to such proceedings. In the event, any proceedings are initiated against the Employer by any relevant authority, then the Contractor shall fully indemnify and compensate the Employer for any cost, liability, penalty, interest and legal fees as a result of such proceedings.

1.14 Joint and Several Liability

If the Contractor, under Appendix of Tender are permitted to constitutes (under applicable Laws) a joint venture, consortium or other unincorporated grouping of two or more persons/companies (a) These persons/ companies shall be deemed to be jointly and severally liable to the

Employer for the performance of the Contract;

(b) These persons/companies shall notify the Employer of their leader who shall have authority to bind the Contractor.

(b) The Contractor shall not alter its composition or legal status without the prior consent

of the Employer. 1.15 Details to be Confidential

The Contractor shall treat the details of the Contract as private and confidential, except to the extent necessary to carry out obligations under it or to comply with applicable laws. The Contractor shall not publish, permit to be published or disclose any particulars of the works in any trade or technical paper of elsewhere wi thout the previous written consent of Employer.

Page 36: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 9/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

2.0 THE EMPLOYER 2.1 Permission of Access to the Site

The Employer shall give the Contractor l icense to enter the Site or part thereof within the time (times) stated in the Appendix to Tender. The access may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right or possession until the Performance Security has been received.

If no such time is stated in the Appendix to Tender, the Employer shall give the Contractor access to the Site within such times as may be required to enable the Contractor to proceed in accordance with the programme submitted under Sub-Clause 7.3 [Programme]. If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such permission within such time, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to:

(a) An extension of time for any such delay, if completion is or will be delayed, under

Sub-Clause 7.4 [Extension of Time for Completion], and

(b) Payment of any such reasonable Cost incurred by the Contractor, which shall be included in the Contract Price.

(c) After receiving this notice, the Engineer shall proceed in accordance with Sub Clause3.4 [Determinations] to agree or determine these matters.

However, if and to the extent that the Employer’s failure was caused by any error or delay or act by the Contractor, including an error in, or delay in the submission of, any of the Contractor’s Documents, the Contractor shall not be entitled to such extension of time, cost or profit.

2.2 Permits, Licenses or Approvals The Employer shall (where he is in a position to do so) provide reasonable assistance to the Contractor at the request of the Contractor:

(a) For the Contractor’s applications for any Permits, Licences or approvals required by

the Laws of the Country:

(i) Which the Contractor is required to obtain under Sub- Clause 1.13 [Compliance with Laws],

(ii) For the delivery of Goods, including clearance through customs.

Page 37: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 10/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

2.3 Employer's Personnel

The Employer shall be responsible for ensuring that the Employer's Personnel and the Employer's other Contractors on the Site: (a) Co-operate with the Contractor’s efforts under Sub-Clause 4.6 [Co-operation],

and

(b) Take actions similar to those, which the Contractor is required to take under sub paragraphs (a), (b) and (c) of Sub-Clause 4.8 [Safety Procedures] and under Sub- Clause 4.18 [Protection of the Environment].

2.4 Employer's Claims

If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract, and/or to any extension of the Defects Liability Period, the Employer or the Engineer shall give notice and particulars to the Contractor. However, notice is not required for payments due under Sub-Clause 4.19 [Site Facilities].

A notice relating to any extension of the Defects Liability Period shall be given before the expiry of such period. The particulars shall specify the Clause or other basis of the claim, of the amount and/or extension to which the Employer considers himself to be entitled in connection with the Contract. The Engineer shall then proceed in accordance with Sub- Clause 3.4 [Determinations] to agree or determine (i) the amount (if any) which the Employer is entitled to be paid by the Contractor, and/or (ii) the extension (if any) of the Defects Liability Period in accordance with Sub Clause 10.3 [Extension of Defects Liability Period]. This amount may be included as a deduction in the Contract Price and Payment Certificates. The Employer shall be entitled to set off against or make any deduction from an amount certified in a Payment Certificate, or to encash the Performance Bank Guarantee or to otherwise claim against the Contractor.

3.0 ENGINEER 3.1 Engineer’s Duties and Authority

The Employer shall appoint the Engineer who shall carry out the duties assigned to him in the Contract.

The Engineer shall have no authority to amend the Contract.

The Engineer may exercise the authority attributable to the Engineer as specified in or necessarily to be implied from the Contract. If the Engineer is required to obtain the approval of the Employer before exercising a specified authority, the requirements shall be as stated in the Special Conditions.

Page 38: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 11/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

However, whenever the Engineer exercises a specified authority for which the Employer’s approval is required, then (for the purposes of the Contract) the Employer shall be deemed to have given approval.

Except as otherwise stated in these Conditions:

(a) Whenever carrying out duties or exercising authority, specified in or implied by the Contract, the Engineer shall be deemed to act for the Employer;

(b) The Engineer has no authority to relieve either Party of any duties, obligations or

responsibilities under the Contract; and

(c) Any approval, check, certificate, consent, examination, inspection, instruction, notice, proposal, request, test, or similar act by the Engineer (including absence of disapproval) shall not relieve the Contractor from any responsibility he has under the Contract, including responsibility for errors, omissions, discrepancies and non- compliances.

3.2 Delegation by the Engineer

The Engineer may from time to time assign duties and delegate authority to assistants, and may also revoke such assignment or delegation. These assistants may include a resident Engineer, and/or independent inspectors appointed to inspect and/or test items of Plant and/or Materials. The assignment, delegation or revocation shall be in writing and shall not take effect until copies have been received by both Parties. However, unless otherwise agreed by both Parties, the Engineer shall not delegate the authority to determine any matter in accordance with Sub-Clause 3.4 [Determinations].

Assistants are suitably qualified persons, who are competent to carry out these duties and exercise this authority; and who are fluent in the language for communications defined in Sub-Clause 1.4 [Law and Language].

Each assistant, to whom duties have been assigned or authority has been delegated, shall only be authorized to issue instructions to the Contractor to the extent defined by the delegation. Any approval, check, certificate, consent, examination, inspection, instruction, notice, proposal, request, test, or similar act by an assistant, in accordance with the delegation, shall have the same effect as though the act had been an act of the Engineer. However

(a) Any failure to disapprove any work, Plant or Materials shall not constitute approval, and shall therefore not prejudice the right of the Engineer to reject the work, Plant or Materials;

(b) If the Contractor questions any determination or instruction of an assistant, the Contractor may refer the matter to the Engineer, who shall promptly confirm, reverse or vary the determination or instruction.

3.3 Instructions of the Engineer

Page 39: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 12/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

The Engineer may issue to the Contractor (at any time) instructions and additional or modified Drawings, which may be necessary for the execution of the works and the remedying of any defects, all in accordance with the Contract. The Contractor shall only take instructions from the Engineer, or from an assistant to whom the appropriate authority has been delegated under this Clause. If an instruction constitutes a Variation, Clause 12 [Variations and Adjustments] shall apply.

The Contractor shall comply with the instructions given by the Engineer or delegated assistant, on any matter related to the Contract. Whenever practicable, their instructions shall be given in writing. If the Engineer or a delegated assistant:

(a) Gives an oral instruction,

(b) Receives a written confirmation of the instruction, from (or on behalf of) the Contractor, within two working days after giving the instruction,

(c) and does not reply by issuing a written rejection and/or instruction within two

working days after receiving the confirmation, Then the confirmation shall constitute the written instruction of the Engineer or delegated assistant (as the case may be).

3.4 Determinations

Whenever these Conditions provide that the Engineer shall proceed in accordance with this Sub-Clause 3.4 to agree or determine any matter, the Engineer shall consult with each Party in an endeavour to reach agreement. If agreement is not achieved, the Engineer shall make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances

The Engineer shall give notice to both Parties of each agreement or determination, with supporting particulars. Each Party shall give effect to each agreement or determination unless and until revised under Clause 19 [Claims, Disputes and Arbitration]

3.5 Management Meetings

The Engineer or the Contractor’s Representative may require the other to attend a management meeting in order to review the arrangements for future work. The Engineer shall record the business of management meetings and supply copies of the record to those attending the meeting.

4.0 THE CONTRACTOR 4.1 Contractor’s General Obligations

The Contractor shall design (to the extent specified in the Contract), execute and complete the Works in accordance with the Contract and with the Engineer’s instructions, and shall remedy any defects in the Works.

The Contractor shall provide the Plant and Contractor’s Documents specified in the Contract, and all Contractor’s Personnel, Goods, consumables and other things and

Page 40: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 13/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

services, whether of a temporary or permanent nature, required in and for this design, execution, completion and remedying of defects. The Contractor shall be responsible for the adequacy, stability and safety of all Site operations and of all methods of construction. Except to the extent specified in the Contract, the Contractor (i) shall be responsible for all Contractor’s Documents, Temporary Works, and such design of each item of Plant and Materials as is required for the item to be in accordance with the Contract, and (ii) shall not otherwise be responsible for the design or specification of the Permanent Works.

The Contractor shall, whenever required by the Engineer, submit details of the arrangements and methods, which the Contractor proposes to adopt for the execution of the works. No significant alteration to these arrangements and methods shall be made without this having previously been notified to the Engineer.

If the Contract specifies that the Contractor shall design any part of the Permanent Works, then

(a) The Contractor shall submit to the Engineer the Contractor’s Documents for this part in

accordance with the procedures specified in the Contract;

(b) These Contractor’s Documents shall be in accordance with the Specification and Drawings, shall be written in the language for communications defined in Sub-Clause 1.4 [Law and Language], and shall include additional information required by the Engineer to add to the Drawings for co-ordination of each Party's designs;

(c) The Contractor shall be responsible for this part and it shall, when the Works are

completed, be fit for such purposes for which the part is intended as are specified in the Contract; and

(d) Prior to the commencement of the Tests on Completion, the Contractor shall submit to the Engineer the "as-built" documents and operation and maintenance manuals in accordance with the Specification and in sufficient detail for the Employer to operate, maintain, dismantle, reassemble, adjust and repair this part of the Works. Such part shall not be considered to be completed for the purposes of taking-over under Sub-Clause 9.1 [Taking over of the Works and Sections] until these documents and manuals have been submitted to the Engineer.

4.2 Performance Security

The Contractor shall obtain (at his cost) and submit a Performance Security for proper performance, in the amount, currencies and mode stated in the Appendix to Tender.

The Contractor shall deliver the Performance Security to the Employer within the time limit

as stated in the Appendix to the tender and shall send a copy to the Engineer. The

Performance Security shall be issued by a Bank approved by the Employer, and shall be in

the format given in Annexure 3 or in another form approved by the Employer.

Page 41: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 14/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

The Contractor shall ensure that the Performance Security is valid and enforceable until the Contractor has executed and completed the works and remedied any defects. If the terms of the Performance Security specify its expiry date, and the Contractor has not become entitled to receive the Performance Certificate by the date 28 days prior to the expiry date, the Contractor shall extend the validity of the Performance Security until the Works have been completed and any defects have been remedied. If the Contractor fails to extend the validity of the Performance Security 28 days prior to the expiry date of the Performance Security the Employer shall be entitled to encash the Performance Security.

4.3 Contractor’s Representative

The Contractor shall appoint the Contractors Representative and shall give him all authority necessary to act on the Contractor’s behalf under the Contract.

Unless the Contractor’s Representative is named in the Contract, the Contractor shall, prior to the Commencement Date, submit to the Engineer for consent the name and particulars of the person the Contractor proposes to appoint as Contractor’s Representative. If consent is withheld or subsequently revoked, or if the appointed person fails to act as Contractor’s Representative, the Contractor shall similarly submit the name and particulars of another suitable person for such appointment. The Contractor shall not , without t h e prior consent o f the Engineer, r e v o k e t h e appointment of the Contractor’s Representative or appoint a replacement.

The whole time of the Contractor’s Representative shall be given to directing the performance of the Contract. If the Contractor’s R e p r e s e n t a t i v e i s to be temporarily absent from the Site during the execution of the Works, a suitable replacement person shall be appointed, subject to the Engineer’s prior consent, and the Engineer shall be notified accordingly.

The Contractor’s Representative shall, on behalf of the Contractor, receive instructions under Sub-Clause 3.3 [Instructions of the Engineer].

The Contractor’s Representative may delegate any powers, functions and authority to any competent person, and may at any time revoke the delegation. Any delegation or revocation shall not take effect until the Engineer has received prior notice signed by the Contractor’s Representative, naming the person and specifying the powers, functions and authority being delegated or revoked.

The Contractor’s Representative and all these persons shall be fluent in the language for communications defined in Sub-Clause 1.4 [Law and Language].

The Contractor’s Representative and all their persons shall also be fluent in English, Hindi and Marathi. If Contractor’s Representative, or these persons, is not fluent in the above languages, the Contractor shall make a competent interpreter available during all working hours.

Page 42: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 15/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

4.4 Sub-Contractors

The Contractor shall not Sub-Contract the whole or part of the Works without prior written consent of Employer / Engineer. In the event Contractor sub-contracts the whole or part of Works, the sub contractors shall be subject to the provisions of the Contract. The Contractor shall be responsible for the acts or defaults of any Sub-Contractor appointed by him except Nominated Sub-Contractor, his agents or employees, as if they were the acts or defaults of the Contractor. However, unless otherwise stated,

(a) The Contractor shall not be required to obtain consent for the purchase of

materials, which are in accordance with the standards specified in the Contract.

(b) The prior consent of the Engineer / Employer shall be obtained to engage other proposed Sub-Contractors. In case Sub-Contract is approved by Engineer / Employer then;

(i) The Contractor shall give the Engineer not less than 28 days notice of the intended

date of the commencement of each Sub-Contractor’s work, and of the commencement of such work on the Site; and

(ii) Each Sub-Contract shall include provisions, which would entitle the Employer to

require the Sub-Contract to be assigned to the Employer under Sub-Clause 4.5 [Assignment of Benefit of Sub-Contract] (if or when applicable) or in the event of termination under Sub-Clause 14.2 [Termination by Employer].

(c) Nothing contained in the Contract shall render the Employer in any manner liable to

any Sub-contractor appointed by contractor except the Nominated Sub-Contractor. The Contractor shall indemnify and hold harmless Employer or any of its Affiliates, in respect of any and all loss, liability, damage, claim, demand, action, proceedings or costs (including legal costs and expenses) arising out of acts or omissions of the Sub-contractor appointed by him except the Nominated Sub-Contractor.

4.5 Assignment of Benefit of Sub-Contract

If a Sub-Contractor’s obligations extend beyond the expiry date of the relevant Defects Liability Period and the Engineer, prior to this date, instructs the Contractor to assign the benefit of such obligations to the Employer, then the Contractor shall do so. The Contractor shall have no liability to the Employer for the work carried out by the Sub- Contractor after the Defect Liability period as defined in the contract.

4.6 Co-operation

The Contractor shall, as specified in the Contract or as instructed by the Engineer, allow appropriate opportunities for carrying out work to:

(a) The Employer's Personnel,

(b) Any other Contractors employed by the Employer, and

(c) The personnel of any legally constituted public authorities,

Page 43: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 16/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

who may be employed in the execution on or near the Site of any work not included in the Contract.

4.7 Setting Out

The Contractor shall set out the Works in relation to original points, lines and levels of reference specified in the Contract or notified by the Engineer. The Contractor shall be responsible for the correct positioning of all parts of the Works, and shall rectify any error in the positions, levels, dimensions or alignment of the Works.

The Employer shall be responsible for any errors in these specified or notified items of reference, but the Contractor shall use reasonable efforts to verify their accuracy before they are used.

If the Contractor suffers delay and/or incurs Cost from executing work which was necessitated by an error in these items of reference, and an experienced Contractor could not reasonably have discovered such error and avoided this delay and/or Cost, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub Clause 19.1 [Contractor’s Claims] to: (a) An extension of time for any such delay, if completion is or will be delayed,

under Sub-Clause 7.4 [Extension of Time for Completion], and (b) Payment of any such Cost, which shall be included in the Contract Price.

After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.4 [Determinations] to agree or determine (i) whether and (if so) to what extent the error could not reasonably have been discovered, and (ii) the matters described in subparagraphs (a) and (b) above related to this extent.

4.8 Safety Procedures

The Contractor shall:

(a) Comply with all applicable safety regulations and/or as per approved SHE plan whichever is stringent,

(b) Take care for the safety of all persons entitled to be on the Site,

(c) Use reasonable efforts to keep the Site and Works clear of unnecessary obstruction so

as to avoid danger to these persons,

(d) Provide fencing, lighting, guarding and watching of the Works until completion and

taking over under Clause 9 [Employer's Taking Over], and

(e) Provide any Temporary Works (including roadways, footways, guards and fences), which may be necessary, because of the execution of the Works, for the use and protection of the public and of owners and occupiers of adjacent land.

4.9 Quality Assurance

The Contractor shall institute a quality assurance system to demonstrate compliance with the requirements of the Contract. The system shall be in accordance with the

Page 44: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 17/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

details stated in the Contract. The Engineer shall be entitled to audit any aspect of the system.

Details of all procedures and compliance documents shall be submitted to the Engineer for information before each design and execution stage is commenced. When any document of a technical nature is issued to the Engineer, evidence of the prior approval by the Contractor himself shall be apparent on the document itself.

Compliance with the quality assurance system shall not relieve the Contractor of any of his duties, obligations or responsibilities under the Contract.

4.10 Site Data

The Employer in good faith shall make available to the Contractor for his information, data in the Employer’s possession relevant to the work. The Contractor shall be solely responsible for interpreting all such data.

The Contractor shall be deemed to have obtained all necessary information as to risks, contingencies and other circumstances which may influence or the Tender or Works. To the same extent, the Contractor shall be deemed to have inspected and examined the Site, its surroundings, the above data and other available information, and to have been satisfied before submitting the Tender as to all relevant matters, including (without limitation): (a) The form and nature of the Site, including sub-surface conditions, (b) The hydrological and climatic conditions, (c) The extent and nature of the work and Goods necessary for the execution and completion of the Works and the remedying of any defects,

(d) The Laws, procedures and labour practices of the Country, and

(e) The Contractor’s requirements for access, accommodation, facilities, personnel, power,

transport, water and other services.

4.11 Sufficiency of the Accepted Contract amount

The Contractor shall be deemed to:

(a) Have satisfied himself as to the correctness and sufficiency of the Accepted Contract amount, and

(b) Have based the Accepted Contract Amount on the data, interpretations, necessary information, inspections, examinations and satisfaction as to all relevant matters referred to in Sub-Clause 4.10 [Site Data].

Unless otherwise stated in the Contract, the Accepted Contract Amount covers the entire Contractor’s obligations under the Contract (including those under Provisional Sums; If any)

Page 45: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 18/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

and all things necessary for the proper execution and completion of the Works and the remedying of any defects.

4.12 Unforeseeable Physical Conditions

In this Sub-Clause, "physical conditions" means natural physical conditions and manmade and other physical obstructions and pollutants, which the Contractor encounters at the Site when executing the Works, including sub-surface and hydrological conditions but excluding climatic conditions. If the Contractor encounters adverse physical conditions, which he considers to have been unforeseeable, the Contractor shall give notice to the Engineer within 3 days.

This notice shall describe the physical conditions, so that they can be inspected by the Engineer, and shall set out the reasons why the Contractor considers them to be unforeseeable. The Contractor shall continue executing the Works, using such proper and reasonable measures as are appropriate for the physical conditions, and shall comply with any instructions, which the Engineer may give. If an instruction constitutes a Variation, Clause 12 [Variations and Adjustments] shall apply.

If and to the extent that the Contractor encounters physical conditions which are unforeseeable, gives such a notice, and suffers delay and/or incurs Cost due to these conditions, the Contractor shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to: (a) An extension of time for any such delay, if completion is or will be delayed,

under Sub-Clause 7.4 [Extension of Time for Completion], and (b) Payment of any such Cost, which shall be included in the Contract Price.

After receiving such notice and inspecting and/or investigating these physical conditions, the Engineer shall proceed in accordance with Sub-Clause 3.4 [Determinations] to agree or determine (i) whether and (if so) to what extent these physical conditions were unforeseeable, and (ii) the matters described in subparagraphs (a) and (b) above related to this extent.

However, before additional Cost is finally agreed or determined under subparagraph (b), the Engineer may also review whether other physical conditions in similar parts of the Works (if any) were more favourable than could reasonably have been foreseen when the Contractor submitted the Tender. If and to the extent that these more favourable conditions were encountered, the Engineer may proceed in accordance with Sub-Clause 3.4 [Determinations] to agree or determine the reductions in Cost which were due to these conditions, which may be included (as deductions) in the Contract Price and Payment Certificates. The Engineer may take account of any evidence of the physical conditions foreseen by the Contractor when submitting the T e n d e r , which may be made available by the Contractor, but shall not be bound, by any such evidence.

4.13 Rights of Way and Facilities

The Contractor shall bear all costs and charges for special and/or temporary rights of way, which he may require, including those for access to the Site. The Contractor shall also

Page 46: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 19/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

obtain, at his risk and cost, any additional facilities outside the Site, which he may require for the purposes of the Works.

4.14 Avoidance of Interference

The Contractor shall not interfere unnecessarily or improperly with:

(a) The convenience of the public, or

(b) The access to and use and occupation of all roads and footpaths, irrespective of whether they are public or in the possession of the Employer or of others.

The Contractor shall indemnify and hold the Employer harmless against and from all damages, losses and expenses (including legal fees and expenses) resulting from any such unnecessary or improper interference.

4.15 Access Route

The Contractor shall be deemed to have been satisfied as to the suitability and availability of access routes to the Site. The Contractor shall use reasonable efforts to prevent any road or bridge from being damaged by the Contractor’s traffic or by the Contractor’s Personnel.

These efforts shall include the proper use of appropriate vehicles and routes. Except as

otherwise stated in these Conditions:

(a) The Contractor shall (as between the Parties) be responsible for any maintenance which may be required for his use of access routes;

(b) The Contractor shall provide all necessary signs or directions along access routes, and shall obtain any permission which may be required from the relevant authorities for his use of routes, signs and directions;

(c) The Employer shall not be responsible for any claims which may arise from the use or otherwise of any access route,

(d) The Employer does not guarantee the suitability or availability of particular access routes, and

(e) Costs due to non-suitability or non-availability, for the use required by the Contractor, of access routes shall be borne by the Contractor.

4.16 Transport of Goods

Unless otherwise stated in the Particular Conditions: (a) The Contractor shall give the Engineer not less than 7 day's notice of the date on which

any Plant or a major item of other Goods will be delivered to the Site; (b) The Contractor shall be responsible for packing, loading, transporting, receiving,

unloading, storing and protecting a l l Goods and other things required for the works; and

(c) The Contractor shall indemnify and hold the Employer harmless against and From all damages, losses and expenses (including legal fees and expenses) resulting from the transport of goods, and shall negotiate and pay all claims arising from their transport.

4.17 Contractor’s equipment

The Contractor shall be responsible for all Contractors’ equipment. When brought on to the Site, Contractor’s equipment shall be deemed to be exclusively intended for the

Page 47: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 20/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

execution of the Works and shall be retained at the site till the completion of the Works. The Contractor shall not remove from the Site any major items of Contractor’s equipment without the consent of the Engineer. However, consent shall not be required for vehicles transporting Goods or Contractor’s personnel off Site. The Employer shall not be held responsible for any loss or damage caused to the Contractor’s Equipment. The Contractor shall indemnify and hold harmless the Employer from and against any claims, proceedings, damages, costs, charges or expenses in respect of damage that may cause to highway, railway, bridges or any other traffic facilities and/or to any person due to traffic caused by the Contractor including movement of Contractor’s Equipment.

4.18 Protection of the Environment

The Contractor shall take all reasonable steps to protect the environment (both on and off the Site) and to limit damage and nuisance to people and property resulting from pollution, noise and other results of his operations.

The Contractor shall ensure that emissions, surface discharges and effluent from the Contractor’s activities shall not exceed the values prescribed by applicable laws and approved SHE plan, whichever is stringent.

The Contractor shall save harmless and indemnify and keep indemnified the Employer in respect of all claims, proceedings, damages or expenses of whatsoever nature due to damage caused to the environment by execution of Works or otherwise by the Contractor in derogation of environmental laws or due to any breach committed by the Contractor of its obligations under this clause.

4.19 Site Facilities

The contractor shall except, as stated below, be responsible for the provision of all power, water and other services he may require

The employer shall make available to the Contractor, free of any charge, Land for Contractor’s site establishment, work areas and labour colony at the designated locations at project site, subject to observing of the rules and regulations as applicable and proper house keeping and maintenance of the site. On completion of work, contractor shall remove itself, its employees, Sub-Contractors and the Contractor’s Equipment from the Site and handover the Site along with the Permanent Works & the area to the Employer in proper condition. .

4.20 Progress Reports

4.20.1 Daily reports:

The contractor shall submit daily report indicating daily activities, weather condition, actual manpower, equipment and the materials arriving on site in the prescribed format duly approved by the Engineer.

4.20.2 Monthly Reports:

Monthly progress reports shall be prepared by the Contractor and submitted to the Engineer in triplicate in the prescribed format duly approved by the Engineer. The first

Page 48: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 21/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

report shall cover the period up to the end of the first calendar month following the Commencement Date. Reports shall be submitted monthly thereafter, each within 7days after the last day of the period to which it relates.

Reporting shall continue until the Contractor has completed all work, which is known to be outstanding at the completion date, stated in the Taking-Over Certificate for the Works.

Each report shall include:

(a) Charts and detailed descriptions of progress, including each stage of design (if any),

Contractor’s Documents, procurement, manufacture, delivery to Site, construction, erection and testing; and including these stages for work by each

Sub- Contractor,

(b) Photographs in hardcopy & digital copy showing the various stages of progress on the Site.

(c) For the manufacture of each main item of Plant and Materials, the name of the manufacturer, manufacture location, percentage progress, and the actual or expected dates of: (i) Commencement of manufacture,

(ii) Contractor’s/ Engineer’s inspections,

(iii) Tests,

(iv) Shipment and arrival at the Site;

(d) The details described in Sub-Clause 5.10 [Records of Contractor’s Personnel and

Equipment];

(e) Copies of quality assurance documents, test results and certificates of Materials;

(f) List of notices given under Sub-Clause 2.4 [Employer's Claims] and notices given under Sub-Clause 19.1 [Contractor’s Claims];

(g) Safety statistics, including details of any hazardous incidents and activities

relating to environmental aspects and public relations; and

(h) Comparisons of actual and planned progress, with details of any events or circumstances w h i c h may jeopardize the completion I n accordance wi t h the Contract, and the measures being (or to be) adopted to overcome delays.

4.21 Security of the Site

Unless otherwise stated

(a) The Contractor shall be responsible for keeping unauthorised persons off the

Site, and

Page 49: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 22/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

(b) Authorised persons shall be limited to the Contractor’s Personnel and the Employer's Personnel; and to any other personnel notified to the Contractor, by the Employer or the Engineer, as authorised personnel of the Employer's other Contractors on the Site.

(c) The contractor shall be fully responsible for watch and ward both at site as well as

the Labour colony at no extra cost to Employer.

4.22 Contractor’s Operations on Site

The Contractor shall confine his operations to the Site, and to any additional areas, which may be obtained by the Contractor and agreed by the Engineer as working areas. The Contractor shall take all necessary precautions to keep Contractor’s Equipment and Contractor’s Personnel within the site and these additional areas, and to keep them off adjacent land.

During the execution of the Works, the Contractor shall keep the Site free from all unnecessary obstruction, and shall store or dispose of any Contractor’s Equipment or surplus materials. The Contractor shall clear away and remove from the Site any wreckage, rubbish and Temporary Works, which are no longer required.

Upon the issue of a Taking-Over Certificate, the Contractor shall clear away and remove, from that part of the Site and Works to which the Taking-Over Certificate refers, all Contractor’s Equipment, surplus material, wreckage, rubbish and Temporary Works. The Contractor shall leave that part of the Site and the Works in a clean and safe condition. However, the Contractor may retain on Site, during the Defects Liability Period, such Goods as are required for the Contractor to fulfill obligations under the Contract.

The Contractor shall be responsible for the removal and where appropriate the marking or lighting of any wreck or debris of the property, equipment or any part thereof owned by or contracted to the Contractor or his Sub-Contractors, or arising from the execution of the Work, where required by Laws, or any competent authority and/or where interfering with the Owner’s operations, and/or a hazard to navigation and/or required under goods industry practice generally followed by international contractors of repute for similar project and shall defend indemnify and hold harmless Employer or any of its Affiliates, in respect of any and all loss, liability, damage, claim, demand, action, proceedings or costs (including legal costs and expenses) of every kind and nature arising out of such wreck or debris, howsoever arising.

4.23 Fossils

All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Site shall be placed under the care and authority of the Employer. The Contractor shall take reasonable precautions to prevent Contractor’s Personnel or other persons from removing or damaging any of these findings.

Page 50: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 23/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

The Contractor shall, upon discovery of any such finding, promptly give notice to the Engineer, who shall issue instructions for dealing with it.

5.0 STAFF AND LABOUR 5.1 Engagement of Staff and Labour

Except as otherwise stated in the Specification, the Contractor shall make arrangements for the engagement of all staff and labour, local or otherwise, and for their payment, housing, feeding, drinking water and transport.

5.2 Rates of Wages and Conditions of Labour

The Contractor shall pay rates of wages, and observe conditions of labour as per prevailing Labour Laws.

5.3 Persons in the Service of Employer/Engineer

The Contractor shall not recruit, or attempt to recruit, staff and labour from amongst the Employer's / Engineer’s / other contractors’ personnel working for this project

5.4 Labour Laws

The Contractor shall comply with all the relevant labour laws applicable to the Contractor’s Personnel, including laws relating to their employment, health, safety, welfare, immigration and emigration, and shall allow them all their legal rights.

The Contractor shall require his employees to obey all applicable laws, including those concerning safety at work.

5.5 Working Hours

No work shall be carried out on the Site on 3 National holidays (26th January, 1st May & 15th August) and on weekly recognized day of rest and two hours beyond normal working hours (eight hours) on any of the working day, without the prior consent of the Employer/Engineer.

5.6 Facilities for Staff and Labour

The Contractor shall be responsible to provide and maintain all necessary accommodation and welfare facilities wherever required for the Contractor’s Personnel without any additional cost to the Employer.

Page 51: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 24/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

5.7 Health and Safety

The Contractor shall at all times take all precautions to maintain the health and safety of the Contractor’s Personnel as per the approved SHE plan. In collaboration with local health authorities, the Contractor shall ensure that medical staff, first aid facilities, sick bay and ambulance service are available at all times at the work Site, and that suitable arrangements are made for all necessary welfare and hygiene requirements and for the prevention of epidemics.

The Contractor shall appoint at its own cost a Safety officer at the Site, responsible for maintaining safety and protection against accidents. This person shall be qualified for this responsibility, and shall have the authority to issue instructions and take protective measures to prevent accidents. Throughout the execution of the Works, the Contractor shall provide whatever is required by this person to exercise this responsibility and authority. The Contractor shall send to the Engineer and the Employer details of any accident and nearness accident occurrence at the site immediately in any case not later than 4 hrs in the prescribed format as approved by Employer/Engineer

The Contractor shall maintain proper records related to Safety Health and environment and make Reports which will be subject to periodic audits by the Engineer. Discrepancies found if any shall be immediately made good. The Contractor shall take all precautions for prevention of accidents at Site.

In event of failure to comply by the contractor, the engineer shall have right to stop the work without allowing any Extension or Compensation to the contractor.

5.8 Contractor’s Superintendence

(i) Throughout the execution of the Works, and as long thereafter as is necessary to fulfill the Contractor’s obligations, the Contractor shall provide all necessary superintendence to plan, arrange, direct, manage, inspect and test the work. Superintendence shall be given by a sufficient number of persons having adequate knowledge of the language for communications (defined in Sub- Clause 1.4 [Law and Language]) and of the operations to be carried out (including the methods and techniques required, the hazards likely to be encountered and methods of preventing accidents), for the satisfactory and safe execution of the Works.

A reasonable proportion of the Contractor’s Superintending staff shall have a working knowledge of English and Hindi or the Contractor shall have a sufficient number of competent interpreters available during all working hours.

(ii) Foreign Staff and Labour

Page 52: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 25/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

The Contractor may engage foreign experts who are necessary for the execution of the Works. The Contractor must ensure that these personnel are provided with the required residence visas and work permits. The Contractor shall be responsible for the return to the place where they were recruited or to their domicile of imported Contractor’s personnel. In the event of the death in the Country of any of these personnel or members of their families, the Contractor shall similarly be responsible for making the appropriate arrangements for their return or burial.

(iii) Measures against Insect and Pest Nuisances

The Contractor shall at all time take necessary precautions to protect all staff and all labour employed on the site from insect and pest nuisance, and to reduce their danger to health. The Contractor shall provide suitable prophylactics for the Contractor’s personnel and shall comply with all the regulations of the local health authorities, including use of appropriate insecticide.

(iv) Alcoholic Liquor or Drugs

The Contractor shal l not, import, sell, give, barter or otherwise dispose of any alcoholic liquor or drugs or permit or allow importation, sale, gift, barter, or disposal by Contractor’s Personnel.

(v) Arms and Ammunition

The Contractor shall not give, barter or otherwise dispose of to any person any arms or ammunition of any kind, or allow Contractor’s Personnel to do so.

(vi) Festivals and Religious Customs

The Contractor shall respect the Country’s recognised festivals and religious or other customs.

5.9 Contractor’s Personnel The Contractor’s Personnel shall be appropriately qualified, skilled and experienced in their respective trades or occupations. The Engineer may require the Contractor to remove (or cause to be removed) any person employed on the Site or Works, including the Contractor’s Representative if applicable, who:

(a) Persists in any misconduct or lack of care,

(b) Carries out duties incompetently or negligently,

(c) Fails to conform with any provisions of the Contract, or

(d) Persists in any conduct, which is prejudicial to safety, health, or the protection of the

environment.

In this event, the Contractor shall then appoint (or cause to be appointed) a suitable replacement person.

Page 53: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 26/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

5.10 Records of Contractor’s Personnel and Equipment

The Contractor shall submit, to the Engineer, details showing the number of each class of Contractor’s Personnel and of each type of Contractor’s Equipment on the Site. Details shall be submitted each calendar month, in a form approved by the Engineer, until the Contractor has completed all work, which is known to be outstanding at the completion date, stated In the Taking-Over Certificate for the Works.

5.11 Disorderly Conduct

The Contractor shall at all times take all reasonable precautions to prevent any unlawful, riotous or disorderly conduct by or amongst the Contractor’s Personnel, and to preserve peace and protection of persons and property on and near the Site.

6.0 PLANT, MATERIALS AND WORKMANSHIP 6.1 Manner of Execution

The Contractor shall execute all Works:

(a) In the manner (if any) specified in the Contract,

(b) In a proper workmanlike and careful manner, in accordance with recognized good

practice, and

(c) With properly equipped facilities and non-hazardous Materials, except as otherwise specified in the Contract.

6.2 Samples

The Contractor shall submit the following samples of Materials, and relevant information, to the Engineer for consent prior to using the Materials, in or for the Works:

(a) Manufacturer’s standard samples of Materials and samples specified in the Contract, all at the Contractor’s cost, and

(b) Additional samples instructed by the Engineer as a variation.

Each sample shall be labelled as to origin and intended use in the Works.

6.3 Inspection

The Employer's Personnel shall at all reasonable times: (a) Have full access to all parts of the Site and to all places from which natural materials

are being obtained, and

(b) During production, manufacture and construction (at the Site and elsewhere), be entitled to examine, inspect, measure and test the materials and workmanship, and to check the progress of manufacture of Plant and production and manufacture of Materials.

Page 54: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 27/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

The Contractor shall give the Employer's Personnel full opportunity to carry out these activities, including providing access, facilities, permissions and safety equipment. No such activity of inspection, examination etc. shall relieve the Contractor from any obligation or responsibility.

The Contractor shall give notice to the Engineer whenever any work is ready and before it is covered up, put out of sight, or packaged for storage or transport. The Engineer shall then either carry out the examination, inspection, measurement or testing without unreasonable delay, or promptly give notice to the Contractor that the Engineer does not require to do so. If the Contractor fails to give the notice, he shall, if and when required by the Engineer, uncover the work and thereafter reinstate and make good, all at the Contractor’s cost.

6.4 Testing

This Sub-Clause shall apply to all tests specified in the Contract, other than the Tests after Completion (if any).

The Contractor shal l provide all apparatus, assistance, documents and other information, electricity, equipment, fuel, consumables, instruments, labour, materials, and suitably qualified and experienced staff, as are necessary to carry out the specified tests efficiently. The Contractor shall agree, with the Engineer, the time and place for the specified testing of any Plant, Materials and other parts of the works.

The Engineer may, under Clause 12 [Variations and Adjustments], vary the location for conducting tests or details of specified tests, or instruct the Contractor to carry out additional tests. If these varied or additional tests show that the tested Plant, Materials or workmanship is not in accordance with the Contract, the cost of carrying out this Variation shall be borne by the Contractor, notwithstanding other provisions of the Contract. The Engineer shall give the Contractor not less than 24 hours' notice of the Engineer’s intention to attend the tests. If the Engineer does not attend at the time and place agreed, the Contractor may proceed with the tests, unless otherwise instructed by the Engineer, and the tests shall then be deemed to have been made in the Engineer’s presence.

If the Contractor suffers delay and/or incurs Cost from complying with these instructions or as a result of a delay for which the Employer is responsible, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to:

(a) An extension of time for any such delay, if completion is or will be delayed,

under Sub-Clause 7.4 [Extension of Time for Completion], and

(b) Payment of any such Cost, which shall be included in the Contract Price.

After receiving this notice, the Engineer shall proceed in accordance with Sub Clause 3.4 [Determinations] to agree or determine these matters.

Page 55: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 28/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

The Contractor shall promptly forward to the Engineer duly certified reports of the tests. When the specified tests have been passed, the Engineer shall endorse the Contractor’s test certificate, or issue a certificate to him, to that effect. If the Engineer has not attended the tests, he shall be deemed to have accepted the readings as accurate.

6.5 Rejection

If, as a result of an examination, inspection, measurement or testing, any Plant, accurate. Materials or workmanship is found to be defective or otherwise not in accordance with the Contract, the Engineer may reject the Plant, Materials or workmanship by giving notice to the Contractor, with reasons. The Contractor shall then promptly make good the defect and ensure that the rejected item complies with the Contract.

If the Engineer requires this Plant, Materials or workmanship to be retested, the tests shall be repeated under the same terms and conditions. If the rejection and retesting cause the Employer to incur additional costs, the Contractor shall pay these costs to the Employer.

6.6 Remedial Work

Notwithstanding any previous test or certification, the Engineer may instruct the Contractor to:

(a) Remove from the Site and replace any Plant or Materials which is not in

accordance with the Contract,

(b) Remove and re-execute any other work which is not in accordance with the Contract, and

(c) Execute any work which is urgently required for the safety of the Works, whether because of an accident, unforeseeable event or otherwise.

The Contractor shall comply with the instruction within a reasonable time, which shall be the time (if any) specified in the instruction, or immediately if urgency is specified under sub-paragraph ( c). If the Contractor fails to comply with the instruction, the Employer shall be entitled to employ and pay other persons to carry out the work.

Except to the extent that the Contractor would have been entitled to payment for work, the Contractor shall pay to the Employer two times all costs arising from this failure without any demur.

6.7 Ownership of Plant and Materials

Each item of Plant and Materials shall, to the extent consistent with the Laws become the property of the Employer at whichever is the earlier of the following times, free from liens and other encumbrances:

(a) When it is delivered to the Site;

Page 56: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 29/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

(b) When the Contractor is entitled to payment of the value of the Plant and Materials under

Sub-Clause 7.10 [Payment for Plant and Materials in event of Suspension] and have placed the Plant and materials at the disposal of the Employer without any liens and other encumbrances.

6.8 Royalties

Unless otherwise stated in the Specification, the Contractor shall pay all taxes, duties, royalties, rents and other statutory payments as applicable.

7.0 COMMENCEMENT, DELAYS AND SUSPENSION 7.1 Commencement of Work

Unless otherwise stated, the Commencement date and the actual commencement date shall be as stated in the Appendix of tender.

The Contractor shall commence the execution of the works as soon as is reasonably practicable after the Commencement Date, and shall then proceed with the Works with due expedition and without delay.

7.2 Time of Completion, Compensation for Delay due to Contractor’s Negligence

(Liquidated damages)

The Contractor shall complete the whole of the Works, and each Section (if any), within

the Time for Completion for the Works or Section (as the case may be), including:

(a) Achieving the passing of the Tests on Completion, and

(b) Completing all work, which is stated in the Contract as being required for the Works or Section to be considered to be completed for the purposes of taking over under Sub-Clause 9.1 [Taking Over of the Works and Sections]?

(c) Time period for completion of the Works shall be that mentioned in the Appendix

to the Tender, starting from the commencement date as defined in clause 7.1

above.

In the event of the Contractor failing to complete the work in all respects within the time specified or within the extended time that may be allowed by the Engineer as per the terms of the Contract, hereof the Contractor shall pay or allow the Employer to recover a sum as specified in the Appendix to Tender as Liquidated Damages.

(d) In case part / portions of the work can be commissioned and if Employer operates the portion for commercial purposes, the rate of Liquidated Damages will be restricted to the uncompleted/ undelivered value of work, the maximum Liquidated Damages being on the entire Contract value.

7.3 Programme

The Contractor shall submit a detailed time programme (resource based activity linked in the form of CPM/PERT network and financial progress in form of “S” curve) to the Engineer, for his consent, within the time as specified in the Appendix to Tender.

Page 57: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 30/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

The programme shall indicate the date of actual start, the monthly progress expected to be achieved and the anticipated completion date of each major item of work to be done by him, also indicating dates of procurement and setting up of materials, plant and machinery

The program submitted by the contractor shall also indicate the detailed input requirement and the stages from Employer/Engineer.

The schedule is to be such as is practicable of achievement towards the completion of the whole work in the time limit and of the particular items and/or milestones, if any, on the due date(s) as specified in the Appendix to Tender

No revised schedule shall be operative without acceptance in writing. The Engineer is further empowered to ask for more detailed schedule or schedules say weekly for any item or items, in case of urgency of work as will be directed by him and the Contractor shall supply the same as and when asked for.

The programme shall be accompanied by: a) Detailed project quality assurance plan b) Method statement(s) defining the Contractor’s methodology for construction c) Construction equipment planning and development duly supported with broad output

calculations and d) Details of the quality control procedures proposed to be adopted, justifying his capability

of achieving the completion of work in accordance with the milestones specified within the stipulated period of completion.

This submission shall be treated as BASE Programme for computation of delay/ time extensions etc.

The Contractor shall also submit a revised / recovery programme whenever the previous programme is inconsistent with actual progress or with the Contractor’s obligations.

Unless the Engineer, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Employer's Personnel shall be entitled to rely upon the programme when planning their activities.

The Contractor shall promptly give notice to the Engineer of specific probable future events or circumstances, which may adversely affect the work, increase the Contract Price or delay the execution of the Works. The Engineer may require the Contractor to submit an estimate of the anticipated effect of the future event or circumstances If, at any time, the Engineer gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor’s stated intentions, the Contractor shall submit a revised programme to the Engineer in accordance with this Sub-Clause., and/or a proposal under Sub-Clause 12.2 [Valuation Procedure].

Page 58: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 31/64

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – General Conditions of Contract RF

Construction of Auction Hall and Allied Infrastructure Works

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

7.4 Extension of Time for Completion

The Contractor shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 9.1 [Taking over of the Works and Sections] is or will be delayed by any of the following causes:

(a) A Variation (unless an adjustment to the Time for Completion has been agreed under

Sub-Clause 12.2 [Valuation Procedure]) or other substantial change in the quantity of an item of work included in the Contract,

(b) A cause of delay giving an entitlement to extension of time under a Sub-Clause of these Conditions,

(c) Exceptionally adverse climatic conditions,

(d) Any delay, impediment or prevention caused by or attributable to the Employer, the

Employer's Personnel, or the Employer's other Contractors on the Site.

If the Contractor considers himself to be entitled to an extension of the Time for Completion, the Contractor shall give notice to the Engineer in accordance with Sub-Clause 19.1 [Contractor’s Claims]. When determining each extension of time under Sub-Clause 19.1, the Engineer shall review previous determinations and may increase, but shall not decrease, the total extension of it.

Further, extension of Contract Period shall be decided by the Engineer with the prior approval of the Employer.

7.5 Delays Caused by Authorities

If the following conditions apply, namely:

(a) The Contractor has diligently followed the procedures laid down by the relevant

legally constituted public authorities in the Country,

(b) These authorities delay or disrupt the Contractor’s work, and

(c) The delay or disruption was unforeseeable,

Then this delay or disruption will be considered as a cause of delay under subparagraph (b) of Sub-Clause 7.4 [Extension of Time for Completion].

7.6 Rate of Progress

If, at any time:

(a) Actual progress is too slow to complete within the Time for Completion

(b) Progress has fallen (or will fall) behind the current programme under Sub-Clause 7.3 [Programme]

Page 59: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 32/64

Volume-I Contract Information – General Conditions of Contract RF

other than as a result of a cause listed in Sub-Clause 7.4 [Extension of Time for Completion], then the Engineer may instruct the Contractor to submit, under Sub-Clause 7.3 [Programme], a revised programme and supporting report describing the revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for Completion.

Unless the Engineer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in the working hours and/or in the numbers of Contractor’s Personnel and/or Goods, at the risk and cost of the Contractor. If these revised methods cause the Employer to incur additional costs, the Contractor shall pay these costs to the Employer based on the determination of the Engineer.

7.7 Contractor’s Responsibility

Notwithstanding the payment of liquidated damages if any under Sub-Clause 7.2, this shall not relieve the Contractor from his obligation to complete the work or from any other obligations / liabilities under this Contract.

7.8 Suspension of Work

The Engineer/Employer may at any time instruct the Contractor to suspend progress of part or all of the Works. During such suspension, the Contractor shall protect, store and secure such part or the Works against any deterioration, loss or damage.

The Engineer/Employer may also notify the cause for the suspension. If and to the extent that the cause is notified and is the responsibility of the Contractor, the following Sub Clauses 7.9, 7.10, and 7.11 shall not apply.

7.9 Consequences of Suspension

If the Contractor suffers delay and/or incurs Cost from complying with the Engineer’s instructions under Sub-Clause 7.8 [Suspension of Work] and. /or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to:

(a) An extension of time for any such delay, if completion is or will be delayed,

under Sub-Clause 7.4 [Extension of Time for Completion], and

(b) Payment of any such Cost, which shall be included in the Contract Price.

After receiving this notice, the Engineer shall proceed in accordance with Sub Clause

3.4 [Determinations] to agree or determine these matters.

The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor’s faulty design, workmanship or materials, or of the Contractor’s failure to protect, store or secure in accordance with Sub-Clause 7.8 [Suspension of Work].

Page 60: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 33/64

Volume-I Contract Information – General Conditions of Contract RF

7.10 Payment for Plant and Materials in event of Suspension

The Contractor shall be entitled to payment of the value (as at the date of suspension) of Plant and/or Materials which have not been delivered to Site, if:

(a) The work on Plant or delivery of Plant and/or Materials has been suspended for

more than 60 days, and

(b) The Contractor has marked the Plant and/or Materials as the Employer's property in accordance with the Engineer’s instructions.

7.11 Prolonged Suspension

If the suspension under Sub-Clause 7.8 [Suspension of Work] has continued for more than 84 days, the Contractor may request the Engineer’s permission to proceed. If the Engineer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Engineer, treat the suspension as an omission under Clause 12 [Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under Sub- Clause 15.2 [Termination by Contractor].

7.12 Resumption of Work

After the permission or instruction to proceed is given, the Contractor and the Engineer shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension.

8.0 TESTS ON COMPLETION

8.1 Contractor’s Obligations

The Contractor shall carry out all tests in accordance with this Clause and Sub Clause 6.4 [Testing], after providing the documents in accordance with sub-paragraph (d) of Sub- Clause 4.1 [Contractor’s General Obligations]. No additional charges on any such account shall be payable by the Employer.

The Contractor shall give to the Engineer not less than 21 days' notice of the date after which the Contractor will be ready to carry out each of the Tests on completion. Unless otherwise agreed, Tests on completion shall be carried out within 14 days after this date, on such day or days as the Engineer shall instruct.

In considering the results o f the Tests on Completion, the Engineer shall make allowances for the effect of any use of the Works by the Employer on the performance or other characteristics of the Works. As soon as the Works, or a Section, have passed any Tests on Completion, the Contractor shall submit a certified report of the results of these Tests to the Engineer.

Page 61: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 34/64

Volume-I Contract Information – General Conditions of Contract RF

8.2 Delayed Tests

If the Tests on Completion are being unduly delayed by the Employer, Sub-Clause 6.4 [Testing] (fifth paragraph) and/or Sub-Clause 9.3 [Interference with Tests on Completion] shall be applicable.

If the Tests on Completion are being unduly delayed by the Contractor, the Engineer may by notice require the Contractor to carry out the Tests within 21 days after receiving the notice. The Contractor shall carry out the Tests on such day or days within that period as the Contractor may fix and of which he shall give notice to the Engineer.

If the Contractor fails to carry out the Tests on Completion within the period of 21 days, the Employer's Personnel may proceed with the Tests at the risk and cost of the Contractor. The Tests on Completion shall then be deemed to have been carried out in the presence of the Contractor and the results of the Tests shall be accepted as accurate.

8.3 Retesting

If the Works, or a Section, fail to pass the Tests on Completion, Sub-Clause 6.5 [Rejection] shall apply, and the Engineer or the Contractor may require the failed Tests, and Tests on Completion on any related work, to be repeated under the same terms and conditions.

8.4 Failure to Pass Tests on Completion

If the Works, or a Section, fail to pass the Tests on Completion repeated under Sub Clause 8.3 [Retesting], the Engineer shall be entitled to:

(a) Order further repetition of Tests on Completion under Sub-Clause 8.3;

(b) If the failure deprives the Employer of substantially the whole benefit of the

Works or Section, reject the Works or Section (as the case may be), in which event the Employer shall have the same remedies as are provided in subparagraph (c) of Sub-Clause 10.4 [Failure to Remedy Defects]; or

(c) Issue a Taking-Over Certificate, if the Employer so requests. In the event of sub-paragraph (c), the Contractor shall proceed in accordance with all other obligations under the Contract, and the Contract Price shall be reduced by such amount as shall be appropriate to cover the reduced value to the Employer as a result of this failure. Unless the relevant reduction for this failure is stated (or its method of calculation is defined) in the Contract, the Employer may require the reduction to be (i) agreed by both Parties (in full satisfaction of this failure only) and paid before this Taking-Over Certificate is issued, or (ii) determined and paid under Sub-Clause 3.4 [Determinations].

9.0 EMPLOYER'S TAKING OVER

9.1 Taking over of the Works and Sections

Except as stated in Sub-Clause 8.4 [Failure to Pass Tests on Completion], the Works shall be taken over by the Employer when (i) the Works have been completed in accordance with the Contract, including the matters described in Sub-Clause 7.2 [Time for Completion] and except as allowed in sub-paragraph (a), below, and (ii) a Taking

Page 62: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 35/64

Volume-I Contract Information – General Conditions of Contract RF

Over Certificate for the Works has been issued, or is deemed to have been issued in accordance with this Sub- Clause. The Contractor may apply by notice to the Engineer for a Taking-Over Certificate not earlier- than 14 days before the Works will, in the Contractors opinion, be complete and ready for taking over. If the Works are divided into Sections, the Contractor may similarly apply for a Taking-Over Certificate for each Section.

The Engineer shall, within 28 days after receiving the Contractor’s application:

(a) Issue the Taking-Over Certificate to the Contractor, stating the date on which the Works or Section were completed in accordance with the Contract, except for any minor outstanding work and defects which will not substantially affect the use of the Works or Section for their intended purpose (either until or whilst this work is completed and these defects are remedied); or

(b) Reject the application, giving reasons and specifying the work required to be done

by the Contractor to enable the Taking-Over Certificate to be issued. The Contractor shall then complete this work before issuing a further notice under this Sub-Clause.

9.2 Taking Over of Parts of the Works The Engineer may, at the sole discretion of the Employer, issue a Taking-Over Certificate for any part of the Permanent Works.

The Employer shall not use any part of the Works (other than as a temporary measure which is either specified in the Contract or agreed by both Parties) unless and until the Engineer has issued a Taking-Over Certificate for this part. However, if the Employer does use any part of the Works before the Taking-Over Certificate is issued:

(a) The part which is used shall be deemed to have been taken over as from the date, on

which it is used,

(b) The Contractor shall cease to be liable for the care of such part as from this date, when responsibility shall pass to the Employer, and

(c) if requested by the Contractor, the Engineer shall issue a Taking-Over Certificate

for this part.

After the Engineer has issued a Taking-Over Certificate for a part of the Works, the Contractor shall be given the earliest opportunity to take such steps as may be necessary to carry out any outstanding Tests on Completion. The Contractor shall carry out these Tests on Completion as soon as practicable before the expiry' date of the relevant Defects Liability Period.

In case part / portions of work can be commissioned and port operates the portion for commercial purposes, the rates of Liquidated Damages will be restricted to uncompleted/ undelivered value of work beyond the stipulated date of completion. The defects liability period for the portions taken over in sections shall be as indicated in the Appendix to Tender.

9.3 Interference with Tests on Completion

If the Contractor is prevented, for more than 28 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible, the Employer shall

Page 63: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 36/64

Volume-I Contract Information – General Conditions of Contract RF

be deemed to have taken over the Works or Section (as the case may be) on the date when the Tests on Completion would otherwise have been completed.

The Engineer shall then issue a Taking-Over Certificate accordingly, and the Contractor shall carry out the Tests on Completion as soon as practicable, before the expiry date of the Defects Liability Period. The Engineer shall require the Tests on Completion to be carried out by giving 14 days notice and in accordance with the relevant provisions of the Contract.

If the Contractor suffers delay and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to:

(a) An extension of time for any such delay, if completion is or will be delayed, under

Sub-Clause 7.4 [Extension of Time for Completion], and (b) Payment of any such Cost, which shall be included in the Contract Price.

After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.4 [Determinations] to agree or determine these matters.

9.4 Surfaces Requiring Reinstatement

Except as otherwise stated in a Taking-Over Certificate, a certificate for a Section or part of the Works shall not be deemed to certify completion of any ground or other surfaces requiring reinstatement.

10.0 DEFECTS LIABILITY

10.1 Completion of Outstanding Work and Remedying Defects

In order that the Works in Contract documents and each Section, shall be in the condition required by the Contract (fair wear and tear excepted) by the expiry date of the relevant Defects Liability Period given in the Appendix to Tender or as soon as practicable thereafter, the Contractor shall:

(a) Complete any work which is outstanding on the date stated in a Taking-Over

Certificate, within such reasonable time as is instructed by the Engineer, and

(b) Execute all work required to remedy defects or damage, as may be notified by (or on behalf of) the Employer on or before the expiry date of the Defects Liability Period for the Works or Section (as the case may be).

If a defect appears or damage occurs, the Contractor shall be notified accordingly, by (or on behalf of) the Employer.

10.2 Cost of Remedying Defects

All work referred to in sub-paragraph (b) of Sub-Clause 10.1[Completion of Outstanding Work and Remedying Defects] shall be executed at the risk and cost of the Contractor, if and to the extent that the work is attributable to:

(a) Any design for which the Contractor is responsible,

Page 64: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 37/64

Volume-I Contract Information – General Conditions of Contract RF

(b) Plant, Materials or workmanship not being in accordance with the Contract, or

(c) Failure by the Contractor to comply with any other obligation. 10.3 Extension of Defects Liability Period

The Employer shall be entitled to an extension of the Defects Liability Period for the Works or a Section if and to the extent that the Works, Section or a major item of Plant (as the case may be, and after taking over) cannot be used for the purposes for which they are intended by reason of a defect or damage. However, a Defects Liability Period shall not be extended by more than two years.

If delivery and/or erection of Works was suspended under Sub Clause 7.8 [Suspension of Work] or Sub-Clause 15.1 [Contractor’s Entitlement to Suspend Work], the Contractors obligations under this Clause shall not apply to any Defects or damage occurring more than two years after the Defects Liability Period for the Plant and/or Materials would otherwise have expired.

10.4 Failure to Remedy Defects

If the Contractor fails to remedy any defect or damage within a reasonable time, a date may be fixed by (or on behalf of) the Employer, on or by which the defect or damage is to be remedied. The Contractor shall be given reasonable notice of this date. If the Contractor fails to remedy the defect or damage by this notified date the Employer may (at his option) carry out the work himself or by others, at the Contractor’s risk and cost.

If the defect or damage deprives the Employer of substantially the whole benefit of the Works or any major part of the Works, terminate the Contract as a whole, or in respect of such major part, which cannot be put to the intended use. Without prejudice to any other rights; under the Contract or otherwise, the Employer shall then be entitled to recover all sums paid for the Works or for such part (as the case may be), plus financing costs and the cost of dismantling the same, clearing the Site and returning Plant and Materials to the Contractor.

10.5 Removal of Defective Work

If the defect or damage cannot be remedied expeditiously on the Site and the Employer gives consent, the Contractor may remove from the Site for the purposes of repair such items of Plant as are defective or damaged. This consent may require the Contractor to increase the amount of the Performance Security by the full replacement cost of these items, or to provide other appropriate security.

10.6 Further Tests

If the work of remedying of any defect or damage may affect the performance of the Works, the Engineer may require the repetition of any of the tests described in the Contract. The requirement shall be made by notice within 28 days after the defect or damage is remedied These tests shall be carried out in accordance with the terms applicable to the previous tests, except that they shall be carried out at the risk and cost of the Party

Page 65: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 38/64

Volume-I Contract Information – General Conditions of Contract RF

liable, under Sub-Clause 10.2 [Cost of Remedying Defects], for the cost of the remedial work.

10.7 Right of Access

Until the Performance Certificate has been issued, the Contractor shall have such right of access to the Works as is reasonably required in order to comply with this Clause, except as may be inconsistent with the Employers reasonable security restrictions.

10.8 Contractor to Search

The Contractor shall, if required by the Engineer, search for the cause of any defect, under the direction of the Engineer. Unless the defect is to be remedied at the cost of the Contractor under Sub-Clause 10.2 [Cost of Remedying Defects], the Cost of the search shall be agreed or determined by the Engineer in accordance with Sub-Clause 3.4 [Determinations] and shall be included in the Contract Price.

10.9 Performance Certificate

Performance of the Contractor’s obligations shall not be considered to have been completed until the Engineer has issued the Performance Certificate to the Contractor, stating the date on which the Contractor completed his obligations under the Contract.

The Engineer shall issue the Performance Certificate within 28 days after the latest of the expiry dates of the Defects Liability Periods after completion of every section, length of which shall be determined by the Engineer, unless otherwise stated in Special Conditions of Contract or as soon thereafter as the Contractor has supplied all the Contractor’s Documents and completed and tested all the Works, including remedying any defects. A copy of the Performance Certificate shall be issued to the Employer. Only the Performance Certificate shall be deemed to constitute acceptance of the Works.

10.10 Unfulfilled Obligations

After the Performance Certificate has been issued, each Party shall remain liable for the fulfillment of any obligation, which remains unperformed at that time. For the purposes of determining the nature and extent of unperformed obligations, the Contract shall be deemed to remain in force.

10.11 Clearance of Site

Upon receiving the Performance Certificate, the Contractor shall remove any remaining Contractor’s Equipment, surplus material, wreckage, rubbish and Temporary Works from the Site.

If all these items have not been removed within 28 days after the Employer receives a copy of the Performance Certificate, the Employer may sell or otherwise dispose of any remaining items. The Employer shall be entitled to be paid the costs incurred in

Connection with, or attributable to, such sale or disposal and restoring the Site.

Page 66: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 39/64

Volume-I Contract Information – General Conditions of Contract RF

Any balance of the moneys from the sale shall be paid to the Contractor. If these moneys are less than the Employer’s costs, the Contractor shall pay the outstanding balance to the Employer.

11.0 MEASUREMENT AND EVALUATION

11.1 Works to be Measured

The Works shall be measured, and valued for payment, in accordance with this Clause. Whenever the Engineer requires any part of the Works to be measured, reasonable notice shall be given to the Contractor’s Representative, who shall:

(a) Promptly either attend or send another qualified representative to assist the Engineer

in making the measurement, and

(b) Supply any particulars requested by the Engineer.

If the Contractor fails to attend or send a representative, the measurement made by (or on behalf of) the Engineer shall be accepted as accurate.

Except as otherwise stated in the Contract, wherever any Permanent Works are to be measured from records, these shall be prepared by the Engineer. The Contractor shall, as and when requested, attend to examine and agree the records with the Engineer, and shall sign the same when agreed. If the Contractor does not attend, the records shall be accepted as accurate.

If the Contractor examines and disagrees the records, and/or does not sign them as agreed, then the Contractor shall give notice to the Engineer of the respects in which the records are asserted to be inaccurate. After receiving this notice, the Engineer shall review the records and either confirm or vary them. If the Contractor does not so give notice to the Engineer within 14 days after being requested to examine the records, they shall be accepted as accurate.

11.2 Method of Measurement

Except as otherwise stated in the Contract and notwithstanding local practice:

(a) Measurement shall be made of the net actual quantity of each item of the Permanent Works, and

(b) The method of measurement shall be in accordance with the Bill of Quantities

or other applicable Schedules.

11.3 Evaluation

Except as otherwise stated in the Contract, the Engineer shall proceed in accordance with Sub-Clause 3.4 [Determinations] to agree or determine the Contract Price by evaluating each item of work, applying the measurement agreed or determined in accordance with the above Sub-Clauses 11.1 and 11.2 and the appropriate rate or price for the item.

For each item of work, the appropriate rate or price for the item shall be the rate or price specified for such item in the Contract.

Page 67: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 40/64

Volume-I Contract Information – General Conditions of Contract RF

11.3.1 However, a new rate or price shall be applicable for such item(s) of work existing in

Contract if the measured quantity of the item varies by more than 25% from the quantity of this item as indicated in the Bill of Quantities, or other schedule and subject to a condition that the amount provided of such item in BOQ exceeds 5 % of accepted total contract amount. For the purpose of clarity no change in the rate or price of any item contained in the Contract shall be considered unless such item accounts for more than 5% of the Contract Amount and the actual quantity of work executed under the item exceeds or falls short of the quantity set out in the Bill of Quantities by more 25%. The revised/modified rates for such items shall only be applicable for those quantities exceeding 125%. Incase of reduction in quantity by more than 25% the rate of entire quantity shall be fixed considering the incidence of commitments made by the contractor.

11.3.2 The new rate or price shall also be appropriate for the items instructed under Clause 12

[Variations and Adjustments], where no rate or price is specified in the Contract for this item.

While determination of the new/revised rates following order of working shall be followed

(a) The rates shall be derived from the rates of item of similar nature existing in the

Bill of Quantities. (No rate as agreed in Day Work shall be applicable while determination, since Day work schedule, if provided in contract, is applicable for the incidental works only for total amount not exceeding 1% of the contract amount.)

(b) The rates shall be derived by Detailed Rate analysis based on

appropriate supporting documents as required for determining the rate of labour/material/plant/equipment etc allowing 15% towards contractors overheads and profits. For determination of such rates engineer shall call for detailed rate analysis from the contractor.

Until such time as an appropriate rate or price is agreed or determined, the Engineer shall determine a provisional rate or price for the purposes of Interim Payment Certificates.

11.4 Omissions

Whenever the omission of any work forms part (or all) of a Variation, the engineer in consultation with Employer and contractor shall determine the value of such Omission.

12.0 VARIATIONS AND ADJUSTMENTS 12.1 Right to Vary

The Engineer shall make any variation of the form, quality or quantity of the works or any part thereof that may, in his opinion, be necessary and for that purpose, or if for any other reason it shall, in his opinion, be appropriate, he shall have the authority to instruct the Contractor to do and the Contractor shall do any of the following.

(a) Increase or decrease the quantity of any work included in the Contract.

Page 68: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 41/64

Volume-I Contract Information – General Conditions of Contract RF

(b) Omit any such work (partially or fully). (c) Change the character or quality or kind of any such work. (d) Change the levels, lines, position and dimension of any part of the work. (e) Execute additional work of any kind necessary for the completion of the work. (f) Change any specified sequence or timing of any work of any part of the works. No such variation shall in any way vitiate or invalidate the Contract, but the effect, if any, of all such variations shall be valued in accordance with Sub-Clause 12.2, provided that where the issue of an instruction to vary the works is necessitated by some default of or breach of Contract by the Contractor or for which he is responsible, any additional cost attributable to such default shall be borne by the Contractor.

The Contractor shall not make any variation without an instruction of the Engineer. Provided that no instruction shall be required for increase or decrease in the quantity of any work where such increase or decrease is not the result of an instruction given under this clause but is the result of the quantities exceeding or being less than those stated in the Bill of Quantities.

12.2 Valuation Procedure

All variations referred to in Sub-Clause 12.1 (also referred to Sub-Clause 1.2.4 of Volume IV, Preamble and Bill of Quantities) shall be valued in the manner as set out under sub-clause 11.3 [Evaluation ]

12.3 Payment in Applicable Currencies

All the payments under this Contract shall be made in the currency indicated in the Appendix to Tender.

12.4 Provisional Sums

Each Provisional Sum shall only be used, in whole or in part, in accordance with the

Engineer’s instructions and the Contract Price shall be adjusted accordingly. The total sum paid to the Contractor shall include only such amounts, for the work, supplies or services which the Provisional Sum relates, as the Engineer shall have instructed. For each to Provisional Sum, the Engineer may instruct:

(a) Work to be executed (including Plant, Materials or services to be supplied) by the

Contractor and valued under Sub-Clause 12.2 [Valuation Procedure]; and/or

(b) Plant, Materials or services to be purchased by the Contractor from a Nominated subcontractor, or otherwise and for which there shall be included in the Contract Price:

(i) The actual amounts paid (or due to be paid) by the Contractor, and

(ii) A sum for overhead charges and profit, calculated as a percentage of these

actual amounts by applying the relevant percentage rate (if any) stated in the appropriate Schedule.

The Contractor shall when required by the Engineer, produce quotations, invoices, vouchers and accounts or receipts in substantiation.

12.5 Adjustments for Changes in Legislation

Page 69: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 42/64

Volume-I Contract Information – General Conditions of Contract RF

The Contract Price shall be adjusted to take account of any increase or decrease in Cost resulting from a change in the Laws of the Country (including the introduction of new Laws and the repeal or modification of existing Laws) or in the judicial or official governmental interpretation of such Laws, made after the Base Date, which affect the Contractor in the performance of his obligations under the Contract.

If the Contractor suffers (or will suffer) delay and/or incurs (or will incur) additional Cost as a result of these changes in the Laws or in such interpretations, made after the Base Date, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 19.1 [Contractor’s Claims] to:

(a) An extension of time for any such delay, if completion is or will be delayed, under

Sub-Clause 7.4 [Extension of Time for Completion], and

(b) Payment of any such Cost, which shall be included in the Contract Price.

After receiving this notice, the Engineer shall proceed in accordance with Sub Clause 3.4 [Determinations] to agree or determine these matters.

13.0 CONTRACT PRICE AND PAYMENT

13.1 The Contract Price

The Contact Price shall be agreed and be subject to adjustments in accordance with the Contract;

(a) The Contractor shall pay all taxes, duties and fees required to be paid by him under

the Contract, and the Contract Price shall not be adjusted for any of these costs

except as stated in Sub-Clause 12.5 [Adjustments for Changes in Legislation] (b) GST as applicable will be reimbursed as per clause No. 26

(c) Any quantities which may be set out in the Bill of Quantities or other Schedule are estimated quantities and are not to be taken as the actual and correct quantities:

(i) of the Works which the Contractor is required to execute, or (ii) for the purposes of Clause 11 [Measurement and Evaluation];

13.2 Advance payment 13.2.1 Mobilization advance

DELEATED

13.2.2 Secured Advance against Materials Brought to the Site

The Contractor shall be entitled for secured advance against following specified materials only

1 Cement

2 Reinforcement Steel

3 Structural Steel

Page 70: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 43/64

Volume-I Contract Information – General Conditions of Contract RF

4 Any specialized manufactured item as approved by Employer. The amount o f advance will be 75% of the cost of specified manufactured material subject to following conditions:

a) The materials are required for the Permanent works.

b) The materials are brought to the site.

c) The cost of individual consignment of materials exceeds Rs.10,00,000/-

d) The materials are inspected, tested and approved by the Engineer or his Representative.

e) The materials are stored in a proper and efficient manner to the satisfaction of the

Engineer or his Representative.

f) The advance is claimed by the Contractor in writing by way of a detailed statement attached to the interim bills after getting the statement duly verified by the Engineer’s Representative. Contractors shal l provide all necessary documents including documents related to payment details for such verification by the Engineer’s Representative.

g) The advance shall not exceed seventy five percent (75%) of the voucher value of the

manufactured materials OR seventy five percent (75%) of the value as assessed by the Engineer OR seventy five percent (75%)of the above material component cost in the tendered rates for the finished items of work, whichever is the lowest. Vouchers for the materials in support of price and ownership shall be submitted along with the statement mentioned in (f) above.

h) No advance will be paid against materials supplied by the Employer.

i) The materials against which advance is claimed shall be insured against

theft/misappropriation/fire.

j) There shall be no lien or encumbrance of any nature on the Materials.

Materials on which the Contractor intends to claim Material Advance shall be procured by the Contractor at his own cost and brought to the site for permanent works subject to following additional conditions:

(a) Materials brought at site are of approved quality, they are required for incorporation

in Permanent work and

(b) Quantity of such materials is reasonable bearing in mind the requirements of works

and the shelf life of the material.

(c) The advance shall be claimed by way of a detailed statement attached to the interim

bills and after getting the statement duly verified by the Engineer’s Representative.

(d) The advance claimed in statement should be supported by photocopies of

vouchers in the name of the Contractor for materials procured by the Contractor.

Page 71: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 44/64

Volume-I Contract Information – General Conditions of Contract RF

(e) In case if other insurance policies are not covering, the Contractor shall take separate insurance policy/policies to cover materials under advance against theft/misappropriation/fire.

The advance paid will be fully recovered through the next bill in which a fresh advance will be paid for the materials then at site, subject to the conditions stipulated in the Contract. No advance will be paid after eighty percent (80%) of the work is completed.

The materials on which advance has been paid shall not be removed from the site. In case of any such removal, no further material advance will be paid to the Contractor. Further, the removal of such materials from the site shall be treated as a criminal breach of trust.

The Contractor shal l provide facilities for inspection and stock-taking o f the materials whenever required by the Engineer.

The Employer will have a lien on all the materials against which advance has been paid.

13.3 Escalation / Price Variation – No escalation will be allowed.

The quoted price shall remain fixed and no adjustment in the Contract Price shall be done on account of rises or falls in the cost of labour, POL and material inputs to the work.

13.4 Application for Interim Payment Certificates

The Contractor shall submit a Statement in four copies to the Engineer after the end of each month, in a form approved by the Engineer, showing in detail the amounts to which the Contractor considers himself to be entitled, together with supporting documents which shall include the report on the progress during this month in accordance with Sub-Clause 4.20 [ Progress reports].

The Statement shall include the following items, as applicable, which shall be expressed in the currencies in which the Contract Price is payable, in the sequence listed:

a) The Contract value of the Works executed and the Contractor’s Documents

produced up to the end of the month (including 'variations but excluding items described in sub-paragraphs (b) to (f) below);

b) Any amounts to be added and deducted for changes in legislation and changes in cost, in accordance with Sub-Clause 12.5 [Adjustments for Changes in Legislation] and Sub- Clause 13.3 [Escalation / Price variation].

c) Any amount to be deducted for retention, calculated by applying the percentage of

retention stated in the Appendix to Tender to the total of the above amounts;

d) Any amounts to be deducted towards repayments of advances in accordance with

Sub- Clause 13.2 [Secured Advance against Materials Brought to the Site];

Page 72: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 45/64

Volume-I Contract Information – General Conditions of Contract RF

e) Any other additions or deductions which may have become due under the Contract or otherwise, including those under Clause 19 [Claims, Disputes and Arbitration]; and

f) The deduction of amounts certified in all previous Payment Certificates.

13.5 Schedule of Payments

The installments quoted in this schedule of payments shall be the estimated Contract values for the purposes of sub-paragraph (a) of Sub-Clause 13.4 [Application for Interim Payment Certificates] subject to a minimum value as stated in Appendix to the Tender.

If the minimum value as stated above is not reached, contractor will skip the installment till it reaches to the minimum value.

13.6 Issue of Interim Payment Certificates

No amount will be certified or paid until the Employer has received and approved the Performance Security. Thereafter, the Engineer shall, within 10 days after receiving a Statement and supporting documents, issue to the Employer an Interim Payment Certificate, which shall state the amount, which the Engineer fairly determines to be due, with supporting particulars. No bill would be processed until all the supporting documents have been submitted.

However, prior to issuing the Taking-Over Certificate for the Works, the Engineer shall not be bound to issue an Interim Payment Certificate in an amount which would (after retention and other deductions) be less than the minimum amount of Interim Payment Certificates (if any) stated in sub-clause 13.5 [Schedule of payments]. In this event, the Engineer shall give notice to the Contractor accordingly.

An Interim Payment Certificate shall not be withheld for any un-disputed bill for any other

Reason, although”

(a) If anything supplied or work done by the Contractor is not in accordance with the Contract, the cost of rectification or replacement may be withheld until rectification or replacement has been completed; and/or

(b) If the Contractor was or is falling to perform any work or obligation in accordance

with the Contract, and had been so notified by the Engineer, the value of this work or obligation may be withheld until the work or obligation has been performed.

The Engineer may in any Payment Certificate make any correction or modification that should properly be made to any previous Payment Certificate. A Payment Certificate shall not be deemed to indicate the Engineer’s acceptance, approval, consent or satisfaction.

13.7 Payment

The Employer shall pay to the Contractor:

Page 73: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 46/64

Volume-I Contract Information – General Conditions of Contract RF

(a) The amount certified in each Interim Payment Certificate within 30 days after the Engineers certificate of the Interim Payment. However, 70% of the invoice amount will be paid within 15 working days on certification / invoice and balance within 30 days on full verification.

(b) The amount certified in the Final Payment Certificate within 90 days after

the Employer receives this Payment Certificate.

Payment of the amount due shall be made into the bank account, nominated by the Contractor.

13.8 Delayed Payment

DELEATED

13.9 Retention Money

Retention money shall be deducted from each running bill at the rate of 5% subject to a maximum accumulation of 5% of Contract Price. After reaching 2.5% of the Contract Price, as retention money, the Contractor can replace it by a Bank Guarantee of an equivalent amount. Balance Retention Money will be continued to be deducted through Interim Bills at the rate of 5% of the Bill amount.

The Bank guarantee against retention money (2.5% of contract value) will be returned to the contractor within 30 days from the start of Defects Liability Period. The balance cash retention money (2.5% of the contract value) will be released at the end of Defects Liability Period.

When calculating these proportions, no account shall be taken of any adjustments under Sub-Clause 12.5 [Adjustments for Changes in Legislation] and Sub-Clause 13.3 [Escalation / Price Variation].

13.10 Statement at Completion

Within 28 days after receiving the Taking-Over Certificate for the Works, the Contractor shall submit to the Engineer four copies of a Statement at completion with supporting documents, in accordance with Sub-Clause 13.4 [Application for Interim Payment Certificates], showing:

(a) The value of all work done in accordance with the Contract up to the date stated

in the Taking-Over Certificate for the Works,

(b) Any further sums which the Contractor considers to be due, and

(c) An estimate of any other amounts, which the Contractor considers, will become due to

him under the Contract. Estimated amounts shall be shown separately in this Statement at completion.

The Engineer shall then certify in accordance with Sub-Clause 13.6 [Issue of Interim [Payment Certificates.]

13.11 Application for Final Payment Certificate

Page 74: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 47/64

Volume-I Contract Information – General Conditions of Contract RF

Within 56 days after receiving the Taking over Certificate of the last part, the Contractor shall Submit, to the Engineer, six copies of a draft final statement with supporting documents showing in detail in a form approved by the Engineer:

(a) The value of all work done in accordance with the Contract,and

(b) Any further sums which the Contractor considers to be due to him under the

Contract or otherwise.

If the Engineer disagrees with or cannot verify any part of the draft final statement, the Contractor shall submit such further information as the Engineer may reasonably require and shall make such changes in the draft as may be agreed between them. The Contractor shall then prepare and submit to the Engineer the final statement as agreed. This agreed statement is referred to in these Conditions as the "Final Statement".

However if, following discussions between the Engineer and the Contractor on the draft final statement, if the disagreement still exists, it becomes evident that a dispute exists. In this event the Engineer shall deliver to the Employer (with a copy to the Contractor) an Interim Payment Certificate for the agreed parts of the draft final statement Thereafter, if the dispute is finally resolved under Sub-Clause 19.2 [Amicable Settlement], the Contractor shall then prepare and submit to the Employer (with a copy to the Engineer) a Final Statement.

13.12 Discharge

When submitting the Final Statement, the Contractor shall submit a written discharge, which confirms that the total of the Final Statement represents full and final settlement of all moneys due to the Contractor under or in connection with the Contract. This discharge may state that it becomes effective when the Contractor has received the Performance Security and the outstanding balance of this total, in which event the discharge shall be effective on such date.

13.13 Issue of Final Payment Certificate

Within 28 days after receiving the Final Statement and written discharge in accordance with Sub-Clause 13.11 [Application for Final Payment Certificate] and Sub-Clause 13.12 [Discharge], the Engineer shall issue, to the Employer, the Final payment Certificate which shall state:

(a) the amount which is finally due and

(b) after giving credit to the Employer for all amounts previously paid by

the Employer and for all sums to which the Employer is entitled, the balance (if any) due from the Employer to the Contractor or from the Contractor to the Employer, as the case may be.

If the Contractor has not applied for a Final Payment Certificate in accordance with Sub- Clause 13.11 [Application for Final Payment Certificate] and Sub-Clause 13.12 [Discharge], the Engineer shall request the Contractor to do so. If the Contractor fails to submit an application within a period of 28 days, the Engineer shall issue the Final Payment Certificate for such amount as he fairly determines to be due.

13.14 Cessation of Employer's Liability

Page 75: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 48/64

Volume-I Contract Information – General Conditions of Contract RF

The Employer shall not be liable to the Contractor for any matter or thing under or in connection with the Contract or execution of the Works, except to the extent that the Contractor shall have included an amount expressly for it:

(a) In the Final Statement and also

(b) (Except for matters or things arising after the issue of the Taking- Over Certificate for the Works) in the Statement at completion described in Sub Clause 13.10 [Statement at Completion].

13.15 Currencies of Payment

The Contract Price shall be paid in the Indian Rupees

14.0 TERMINATION BY EMPLOYER 14.1 Notice to Correct

If the Contractor fails to carry out any obligation under the Contract, the Engineer may by notice require the Contractor to make good the failure and to remedy it within a specified reasonable time.

14.2 Termination by Employer

The Employer shall be entitled to terminate the Contract if the Contractor:

(a) Fails to comply with Sub-Clause 4.2 [Performance Security] or with a notice under Sub-Clause 14.1 [Notice to Correct],

(b) Abandons the Works or otherwise plainly demonstrates the intention not to continue

performance of his obligations under the Contract,

(c) Without reasonable excuse fails:

(i) To proceed with the Works in accordance with Clause 7 [Commencement, Delays and Suspension], or

(ii) To comply with a notice Issued under Sub-Clause 6.5 [Rejection] or Sub

Clause 6.6 [Remedial Work], within 28 days after receiving it.

(d) Sub-Contracts the whole of the Works or assigns the Contract without the required agreement,

(e) Becomes bankrupt or insolvent, goes into liquidation, has a receiving or

administration order - made against him, compounds with his creditors, or carries on business under a receiver, trustee or manager for the benefit of his creditors, or if any act is done or event occurs which (under applicable Laws) has a similar effect to any of these acts or events, or

(f) Gives or offers to give (directly or indirectly) to any person any bribe, gift, gratuity,

commission or other thing of value, as an inducement or reward:

(i) For doing or forbearing to do any action in relation to the Contract,

(ii) For showing or forbearing to show favour or disfavour to any person in relation to the Contract

Page 76: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 49/64

Volume-I Contract Information – General Conditions of Contract RF

Or if any of the Contractor’s Personnel, agents or Sub-Contractors gives or offers to give (directly or indirectly) to any person any such inducement or reward as is described in this sub-paragraph (f). However lawful inducements and rewards to Contractor’s Personnel shall not entitle termination.

(g) When the cap for the liquidated damages have been reached;

In any of these events or circumstances, the Employer may, upon giving 14 days notice to the Contractor terminate the Contract and expel the Contractor from the Site. However, in the case of sub-paragraph (e) or (f), the Employer may by notice terminate the Contract immediately. The Employer's election to terminate the Contract shall not prejudice any other rights of the Employer, under the Contract or otherwise. The Contractor shall then leave the Site and deliver all required Goods, all Contractors’ Documents, and other design documents made by or for him, to the Engineer. However, the Contractor shall use his best efforts to comply immediately with any reasonable instructions included in the notice (i) for the assignment of any Sub- Contract, and (ii) for the protection of life or property or for the safety of the Works.

After termination, the Employer may complete the Works and/or arrange for any other entities to do so. The Employer and these entities may then use any Goods, Contractor’s Documents and other design documents made on behalf of the Contractor.

The Employer shall then give notice that the Contractor’s Equipment and Temporary Works will be released to the Contractor at or near the Site. The Contractor shall promptly arrange their removal, at the risk and cost of the Contractor. However, if by this time the Contractor has failed to make a payment due to the Employer, these items may be sold by the Employer in order to recover this payment. Any balance of the proceeds shall then be paid to the Contractor.

14.3 Valuation at Date of Termination

As soon as practicable after a notice of termination under Sub-Clause 14.2 [Termination by Employer] has taken effect, the Engineer shall proceed in accordance with Sub Clause 3.4 [Determinations] to agree or determine the value of the Works, Goods and Contractor’s Documents, and any other sums due to the Contractor for work executed in accordance with the Contract.

14.4 Payment after Termination

After a notice of termination under Sub-Clause 14.2 [Termination by Employer] has taken effect, the Employer may:

(a) Proceed in accordance with Sub-Clause 2.4 [Employer's Claims],

(b) Withhold further payments to the Contractor until the costs of execution, completion and remedying of any defects, damages for delay in completion (if any), and all other costs incurred by the Employer, have been established, and/or

(c) Recover from the Contractor any losses and damages incurred by the Employer and

any extra costs of completing the Works, after allowing for any sum due to the

Page 77: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 50/64

Volume-I Contract Information – General Conditions of Contract RF

Contractor under Sub-Clause 14.3 [Valuation at Date of Termination]. After recovering any such losses, damages and extra costs, the Employer shall pay any balance to the Contractor.

14.5 Employer’s Entitlement to Termination The Employer shall be entitled to terminate the Contract, at any time for the Employer's Convenience, by giving notice of such termination to the Contractor. The termination shall take effect 28 days after the later of the dates on which the Contractor receives this notice or the Employer returns the Performance Security. The Employer shall not terminate the Contract under this Sub-Clause in order to execute the Works himself or to arrange for the Works to be executed by another Contractor. After this termination, the Contractor shall proceed in accordance with Sub Clause 15.3 [Cessation of Work and Removal of Contractor’s Equipment] and shall be paid in accordance with Sub-Clause 18.6 [Optional Termination, Payment and Release].

15.0 SUSPENSION AND TERMINATION BY CONTRACTOR 15.1 Contractor’s Entitlement to Suspend Work

If the Engineer fails to certify in accordance with Sub-Clause 13.6 [Issue of Interim Payment Certificates] or Sub-Clause 13.7 [Payment], the Contractor may, after giving not less than 28 days' notice to the Employer, on expiry of the notice period, suspend work (or reduce the rate of work) unless and until the Contractor has received the Payment Certificate, reasonable evidence or payment, as the case may be and as described in the notice.

The Contractor’s action shall not prejudice his entitlements to financing charges under Sub - Clause 13.8 [Delayed Payment] and to termination under Sub-Clause15.2 [Termination by Contractor].

If the Contractor subsequently receives such Payment Certificate, evidence or payment (as described in the relevant Sub-Clause and in the above notice.) before giving a notice of termination, the Contractor shall resume normal working as soon as is reasonably practicable.

15.2 Termination by Contractor

The Contractor shall be entitled to terminate the Contract if: (a) The Engineer fails, within 56 days after receiving a Statement and supporting

documents; to issue the relevant Payment Certificate except where the Bill is disputed,

(b) The Contractor does not receive the amount due under an Interim

Payment Certificate within 60 days after the expiry of the time stated in Sub-Clause 13.7 [Payment] within which payment is to be made (except for deductions in accordance with Sub-Clause 2.4 [Employer's Claims]) and/or where Payment Certificate is withheld in respect of Disputed Bill(s),

(c) The Employer substantially fails to perform his obligations under the Contract

(d) The Employer fails to comply with Sub-Clause 1.6 [Contract Agreement]

(e) A prolonged suspension affects the whole of the Works as described in Sub Clause 7.11 [Prolonged Suspension], or

Page 78: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 51/64

Volume-I Contract Information – General Conditions of Contract RF

In any of these events or circumstances, the Contractor may, upon giving 28 days' notice to the Employer, terminate the Contract.

The Contractor’s election to terminate the Contract shall not prejudice any other rights of the Contractor, under the Contract or otherwise.

15.3 Cessation of Work and Removal of Contractor’s Equipment

After a notice of termination under Sub-Clause 14.5 [Employer's Entitlement to

Termination], Sub-Clause 15.2 [Termination by Contractor] or Sub-

Clause18.6 [Optional Termination, Payment and Release] has taken effect, the

Contractor shall promptly:

(a) Cease all further work, except for such work as may have been instructed by the Engineer for the protection of life or property or for the safety of the Works, (b) Hand over Contractor’s Documents, Plant, Materials and other work, for which the

Contractor has received payment, and

(c) Remove all other Goods from the Site, except as necessary for safety, and leave the Site.

15.4 Payment on Termination

After a notice of termination under Sub-Clause 15.2 [Termination by Contractor] has taken effect, the Employer shall :

(a) Return the Performance Security to the Contractor as soon as possible in any case

not later than 90 days, (b) Pay the Contractor in accordance with Sub-Clause 18.6 [Optional Termination,

Payment and Release], and 16.0 RISK AND RESPONSIBILITY

16.1 Indemnities

The Contractor shall indemnify and hold harmless the Employer, the Employer's Personnel, and their respective agents, against and from all claims, damages, losses and expenses (including legal fees and expenses) in respect of:

(a) Bodily injury, sickness, disease or death, of any person whatsoever arising out of or

In the course of or by reason of the Contractor’s design (if any), the execution and completion of the Works and the remedying of any defects, unless attributable to any negligence, wilful act or breach of the Contract by the Employer, the Employer's Personnel, or any of their respective agents, and

(b) Damage to or loss of any property, real or personal (other than the Works), to the extent that such damage or loss:

(i) Arises out of or in the course of or by reason of the Contractor’s design

(if any), the execution and completion of the Works and the remedying of any defects, and

Page 79: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 52/64

Volume-I Contract Information – General Conditions of Contract RF

(ii) Is attributable to any negligence, wilful act or breach of the Contract by the

Contractor, the Contractor’s Personnel, their respective agents, or anyone directly or indirectly employed by any of them.

(c) Intellectual property rights and violation of any law viz, labour laws etc.

The Employer shall indemnify and hold harmless the Contractor, the Contractor’s Personnel, and their respective agents, against and from all claims; damages, losses and expenses (including legal fees and expenses) which is attributable to any negligence, wilful act or breach of the Contract by the Employer, and (2) the matters for which the liability may be excluded from Insurance cover, as applicable and described in Sub-Clause 17

16.2 Contractor’s Care of the Works

The Contractor shall take full responsibility for the care of the Works and Goods from the Commencement Date until the Taking-Over Certificate is issued (or is deemed to be issued under Sub-Clause 9.1 [Taking Over of the Works and Sections]) for the works, when responsibility for the care of the Works shall pass to the Employer. If a Taking- Over Certificate is issued (or is so deemed to be issued) for any Section or part of the Works, responsibility for the care of the Section or part shall then pass to the Employer.

After responsibility has accordingly passed to the Employer, the Contractor shall take responsibility for the care of any work, which is outstanding on the date stated in a Taking-Over Certificate, until this outstanding work has been completed.

If any loss or damage happens to the Works, Goods or Contractor’s Documents during the period when the Contractor is responsible for their care, from any cause not listed in Sub- Clause 16.3 [Employer's Risks], the Contractor shall rectify the loss or damage at the Contractor’s risk and cost, so that the Works, Goods and Contractor’s Documents confirm with the Contract.

The Contractor shall be liable for any loss or damage caused by any actions performed by the Contractor after a Taking-Over Certificate has been issued. The Contractor shall also be liable for any loss or damage, which occurs after a Taking Over Certificate, has been issued and which arose from a previous event for which the Contractor was liable.

16.3 Employer's Risks

The risks referred to in Sub-Clause 16.4 below are:

(a) War, hostilities (whether war be declared or not), invasion, act of foreign enemies,

(b) Rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war, within the Country,

(c) Riot, commotion or disorder within the Country by persons other than the

Contractor’s Personnel and other employees of the Contractor and Sub- Contractors,

Page 80: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 53/64

Volume-I Contract Information – General Conditions of Contract RF

(d) Munitions of war, explosive materials, ionising radiation or contamination by

radioactivity, within the Country, except as may be attributable to the Contractor’s use of such munitions, explosives, radiation or radioactivity,

(e) Pressure waves caused by aircraft or other aerial devices travelling at sonic

or supersonic speeds,

(f) Design of any part of the Works by the Employer's Personnel or by others for whom the Employer is responsible, and

16.4 Consequences of Employer's Risks

If and to the extent that any of the risks listed in Sub-Clause 16.3 above results in loss or damage to the Works, Goods or Contractor’s Documents, the Contractor shall promptly give notice to the Engineer and shall rectify this loss or damage to the extent required by the Engineer. If the Contractor suffers delay and/or incurs cost from rectifying this loss or damage, the Contractor shall give a further notice to the Engineer and shall be entitled subject to Sub- Clause 19.1 [Contractor’s Claims] to:

(a) An extension of time for any such delay, if completion is or will be delayed,

under Sub-Clause 7.4 [Extension of Time for Completion], and

(b) Payment of any such Cost, which shall be, included in the Contract Price in the case of sub-paragraphs (f) and (g) of Sub-Clause 16.3 [Employer's Risks], on the Cost shall also be included.

After receiving this further notice, the Engineer shall proceed in accordance with SubClause 3.4 [Determinations] to agree or determine these matters.

16.5 Intellectual and Industrial Property Rights

In this Sub-Clause, "infringement" means an infringement (or alleged infringement) of any patent, registered design, copyright, trademark, trade name, trade secret or other intellectual or industrial property right relating to the Works; and "claim" means a claim (or proceedings pursuing a claim) alleging an infringement.

Whenever a Party does not give notice to the other Party of any claim within 28 days of receiving the claim, the first Party shall be deemed to have waived any right to indemnity under this Sub-Clause.

The Employer shall Indemnify and hold the Contractor harmless against and from any claim alleging an infringement which is or was:

(a) An unavoidable result of the Contractor’s compliance with the Contract, or (b) A result of any Works being used by the Employer:

(i) For a purpose other than that indicated by, or reasonably to be inferred from, the

Contract, or

Page 81: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 54/64

Volume-I Contract Information – General Conditions of Contract RF

(ii) In conjunction with any thing not supplied by the Contractor, unless such use was disclosed to the Contractor prior to the Base Date or is stated in the Contract.

The Contractor shall indemnify and hold the Employer harmless against and from any other claim which arises out of or in relation to (i) the manufacture, use, sale or import of any Goods, or (ii) any design for which the Contractor is responsible.

If a Party is entitled to be indemnified under this Sub-Clause, the indemnifying Party may (at its cost) conduct negotiations for the settlement of the claim, and any litigation or arbitration, which may arise from it. The other Party shall, at the request and cost of the indemnifying Party, assist in contesting the claim. This other Party (and its Personnel) shall not make any admission, which might be prejudicial to the indemnifying Party, unless the indemnifying Party failed to take over the conduct of any negotiations, litigation or arbitration upon being requested to do so by such other Party.

16.6 Limitation of Liability

Neither Party shall be liable to the other Party for loss of use of any Works, loss of profit, loss of any Contract or for any indirect or consequential loss or damage which may be suffered by the other Party in connection with the Contract, other than under Sub-Clause 15.4 [Payment on Termination] and Sub-Clause 16.1 [Indemnities].

The total liability of the Contractor to the Employer, under or in connection with the Contract other than under Sub-Clause 4.19 [Site Facilities] and Sub-Clause 16.1 [Indemnities] shall not exceed the Accepted Contract Amount.

This Sub-Clause shall not limit liability in any case of fraud, deliberate default or reckless misconduct by the defaulting Party.

17.0 INSURANCE

17.1.1 The Contracor shall, to ensure the Contractor’s Obligations and responsibilities under the Contract , shall insure:

(a) the Works, together with Materials and Plant for incorporation therein, to the

full replacement cost (the term “cost” in this context shall include profit) (b) an additional sum of 15 per cent of such replacement cost, to cover any additional

costs of and incidental to the rectification of loss or damage including professional fees and the cost of demolishing and removing any part of the Works and of removing debris of whatsoever nature, and;

(c) Third Party Insurance

17.1.2 There shall be no obligation for the insurances in above to include loss or damage caused by: (a) war, hostilities (whether war be declared or not), invasion, act of foreign enemies, (b) rebellion, revolution, insurrection, or military or usurped power, or civil war, (c) ionising radiations, or contamination by radio-activity from any nuclear fuel, or from

any nuclear waste from the combustion of nuclear fuel, radio-active toxic explosive

Page 82: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 55/64

Volume-I Contract Information – General Conditions of Contract RF

or other hazardous properties of any explosive nuclear assembly or nuclear component thereof, or,

(d) pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds.

17.2 Scope of cover

17.2.1 The insurance in paragraphs (a) and (b) of sub-clause 17.1.1 shall be in the joint names

of Employer and Contractor and shall cover

i. the Employer and the Contractor against loss or damage as provided in the details of insurance annexed to these Conditions, from the start of work at the Site until the date of issue of the relevant Taking-Over Certificate in respect of the Works or any Section or part thereof as the case may be, and

ii. the Contractor for his liability:

a) during the Defects Liability Period for loss or damage arising from a cause occurring prior lo the commencement of the Defects Liability Period, or

b) occasioned by the Contractor in the course of any operation.'; carried out

by him for the purpose of complying with his obligations under Clause 10,

17.2.2 The insurance in paragraphs (c) of sub-clause 17.1.1 shall be in the joint names of the Employer and Contractor and shall cover: goods and materials in transit by land, sea or air from commencement of loading to delivery to the Site or to any off Site place of storage or fabrication and /or Goods, Plant and Materials in transit by land, sea or air between parts of the Site or from any off Site place of storage or to delivery to the Site or to any off Site place of storage or fabrication to the Site.

17.2.3 (a) The Employer shall effect and maintain for the benefit and joint names of the Employer, the Contactor and sub-Contractor(s) of any level as deemed necessary by the Employer, insurance covering liability of each one and them arising out of claims for third party personal injury (including bodily injury and death) and third party properly damage arising out of execution of the Works or complying with obligations under Defect Liability Period.

(b) The obligation and the responsibility of the Contractor to fulfill its obligations under the Contract without any omission or negligence shall not be diluted or comprised in view of the Employer’s responsibility to maintain insurance as stated in the preceding clause.

(c) In the event the Employer does not or is unable to derive benefit under the insurance cover as stated above, by it for any liability arising out of claims for third party personal injury (including bodily injury and death) and third party property damage due to any act, omission or negligence of the Contractor and/or Sub-Contractor, the Contractor shall be solely responsible for indemnifying and making good the loss of the Employer to the extent that it did not receive benefit under the insurance cover to be maintained under clause 17.2.3 (a).

17.3 Insurances by the Contractor

The Contractor shall take out & maintain the following policies of Insurance

(a) Insurance of Contractor’s Equipment (b) Insurance against accident to the Workmen

Page 83: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 56/64

Volume-I Contract Information – General Conditions of Contract RF

(c) Insurance for Salvage, Plants and floating Craft (d) Other Insurances as mentioned under Clause 17.3.4 (e) Commercial General Liability Insurance

17.3.1 Insurance of Contractor’s Equipment

The Contractor shall, without limiting his obligations and responsibilities under Clause 16.2, insure the Contractor's Equipment and other things brought onto the site by the Contractor, for a sum sufficient to provide for their replacement at the Site.

17.3.2 Insurance against Accident to Workmen

(a) The Contractor shall insure against such liability and shall continue such insurance

during the whole of the time that any persons are employed by him on the Works. Provided that, in respect of any persons employed by any Subcontractor, the Contractor’s obligations to insure as aforesaid under this Sub-Clause shall be satisfied if the Subcontractor shall have insured against the liability in respect of such persons in such manner that the Employer is indemnified under the policy, but the Contractor shall require such subcontractor to produce to the Employer, when required, such policy of insurance and the receipt for the payment of the current premium.

(b) Accident or Injury to Workmen

The Employer shall not be liable for or in respect of any damages or compensation payable to any workman or other person in the employment of the Contractor or any Subcontractor, or consultant/sub-consultant, or the person(s) engaged by them in any other capacity, other than death or injury resulting from any act or default of the Employer, his agents or servants. The Contractor shall indemnify and keep indemnified the Employer against all such Damages and compensation, other than those for which the Employer is liable as aforesaid, and against all claims, proceedings, damages, costs, charges, and expenses whatsoever in respect thereof or in relation thereto.

17.4 Responsibility for amount not recovered

Any amounts not insured or not recovered from the insurers shall be borne by the Employer or the Contractor in accordance with their responsibilities under Clause 16[Risk and responsibility].

The Contractor shall be responsible for any deductible amount under the insurances to the extent to which the claim results from an act, omission or default on the part of the Contractor or from circumstances for which the Contractor indemnifies the Employer under the Contract. Regardless of the loss, any deductible in excess of the deductibles prescribed under the insurances, or any amounts not recovered from the insurer shall be responsibility of the Contractor.

17.5 Indemnity by Contractor

The Contractor shall indemnify the Employer against all claims, proceedings, damages, costs, charges and expenses in respect of the matters referred to in the exceptions defined in Sub-Clause 17.2.3

17.6 Cross Liabilities

Page 84: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 57/64

Volume-I Contract Information – General Conditions of Contract RF

The insurance policy shall include a cross liability clause such that the insurance shall apply to the Employer, Contractor, Sub Contractor of any level as deemed necessary by the Employer as separate insured.

17.7 Evidence and Terms of Insurances

The Contractor shall provide evidence to the Employer prior to the start of work at the Site that the insurances required under the Contract have been effected and shall, within 84 days of the Commencement Date, provide the insurance policies to the Employer. When providing such evidence and such policies to the Employer, the Contractor shall notify the Engineer of so doing. Such insurance policies shall be consistent with the general terms agreed prior to the issue of the Letter of Acceptance. The Contractor shall effect all insurances for which he is responsible with insurers and in terms approved by the Employer. The Employer at the request of the Contractor, from time to time, provide to the Contractor copies of all insurance policies (or appropriate endorsements, certificates or other satisfactory evidence of insurance) obtained in accordance with the Contract (including the copies of the renewal conformations).

17.8 Adequacy of Insurances

The Contractor shall notify the insurers of changes in the nature, extent or programme for the execution of the Works and ensure the adequacy of the insurances at all times in accordance with the terms of the Contract and shall, when required, produce to the Employer the insurance policies in force and the receipts for payment of the current premiums.

17.9 Remedy on Contractor’s Failure to Insure

If the Contractor fails to effect and keep in force any of the insurances required under the Contract, or fails to provide the policies to the Employer within the period required under the Contract, then and in any such case the Employer may effect and keep in force any such insurances and pay any premium as may be necessary for that purpose and from time to time deduct the amount so paid from any monies due or to become due to the Contractor, or recover the same as a debt due from the Contractor.

17.10 Compliance with Policy Conditions

In the event that the Contractor or the Employer fails to comply with conditions imposed by the insurance policies effected pursuant to the Contract, each shall indemnify the other against all losses and claims arising from such failure.

18.0 FORCE MAJEURE 18.1 Definition of Force Majeure

In this Clause, "Force Majeure" means an exceptional event or circumstance: (a) Which is beyond a Party's control, (b) Which such Party could not reasonably have provided against before entering

into the Contract, (c) Which, having arisen, such Party could not reasonably have avoided or overcome,

and

Page 85: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 58/64

Volume-I Contract Information – General Conditions of Contract RF

(d) Which is not substantially attributable to the other Party.

Force Majeure shall mean the following exhaustive events listed below:

(i) War, hostilities (whether war be declared or not), invasion, act of foreign enemies, (ii) Rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war, (iii) Riot, commotion, disorder, strike or lockout by persons other than the Contractor’s

Personnel and other employees of the Contractor and Sub- Contractors, (iv) Munitions of war, explosive materials, ionising radiation or contamination by

radioactivity, except as may be attributable to the Contractor’s use of such munitions, explosives, radiation or radioactivity, and

(v) Natural catastrophes such as earthquake, tsunami, hurricane, typhoon or volcanic activity.

18.2 Notice of Force Majeure

If a Party is or will be prevented from performing any of its obligations under the Contract by Force Majeure, then it shall give notice to the other Party of the event or circumstances constituting the Force Majeure and shall specify the obligations, the performance of which is or will be prevented. The notice shall be given within 14 days after the Party became aware, (or should have become aware), of the relevant event or circumstance constituting Force Majeure.

The Party shall, having given notice, be excused performance of such obligations for so long as such Force Majeure prevents it from performing them.

Notwithstanding any other provision of this Clause, Force Majeure shall not apply to obligations of either Party to make payments to the other Party under the Contract.

18.3 Duty to Minimize Delay

Each Party shall at all times use all reasonable endeavours to minimise any delay in the performance of the Contract as a result of Force Majeure.

A Party shall give notice to the other Party when it ceases to be affected by the Force Majeure.

18.4 Consequences of Force Majeure

If the Contractor is prevented from performing any of his obligations under the Contract by Force Majeure of which notice has been given under Sub-Clause 18.2 [Notice of Force Majeure], and suffers delay and/or incurs Cost by reason of such Force Majeure, the Contractor shall be entitled subject to Sub-Clause 19.1[Contractor’s Claims] to:

(a) An extension of time for any such delay, if completion is or will be delayed, under

Sub-Clause 7.4 [Extension of Time for Completion], and

(b) If the event or circumstance is of the kind described in sub-paragraphs (i) to (v) of Sub-Clause 18.1 [Definition of Force Majeure] and, in the case of subparagraphs (ii) to (iv), occurs in the Country, payment of any such Cost.

After receiving this notice, the Engineer shall proceed in accordance with Sub Clause 3.4 [Determinations] to agree or determine these matters.

Page 86: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 59/64

Volume-I Contract Information – General Conditions of Contract RF

18.5 Force Majeure Affecting Sub-Contractor

If any Sub-Contractor is entitled under any Contract or agreement relating to the Works to relief from force majeure on terms additional to or broader than those specified in this Clause, such additional or broader Force Majeure events or circumstances shall not excuse the Contractor’s non-performance or entitle him to relief under this Clause.

18.6 Optional Termination, Payment and Release

If the execution of substantially all the Works in progress is prevented for a continuous period of 84 days by reason of Force Majeure of which notice has been given under Sub-Clause 18.2 [Notice of Force Majeure], or for multiple periods which total more than 140 days due to the same notified Force Majeure, then either Party may give to the other Party a notice of termination of the Contract. In this event, the termination shall take effect 14 days after the notice is given, and the Contractor shall proceed in accordance with Sub-Clause 15.3 [Cessation of Work and Removal of Contractor’s Equipment].

Upon such termination, the Engineer shall determine the value of the work done and issue a Payment Certificate which shall include:

(a) The amounts payable for any work carried out for which a price is stated in the

Contract;

(b) The Cost of Plant and Materials ordered for the Works which have been delivered to the Contractor, or of which the Contractor is liable to

accept delivery: this Plant and Materials shall become the property of (and be at the risk of) the Employer when paid for by the Employer, and the Contractor shall place the same at the Employer's disposal;

(c) Any other Cost or liability which in the circumstances was reasonably incurred by the Contractor in the expectation of completing the Works;

(d) The Cost of removal of Temporary Works and Contractor’s Equipment from the Site

and the return of these items to the Contractor’s works in his country (or to any other destination at no greater cost).

18.7 Release from Performance under the Law

Notwithstanding any other provision of this Clause, if any event or circumstance outside the control of the Parties (including, but not limited to, Force Majeure) arises which makes it impossible or unlawful for either or both Parties to fulfill its or their Contractual obligations or which, under the law governing the Contract, entitles the Parties to be released from further performance of the Contract, then upon notice by either Party to the other Party of such event or circumstance:

• The Parties shall be discharged from further performance, without prejudice to the rights of either Party in respect of any previous breach of the Contract, and

• The sum payable by the Employer to the Contractor shall be the same as would have been payable under Sub-Clause 18.6 [Optional Termination, Payment and Release] if the Contract had been terminated under Sub-Clause 18.6.

Page 87: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 60/64

Volume-I Contract Information – General Conditions of Contract RF

19.0 CLAIM, DISPUTES AND ARBITRATION

19.1 Contractor’s Claims

If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable as and not later than 28 days after the Contractor became aware; or should have become aware, of the event or circumstance.

If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim. Otherwise, the following provisions of this Sub-Clause shall apply.

The Contractor shall also submit any other notices which are required by the Contract, and supporting particulars for the claim, all as relevant to such event or circumstance. The Contractor shall keep such contemporary records as may be necessary to substantiate any claim, either on the Site or at another location acceptable to the Engineer without admitting the employer’s liability, the Engineer may; after

receiving any notice under this Sub-Clause, monitor the record-keeping and/or instruct the Contractor to keep further contemporary records. The Contractor shall permit the Engineer to inspect all these records, and shall (if instructed) submit copies to the Engineer.

Within 42 days after the Contractor became aware (or should have become aware) of the event or circumstance giving rise to the claim, or within such other period as may be proposed by the Contractor and approved by the Engineer, the Contractor shall send to the Engineer a fully detailed claim which includes full supporting particulars of the basis of the claim and of the extension of time and/or additional payment claimed. if the event or circumstance giving rise to the claim has a continuing effect:

This fully detailed claim shall be considered as interim;

The Contractor shall send further interim claims at monthly intervals, giving the accumulated delay and/or amount claimed, and such further particulars as the Engineer may reasonably require; and

The Contractor shall send a final claim within 28 days after the end of the effects resulting from the event or circumstance, or within such other period as may be proposed by the Contractor and approved by the Engineer.

Within 42 days after receiving a claim or any further particulars supporting a previous claim, or within such other period as may be proposed by the Engineer and approved by the Contractor, the Engineer shall respond with approval, or with disapproval and detailed comments. He may also request any necessary further particulars, but shall nevertheless give his response on the principles of the claim within such time.

Page 88: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 61/64

Volume-I Contract Information – General Conditions of Contract RF

Each Payment Certificate shall include such amounts for any claim as have been reasonably substantiated as due under the relevant provision of the Contract. Unless and until the particulars supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to payment for such part of the claim, as he has been able to substantiate.

The Engineer shall proceed in accordance with Sub-Clause 3.4 [Determinations] to agree or determine (i) the extension (if any) of the Time for Completion (before or after its expiry) in accordance with Sub-Clause 7.4 [Extension of Time for Completion], and/or (ii) the additional payment (if any) to which the Contractor is entitled under the Contract.

The requirements of this Sub-Clause are in addition to those of any other Sub-Clause, which may apply to a claim. If the Contractor fails to comply with this or another Sub-Clause in relation to any claim, any extension of time and/or additional payment shall take account of the extent (if any) to which the failure has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the second paragraph of this Sub- Clause.

19.2 Amicable Settlement

In case of any disputes, both Parties shall attempt to settle the dispute amicably through suitable mechanism mutually discussed and agreed upon before the commencement of arbitration.

However, unless both Parties agree otherwise, arbitration may be commenced even if no attempt at amicable settlement has been made.

19.3 Arbitration

Unless settled amicably, disputes shall be settled by arbitration and shall be subject to the provisions of the Arbitration and Conciliation Act 1996 (or any modifications to or any re- enactments thereof as in force at the time). Each Party shall be entitled to nominate an arbitrator and the two arbitrators so nominated shall jointly nominate a third presiding arbitrator. The three Arbitrators shall form the arbitral tribunal the (“Tribunal”). The Tribunal shall give a reasoned award within sixty (60) days from the date of constitution of the Tribunal. The place of arbitration shall be Mumbai and the language of the arbitration shall be English.

20.0 USE OF EXPLOSIVES

Being in CRZ area use of explosives is not allowed.

21.0 PROPERTY IN EXCAVATED MATERIALS

All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found during excavation / dredging shall be placed under the care and authority of the Employer. The Contractor shall take reasonable precautions to prevent the Contractor’s personnel or other persons

Page 89: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 62/64

Volume-I Contract Information – General Conditions of Contract RF

from removing or damaging any of these findings. The Contractor shall upon discovery of such finding, immediately give notice to the Employer.

22.0 DRAWINGS & DESIGNS

(a) General details of the works are shown on the drawings accompanying this tender

document. The Engineer will supply to the Contractor from time to time during the progress of the works such further working drawings as will be necessary in his opinion for the proper and adequate execution and maintenance of the Works in accordance with the Engineer’s designs and/or any modification thereof as decided by the Engineer and the Contractor shall carry out the work in accordance with the said working drawings. Two sets of such working drawings will be issued. If the Contractor requires more sets he will have to make his own arrangement at his cost.

(b) Three complete sets of tracing on linen or tracing film of all drawings showing every

and all works 'As Made' under the Contract shall be made by the Contractor at his own expense and delivered to the Engineer within one month of the completion of the various sections of the work or at such times as directed by the Engineer. All departure/alteration/modifications from the Contract Drawings and supplementary working drawings issued by the Engineer also shall be incorporated in the "As Made" drawings. The drawings shall be fully dimensioned, of an approved size and as approved by the Engineer.

23.0 FILLING IN HOLES AND TRENCHES

The Contractor immediately upon completion of any work under the Contract shall at his own expenses fill up all holes or trenches which have been made or dug, level or remove mounds of earth that may have been made and clear away all rubbish occasioned in the execution of the Works or Temporary Works. The Contractor shall bear and pay all costs, charges, damages and expenses which may be incurred or sustained on account or in consequence of any accident which may happen by reason of holes and trenches connected with the work being left unfenced or materials being left or placed in improper situations.

24.0 CONTRACT SUPERSEDES PREVIOUS DOCUMENTS

The Contractor shall have no right to any increase in the rates in the Bill of Quantities nor any other right whatsoever by reason of any representative explanation or statement or alleged representative explanation or statement made or by reason of any information promise or guarantee given or alleged to have been given to him by any person (whether in the employment of the Employer or not) before the date of the Contract embodies the whole arrangements between the parties with reference to the

Contract hereby constituted and all previous, correspondence/negotiation/ representations/ explanations/ statements/ promises or guarantee whether oral or written shall be excluded.

25.0 BRIBES AND COMMISSION

Any bribe, commission, gift or advantage given, promised or offered by or on behalf of the Contractor or his or their behalf to any officer, servant, representative or

Page 90: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 63/64

Volume-I Contract Information – General Conditions of Contract RF

agent of the Engineer or to any person on his behalf in relation to the btaining or to be execution of this or any other Contract with the Employer shall in addition to any criminal liability which he may incur subject the Contractor to the cancellation of this and all other Contracts with the Employer and also to the payment of any loss or damage resulting from any such cancellation, and the Employer shall be entitled to deduct the amounts so payable from any money otherwise due to the Contractor under this or any other Contract.

26.0 GST The Contractor if applicable is allowed to bill GST at prevailing rate in running account bill and final bill. The Employer shall pay the amount of GST billed (as corrected in audit) in proportion of payment (Clause No.13.7 of General Conditions of Contract) to be released. The Contractor shall produce the receipts / evidence of remittances of service tax before the next Interim bill or as stipulated in latest GST rules from the date of payment of GST whichever is earlier. In case of failure, the amount paid towards service tax shall be deducted from the next interim bill due or any other money due to the Contractor and same shall be reimbursed on production of service tax remittance proof only.

27.0 SECURITY CLEARANCE

Award of Contract is subject to security clearance, if required, from the Government. The bids received from any tenderer may be summarily rejected on National Security consideration without any intimation thereof to the tenderer.

28.0 LIFE SAVING APPLIANCES AND FIRST AID EQUIPMENT

The Contractor shall provide and maintain upon the Works sufficient, proper and efficient life-saving appliances and first aid equipment to the approval of the Engineer and in accordance with the requirements of ILO Convention No.62. The appliances and equipment shall be available for use at all times.

29.0 DRAWINGS AND PHOTOGRAPHS OF THE WORKS

The Contractor shall not disclose details of drawings furnished to him and Works on which he is engaged without the approval of the Engineer. No photographs of the Works or any part thereof or plant employed thereon shall be taken or permitted by the Contractor to be taken by any of his employees or any employees of his SubContractors without the approval of the Engineer and no such photographs shall be published or otherwise circulated without the approval of the Engineer.

30.0 TAXATION

30.1 General

Page 91: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 64/64

Volume-I Contract Information – General Conditions of Contract RF

The Contractor and his staff shall pay all taxes, duties, levies, work contract tax, excise duties and other duties and taxes (excluding service tax on work), etc. and sales tax//VAT/turnover tax on works of the Government of India and the Maharashtra Government as per the existing laws of India.

Deduction of income tax shall be made from each Running Bill of payment as per the relevant provisions of the Income Tax Act or as per the advice of the Income Tax Authority.

30.2 Customs Duty Not applicable

31.0 NOISE AND DISTURBANCE

All Works shall be carried out without unreasonable noise and disturbance. The Contractor shall indemnify the Employer from and against any liability for damages on account of noise or other disturbance created while or in carrying out the work and from and against all claims demands proceedings damages costs charges and expenses whatsoever in regard or in relation to such liability.

32.0 SECURITY REQUIREMENTS

The Contractor shall comply with all regulations as applicable in respect of the passage of plant, vehicles, materials and personnel.

35.0 POLLUTION

Subject and without prejudice to any other provision of the Contract, the Contractor shall take all reasonable precautions as per the approved SHE plan.

37.0 ADVERTISING

No advertisement shall be placed on any hoarding, fencing, building or scaffolding erected in connection with this Contract without the written permission of the Employer.

Page 92: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 1/2

Volume-I Contract Information – Special Conditions of Contract RF

SPECIAL CONDITIONS OF CONTARCT

General

3.1 Engineer’s Duties and Authority 3.1.1 Specific approvals by Employer

4.6 Co-operation 4.6.1 Operation of the Employer and Others 4.6.2 Existing Services

4.7 Setting Out 4.7.1 Surveys and levels to be Agreed

4.7.2 Survey control for works

4.7.3 Co-ordination and Inspection of Works

4.8 Safety Procedures

4.13 Rights of Way and Facilities

4.0 The Contractor 4.24 4.25 4.26

4.27 Nominated Subcontractor

4.27.1 Definition of “Nominated Subcontractors” 4.27.2 Appointment of Nominated Subcontractors 4.27.3 Design Requirements to be Expressly Stated 4.27.4 Payments to Nominated Subcontractors

5.5 Working Hours 5.5.1 Working in shifts 5.5.2 Work in Monsoon

5.6 Facilities for Staff & Labour

6.4 Testing 6.4.1 Site Laboratory

7.2 (e) Time of Completion, Compensation for Delay due to Contractor’s Negligence (Liquidated damages)

11.2 Method of Measurements

12.4 Provisional Sums 12.4.1 Definition of ‘Provisional Sums’ 12.4.2 Use of Provisional Sums

Page 93: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 2/2

Volume-I Contract Information – Special Conditions of Contract RF

12.5 Variations & Adjustments

12.6 Value Engineering

Page 94: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 1/10

Volume-I Contract Information – Special Conditions of Contract RF

SPECIAL CONDITIONS OF CONTARCT

General

Special Conditions shall be read in conjunction with the General Conditions of Contract, Specification, Drawings and any other documents forming part of this Contract wherever the context so requires.

Notwithstanding the Sub-division of the documents in to these separate section and volume every part of each shall be deemed to be supplementary to and complementary of every other part and shall be read with and into the Contract so far as it may be practicable to do so. Where any portion of the General Conditions of Contract is repugnant to or at variance with any provisions of the Special Conditions, the provisions of the Special Conditions shall be deemed to over-ride the provisions of the General Conditions of Contract and shall to the extent of such repugnancy of variations, prevail. Where it is mentioned in the Specification that the Contractor shall perform certain work or provide certain facilities, it is understood that the Contractor shall do so at his own cost. The materials, design and workmanship shall satisfy the relevant Indian Standard, the specification conditioned herein and codes referred to. Where the specifications stipulate requirement in addition to those contained in the Standard Codes and Specifications these additional requirements shall also be satisfied.

Page 95: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 2/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

1. 3.1 – Engineer’s Duties and Authority

Add the following after the clause as 3.1: 3.1.1 – Specific approvals by Employer

The Engineer shall obtain the specific approval of the Employer before exercising any authority or taking any action under following clauses to the condition of the contract. While the Employer will finally accord his approval, the recommendations of the Engineer on all these clauses are mandatory:

(a) Clause 12.1(a) Increase or decrease in the quantity of the existing item in tender beyond 25 %.

(b) Any additional item with a financial implication more than 1 % of the contract amount.

(c) Omission of any work partially or fully. (d) Granting extension of time and claims to the contractor. (e) Granting approval to the contractor for the breakdown of the lump sum

prices as submitted by him under sub-clause 11.2 (c)

Notwithstanding the obligation, as set out in Clause 3.1.1 above, to obtain approval, if, in the opinion of the Engineer, an emergency occurs affecting the safety of life or of the Works or of adjoining property, he may, without relieving the Contractor of any of his duties and responsibilities under the Contract, instruct the Contractor, under intimation to the Employer to execute all such work or to do all such things as may, in the opinion of the Engineer, be necessary to abate or reduce the risk. The Contractor shall forthwith comply, despite the absence of specific approval of the Employer, with any such instruction of the Engineer. The Engineer shall determine an addition to the Contract Price, in respect of such instructions, in accordance with Clause 12 and shall notify the Contractor accordingly, with a copy to the Employer.

2. 4.6 – Co- operation

Add the following sub-clause:

4.6.1 – Operation of the Employer and Others

(a) The ordinary business and works of the Employer and others as carried out on and in the vicinity of the site will be continued during the construction, completion and maintenance of the works and the execution of the Contract shall be conducted in such a way as to avoid interference with traffic of every kind by land and by water and with any other works in progress in vicinity. The contractor shall carry out his work strictly in a manner which would not obstruct or endanger the normal use of waterways, anchorages, wharves and approaches thereto, whether in the possession of the Employer or any other persons.

The contractor has to comply with all relevant laws and safety regulations imposed by the Employers Fire and Safety Officer.

Page 96: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 3/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

(b)The Contractor shall where so directed by the Engineer be required to work to other Contractor’s drawings where-so-ever drawings for work not included in this Contract are related to particular details of the works.

(c) The Contractor shall from time to time as the Engineer may direct, provide assistance to the other contractors and carry out minor works in connection with such Contracts. The cost of providing such assistance shall be determined by the Engineer as per the sub- clause 3.4 (Determination).

4.6.2 – Existing Services

(a) Drains, pipes, cables, overhead-wires and similar services encountered in the course of the work shall be guarded from injury by the Contractor at his own cost so that they may continue in full and uninterrupted use to the satisfaction of the owners thereof or otherwise occupy any part of the site in a manner likely to hinder the operation of such services.

(b) Should any damage be done by the Contractor to the aforesaid Drains, pipes, cables, overhead-wires and similar services Whether or not shown on the drawings the Contractor must make good or bear the cost of making good the same without delay to the satisfaction of the Engineer and of the owners.

3. 4.7 – Setting Out

Add the following sub-clause:

4.7.1 – Surveys and levels to be Agreed

(a) Before the works of any part thereof begin, the Contractor’s agent and the Engineer’s Representative shall together survey and take levels of the site of the works both above and below water level / Chart Datum level, and agree all particulars on which the measurements of the works are to be based. Such particulars shall be plotted on drawings by the Contractor and after agreement; the drawings shall be signed by the Engineer or his authorised representative.

(b) Failing such surveys and agreements being prepared and/or signed by the Contractor, the survey of the Engineer shall be final and binding on the Contractor.

(c) The Contractor shall be entirely responsible for the horizontal and vertical alignment, the levels and correctness of every part of the work and shall rectify any errors or imperfection therein. Such rectification shall be carried out by the Contractor, at his own cost.

4.7.2 – Survey control for works

(a) The Engineer shall furnish the relevant existing grid points with bench Mark reference. It shall be Contractor’s responsibility to the set out the necessary central points on land and to set out alignment. The Contractor shall have in his employ efficient survey team for this purpose and the accuracy of such setting out works shall be Contractor’s sole responsibility.

Page 97: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 4/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

(b) Before beginning the work the Contractor shall work out the control points on ground or elsewhere with suitable markers as approved by the Engineer. All these points and markings shall be checked and approved by the Engineer or Engineer’s Representative before starting the work.

(c) The Contractor shall also provide necessary equipment, labour and other facilities for proper checking of triangulation / bench mark stations and inspection of the points during the survey operations at no cost to the Employer.

(d) The Contractor shall give the Engineer not less than 24 hours notice in writing of his intention to set out or give levels for any part of the works so that arrangements may be made for checking the work.

(e) Work shall be suspended as per the instructions of the Engineer for such times as necessary for checking lines and levels on any part of the works.

(f) The Contractor shall at his own expense provide all assistance which the Engineer may require for checking the setting out.

4.7.3 – Co-ordination and Inspection of Works

The Co-ordination and inspection of the day-to-day work under the Contract shall be the responsibility of the Engineer. The written instructions regarding any particular work will be normally passed by the Engineer. A work order book will be maintained by the Contractor for each sector which aforesaid written instructions will be entered. These will be signed by the Contractor or his authorised representative by way of acknowledgment within 12 hours.

4. 4.8 – Safety Procedures

Add the following as clause 4.8 (f):

4.8 (f) – The Contractor shall take all possible precaution to prevent outbreaks of fire on the site and in all offices, stores, camps and other places and things connected therewith and especially with respect to the safe storage of petroleum products, explosives and all other dangerous or hazardous goods. He shall comply with all rules, regulations and orders of any Statutory Authority and of the Engineer at no extra cost to the Employer.

In addition to the safety procedures mentioned above any particular safety

and security code and requirements as instructed / laid down by the

Employer from time to time shall be strictly followed by the contractor

without any additional cost to the Employer.

Page 98: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 5/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

6. 4.0 – The Contractor

Add the following sub-clause: 4.24 –

In the event if the employer supplies any useful material (like material for backfilling, materials useful for making the temporary approaches & roads, useful material for aggregate manufacturing etc.) to the contractor forming the part of the temporary/permanent works, the rates for the same shall be mutually discussed and agreed upon and shall be adjusted against the Contract Price.

4.25 – In the event if the Employer supplies or rent out the plants & equipments for the use of contractor, the charges for the same shall be deducted from contractor’s bill at actual + 15% overhead charges of employer.

4.26 - In the event if the Employer permits the use of the existing temporary facility other than stated in sub-clause 4.19 the charges for the same shall be deducted from contractor’s R.A. bill

4.27 Nominated Subcontractor

4.27.1 Definition of “Nominated Subcontractors”

All specialists, merchants, tradesmen and others executing any work or supplying any goods, materials, Plant or services for which Provisional Sums are included in the Contract, who may have been or be nominated or selected or approved by the Employer or the Engineer, and all persons to whom by virtue of the provisions of the Contract the Contractor is required to subcontract shall, in the execution of such work or the supply of such goods, materials, Plant or services, be deemed to be subcontractors to the Contractor and are referred to in this Contract as “nominated Subcontractors”.

4.27.2 Appointment of Nominated Subcontractors

The Contractor shall not be required by the Employer or the Engineer, or be deemed to be under any obligation, to employ any nominated Subcontractor who declines to enter into a subcontract with the Contractor containing provisions: (a) that in respect of the work, goods, materials, Plant or services the

subject of the subcontract, the nominated Subcontractor will undertake towards the Contractor such obligations and liabilities as will enable the Contractor to discharge his own obligations and liabilities towards the Employer under the terms of the Contract and will save harmless and indemnify the Contractor from and against the same and from all claims, proceedings, damages, costs, charges and expenses whatsoever arising out of or in connection therewith, or arising out of or in connection with any failure to perform such obligations or to fulfill such liabilities, and

Page 99: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 6/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

(b) that the nominated Subcontractor will save harmless and indemnify the Contractor from and against any negligence by the nominated Subcontractor, his agents, workmen and servants and from and against any misuse by him or them of any Temporary Works provided by the Contractor for the purposes of the Contract and from all claims as aforesaid.

4.27.3 Design Requirements to be Expressly Stated If in connection with any Provisional Sum the services to be provided include any matter of design or specification of any part of the Permanent Works or of any Plant to be incorporated therein, such requirement shall be expressly stated in the Contract and shall be included in any nominated Subcontract. The Nominated Subcontract shall specify that the Nominated Subcontractor providing such services will save harmless and indemnify the Contractor from and against the same and from all claims, proceedings, damages, costs, charges and expenses whatsoever arising out of or in connection with any failure to perform such obligations or to fulfill such liabilities.

4.27.4 Payments to Nominated Subcontractors

For all work executed or goods, materials, Plant or services supplied by any nominated Subcontractor, the Contractor shall be entitled to:

(a) the actual price paid or due to be paid by the Contractor, on the instructions of the Engineer, and in accordance with the subcontract;

(b) in respect of labour supplied by the Contractor, the sum, if any, entered in the Bill of Quantities or, if instructed by the Engineer pursuant to paragraph (a) of Sub-Clause 12.4.2, as may be determined in accordance with Clause 12; and

(c) in respect of all other charges and profit, a sum being a percentage rate of the actual price paid or due to be paid calculated, where provision has been made in the Bill of Quantities for a rate to be set against the relevant Provisional Sum, at the rate inserted by the Contractor against that item or, where no such provision has been made, at the rate inserted by the Contractor in the Appendix to Tender and repeated where provision for such is made in a special item provided in the Bill of Quantities for such purpose.

4.27.5 Certification of Payments to Nominated Subcontractors Before issuing, under Clause 13, any certificate, which includes any payment in respect of work done or goods, materials, Plant or services supplied by any nominated Subcontractor, the Engineer shall be entitled to demand from the Contractor reasonable proof that all payments, less retentions, included in previous certificates in respect of the work or goods, materials, Plant or services of such nominated Subcontractor have been paid or discharged by the Contractor. If the Contractor fails to supply such proof then, unless the Contractor:

Page 100: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 7/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

(a) satisfies the Engineer in writing that he has reasonable cause for withholding or refusing to make such payments, and

(b) produces to the Engineer reasonable proof that he has so informed such nominated Subcontractor in writing,

the Employer shall be entitled to pay to such nominated Subcontractor direct, upon the certificate of the Engineer, all Subcontract, which the Contractor has failed to make to such nominated Subcontractor and to deduct by way of set-off the amount so paid by the Employer from any sums due or to become due from the Employer to the Contractor.

Provided that, where the Engineer has certified and the Employer has paid direct as aforesaid, the Engineer shall, in issuing any further certificate in favour of the Contractor, deduct from the amount thereof the amount so paid, direct as aforesaid, but shall not withhold or delay the issue of the certificate itself when due to be issued under the terms of the Contract.

7 5.5 – Working Hours

Add the following sub-clause:

5.5.1 – Working in shifts

Considering the nature of the work and notwithstanding any provisions made in clause 5.5, the contractor shall have the option to work continuously in shift by day & night and also on locally day of rest, provided that the contractor have make the suitable satisfactory arrangement for the same and inform the engineer well in advance and provided further that the rates and prices entered by the contractor in the contract shall not vary on this account.

In the event such permission is granted to work beyond the normal working hours, the additional charge due to shift working by the Employer’s / Engineer’s workmen/ supervisory and managerial staff shall be borne by the contractor.

5.5.2 – Work in Monsoon

The execution of the work entails working in the monsoon also. The Contractor must maintain sufficient labour force as may be required for the work and plant and execute the construction and erection according to the prescribed schedule. No special rate will be considered for such work in monsoon.

Page 101: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 8/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

8 5.6 – Facilities for Staff & Labour

Add the following sub-clause: 5.6.1 –

The contractor at his office at Site shall make the provision & maintain the following facilities, within 30 days from the Commencement Date till the date of completion of works, without any additional cost to the Employer -

• Office accommodation admeasuring 50 Sq. m. for Employer and Engineers representative.

• Independent furnished Conference room facility for 8/10 personals.

9 6.4 – Testing Add the following

6.4.1 – Site Laboratory

The contractor within 21 days from the Commencement Date shall forward a detailed Project Quality Plan (PQP) as per the sub-clause 7.3 (Programme). The contractor shall establish a full fledged laboratory within 30 days from the date of commencement & maintain the same till the completion of contract. The site laboratory shall be headed by qualified Quality Assurance Engineer as approved by the Employer/ Engineer. The Q.A. Engineer shall be assisted by the qualified and experience staff. The layout of Site laboratory shall be prepared by the contractor and got approved from the Engineer and the laboratory shall have the following minimum testing apparatuses and equipments –

A Aggregate Testing

1 Speedy moisture meter complete with chemicals 1 Set

2 Core cutter apparatus 10 cm dia., 10/15 cm height, complete with dolly, rammer etc

1 Set

3 Aggregate impact value test apparatus/ Los angeles abrasion test apparatus

1 Set

4 Flakiness & Elongation test gauges 1 Set

5 Standard measures of 30, 15 and 3 litres capacity along with standard tamping rod

1 Set

6 California bearing ratio test apparatus 1 Set

B Cement & Cement Concrete

1 Vicat apparatus for testing setting time 1 Set

2 Slump Testing apparatus 5 Set

3 Compression and Flexural Strength Testing machine of 200 Tonne capacity with additional dial for flexural testing

1 No.

4 Needle vibrators 2 Nos

5 Air meter 1 No

6 Vibratory Tables 1 No.

7 Cube moulds As required, but not less than 60 nos. of moulds

Page 102: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 9/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

8 Chloride Testing kit for rapid determination chloride content.

2 No.

9 ION Exchange kit for chemical analysis for Sulphate Testing. 2 No.

10 Laboratory motorized concrete mixer. 1 No.

11 Concrete core cutter 1 No.

C Pile Testing Arrangements As required. D General –

1 Oven – Electrically operated, thermostatically controlled, range up to 200 degree Celsius

1 No 2 Electronic balance 300 Kg capacity accuracy 0.5

gram 2 Nos

3 Water Bath - Electrically operated, and thermostatically controlled with adjustable shelves, sensitivity 1 degree Celsius.

1 Nos

4 Thermometer Mercury–in-glass thermometer range 0 degree to 250 degree Celsius

3 Nos

5 Thermometer 2 Nos 6 Kerosene or gas stove or electric hot plate 1 No

7 Glasswares, spatulas, wire gauzes, steel scales, measuring tape, casseroles, karahis, anamelled treys of assorted sizes, pestle- mortor, porcelain dishes, gunny bags, plastic bags, chemicals, digging tools like pick axes, showels, etc.

As required

8 Set of I.S. Sieves with lid& pan- 450 mm dia.:- 63 mm, 53mm, 37.5 mm, 26.5mm, 13.2 mm, 9.5 mm, 6.7 mm and 4.75 mm size

1 Set

200 mm dia.:- 2.36 mm, 2.00 mm, 1.18 mm, 600 micron, 425 micron, 300 micron, 150 micron and 75 micron size

2 Sets

9 Water Testing Kit 1 Set

10 First aid box

2 Set

All the tests as required to be carried out shall confirm to the standard

procedures and with the defined frequency as per the approved Quality

Assurance plan and shall be witnessed by Engineer’s representative.

The items and their numbers listed above should be earmarked for Site

laboratory use only. External testing required if any, shall be done by

the contractor from the recognized/NABL accredited testing Laboratory as

approved by the Engineer. The charges for the same shall be borne by the

contractor.

The Laboratory and equipments provided shall remain the property of the Contractor, who should demolish the same and dispose off the debris, as directed by the Engineer at the end of the construction period.

Page 103: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 10/10

Volume-I Contract Information – Special Conditions of Contract RF

Sr. No

G.C.C. Clause Reference No

Amendments

10 7.2 - Time of Completion, Compensation for Delay due to Contractor’s Negligence (Liquidated damages)

Add the following

7.2 (e) – If there is any delay in achieving the milestone specified in the Appendix Contractor shall pay or allow the Employer to recover the Liquidity Damages applicable for non-achievement of milestones as specified in the Appendix to the Tender.

11 11.2 – Method of Measurements

Add the following: (c) In case any items in the Bill of Quantities requires to quote Lump

sum price of a item, the contractor shall submit to the Engineer, within 21 days after the Commencement Date, a proposed breakdown of each lump sum price in the Schedules for approval. The Engineer may take account of the breakdown when preparing Payment Certificates.

(d) In case of any dispute as to the mode of measurement not covered by the Contract to be adopted for any item of work, mode or measurement as per relevant Indian Standard Specification (Latest Revision) shall be followed.

12 12.4 – Provisional Sums

Replace 12.4 as under –

12.4.1 – Definition of ‘Provisional Sums’

“Provisional Sum” means a sum included in the Contract and so designated in the Bill of Quantities for the execution of any part of the Works or for the supply if goods, materials, Plant or services, or for contingencies, which sum may be used, in whole or in part, or not at all, on the instructions of the Engineer. The Contractor shall be entitled to only such amounts in respect of the work, supply or contingencies to which such Provisional Sums relate as the Engineer shall determine in accordance with this Clause. The Engineer shall notify the Contractor of any determination made under this Sub- Clause, with a copy to the Employer.

12.4.2 – Use of Provisional Sums

For each Provisional Sum, the Engineer may instruct: (a) Work to be executed (including Plant, Materials or services to be

supplied) by the Contractor and valued under Sub-Clause 12.2 [Valuation Procedure]; and/or

(b) Plant, Materials or services to be purchased by the Contractor

from a nominated subcontractor (as defined in the contract), or otherwise and for which there shall be included in the Contract Price: (i) The actual amounts paid (or due to be paid) by the

Contractor, and (ii) A sum for overhead charges and profit, calculated as a

percentage of these actual amounts by applying the relevant percentage rate as stated in the Appendix to the Tender.

12.4.3 – Production of vouchers

The Contractor shall when required by the Engineer, produce quotations, invoices, vouchers and accounts or receipts in substantiation.

Page 104: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 1/14 Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Halls and Allied Infrastructure works

ANNEXURES TABLE OF CONTENTS

S. No. ANNEXURE PARTICULAR

1 ANNEXURE – 1 PROFORAMA OF LETETR OF AUTHORITY 2 ANNEXURE – 2 FORM OF BANK GUARANTEE FOR TENDER SECURITY / BID

SECURITY

3 ANNEXURE – 3 PROFORMA OF IRREVOCABLE BANK GUARANTEE FOR

CONTRACT PERFORMANCE

4 ANNEXURE – 4 PROFORMA OF CONTRACT AGREEMENT

5 ANNEXURE – 5 AVERAGE ANNUAL FINANCIAL TURNOVER DURING THE LAST

THREE YEARS ENDING 31ST MARCH 2017

6 ANNEXURE – 6 LIST OF MAJOR EQUIPMENT PROPOSED

7 ANNEXURE – 7 ORGANIZATION CHART FURNISHING THE NAMES OF KEY

PERSONNEL & THEIR BIO DATA TO BE DEPLOYED FOR THIS

PROJECT

8 ANNEXURE – 8 PROFORMA OF BANK GUARANTEE FOR SECURITY AGAINST

MOBILIZATION ADVANCE

9 ANNEXURE – 9 DOCUMENTS TO BE ATTACHED

Page 105: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 2/14 Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Halls and Allied Infrastructure works

LETTER OF SUBMISSION

From :

To, Subject :

. Reference : Sir, We hereby submit the relevant information for the Construction of Auction Hall(s) & other allied Buildings and infrastructure facilities. 1. We agree to abide by all the instructions, terms and conditions mentioned in the Bid documents.

2. We hereby certify that all the statements made and information supplied in the enclosed

forms and accompanying statements are true and correct.

Name of Bidder Sign Date

Page 106: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 3/14 Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Halls and Allied Infrastructure works

ANNEXURE 1

(Ref. Sub Clause 4.1.2 of Instructions To Bidders)

PROFORAMA OF LETETR OF AUTHORITY

To

The (Address)

Dear Sir,

We do herebyconfirm that M/s (Name and Address) is/are authorized to represent us to bid, negotiate and conclude the agreement on our behalf with you against Tender No MFDC01 for the Construction of Auction Halls, Harbour Management Building, other allied building and infrastructure

We confirm that we shall be bound by all and whatsoever our said agents shall commit.

Yours faithfully,

Signature:

Name & Designation:

For & on behalf of:

Page 107: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 4/14 Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Halls and Allied Infrastructure works

ANNEXURE 2

(Ref. Sub Clause 2.2.8 of Instructions to Bidders)

FORM OF BANK GUARANTEE FOR TENDER SECURITY/ BID SECURITY

(To be issued by a Scheduled Bank)

WHEREAS (Name of Tenderer) (hereinafter called "the Tenderer" has submitted its tender dated (date) for the execution of (Name of Contract) (hereinafter called "the Tender").

KNOW ALL MEN by these presents that we (name of Bank) of having our Registered Office at (hereinafter called "the

Bank") are bound unto the Maharashtra Fisheries Development Corporation (hereinafter called “ the E m p l o y e r ") i n t h e s u m o f Rs. (Rupees ) for which payment well andtruly to be made to the said Employer the Bank binds itself, its successors and assigns by these presents. Sealed with Common Seal of the said Bank this day of 2010. THE CONDITIONS of this obligation are:

a) If the Tenderer withdraws its Tender during the period of Tender validity specified in the Tender; or

b) If the Tenderer having been notified of the acceptance of his Tender by the Employer during the period of Tender Validity;

i. in the opinion of the Employer fails or refuses to execute the Agreement, if required; or

ii. fails or refuses to furnish the Performance Security, in accordance with Sub -Clause 4.2 of the General Conditions of Contract.

We undertake to pay to the Employer upto the above amount upon receipt of his first written demand, without the Employer having or required to substantiate his demand, amount claimed by him.

This guarantee will remain in force upto and including the date thirty (30) days after the date of expiry of the period of tender validity, and any demand in respect thereof should reach the Bank not later than the date of expiry of this guarantee.

Signature of the Bank

Signature of the Witness

Name of the Witness

Address of the Witness

Page 108: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 5/14 Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Halls and Allied Infrastructure works

ANNEXURE 3

(Ref. Sub Clause 2.1.11 of Instructions to Bidders and Sub Clause 4.2 of General Conditions of Contract)

PROFORMA OF IRREVOCABLE BANK GUARANTEE FOR CONTRACT PERFORMANCE

(To be submitted on Non-judicial Stamp Paper)

Ref Bank Guarantee No_ Date

To

The Managing Director,

Maharashtra Fisheries Development Corporation Ltd.

Dear Sirs,

WHEREAS (Name and Address of the Contractor) (hereinafter called “the Contractor” has undertaken, in pursuance of Tender No. MFDC01 to execute the work of “Construction of Auction Halls, Harbour Management Building , other allied buildings and infrastructure works,” (hereinafter called “the Contract”);

AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you with a Bank Guarantee by a recognized bank for the sum specified therein as Performance Security for compliance with his obligations in accordance with the Contract;

AND WHEREAS we [•] [name of the bank] (constituted and established under [•]) having our office at [•] (Phone No.: Fax No.:..Q) have unconditionally and irrevocably agreed to give the Contractor such a Bank Guarantee;

NOW THEREFORE we hereby undertake and affirm that we are the Guarantor and responsible to you, on behalf of the Contractor, upto a total of (amount of Guarantee) (in words), such sum being payable in the types and proportions of currencies in which the Contract Price is payable, and we hereby agree and undertake to pay you, upon your first written demand and without any demur, protest or argument, anysum or sums within the limits of (amount of Guarantee) as aforesaidwithout your needing to prove or to show grounds or reasons for your demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before presenting us with the demand.

We further, agree that no change or addition to or other modification of the terms of the Contract or of the Works to be performed thereunder or of any of the Contract documents

Page 109: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 6/14 Unison Project Management Pvt. Ltd.Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

which may be made between you and the Contractor shall in any way release us from any

liability under this guarantee and we hereby waive notice of any such change, addition or modification.

This guarantee shall be valid until the date of issue of the Performance Certificate.

“Notwithstanding anything contained herein: a) Our liability under this Bank Guarantee is unconditional and shall not exceed (amount of

Guarantee); b) This Bank Guarantee shall be valid upto issue of the Performance Certificate with a claim

period of [•] months.; c) A demand for payment under this Bank Guarantee shall be deemed to have been sufficiently

made if a claim in writing is sent by post or by fax or hand delivered to us to the above- mentioned address.

Dated this day of For (bank)

Authorised Signatories

Bank Seal

Page 110: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 7/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

ANNEXURE 4

(Ref. Sub Clause 1.6 of the General Conditions of Contract)

PROFORMA OF CONTRACT AGREEMENT

THIS AGREEMENT made at Mumbai on this day of 2017 between the Maharashtra Fisheries Development Corporation Limited (hereinafter called the “MFDC” which expression shall where the context so admits, includes its successors in office, affiliates and assigns) of the onepart and Messrs a company having its registered office at (hereinaftercalled “the CONTRACTOR” which expression shall, where the context so admits, includes its successors in office, affiliates and assigns) of the other part.

WHEREAS the MFDC invited tenders for the work “Construction of Auction Hall, Harbour

Management Building, other allied buildings and infrastructure works.” (Tender No. MFDC01) and whereas the Contractor submitted his Bid for the works dated which Bid was accepted by the MFDC by the letter of its Acceptance/intentbearing no

dated for the execution and completion of the Works and

Page 111: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 8/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

remedying of the defects therein and whereas the Contractor has tendered Bank Guarantee with the MFDC for a sum of Rs. (Rupees ) as Performance Security for the due performance of this Contract.

NOW THIS AGREEMENT WITNESSETH as follows:-

1. In this Agreement the words and expressions shall have the same meanings as are

respectively assigned to them in the Conditions of Contract hereinafter referred to.

2. The following documents annexed shall be deemed to form and be read and construed as part of this Agreement viz., a) The Letter of Acceptance/Intent b) The said Bid c) The Tender Call Notice d) The Instruction to Bidders/ Tenderers. e) The General Conditions of Contract f) The Special Conditions of Contract g) The Technical Specifications h) The Preamble to BOQ and Bill of Quantities i) All the Annexure to the bid j) The Appendix to Tender k) The Drawings l) The Tender Form m) The Addenda, issued, if any n) The written clarifications issued in response to queries raised during the

Pre-Bid Meeting. o) The correspondence exchanged between the Bidder & the Employer

3. In consideration of the payment to be made in terms of Contract by the MFDC to the Contractor as hereinafter mentioned, the Contractor DO and each of them DOTH severally and jointly hereby COVENANTS with the MFDC to carry out and complete within the stipulate period the work of “Construction of Auction Halls, Harbour Management Building, other allied buildings and infrastructure works” ” (Tender No. MFCD01) and all other ancillary work as described in the drawings, in accordance with the Specifications and in conformity in all respects with the provisions of the Contract or which are to be implied there from or may be reasonably necessary and remedying any defects therein as provided in the Conditions of Contract.

4. In consideration of the Contract for carrying out and completing the work within a

stipulated period the MFDC does hereby agree to pay the Contractor the respective amounts for the work actually done by him and approved by the MFDC at the Scheduled Rates and such other sum payable to the Contractor under the provisions of the Contract, at such time and in such manner as provided for in the Contract.

5. The Contractor doth hereby agree to pay such sums as may be due to the MFDC for the

service(s) rendered by the MFDCto the Contractor in the course of provision, execution, completion of the Contract work, as may become due and payable to the MFDC in respect of the Contract work and such other sums as may become due and payable to the MFDC towards loss, damage to the MFDC structures, equipment, at such time and in such manner as is provided in the Contract.

6. It is specifically and distinctly understood and agreed between the MFDC and the

Contractor shall have no right, title or interest in the Site made available by the MFDC for the Contract work or in the work executed on the said site by the Contractor or in the

Page 112: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 9/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

goods, articles, materials etc. brought on the said site (unless the same actually belongs to the Contractor) and the Contractor shall not have nor deemed to have any lien whatsoever or charge for unpaid bills nor shall be entitled to assume or retain possession or control of the Site or structures under any circumstances whatsoever and the MFDC shall have an absolute and unfettered right to take full possession of the Site and structures and to remove the Contractor, his servants, agents and materials belonging to the Contractor and lying on the Site.

7. The Contractor shall be allowed to enter upon the site for execution of the works only as

a licensee simpliciter and shall not have any claim, right, title or interest in the Site made available by the MFDC for execution of the Works. The Contractor shall use such site allotted by the MFDC only and exclusively for the Works.

8. On termination of the Contract, the Contractor shall forthwith hand over possession of

the Site together with the Works whenever called upon to do so by the MFDC or any of his representative(s) to the MFDC without any let or hindrance or demur whatsoever.

9. All the materials excavated during the execution of the works shall unless otherwise

explicitly agreed under this Contract, exclusively belong to the MFDC and the Contract shall have no right, title, interest or claim over the same and such excavated materials should be disposed off according to the instructions in writing issued from time to time by the MFDC or his representative.

IN WITNESS whereof the Contractor has hereunto subscribed and set his respective hand and seal through the duly constituted Attorney of and for and on behalf of the Contractor and the of the MFDC for and on behalf of the MFDC has set his hand and seal and the common seal of the MFDC had been hereunto affixed the day and year first above written.

SIGNED, SEALED AND DELIVERED

by Constituted Attorney to be duly constituted attorney of for and on behalf of

SIGNED, SEALED AND DELIVERED

by

the

of the MFDC in presence of

The Common Seal of the MFDC was affixed in the presence of

Page 113: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 10/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

ANNEXURE 5

(Ref. Clause No. 4.1.3 of Instructions to Bidders)

AVERAGE ANNUAL FINANCIAL TURNOVER DURING THE LAST THREE YEARS

ENDING 31ST MARCH 2017

Sr. No. Year Financial Turnover (Rs)

1

2

3

Total

Average

Certified by C.A. Stamp and Signature of the C.A.

Stamp and Signature of the Bidder

Note : Certified copy of Balance sheet

Page 114: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 11/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

ANNEXURE 6

(Ref. Sub Clause 4.1.1 (d) of Instructions To Bidders)

LIST OF MAJOR EQUIPMENT PROPOSED

Sr. No.

Equipment proposed

Capacity/Size of the

Equipment

Year of built Type of Ownership

Remarks

Note:

The bidder is requested to give relevant and complete information. Additional sheets may be used if necessary.

DATE SIGNATURE OF BIDDER

Page 115: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 12/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

ANNEXURE 7

ORGANIZATION CHART FURNISHING THE NAMES OF KEY PERSONNEL & THEIR BIO

DATA TO BE DEPLYOED FOR THIS PROJECT

(Ref. Sub Clause 4.1.1 (c) of Instructions To Bidders)

The bidder should provide the Proposed Organization Chart showing the structure of the organization, including the names and designation of the responsible personnel. The bidder shall also provide the Bio data of the Key Personnel to be deployed for this project.

Sr. No.

Description Information

1. Name of Bidder

2. Name of Company

3. Type of Firm Proprietary/Partnership/Joint Venture/Private Limited/Limited Companies

4. Company Registration No. & Date

5. Name of Directors

6. Office Details

i) Address

ii). Contact No. & E-mail

7. PAN No. of Company

8. GST Registration No .

9. PF Registration No

10. Details of Key Personnel with their brief CV

Attached Separately

Page 116: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 13/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

ANNEXURE 8

PROFORMA OF BANK GUARANTEE FOR SECURITY AGAINST MOBILIZATION ADVANCE

(Ref. Sub Clause 13.2.1 of General Conditions of Contract)

Page 117: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

Page: 14/14

Unison Project Management Pvt. Ltd.

Volume-I Contract Information – Annexures RF

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

ANNEXURE 9

DOCUMENTS TO BE ATTACHED

(Ref. Sub Clause 4.1.4 of Instructions to Bidders)

Sr. No. Documents

1. Company Profile

2. Certificate of Incorporation & GST Registration Certificate

3. CA Certificate for Turn Over with Audited Balance Sheet for Last 3 Years

4. Project Completion Certificate from Clients

5. Statement showing work in progress with contract value & Completion Period

Page 118: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 1/4

Volume-I Contract Information – Appendix to Tender RF

APPENDIX TO TENDER

Sr. No.

Item Reference Clause Particulars

1 Time for Completion of Work 2.1.4 of I.T.B. and

7.2 of G.C.C.

18 months from the date of Commencement

2 Date, time and Place of Pre-

bid

2.1.5 of ITB As per notification

3 Employer 2.1.6 of I.T.B. and

1.1.2.2 of G.C.C.

The Managing Director,

Maharashtra State Fisheries Development

Corporation Ltd.

4 Performance Security

a) Amount of Performance

Security

b) Delivery/Submission of

performance security

2.1.11 of I.T.B.

and 4.2 of G.C.C

10% of the accepted Contract Amount in Rupees in

the form of Bank Guarantee of any

Nationalised/Scheduled (Except Co-operative)

acceptable to the Employer as per the Performa

enclosed in Annexure 3.

Within 10 days after receiving the Letter of

Acceptance.

5 Amount of Bid Security/EMD 2.2.8 of ITB 20 Lakhs

6 Bid validity 2.3.3 of ITB 90 days from the date of Bid Submission

7 Last date and time of

submission of bid

7.1 (c) and 8.1 of

I.T.B.

8 Date, time and Place of

opening of Technical Bid

(Part-I)

12.1 of I.T.B.

9 Contractor 1.1.2.3 of G.C.C. Successful Bidder

10 Communication(Electronic

transmission )

1.3 of G.C.C Fax and E-mail

11 Governing Law 1.4 of G.C.C Constitution of India

12 Ruling language 1.4 of G.C.C English

13 Language for communication 1.4 of G.C.C English / Hindi / Marathi

14 Contract Agreement 1.6 of G.C.C. Within 14 days after the Contractor receives the

Letter of Acceptance of Bid.

15 Joint and Several Liability – 1.14 of G.C.C. Joint Ventures of more than two parties are not

permitted

16 Time for access to the site to

commence the Work

2.1 of G.C.C. From the Commencement Date.

Page 119: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 2/4

Volume-I Contract Information – Appendix to Tender RF

17 Commencement Date 7.1 of G.C.C. 14 days from the date of issue of the Letter of

Acceptance of Bid.

17.1 Actual Commencement Date 7.1 of G.C.C. 14 days from the date of issue of the Letter of

Acceptance of Bid having the prerequisites of

submission of performance security and Advance

Bank Guarantee & evidences of Insurance policies

procured.

18 Liquidated Damages 7.2 of G.C.C. Three milestones are specified hereunder as M1,

M2 and M3. The Liquidated Damages applicable for

non achievement of these mile stone shall be

operational as under:

a) Non Achievement of Mile Stone M1:

Rs 5 Lakhs per week of part thereof shall be

levied from the time specified or the extended

time as per contract provisions, until its

achievement.

However in case Mile Stone M2 is completed by

the time specified or the extended time as per

contract provisions, the Liquated Damages so

recovered against M1 shall be released.

b) Non Achievement of Mile Stone M2:

Rs 7 Lakhs per week of part thereof shall be

levied from the time specified or the extended

time as per contract provisions, until its

achievement.

However in case Mile Stone M3 is completed by

the time specified or the extended time as per

contract provisions, the Liquated Damages so

recovered against M1 & M2 shall be released.

c) Non Achievement of Mile Stone M3

(Completion of Entire work under Contract):

0.5% of the Contract Amount per week or part

thereof:

Page 120: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 3/4

Volume-I Contract Information – Appendix to Tender RF

The Liquidated Damages levied of non achievement

of Mile Stones M1 and/ or M2 and/or M3 shall

subject to maximum of 10 % of the Accepted

Contract Amount

19 Defect Liability Period 10 of G.C.C 60 months from the date of taking over for full work.

20 Programme –

Submission of Detailed time

programme

7.3 of G.C.C. The Contractor shall submit a detailed time

programme (resource based activity linked in the

form of CPM/PERT network and financial progress

in form of “S” curve) to the Engineer, for his

consent, within 28 days after receiving the notice

of commencement of work (Clause 7.1 of G.C.C.).

21 Programme –

Contract Milestone

7.3 of G.C.C.

Mile

Stone

no.

Particular Time period

from

commencement

date M1 Construction of

Auction Hall Civil

Works complete in all

respect.

10 months

M2 Construction of all

other buildings

14 months

M3 Completion of Entire work

18 months

22 Currency of Payment 12.3 and 13.15 of

G.C.C.

Indian Rupees

23 Advances Payment –

a) Mobilization Advance

13.2.1 of G.C.C.

Deleted

Page 121: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works

Unison Project Management Pvt. Ltd. Page: 4/4

Volume-I Contract Information – Appendix to Tender RF

24

Retention Money 13.4 and 13.9 of

G.C.C

• Limit of retention money - 5% of Accepted Contract Price.

• Percentage of retention money – 5 % of value of each Interim Bill. After reaching 2.5% of the Contract Price, the contractor can replace it by a Bank Guarantee of equivalent amount. Balance retention money will be continued to be deducted through Interim Bills at the rate of 5 % of the bill amount.

• The Bank guarantee against retention money (2.5% of contract value) will be returned to the contractor within 30 days from the start of Defects Liability Period.

• The balance cash retention money (2.5% of the contract value) will be released at the end of Defects Liability Period.

25 Minimum Amount of Interim

Payment certificate

13.5 Rs.75 Lacs

26 Period for submission of

Insurances:

Evidence of Insurance

17.1 of G.C.C. The Contractor shall provide evidence to the Employer prior to the start of work at the Site that the insurances required under the Contract have been effected and shall, within 84 days of the Commencement Date, provide the insurance policies to the Employer.

27 Minimum Amount of Insurance 17.8 of G.C.C. Rs. 1 million per occurrence.

Number of occurrences unlimited.

28 Payments to Nominated

Subcontractors

4.27.4 of S.P.C. Co-ordination charges - 3 % in addition to the

payment made to the Nominated Sub-Contractor for

the works.

29 ENGINEER 1.1.2.4 of G.C.C. Unison Project Management Pvt. Ltd. 11-12, Building No. 3, S. D. C. Area, Poornanagar Complex, Chikhali, Pimpri, Pune 411 019, Maharashtra.

(020) 2749 2357 / 2749 0594

Page 122: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 1/1 Volume-I Contract Information – Checklist RF

Check List

Sr. No. Description Yes No

1 Copy Tender Document Payment receipt.

2 EMD

(Copy of BG/DD/Receipt of online payment) Refer Annexure 2

3 Submission Letter

4 Annexure 1 Letter of Authority duly Signed.

5 Annexure 5 Average Annual Turnover along with Certified copy by CA and Balance sheets.

6 Annexure 6 List of major equipment proposed along with proof of ownership.

7 Annexure 7 Organization chart furnishing the names of key personnel & their bio data to be deployed for this project

8 Detail Approach & Methodology.

9 Un priced Tender Document duly signed.

10 Volume 4 Price Bid duly signed.

11 Nature of similar jobs with certificate of completion from owner along with cost of the work

12 In Case of JV attach Memorandum of Understanding

13 Annexure 9 Documents to be Attached

Page 123: MAHARASHTRA FISHERIES DEVELOPMENT ...adf.maharashtra.etenders.in/tpoimages/adf/tender/Tender...Tender Reference code – MFDC-CIVIL-01/432/2017, Dtd. 20/11/2017 Dear Sir(s) Maharashtra

MAHARASHTRA FISHRIES DEVELOPMENT CORPORATION

Modernization of Sassoon Dock

Construction of Auction Hall and Allied Infrastructure works Unison Project Management Pvt. Ltd. Page: 2/1 Volume-I Contract Information – Checklist RF