Magnet Controls GroupOctober 4, 20061
Scope, Cost Estimate and Schedule
To Complete The
LCLS Magnet PS Controls
P Bellomo and Kristi Luchini
Magnet Controls GroupOctober 4, 20062
Topics
Scope
ETC
DescriptionsAreas
Intermediate Power Supplies and Controls
MCOR Power Supplies and Controls
Kicker Pulsers
Schedule
Cost Details
Magnet Controls GroupOctober 4, 20063
Scope
Magnet power supplies and associated controls
Hardware from dc output terminals on power supply to the EPICS - Ethernet Interface. Local control software
Includes
Power supplies, power supply controllers, VME controls, PLCs current transductors, and intra-rack cables, rack mounting and other miscellaneous equipment. ED&I, M&S and Assembly.
Does not include
Racks, long haul cables, global control software, field installation
Areas – primarily downstream of Tune-up Dump
Complete by March 31, 2008
Magnet Controls GroupOctober 4, 20064
Scope
Magnet Controls GroupOctober 4, 20065
Estimate to Complete
WBS Task EDI (k$) MS Labor Comments
1.01.03.05.09 Global 772 0 0 EDI + Management
1.03.02.04.01 1.03.02.04.02 1.03.02.04.03
LINAC 341 1,193 170All areas, except Injector and Undulator
1.04.02.08 Undulator 29 200 57
2.03.02.04.01 2.03.02.04.02 2.03.02.04.03
Contingency 0 94 0Parts needed to ensure success
NA Totals 1,141 1,487 228
Grand Total 2,856
Estimated Cost (k$)
Magnet Controls GroupOctober 4, 20066
Areas
Areas
Injector, Sector 21 and BC1 – needed for first injection to Tune-up Dump at BC1, field test systems only
Magnet Controls GroupOctober 4, 20067
Areas - New Systems - Injector, Sector 21 and BC1
Field test 6 new Intermediate and 96 new MCOR systems
Magnet Controls GroupOctober 4, 20068
Areas - Sector 21 QE System Modification
Bulk PS
Boost PS
Q21201
Q21301
Q21401…
Q21901
SLC Mode
Bulk PS
Boost PS
Q21201
Q21301
Q21401…
Q21901
LCLS Mode
Isolation Switch
Reversing/Shorting Switch
Magnet Controls GroupOctober 4, 20069
Areas - New Systems Downstream of the Tune-up Dump
Sector 24, BC2, BSY, LTU, Undulator, Dump
32 new Intermediate systems, typically 10kW and 15kW rated
105 new MCOR systems, typically 240W rated (33 of these are in the Undulator under recently added scope)
2 new pulsed kicker systems
27 new and reused racks
Magnet Controls GroupOctober 4, 200610
Intermediate Power Supplies
Magnet Controls GroupOctober 4, 200611
IE Power, Incorporated12 Falconer Drive, Unit 15Mississauga, OntarioCanada L5N [email protected]
• 2.5 kW to 22.5 kW
• 208 V / 480 V input
• Series and parallelable
• 27cm H*48cm W*61cm D
• 8.74” * 19” * 24”
Intermediate Power Supply - Front View
Magnet Controls GroupOctober 4, 200612
Intermediate Power Supply - Rear View
J1 J2
+ -DC Output AC Input
DC Output Cables
TerminalCover
Totally covered connectors
Magnet Controls GroupOctober 4, 200613
Intermediate PS - Ethernet PS Controller (EPSC)
Magnet Controls GroupOctober 4, 200614
Intermediate PS - EPSC
PurposeReplaces the PEP 2 Bitbus Power Supply Controller
Provides commonality with the Bitbus Controller
Performance better then the Bitbus Controller 20bit ADC 24bit DAC
Equal to or less expensive then Bitbus ControllerRationale for Replacement
Bitbus DAC obsolete - new DAC required
Bitbus network obsolete - convert to Ethernet (10/100 Mb/sec over UDP)
FPGAs at end of life and not good choices for new designs
8044 processor is obsolete
Use standard +/-15VDC power supply
Magnet Controls GroupOctober 4, 200615
Intermediate PS - EPSC
FunctionsPrecision current regulation
Readback of current, voltage, and ground current
Ground fault detection and protection
Hardware magnet and power supply protection
Fault latching and reporting
Simple low cost serial communication to central control
Control of power supplies of many ratings, types and from different vendors
Standard cables (Cat 5 UTP and D-sub computer cables)
Magnet Controls GroupOctober 4, 200616
GMW Associates955 Industrial RoadSan Carlos, CA 94070650-802-8292 [email protected]
+/- 150A or +/- 600A Accuracy < 2ppm Linearity < 1ppm 0.3 ppm / C Bandwidth 100kHz
Intermediate PS - DC Current Transductors
Magnet Controls GroupOctober 4, 200617
Intermediate PS - System Architecture
Terminal Server
Network SwitchSLAC
Ethernet PS Controller
Ethernet
OPI
EPICSIOC
Intermediate PSTransductors
Interlocks
Magnet Controls GroupOctober 4, 200618
The MCOR Systems
• Power 6A, 12A, and 30A correctors, small quadrupoles, and trim magnets that require unipolar or bipolar current
• MCOR6 - 40V, 6A, 240W
• MCOR12 - 40V, 12A, 480W
• MCOR30 – 40V, 30A, 1,200W
Magnet Controls GroupOctober 4, 200619
The MCOR6 and MCOR12
Magnet Controls GroupOctober 4, 200620
The MCOR30
Magnet Controls GroupOctober 4, 200621
MCOR Systems - PLC Uses
Uses
SPEAR 3 experienced MCOR30 bridge MOSFET failures during bulk power supply turn on – need PLC for soft-start
MCORs not provided with ground fault detection. A PLC with external circuitry is needed
MCORs power some magnets that are water-cooled. MCORs are not provided with a Klixon or water flow switch interface. A PLC is needed
Provides bulk power supply remote turn-on and turn-off
Provides bulk power supply output voltage and current monitoring
Magnet Controls GroupOctober 4, 200622
MCOR System Architecture
OPI OPI
EPICS IOC
VME Crate
Bulk PS
MCOR Gnd Current
Monitor
MCOR12
16 Magnets@12Amps max
MCOR Soft-Start
Magnet Controls GroupOctober 4, 200623
MCOR VME Controls
Acromag IP231-16E: MCOR DAC (control)Bipolar voltage +/- 10V 16-bit resolution, 16-channels, single-ended
Hytec IP-ADC-8413: MCOR ADC (monitor)Bipolar voltage +/- 10V16-bit resolution, 16-channel, differential
Acromag IP-440-2E DI: MCOR Ground I Monitor (monitor)32-ChannelInput voltage range +/- 16V to +/- 40VOptically Isolated
Acromag IP-445-E DO: MCOR Ground I Monitor (control)32-ChannelVoltage range +/-60VOptically Isolated
Magnet Controls GroupOctober 4, 200624
MCOR VME Controls Continued
MVME6100 CPU – Power PCTwo Ethernet portsTwo PMC slots
Wiener VME-64X Crate with fan and Ethernet Control
Acromag AVME9670 - 64X IP Carrier (1 per MCOR crate)4 Ports
Acromag Tran-200: Transition Module Install in rear of VME crate4 SCSI-2 Connectors (50-pin)
Magnet Controls GroupOctober 4, 200625
The Kicker Pulsers
Q D
+
C
CAP
CHARGING
HVPS
DRIVER
ONE-SHOT> 1.5 msec
GND FAULTDETECTION
PULSE CURRENTAMPLIFIER
TRIGGER
CT+
CT-
PULSER CONTROLLER
KICKER PULSER
BXKIKOR
BYKIK
HV REF
HV READBACK
HVPS STATUS
Magnet Controls GroupOctober 4, 200626
The Kicker Pulsers
BXKIK BYKIK unit
Peak Current 263 263 A
Inductance 0.15 0.6 mH
Resistance 5 20 mΩ
Voltage 150 600 V
PRR 120 120 Hz
Magnet Controls GroupOctober 4, 200627
The Schedule
Magnet Controls GroupOctober 4, 200628
Materials CostItem Quantity Cost Each (k$) Extended Cost (k$)
Magnets from Intermediate PS 32 19.9 637
Intermerdiate PS 10 and 15kW 38 8.5 323
Intermediate PS 15kW 14 12.0 168
Power supply controllers 40 2.5 100
Transductors 70 0.7 46
Magnets from MCORs 105 5.9 616
MCOR PS 120 2.0 240
Interface boards, crates,blowers 15 5.0 75
MCOR bulk PS 10 8.5 85
PLC and VME crates 9 24.0 216
Kicker magnets from pulsers 2 72.0 144
Network Switches and Servers 7 3.0 21
Racks, Accessories, Misc Parts 27 2.5 68
Total Cost 1,487
Magnet Controls GroupOctober 4, 200629
EDI
Person Task Rate (k$/mo) Percent time Duration (mos) Cost (k$)
Management 25% 15 74
Engineering 25% 13 74
Engineering 50% 13 129
Testing 25% 15 74
Engineering 35% 13 90
Testing 15% 15 45
Management 25% 15 70
Engineering 35% 13 85
Programming 25% 13 61
Testing 15% 15 42
Debbie Rogind Programming 18.6 100% 3 56
Coordination 50% 13 90
Programming 15% 11 23
Coordinator Design and purchase 13.8 75% 14 145
Technician Testing 11.1 50% 15 83
1,141
Associate 13.8
Dave MacNair 19.8
Kristi Luchini 18.6
Paul Bellomo 19.8
Antonio de Lira 19.8
Magnet Controls GroupOctober 4, 200630
Labor – last Slide
Assemble systems into 27 racks and wire8 techs * 4 months * $8.3k/month * 1.34 overhead = $341k