LVLS-DCI-PUN-001 (L26-HALLWAY).docx
Transcript of LVLS-DCI-PUN-001 (L26-HALLWAY).docx
Date
Punchlist
design coordinates, inc.LVLS-DCI-PUN-2600THE LEVELS Phase 1Pacific Rim, Corner Petron Road, Filinvest Corporate City, Alabang, Muntinlupa City
Date:03 FEB 2015
Subject:PUNCHLIST
Contractor:(See Responsible)
Area:LEVEL 26 HALLWAY
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
I. Elevator Lobby
Floor1. CleaningClean tilesFEB. 11, 2015TRASS
2. CleaningRemove paint stain on tilesFEB. 11, 2015TRASS
3. ApplicationImprove grout applicationFEB. 11, 2015EEI
4. Installation Unfinished aluminum base guard termination FEB. 11, 2015TRASS
Wall5. Cleaning Remove paint stain on laminated wall, steel grooveFEB. 11, 2015TRASS
6. PaintingRetouch wall paintFEB. 11, 2015TRASS
7. ApplicationImprove sealant application on windowFEB. 11, 2015AP
8. Cleaning Remove paint stain on window panel and window frameFEB. 11, 2015TRASS
9. Cleaning Remove sealant stain on window panelFEB. 11, 2015AP
10. Cleaning Clean tubularFEB. 11, 2015AP
11. Installation Rectify inverted beam edgeFEB. 11, 2015TRASS
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
12. Cleaning Clean inverted beamFEB. 11, 2015TRASS
13. InstallationNo cover on floor polish outletFEB. 11, 2015TBI
14. InstallationRectify cladding edgeFEB. 11, 2015TRASS
15. CleaningClean stainless steelFEB. 11, 2015TRASS
16. CleaningClean level signageFEB. 11, 2015TRASS
17. CleaningRemove newspaper and tape on elevator doorFEB. 11, 2015TRASS
18. PaintingPeeling of paint on wallFEB. 11, 2015TRASS
19. InstallationUnaligned elevator buttonFEB. 11, 2015IEEI
20. InstallationRectify gap between laminated wall and stainless steelFEB. 11, 2015TRASS
21. CleaningRemove tape on corner guardFEB. 11, 2015TRASS
22. CleaningClean fire alarm annunciatorFEB. 11, 2015TBI
23. InstallationProvide cover on switch and chimeFEB. 11, 2015TBI
24. InstallationProvide pipe chase cover and locksetFEB. 11, 2015TRASS
Ceiling25. CleaningRemove paint stain on sprinkler and lighting fixtureFEB. 11, 2015TRASS
26. CleaningRemove sprinkler coverFEB. 11, 2015TRASS
27. InstallationRectify cove edgeFEB. 11, 2015TRASS
28. Painting Retouch ceiling paintFEB. 11, 2015TRASS
29. Painting Retouch paint around smoke detectorFEB. 11, 2015TRASS
30. Installation Rectify shadow lineFEB. 11, 2015TRASS
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
31. CleaningClean ceilingFEB. 11, 2015TRASS
II. Exit 1
Floor32. CleaningClean tilesFEB. 11, 2015TRASS
33. CleaningRemove stains and tape on tilesFEB. 11, 2015TRASS
Wall34. PaintingRetouch base paint ( not complying to specs)FEB. 11, 2015TRASS
35. CleaningRemove tape on wall, fire alarmFEB. 11, 2015TRASS
36. CleaningClean tape marks on pipe chase jambFEB. 11, 2015TRASS
37. Installation 4 pipe chase cover not installedFEB. 11, 2015TRASS
38. CleaningRemove paint stain on telephone jack, fire alarm, and fire alarm buttonFEB. 11, 2015TRASS
39. PaintingRetouch paint around fire alarm and fire alarm buttonFEB. 11, 2015TRASS
40. Painting Retouch wall paintFEB. 11, 2015TRASS
41. CleaningRemove dirt stains on wallFEB. 11, 2015TRASS
42. InstallationProvide doorbell coverFEB. 11, 2015TBI
43. CleaningClean unit signageFEB. 11, 2015TRASS
44. CleaningClean exit signageFEB. 11, 2015TBI
45. Painting Retouch paint around emergency lightFEB. 11, 2015TRASS
46. Installation Awning window hard to closeFEB. 11, 2015AP
47. Installation Rectify door sealFEB. 11, 2015TRASS
48. InstallationNo stair signageFEB. 11, 2015M&G
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
49. Installation Rectify wall edges along window and fire exit doorFEB. 11, 2015TRASS
50. CleaningClean window frame and window panelFEB. 11, 2015AP
51. CleaningRemove paint stain on window frame and window panelFEB. 11, 2015AP
52. CleaningClean door lockset, door panel, and door window frameFEB. 11, 2015TRASS
53. CleaningRemove paint stain on panic barFEB. 11, 2015TRASS
54. CleaningRemove tape on panic bar, door hingeFEB. 11, 2015TRASS
55. CleaningRemove paint stain and tape on door handleFEB. 11, 2015TRASS
Ceiling56. InstallationRectify gap on manholeFEB. 11, 2015TRASS
57. Installation Rectify shadow lineFEB. 11, 2015TRASS
58. CleaningClean all escutcheonFEB. 11, 2015PPDC
59. Installation Rectify gap on lighting fixturesFEB. 11, 2015TBI
60. Painting Retouch ceiling paintFEB. 11, 2015TRASS
61. CleaningRemove cover and clip on sprinklerFEB. 11, 2015PPDC
III. Exit 2
Floor62. Cleaning Clean floor tilesFEB. 11, 2015TRASS
63. Application Improve grout application
FEB. 11, 2015EEI
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
Wall64. Painting Retouch base paint and not complying to specsFEB. 11, 2015TRASS
65. Painting Retouch wall paintFEB. 11, 2015TRASS
66. CleaningRemove dirt stain on wallFEB. 11, 2015TRASS
67. Installation Rectify wall edgesFEB. 11, 2015TRASS
68. Installation (3) Unfinished doorbell termination FEB. 11, 2015TBI
69. Installation Provide (3) doorbell coverFEB. 11, 2015TBI
70. CleaningClean unit signageFEB. 11, 2015TRASS
71. Painting Retouch paint around fire alarm, fire alarm, and telephone jackFEB. 11, 2015TRASS
72. CleaningRemove paint stain on fire alarm and fire alarm buttonFEB. 11, 2015TRASS
73. Installation (3) pipe chase cover not installedFEB. 11, 2015TRASS
74. CleaningRemove paint stain on pipe chase jambsFEB. 11, 2015TRASS
75. Installation Rectify door sealFEB. 11, 2015TRASS
76. CleaningClean lockset, panic bar, door window, door panel, door hinge, and door handleFEB. 11, 2015TRASS
77. CleaningRemove tape on door window frame, panic bar, door hinge and door handleFEB. 11, 2015TRASS
78. Painting Retouch paint around emergency light
FEB. 11, 2015TRASS
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
79. CleaningRemove paint stain on window frameFEB. 11, 2015AP
80. CleaningClean window panel and window frameFEB. 11, 2015AP
Ceiling81. Installation Rectify shadow lineFEB. 11, 2015TRASS
82. Installation Unfinished light fixture termination FEB. 11, 2015TBI
83. CleaningClean all escutcheonFEB. 11, 2015PPDC
84. CleaningRemove cover on all escutcheonFEB. 11, 2015PPDC
85. Painting Retouch ceiling paintFEB. 11, 2015TRASS
86. Installation Rectify hole on ceilingFEB. 11, 2015TRASS
IV. EE Room
Floor87. InstallationImprove floor finishFEB. 11, 2015TBI
88. CleaningRemove paint stainFEB. 11, 2015TBI
89. Cleaning
Clean floorFEB. 11, 2015TBI
90. InstallationImprove zucalllo finishFEB. 11, 2015TBI
Wall91. InstallationIncomplete bushingFEB. 11, 2015TBI
92. InstallationCover not installed on panel boardFEB. 11, 2015TBI
93. CleaningRemove stains on wallFEB. 11, 2015TBI
94. InstallationNo cover on pull boxFEB. 11, 2015TBI
95. InstallationProvide exhaust coverFEB. 11, 2015TBI
96. InstallationProvide cover on 4x4 pull boxFEB. 11, 2015TBI
97. Cleaning Clean and remove paint satin on angle barsFEB. 11, 2015TBI
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
98. InstallationRectify door jambFEB. 11, 2015TBI
99. Installation 6 missing screw on pull boxFEB. 11, 2015TBI
100. Installation Improve wall penetrationFEB. 11, 2015TBI
101. Painting Improve wall paintFEB. 11, 2015TBI
Ceiling102. Installation Improve cover installation on pull boxFEB. 11, 2015TBI
103. Cleaning Remove stains on ceilingFEB. 11, 2015TBI
104. Application No sealant on ceiling penetrationFEB. 11, 2015TBI
105. InstallationExposed pipeFEB. 11, 2015TBI
106. Installation Improve installation of smoke detectorFEB. 11, 2015TBI
107. Installation Rectify claddingFEB. 11, 2015TBI
V. Refuse Room
Floor108. Cleaning Clean tilesFEB. 11, 2015TRASS
109. CleaningRemove paint stain on tilesFEB. 11, 2015TRASS
110. Application Improve grout applicationFEB. 11, 2015EEI
111. InstallationUnfinished floor drain installationFEB. 11, 2015PPDC
Wall112. Painting Improve paint on door jambFEB. 11, 2015TRASS
113. CleaningRemove paint stain on signageFEB. 11, 2015TRASS
114. CleaningRemove tape on door hingeFEB. 11, 2015TRASS
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
115. CleaningRemove paint stain on door hinge and door handleFEB. 11, 2015TRASS
116. Painting Rectify door panel paintFEB. 11, 2015TRASS
117. InstallationRectify gap on locksetFEB. 11, 2015TRASS
118. InstallationUnfinished zuccaloFEB. 11, 2015TRASS
119. InstallationRectify gap around pipeFEB. 11, 2015PPDC
120. InstallationRectify gap around exhaustFEB. 11, 2015SIC
121. InstallationUneven tilesFEB. 11, 2015TRASS
122. Application Improve grout applicationFEB. 11, 2015EEI
123. InstallationImprove wall plasteringFEB. 11, 2015TRASS
Ceiling124. Cleaning Remove paint stain on lighting fixture FEB. 11, 2015TRASS
125. Painting Uneven ceiling paintFEB. 11, 2015TRASS
126. PaintingNo paint on cover plateFEB. 11, 2015TRASS
127. InstallationRectify ceiling edgeFEB. 11, 2015TRASS
128. InstallationRectify gap around pipeFEB. 11, 2015PPDC
VI. Service Lobby
Floor129. CleaningRemove carton and garbageFEB. 11, 2015TRASS
130. Cleaning Remove paint stain on tilesFEB. 11, 2015TRASS
131. ApplicationImprove grout applicationFEB. 11, 2015EEI
132. Cleaning Clean tilesFEB. 11, 2015TRASS
Wall133. Painting Retouch door jamb paintFEB. 11, 2015TRASS
134. Cleaning Remove paint stain on door hinge, door window panel, door panel, door handleFEB. 11, 2015TRASS
LocationItems of workRemarksRequired date of completion and rectificationResponsibleJoint Inspected andAccepted by:
ContractorDCI/FAI/C+A/Proexcel/CRC
135. Cleaning Clean service room and disposal room signageFEB. 11, 2015TRASS
136. CleaningRemove lockset coverFEB. 11, 2015TRASS
137. Cleaning Clean elevator button and elevator annunciatorFEB. 11, 2015TRASS
138. Painting Retouch paint around elevator buttonFEB. 11, 2015TRASS
139. Cleaning Clean level signageFEB. 11, 2015TRASS
140. Painting Retouch wall paintFEB. 11, 2015TRASS
141. Cleaning Remove newspaper and tape on elevator doorFEB. 11, 2015TRASS
142. Cleaning Clean elevator doorFEB. 11, 2015TRASS
143. Installation Rectify elevator door edgeFEB. 11, 2015TRASS
Ceiling144. Cleaning Remove stain on pipesFEB. 11, 2015TRASS
145. Installation Rectify gapFEB. 11, 2015TRASS
146. Painting Retouch paint on cover plateFEB. 11, 2015TRASS
147. Painting Retouch ceiling paintFEB. 11, 2015TRASS
148. Installation Rectify cladding edgeFEB. 11, 2015TRASS
All defective works (whether the result of poor workmanship, of defective materials, damages through carelessness or of other causes) found to exist shall be rectified immediately. Work and materials not conforming to the standards shall be replaced or remedied in an acceptable manner.
All corrective works of any description, removal and replacement of unsatisfactory materials shall be done at the Contractors expense.
Prepared by:DESIGN COORDINATES, INC.Construction Project Managers
Concurred by: FAI C+A CRC BM-PRO EXCEL
__________________ DCIDCI-PUN rev. 02Page 10 of 10