LEED HVAC DesignLEED Commissioning
How Does the MechanicalEngineer & Cx ProviderImpact the Success of aSustainable Building?
Presented by MBO Inc.
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
2/39
Your Speakers for Today
Jorge Torres CotoBuilding Systems Commissioning EngineerMBO, Inc.
Brought to you by
MBO, Inc.
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
3/39
Side Note
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
4/39
Outline
What is LEED?
Benefits and cost of LEED HVAC design and Cx
HVAC design for LEED Requirements and Tips WEc2, WEc3.1, WEc3.2
EAp1, EAp2, EAp3
EAc1, EAc3, EAc4, EAc5
EQp1
EQc1, EQc5, EQc6.2, EQc7.1, EQc7.2
Examples and experience on LEED HVAC design and Cx
Who can be the Cx Provider?
Going beyond the LEED requirements and expectations
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
5/39
What is LEED?
LEED = Leadership in Energy & Environmental Design
Developed by USGBC (U.S. Green BuildingCouncil) in conjunction with
DOE
EPA
GSA (U.S. General Services Administration
DoD
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
6/39
What is LEED?
The economic goals of the LEED program
include: Reduced or neutralized first cost
Enhanced asset value/increased profits
Optimized life cycle economic performance
Improved productivity (due to a healthier indoorenvironment)
Reduced liability
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
7/39
Why Does It Matter?
BECAUSE IT IS THE RIGHT THING TO DO!
Some states, cities, and/or the FederalGovernment offer tax incentives for buildings
that meet Green building codes or become
LEED Certified.
GSA, state, and some municipalities requirenew building projects to meet LEED.
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
8/39
LEED Certifications
LEED-NC (New Construction)
LEED-CI (Commercial Interiors)
LEED-EB (Existing Buildings)
LEED-CS (Core & Shell; Commercial)
LEED-H (Single Family Residential)
LEED-ND (Residential Neighborhood
Developments)
LEED-Schools
Other in the works
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
9/39
LEED-NC
Four Levels of LEED Certification
LEED Certified 26-32 points LEED Silver 33-38 points
LEED Gold 39-51 points
LEED Platinum 52-69 points
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
10/39
Water
Efficiency
8%Energy &
Atmosphere
27%
Materials &
Resources
20%
Sustainable
Sites
22%
Indoor
Environmental
Quality
23%
Five LEED credit categories
*NOTE: 60% of the points are WE, EA and IEQ
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
11/39
LEED-NC
ASS levels of certification
Half Assed LEED equivalent Cheap Assed Minimum (after-thought)
Bad Ass Integrated Design
Kick Ass Everybody bought in
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
12/39
LEED-NC
Seven Prerequisites SSp1 Construction Activity Pollution Prevention (Civil
Engineer) EAp1 Fundamental Commissioning (Cx Provider)
EAp2 Minimum Energy Performance (ASHRAE 90.1
and/or CEC Title 24) (Mechanical Engineer)
EAp3 Fundamental Refrigerant Management
(Mechanical Engineer) MRp1 Storage and collection of recyclables (Arch/Owner)
EQp1 Minimum IAQ performance (ASHRAE 62.1 and/or
CEC Title 24) (Mechanical Engineer)
EQp2 Environmental Tobacco Smoke Control (Arch/Owner)
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
13/39
Mechanical Engineering
Solutions
Choosing the right Mechanical Engineer onthe design team can help satisfy up to 60%
of the requirements for LEED certification WE 3 out of 5 points
EA 2 out of 3 prerequisites
12 out of 17 points
EQ 2 out of 2 prerequisites
7 out of 13 points
ID 2 out of 5 points
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
14/39
Mechanical Engineering
Solutions (WE)
WEc2, WEc3.1, WEc3.2
Grey water systems Waterless urinals and W.C.
Water conserving fixtures
Secondary metering on high volume systems (i.e.
kitchens, mechanical equipment, etc.) Synergy with EAc5 (M&V)
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
15/39
MechanicalEngineeringSolutions (EA)
EAp2, EAc1 ASHRAE 90.1-2004Title 24 Prerequisite is mandatory in California.
Communication is critical between design team to accomplishhigher energy savings and find economic balance (Arch, EE,ME, Owner)
Proper selection of HVAC system for type of building andoccupancy is critical for optimum building operation andreduction of energy usage. (Team decisions are key)
Fundamental understanding of Synergies and Trade-offswith other credits and standards
EAc1 vs. EQc2 (Energy Consumption vs. Ventilation Air)
EAc1 vs. EAc5 (Verification Built into Design)
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
16/39
Mechanical Engineering
Solutions (EA)
EAc5: M & V (IPMVP)
Not usually implemented. Key to verifying performance of building systems
once it is in operation.
Useful in verifying at post-occupancy EAc1,WEc2, WEc3, EQc1, EQc2, EQc6, EQc7
Some ease of implementing with a calibratedenergy model and Building Automation System(BAS).
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
17/39
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
18/39
Mechanical Engineering
Solutions (ID)
LEED AP
40% water use reduction
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
19/39
HVAC Standards & Guidelines
ASHRAE 55-2004 Thermal Comfort
ASHRAE 62.1-2004 Ventilation ASHRAE 90.1-2004 Energy
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
20/39
Cx Requirements for LEED
Basics
IT IS A PREREQUISITE EAp1
Verify and ensure that fundamental building elements and
systems are deigned, installed and calibrated to operate as
intended.
It is imperative that at least 26 points be achieved to reach
the certification level, Cx is an excellent tool during design,
construction and post-occupancy.
Do you like the Opera or NFL?
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
21/39
ASHRAE Cx Process
The 4 phases of the Cx Process
OCCUPANCYOPERATIONS
CONSTRUCTION
DESIGN
PREDESIGN
Cx Process
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
22/39
Energy &
Atmosphere
Pre-1 Fundamental Systems Cx
1. Designate a Cx Authority2. Document OPR and develop BOD
3. Incorporate Cx requirements into CD
4. Develop and implement Cx plan
5. Verify the installation and performance of theCommissioned systems
6. Complete a summary of the Cx Report
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
23/39
1. Designate the Cx Authority
Part of the owners team (ideally)Third party in preferred but can be part of the design team
CxA shall be independent of the projects design and construction
management, though they may be employees of the firms
providing those services.
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
24/39
2. Document OPR & BOD
OPR Completed by Owner, CxA and Project Team
Owner and user requirements
Environmental and sustainable goals
Energy efficiency goals
IEQ requirements
Equipment and System expectations
Building occupant and O&M personnel requirements
BOD Completed by the design team
Primary design assumptions
Standards
Narrative descriptions
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
25/39
3. Incorporate Cx into CDs
Project Specifications
Typically the Cx requirements are in the specs. US DOE / PECI Guide
http://peci.org/library/mcpgs.htm
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
26/39
4. Develop & Implement Cx Plan
Start early
Preferably during DD It is not a rigid document
changes with planning, scheduling, etc.
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
27/39
5. Verify the installation &
performance of the systems
Installation inspection
System performance testing Evaluation of results compares to OPR/BOD
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
28/39
6. Complete Cx Report
Executive summary on the process & results
Deficiency list with resolutions Performance test results
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
29/39
Certification Submittals
LEED Letter template
Completed OPR and BOD Incorporated Cx into specifications
Cx plan
Verified installation and performance of systems
Completed Cx Report
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
30/39
Cre-3 Enhanced Cx
Cx Authority must be an independent party
The CxA shall perform at least: Design review prior to CDs
Review contractor submittals
Review building operation (post-occupancy)
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
31/39
4. Design Review
Minimum one Cx design review of:
OPR BOD
Design documents prior to mid-CD phase
Back check review comments in subsequent
submission
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
32/39
6. Review Contractor Submittals
Only review submittals applicable to systems
being commissioned for compliance with
OPR and BOD.
Do they meet OPR and BOD
O & M requirements
Facilitating performance testing
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
33/39
8. Develop Systems Manual
In addition to the O&M manual that is provided to the staff bythe contractor.
Focuses on operations rather than maintenance. Specifics of interactions between equipment
Final version of BOD
Single line diagrams
As-built sequences of operation
Operating instruction for integrated systems
Recommended maintenance schedules
Recommended retesting schedules with blank test forms
Recommended recalibration schedules for sensors and actuators
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
34/39
9. Verify Requirements for Training
Document training expectations and needs
with the owner
Ensure staff and occupants receive training
and orientation
Special attention should target new or
uncommon design features that have apotential of being over-ridden or removed
due to lack of understanding.
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
35/39
11. Review Building Operations
After handover ( 8 10 months) reviewperformance of building/facility with owner
and O&M staff. Create a deficiencies list (prior to
manufacturer / contractors warrantyexpiration)
Any items listed on the deficiencies list thatwill not be corrected shall be documented inthe Systems Manual
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
36/39
Certification Submittals
LEED Letter template
CxA conducted design review
CxA reviewed submittals
Systems Manual
O&M staff and occupants have been trained
CxA review of building operation post-occupancy
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
37/39
Cx Standards & Guidelines
ASHRAE guideline 0.
ASHRAE guideline 1. NIBS guidelines 2 through 14
NEBB Building Systems Commissioning
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
38/39
Open Forum
Questions?
Comments?Complaints?
Praises?
-
7/28/2019 Leed Hvac Design & Leed Commissioning - Jorge - Mbo - Smri
39/39
THANK YOU