Lecture5---Gantt Chart
-
Upload
danishrafiq -
Category
Technology
-
view
128 -
download
1
description
Transcript of Lecture5---Gantt Chart
![Page 1: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/1.jpg)
LECTURE 5 – GANTT CHART• GANTT Charts• Constructing GANTT Charts• Staffing and Re-scheduling• Project Management Software
Software Project Management Maria Petridou
1
![Page 2: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/2.jpg)
GANTT CHART
A GANTT chart is a type of bar chart that illustrates a project schedule.
After the PERT/CPM analysis is completed, the following phase is to construct the GANTT chart and then to re-allocate resources and re-schedule if necessary.
GANTT charts have become a common technique for representing the phases and activities of a project work breakdown structure.
It was introduced by Henry Gantt around 1910 – 1915.
Software Project Management
2
Maria Petridou
![Page 3: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/3.jpg)
GANTT CHART
Software Project Management
3
Maria Petridou
![Page 4: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/4.jpg)
GANTT CHART Characteristics:
The bar in each row identifies the corresponding task The horizontal position of the bar identifies start and
end times of the task Bar length represents the duration of the task Task durations can be compared easily Good for allocating resources and re-scheduling Precedence relationships can be represented using
arrows Critical activities are usually highlighted Slack times are represented using bars with doted lines The bar of each activity begins at the activity earliest start time (ES) The bar of each activity ends at the activity latest finish time (LF).
Software Project Management
4
Maria Petridou
![Page 5: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/5.jpg)
GANTT CHART
Software Project Management
5
Maria Petridou
Advantages Simple Good visual communication to others Task durations can be compared easily Good for scheduling resources
Disadvantages Dependencies are more difficult to visualise Minor changes in data can cause major changes in the chart
![Page 6: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/6.jpg)
CONSTRUCTING GANTT CHART The steps to construct a GANTT chart from the information
obtained by PERT/CPM are:1. Schedule the critical tasks in the correct position.2. Place the time windows in which the non-critical tasks
can be scheduled.3. Schedule the non-critical tasks according to their
earliest starting times.4. Indicate precedence relationships between tasks.
Software Project Management
6
Maria Petridou
![Page 7: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/7.jpg)
CONSTRUCTING GANTT CHART Example of an early GANTT chart construction:
Software Project Management
7
Maria Petridou
![Page 8: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/8.jpg)
CONSTRUCTING GANTT CHART
Step 1. Schedule critical tasks:
Software Project Management
8
Maria Petridou
![Page 9: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/9.jpg)
CONSTRUCTING GANTT CHART
Step 2. Place time windows for non-critical tasks:
Software Project Management
9
Maria Petridou
![Page 10: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/10.jpg)
CONSTRUCTING GANTT CHART
Step 3. Schedule non-critical tasksStep 4. Indicate precedence relationships:
Software Project Management
10
Maria Petridou
![Page 11: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/11.jpg)
STAFFING & RE-SCHEDULING Once the project schedule, (e.g. GANTT chart), has been
constructed, take into account available staff hours slack times and the project schedule
Assign staff and other resources to each activity in the project
Software Project Management
11
Maria Petridou
![Page 12: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/12.jpg)
STAFFING & RE-SCHEDULING
Resource Smoothing Resource Smoothing is a technique used to re-allocate resources and re-schedule activities.
In resource smoothing, non-critical tasks are re-scheduled within their time window.
Staff Utilization:(duration of activity x staff required for each activity, all added together) / (maximum staff required x duration of project)
Software Project Management
12
Maria Petridou
![Page 13: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/13.jpg)
STAFFING & RE-SCHEDULING
Software Project Management
13
Maria Petridou
Example1 Example1
![Page 14: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/14.jpg)
STAFFING & RE-SCHEDULING
Software Project Management
14
Maria Petridou
The original schedule (constructed above) for this project is as shown below.
1. Staff utilisation = (3x2+4x4+5x1+7x3+2x1+4x2+3x5)/(14x6) = 0.857 = 85.5%
![Page 15: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/15.jpg)
STAFFING & RE-SCHEDULING
Software Project Management
15
Maria Petridou
2. Work out the Staff Profile
![Page 16: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/16.jpg)
STAFFING & RE-SCHEDULING Now, assume that there are 6 people available for working in this project but
one of them returns from holidays at time=2. So re-scheduling is needed because activities A and B cannot be carried out in
parallel until time=2.
Software Project Management
16
Maria Petridou
![Page 17: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/17.jpg)
STAFFING & RE-SCHEDULING Suppose another scenario in which equipment and materials needed to carry
out activities E and F are available at time=5 and time=9 respectively instead of being available at the activities ES time. Then, rescheduling is needed but the overall duration of the project is not affected.
Software Project Management
17
Maria Petridou
![Page 18: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/18.jpg)
STAFFING & RE-SCHEDULING
The obvious way to reduce the overall project duration, it is by reducing the duration of the critical activities.
Crashing Critical Activities refers to reducing the duration of a critical activity by allocating more resources to it.
The risk is that crashing activities may actually reduce productivity and increase costs.
Software Project Management
18
Maria Petridou
![Page 19: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/19.jpg)
STAFFING & RE-SCHEDULING Example 2Example 2
Apply the PERT/CPM method and construct a GANTT chart for the following list of activities with precedence and duration.
Software Project Management
19
Maria Petridou
![Page 20: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/20.jpg)
STAFFING & RE-SCHEDULING
Software Project Management
20
Maria Petridou
![Page 21: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/21.jpg)
STAFFING & RE-SCHEDULING
Step 1. Step 1. Schedule critical tasks.
Software Project Management
21
Maria Petridou
![Page 22: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/22.jpg)
STAFFING & RE-SCHEDULING
Step 2. Step 2. Place time windows for non-critical tasks:
Software Project Management
22
Maria Petridou
![Page 23: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/23.jpg)
STAFFING & RE-SCHEDULING
Step 3. Step 3. Schedule non-critical tasks:Step 4. Step 4. Indicate precedence relationships:
Software Project Management
23
Maria Petridou
![Page 24: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/24.jpg)
PROJECT MANAGEMENT SOFTWARE There are a number of project management software tools
available to help in the planning and control of large software development projects. E.g. MS Project is a CASE software tool for Project Management This software is available in the main computer room in CSIT
Most tools include functions to plan, schedule and control, but decision-making still has to be done by the project manager.
Software Project Management
24
Maria Petridou
![Page 25: Lecture5---Gantt Chart](https://reader033.fdocuments.net/reader033/viewer/2022061300/54c7220c4a7959bf018b4569/html5/thumbnails/25.jpg)
PROJECT MANAGEMENT SOFTWARE Benefits of project management software:
Calculate project schedule Resource smoothing Automatic generation of reports and charts
Limitations of project management software Allocation of resources to tasks Estimation of tasks durations Make decisions
Reading: (Kendall&Kendall, chapter 3), (Dennis &Wixom, chapter 3).
Software Project Management
25
Maria Petridou