Lecture 15. Lecture Overview Types of Costing Systems Used to Determine Product Costs Differences...
-
Upload
arlene-tucker -
Category
Documents
-
view
212 -
download
0
Transcript of Lecture 15. Lecture Overview Types of Costing Systems Used to Determine Product Costs Differences...
Lecture 15
Lecture Overview
• Types of Costing Systems Used to Determine Product Costs
• Differences Between Job-Order and Process Costing
• Sequential Processing Departments• Parallel Processing Departments• Flow of Materials, Labor and Overhead Costs• Materials, Labor, and Overhead Cost Entries
Equivalent Units of ProductionEquivalent units are partially complete and are part of
work in process inventory. It is the concept of expressing partially completed products as a smaller
number of fully completed units.
Equivalent units are partially complete and are part of work in process inventory. It is the concept of
expressing partially completed products as a smaller number of fully completed units.
+ =
Two one-half completed products are equivalent to one completed product. So, 10,000 units 70%
complete are equivalent to 7,000 complete units.
Two one-half completed products are equivalent to one completed product. So, 10,000 units 70%
complete are equivalent to 7,000 complete units.
For the current period, Matrix started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Matrix have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
For the current period, Matrix started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Matrix have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
MCQs Test
For the current period, Matrix started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Matrix have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
For the current period, Matrix started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Matrix have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
MCQs Test
10,000 units + (5,000 units × .30) = 11,500 equivalent units 10,000 units + (5,000 units × .30) = 11,500 equivalent units
Equivalent Units of Production
To calculate the cost perequivalent unit for the period:
To calculate the cost perequivalent unit for the period:
Cost perequivalent
unit
=Costs for the period
Equivalent units of productionfor the period
Now assume that Matrix incurred $27,600 in production costs for the 11,500
equivalent units of production. What was Matrix’s cost per equivalent unit for
the period?
a. $1.84
b. $2.40
c. $2.76
d. $2.90
MCQs Test
Now assume that Matrix incurred $27,600 in production costs for the 11,500
equivalent units of production. What was Matrix’s cost per equivalent unit for
the period?
a. $1.84
b. $2.40
c. $2.76
d. $2.90
MCQs Test
$27,600 ÷ 11,500 equivalent units
= $2.40 per equivalent unit
$27,600 ÷ 11,500 equivalent units
= $2.40 per equivalent unit
Weighted Average Method
Units transferred to the next department or to finished goods 10,000 Equivalent units in ending work in process inventory + 4,200
Equivalent units of production = 14,200
Under the weighted-average method equivalent units will always be calculated as follows:
Weighted Average Method
Matrix, Inc. reported the following activity in Mixing Department for the month of June:
Percent Completed
Units Materials Conversion
Work in process, June 1 300 40% 20%
Units started into production in June 6,000
Units completed and transferred out 5,400 100% 100% of the Mixing Department during June
Work in process, June 30 900 60% 30%
Equivalent units are calculated as follows:
Weighted Average Method
Materials Conversion
Units completed and transferred out of Mixing in June 5,400 5,400
Equivalent units are calculated as follows:
Weighted Average Method
Materials Conversion
Units completed and transferred out of Mixing in June 5,400 5,400
Work in process June 30
(900 units x 60% complete) 540
Equivalent units are calculated as follows:
Weighted Average Method
Materials Conversion
Units completed and transferred out of Mixing in June 5,400 5,400
Work in process June 30
(900 units x 60% complete) 540
(900 units x 30% complete) 270
Equivalent units of production in the Mixing Deparment 5,940 5,670
Equivalent units of production always equals: Units completed and transferred + Equivalent units remaining in work in process
Equivalent units of production always equals: Units completed and transferred + Equivalent units remaining in work in process
BeginningWork in Process
300 Units40% Complete
EndingWork in Process
900 Units60% Complete
6,000 Units Started
5,400 Units Completed
5,100 Units Startedand Completed
Weighted Average MethodMaterialsMaterials
5,400 Units Completed 540 Equivalent Units
900 × 60%
5,940 Equivalent units of production
6,000 Units Started
5,400 Units Completed 270 Equivalent Units 900 × 30%
5,670 Equivalent units of production
Weighted Average MethodConversionConversion
BeginningWork in Process
300 Units40% Complete
EndingWork in Process
900 Units30% Complete
5,100 Units Startedand Completed
Production Report
Production Report
Section 1
Section 2
Section 3
A computation of cost per equivalent unit.
A computation of cost per equivalent unit.
Quantity schedule with computation of equivalent units.
Quantity schedule with computation of equivalent units.
A reconciliation of cost flows for the period. A reconciliation of cost flows for the period.
• Double Diamond Skis uses process costing to determine unit costs in its Shaping and Milling Department.
• Double Diamond uses the weighted average cost procedure.
• Using the following information for the month of May, let’s prepare a production report for Shaping and Milling.
• Double Diamond Skis uses process costing to determine unit costs in its Shaping and Milling Department.
• Double Diamond uses the weighted average cost procedure.
• Using the following information for the month of May, let’s prepare a production report for Shaping and Milling.
Production Report Example
Work in process, May 1: 200 units Materials: 50% complete. $ 3,000Conversion: 30% complete. 1,000
Units started into production in May: 5,000Units completed and transferred out in May: 4,800
Costs added to production in MayMaterials cost $ 74,000Conversion cost 70,000
Work in process, May 31: 400 unitsMaterials 40% complete.Conversion 25% complete.
Work in process, May 1: 200 units Materials: 50% complete. $ 3,000Conversion: 30% complete. 1,000
Units started into production in May: 5,000Units completed and transferred out in May: 4,800
Costs added to production in MayMaterials cost $ 74,000Conversion cost 70,000
Work in process, May 31: 400 unitsMaterials 40% complete.Conversion 25% complete.
Cost
Production Report Example
Step: Quantity Schedule with Equivalent Units
Production Report Example
Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200
Equivalent unitsMaterials Conversion
Units accounted for as follows: Completed and transferred 4,800 4,800 4,800
Production Report Example
Units to be accounted for: Work in process, May 1 200 Started into production 5,000 Total units 5,200
Equivalent unitsMaterials Conversion
Units accounted for as follows: Completed and transferred 4,800 4,800 4,800 Work in process, May 31 400 Materials 40% complete 160 Conversion 25% complete 100
5,200 4,960 4,900
Step: Quantity Schedule with Equivalent Units
Section: Compute cost per equivalent unit
Production Report Example
TotalCost Materials Conversion
Cost to be accounted for: Work in process, May 1 4,000$ 3,000$ 1,000$ Costs added in the Shipping and Milling Department 144,000 74,000 70,000
Total cost 148,000$ 77,000$ 71,000$
Equivalent units 4,960 4,900
Production Report Example
TotalCost Materials Conversion
Cost to be accounted for: Work in process, May 1 4,000$ 3,000$ 1,000$ Costs added in the Shipping and Milling Department 144,000 74,000 70,000
Total cost 148,000$ 77,000$ 71,000$
Equivalent units 4,960 4,900
Cost per equivalent unit 15.524$
$77,000 ÷ 4,960 units = $15.524 (rounded)
Section: Compute cost per equivalent unit
TotalCost Materials Conversion
Cost to be accounted for: Work in process, May 1 4,000$ 3,000$ 1,000$ Costs added in the Shipping and Milling Department 144,000 74,000 70,000
Total cost 148,000$ 77,000$ 71,000$
Equivalent units 4,960 4,900
Cost per equivalent unit 15.524$ 14.490$ Total cost per equivalent unit = $15.524 + $14.490 = $30.014
Production Report Example
$71,000 ÷ 4,900 units = $14.490 (rounded)$71,000 ÷ 4,900 units = $14.490 (rounded)
Section: Compute cost per equivalent unit
Section : Cost Reconciliation
Production Report Example
Total Equivalent UnitsCost Materials Conversion
Cost accounted for as follows: Transferred out during May 4,800 4,800 Work in process, May 31: Materials 160 Conversion 100
Total work in process, May 31
Total cost accounted for
Total Equivalent UnitsCost Materials Conversion
Cost accounted for as follows: Transferred out during May 144,067$ 4,800 4,800 Work in process, May 31: Materials 160 Conversion 100
Total work in process, May 31
Total cost accounted for
4,800 units @ $30.0144,800 units @ $30.014
Production Report Example Section : Cost Reconciliation
Total Equivalent UnitsCost Materials Conversion
Cost accounted for as follows: Transferred out during May 144,067$ 4,800 4,800 Work in process, May 31: Materials 2,484 160 Conversion 1,449 100
Total work in process, May 31 3,933
Total cost accounted for 148,000$
160 units @ $15.524160 units @ $15.524
Production Report Example
100 units @ $14.49100 units @ $14.49
All costs accounted for
All costs accounted for
Section : Cost Reconciliation
Lecture Overview
• Equivalent Units of Production• MCQs Test• Weighted Average Method• Production Report• Production Report Example
End of Lecture 15