Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T...
-
Upload
nguyenkhanh -
Category
Documents
-
view
222 -
download
0
Transcript of Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T...
![Page 1: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/1.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Lean Design: Mock-ups, Simulation, and Design for Prefabrication
October 18, 2017
Timothy Williams, Southland Industries
Steve Greulich, Penn Medicine
Daryl Bodewin, HDR
Ed Hanzel, LF Driscoll/ Balfour Beatty JV
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
© LEAN CONSTRUCTION INSTITUTE
![Page 2: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/2.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Presenters
2
Timothy Williams
Sr. Project Manager, Southland Ind.
Steve Greulich
Sr. Project Manager, Penn Medicine
Daryl Bodewin
Project Executive, HDR
Ed Hanzel
Project Executive, LF Driscoll/Balfour
Beatty JV
![Page 3: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/3.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Project Overview and Challenges
© LEAN CONSTRUCTION INSTITUTE
![Page 4: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/4.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Project Overview
4
• 1.5 Million SF
• 17 stories
• 6 Years
• 47 Operating Rooms
• 500 Private Patient Rooms
• 60 Emergency Department Rooms
• 690 Parking Spaces
![Page 5: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/5.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Site Logistics
5
• Curb-to-curb construction
• Active medical campus
• Limited Laydown Area
• Heavy Traffic and Limited Parking
![Page 6: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/6.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Site Logistics
6
![Page 7: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/7.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Target Budgets vs Design
7
![Page 8: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/8.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
• Peak Manpower (w/ Prefabrication): 1000
Projected Project Manpower
8
• Peak Manpower (Traditional): 1,200
![Page 9: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/9.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
LCI CONGRESS PRESENTATION STYLE GUIDEDesign for Prefabrication
© LEAN CONSTRUCTION INSTITUTE
![Page 10: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/10.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Design for Prefabrication
10
![Page 11: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/11.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Prefabrication Maps
11
• Conceptualize prefabricated
elements before design is
completed.
• Mechanical layout supports
prefabrication on day 1
• Effective communication tool
to show architectural team
construction constraints
• Visual guide to % of off site
manufacturing (OSM)
![Page 12: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/12.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Prefabrication Maps
12
• Maintained Digitally and posted in the
big room
• Not limited to mechanical and
plumbing elements. Includes multi-
trade, electrical, and drywall elements
too
• No one loses sight of the installation
plan
![Page 13: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/13.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Early Install Duct Headers
13
• Large ductwork for mechanical rooms injected
into steel erection sequence
• Multi-party Collaborative Effort
• Structural Designer – added supplemental
steel
• Structural Erector – sequenced installation
• Design Engineer – Early validation of duct
sizing
• Mechanical Installer – Duct construction
and reinforcing for bulk hoisting
• Reduced mechanical room install hours by1/3
![Page 14: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/14.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Patient Level Rack
14
Patient Room
Mock-Up
• Who’s in the Room?
• Owner
• Engineering
• Architect
• Const. Manager
• Key
Subcontractors
• Sprinkler
• Mechanical
• Plumbing
• Electrical
• Low Voltage
Patient Rack
Mock-Up
![Page 15: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/15.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Patient Level Rack
15
• Early Concept
• During Programming
• Structure respected
rack to achieve
desired ceiling height
• 1 Room : 1 Rack
• Sized to minimize
material handling
![Page 16: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/16.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Patient Level Rack
16
![Page 17: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/17.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Bathroom PODS
17
• Utilized in all 500 patient beds
• Complete bathroom module
• Constructed at PennFAB
• 50,000 sqft multi-trade facility
• Project dedicated space
• Single point connections
• Plumbing, electrical, HVAC
![Page 18: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/18.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Bathroom Pods
18
• Functional Mock-up
• Showerhead placement
• Finish material resiliency
• Full Mock-up
• Validates cost and time estimates
• More precise scheduling
• Expedited learning curve
• Construction quality check
• Design finishes validation
![Page 19: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/19.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Precast Foundation Walls
19
• 120 precast wall and buttress panels
5’x30’x1’
• Reduced Schedule – 500 lf of
foundation wall installed in 8 days
• Reduced Cost
• Reduced truck traffic to site – rebar
deliveries/formwork/concrete trucks
• Reduced Man-Power on site
![Page 20: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/20.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Precast Parking Garage
20
• 700 parking space below grade parking
garage
• Reduced Schedule – 3 month savings
vs cast in place
• Reduced Cost – 30% reduction vs cast
in place
• Reduced truck traffic to site – rebar
deliveries/formwork/concrete trucks
• Reduced Man-Power on site
![Page 21: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/21.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
LCI CONGRESS PRESENTATION STYLE GUIDEMock-Ups and Simulations
© LEAN CONSTRUCTION INSTITUTE
![Page 22: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/22.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Individual Room Mock-Ups
22
• Operating Rooms (various sizes)
• Initial focus: Table and Booms
• Styrofoam – to – Finishes
• Room specific simulations
![Page 23: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/23.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Individual Room Mock-Ups
23
• Hospital users and patient/family
feedback
• Ongoing adaptation based upon input
• Styrofoam – to – Finishes
• Equipment placement
• Room specific simulations
![Page 24: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/24.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Individual Room Mock-Ups
24
![Page 25: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/25.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Original Building Design: Inpatient Floor
25
1
2
34
567
![Page 26: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/26.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Design Confirmation
26
Full-Scale Prototype
• Objectives:
• Test functional performance
• Feedback and data
• Steps:
• Facilitated Tours
• Designed Simulations
• General Tours
• Surveys
• Data Analysis
![Page 27: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/27.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Simulation Overview
27
Meet Objectives
• Focus on Patient Care Unit
• Collect and provide tangible, detailed
qualitative and quantitative data to
the design team
• Extensive use of internal resources
• Engage executive leaders in these
activities in order to initiate change
management process
![Page 28: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/28.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Simulation Overview
28
Process
• Utilized PDCA cycle
• Applied to Inpatient and
Interventional Floors
• Modified Design based on
feedback from simulation
• Revisited simulations for
confirmation of new design
![Page 29: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/29.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Full Scale Prototypes
29
![Page 30: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/30.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Tour Data
30
• 22 Tours completed, 546 Tour participants, 291 Surveys submitted
• Faculty, nursing, services
• Employee experience ranging from 1-45 years
![Page 31: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/31.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Simulation Data
31
7 Sessions on initial mock-up
• 138 Participants,108 Hours of video reviewed
3 Sessions on revised mock-up
• 57 Participants, 40 Hours of video reviewed
![Page 32: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/32.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Original Building Design: Inpatient Floor
32
1
2
34
567
![Page 33: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/33.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
New Building Design: Inpatient Floor
33
![Page 34: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/34.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Full Scale Prototypes: Interventional Floor Mock-up Plan
34
![Page 35: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/35.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Simulation Video
35
![Page 36: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/36.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Simulation Outcome
36
Enabled evaluation of the physical layout
of the entire patient care unit.
The modified design will provide a
positive employee experience.
The modified design will provide a
positive patient experience.The modified design will provide a
positive visitor experience.
94%Strongly Agree or Agree
90%Strongly Agree or Agree
98%Strongly Agree or Agree
96%Strongly Agree or Agree
![Page 37: Lean Design: Mock-ups, Simulation, and Design for ... Lean Design Mock-ups, Simulatio… · C A P T U R E A N D L E V E R A G E T H E L E A N A D VA N TA G E Lean Design: Mock-ups,](https://reader034.fdocuments.net/reader034/viewer/2022051720/5a78d5d27f8b9ae6228daad1/html5/thumbnails/37.jpg)
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
In the spirit of continuous improvement, we would like to remind you to complete this session’s survey in the Congress app! We look forward to receiving your feedback. Highest rated presenters will be recognized.
© LEAN CONSTRUCTION INSTITUTE