LCLS-II Project Overview

15
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012

description

LCLS-II Project Overview. David Schultz LCLS-II Deputy Project Director March 19, 2012. Outline. Project priorities and status Key features Project o verview & layout Project schedule and path forward. LCLS-II Project Priorities. Build a highly productive scientific user facility - PowerPoint PPT Presentation

Transcript of LCLS-II Project Overview

Page 1: LCLS-II Project Overview

LCLS-II Project Overview

David SchultzLCLS-II Deputy Project Director

March 19, 2012

Page 2: LCLS-II Project Overview

Outline

Slide 2

• Project priorities and status• Key features• Project overview & layout• Project schedule and path forward

LCLS-II New Instruments Workshops, March 19-22, 2012

Page 3: LCLS-II Project Overview

LCLS-II Project Priorities

• Build a highly productive scientific user facility Maximize technical capabilities for the longer-

range future• Simultaneous SXR and HXR operation• Experiment hall capacity• Undulator hall length

• Control the Project Cost/Schedule DOE Guidance is $405M Total Project Cost Formal Project completion (CD-4) in 2019

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 3

Page 4: LCLS-II Project Overview

• Conceptual Design (CD-1) approval 10/14/11• Long-lead procurements approval 3/14/12

• Injector system and support facility• Fully funded for FY12• DOE Preliminary Design (CD-2) Review as early as

August, 2012• Establish Project baseline schedule and budget

LCLS-II Project Status

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 4

Page 5: LCLS-II Project Overview

• Second 120 Hz injector and 1km LINAC section LCLS-1 and LCLS-II operate independently

• Two New Undulator sources with variable gap In a new undulator tunnel Electrons to two undulators in parallel, 60 Hz each Soft (250 - 2,000 eV) Hard (2,000 - 13,000 eV)

New underground experiment hall, two floors

Key Features of LCLS-II

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 5

Page 6: LCLS-II Project Overview

Slide 6

DOE CD-3a Review of the LCLS-II Project, Dec 6-7, 2011

Linac Coherent Light Source IIInjector @1-km point

Sectors 10-20 ofLinac (1 km)

CD-0 10 April 2010, CD-1 14 October 2011CD-0 10 April 2010, CD-1 14 October 2011

X-ray Transport Optics/Diagnostics

New Underground Experiment Hall

Bypass LCLS Linacin PEP Xport Line

New Beam Transport Hall

SXR, HXR Undulators

Page 7: LCLS-II Project Overview

Electron Systems Schematic Layout

LCLS-II New Instruments Workshops, March 19-22, 2012

0

• Electron Systems largely copied from LCLS-1• Gun, BC’s, diagnostics, e- dumps

Slide 7

Page 8: LCLS-II Project Overview

LCLS-II New Construction Layout

LCLS-II New Instruments Workshops, March 19-22, 2012

LCLS-1

Experimental Hall 2Undulator Hall 2Beam Transport Hall 2

Slide 8

Page 9: LCLS-II Project Overview

LCLS-II Undulator Hall

Space for SXR Seeding and Tapering

• Undulator tunnel is 286 meters in length Space for baseline 114 m HXR and 66 m SXR undulators Room allocated for seeding and tapering extensions

LCLS-II New Instruments Workshops, March 19-22, 2012

Space for HXR Seeding and Tapering

Baseline SXR

Baseline HXR

e- Beam Dump

Front End

Slide 9

Page 10: LCLS-II Project Overview

Undulator Magnets

• LCLS-II Undulators are based on undulators designed at LBNL for the ALS.

Servo Motor

Strongbacks

CompensatingSprings

Linear Encoder

Linear Slide

MagneticStructure

LCLS-II New Instruments Workshops, March 19-22, 2012

Undulator Hall Cross Section

• Undulator tunnel is similar in cross section to the LCLS tunnel.

Slide 10

Page 11: LCLS-II Project Overview

Experimental Hall 2 Layout

• Space for 4 experimental stations in an 80m long cavern.• Full size second floor for HVAC, racks, control rooms

LCLS-II New Instruments Workshops, March 19-22, 2012

Front End Systems Area for Soft X-rays Area for Hard X-rays

80m

14m

Slide 11

Page 12: LCLS-II Project Overview

LCLS-II Project Schedule

Slide 12LCLS-II New Instruments Workshops, March 19-22, 2012

First Light

Install Instruments

EH2 complete

Page 13: LCLS-II Project Overview

2012 plans

• Start Injector facilities construction in July• Start Injector technical system fabrication• Complete Construction designs by the end of the

year.• Develop the Project baseline schedule and

budget for presentation to DOE in August.

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 13

Page 14: LCLS-II Project Overview

Summary

• LCLS-II will add capacity and capability to the LCLS scientific program, and will provide space for expansion.

• To minimize cost and risk, electron systems rely heavily on LCLS-1 designs.

• LCLS-II will dovetail with the LUSI-II project. First light in 2018.

LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 14

Page 15: LCLS-II Project Overview

End of Presentation