Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector –Linac System OverviewInjector –Linac System Overview E. BongE. Bong

LCLS FACLCLS FACOctober 27, 2005October 27, 2005

LCLSLCLS

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector - Linac System OverviewInjector - Linac System Overview

Installation – Progress & Emphasis

Region Designs

Diagnostics

Gun, Linac & RF

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector and Linac Installation DatesInjector and Linac Installation Dates

(RF phase: (RF phase: rfrf = 0 is at accelerating crest)= 0 is at accelerating crest)

SLAC linac tunnelSLAC linac tunnel research yardresearch yard

Linac-1Linac-1Aug-NovAug-Nov

20062006

Linac-2Linac-2July-SepJuly-Sep

20072007

Linac-3Linac-3July-SepJuly-Sep

20072007

BC-1BC-1Aug- NovAug- Nov

20062006

BC-2BC-2July-SepJuly-Sep

20072007 LTULTUOct 2007Oct 2007Dec 2007Dec 2007

DL-1DL-1Aug-NovAug-Nov

20062006

undulatorundulatorSLAC linacSLAC linac 21-1b21-1b21-1d21-1d XX

RF GunRF GunNov 2006Nov 2006

21-3b21-3b24-6d24-6d

25-1a25-1a30-8c30-8c

E-DumpE-DumpDec 2007Dec 2007Feb 2008Feb 2008

Inj VaultInj VaultJun-JulJun-Jul20062006

L0a&b

L0a&b

rfrfgungun

Installation in SLAC Linac tunnel only during down-time

Forces priority to components and systems in Linac housing

Linac-Linac-XXAug-NovAug-Nov

20062006

Linac Down: August – November 2006

July – September 2007

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Installation

PORCU

PINE CATHODE

HOLDE

R

UHV A

LL METAL

GATE VALVES

SPOOLS FRO

M VALVE

SEAL

LONG B

ELLOWS

ASSEM

BLY

TREATMEN

T CHAM

BER

VACUU

M PUMPS

Drive Laser June 2006

Laser Launch July 2006

Gun Region July 2006

Accel Region June 2006

Heater Region June 2006

Wall Region October 2005

Injection Region Aug-Nov 2006

Spect Region Aug-Nov 2006

Waveguide through wall and up penetration October 2005

Gun installation November 2006 Following Hot Test in Klystron Lab

Injector Commissioning Start December 2006

Priority – Linac Housing Installation

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Linac 2006 Installation

Quad + BPM, YCOR,XCOR,

QE, Toroid

Emittance Diagnostics.

Bunch Compressor &

Diagnostics

Two short accelerator structures, refurbished

Quads+BPMs,X&YCOR

Linac 1 (L1)

Electrons

Bunch Compressor 1 (BC1)

L1 design and details complete & in fab Short structures available

X-Band design complete & in fab

BC1 Compressor articulation design & details complete & in fab

BC1 emittance diagnostics section design going

BLM moved to SLAC design, two devices, need for feedback

Must install during 2006 downtime

Remove 5 S-Band Structures

X-Band Structure

(NLC)

LX

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Wall Region

Spans through shielding walls separating Injector Vault form Linac Housing.October 2005 installation included pipes through walls and stopper. 2006 installation of wire scanners, profile monitors and quad on Linac side of shielding wall.Device designs complete and in fab or on hand.Low risk for 2006 install.

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Insertion/SAB Region

Support modal analysis complete stiffened as result to meet vibration tolerance.Common OTR optics design late. Special OTR at spect end from ANL. Magnets designs complete. On order or received except spect bend. Chamber designs complete.Second least mature region design.

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

L1 RegionAll detail drawings complete and part on hand or in fabrication less correctors

Low risk for 2006 installation

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

XL4 Klystron fabrication complete. Waveguide fabrication in progress.Structure support design complete & in fabNeed LLRF, modulator modsVacuum assy install required.Region operation not necessary for ’06/’07 commissioning.

X-Band System (LX)

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

BC1 Articulation Region Design

Beamline segment from X-Band system to structure BC1-Out diagnostics section.

Compressor articulation in fabrication at outside vendor. Fabrication halted and restarted to modify chamber to provide sufficient aperture for BLM.

Manget design reviewed at vendor.

Compressor diagnostics incomplete. Manpower added.

Most risk in diagnostics package; collimator, BPM & OTR.

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

BC1-Out Region Design

Beamline segment from BC1 compressor articulation to structure Li21-2b.

Downstream emittance section layout complete. Uses existing wire scanner, quadrupole, stopper and BPM designs with support stands modified to mount on accelerator lightpipe.

Collaboration with UCLA on single shot bunch length monitor dropped. Design to be done at SLAC. Two devices to be built. See later talk. Design most at risk. Relative bunch length measurement required for RF feedback.

SLAC Engineer and top physics support assigned to BLM project

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Vault

Installation of stub columns started.

Water system design critical to commissioning start.

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Waveguide Design

Installation penetration-wall October ’05

Installation Vault & Gallery starting Spring ’06.

Waveguide design complete, fabrication underway. Waveguide supports in final design.

3-D Layout integrated into Injector system assembly.

Gun and structures fed from Li-20-6, 7 & 8 klystrons, T-Cav fed from Li-20-5d structure exhaust.

Old waveguide runs have been disconnected from Klystrons.

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Gun Region

Installation July 2006 except gun November 2006

Component designs in check

Gun in fabrication hot test to be performed in Klystron test lab must have priority

Solenoid delivered Spectrometer bend design complete

YAG/OTR optics package incompleteBase support design incomplete

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Accelerator Region

Installation June 2006

Dual feed structure in fabrication

Quads delivered

Solenoid due next week

Need floor support design

L0a and solenoid on common support girder to allow relative alignment in lab prior to install.

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Heater Region Design

Beamline segment Between Accelerators and Shielding Wall

Installation June 2006

Undulator installation 2007

Transverse structure on hand.

Quads received

OTR actuator design complete need optics

Bend magnet design reviewed at vendor

Floor support design in progress

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Region Design Status (2006 Install)Region Design Status (2006 Install)Linac Housing First Priority (due to fixed down)

Wall Region Complete

Insertion Region In Process

SAB Spectrometer Region In Process

L1 Complete

LX Complete

BC1 Articulation Complete, BC1-Out In Process

Injector Vault Second PriorityGun Region In Process

Accelerator Region In Process

Heater Region In Process

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Actions to Achieve 2006 Installation Goals

Monitor P3 schedule against design and fabrication activitiesMonitor critical path to installation against device fabrication progressAnalyze any schedule variance impact on installation Adjust assignments to recover from any schedule varianceComplete Injector & Linac region designsPrioritize design activities based on downtime schedule datesComplete Gun fabrication and testingReceive & test vendor magnetsComplete X-Band component fabricationFabricate Insertion/SAB, L1, BC1 Articulation & BC1 Diagnostics SectionComplete water system design and installFinish detailed installation plan, update P3Complete commissioning plans, update P3

Eric BongLCLS FAC Injector-Linac System Overview [email protected] 27, 2005

Injector Design / Diagnostics / Injector Design / Diagnostics / Gun & Linac RF DesignGun & Linac RF Design

Conclusion

Progress is being made toward completing beamline and component design for 2006 installation supporting January 2007 commissioning but with some riskPriority of design activities must be placed on components to be installed in Linac Housing during 2006 downtimeInjector Vault water system design and installation must be expedited