Laser FT updated (final?) proposal Sowjanya, Kendall November 7, 2017 DUNE Calibration TF meeting 1

Transcript of Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT...

Page 1: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

Laser FT updated (final?) proposal

Sowjanya, Kendall November 7, 2017

DUNE Calibration TF meeting

1

Page 2: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

2

Counter Proposal• To get around the problem of only 3 ports along the outer APAs, leverage on the

instrumentation ports that are outside the Field cage

• This gives crossing tracks but probably lasers L1, L2, L3 & L4 are constrained in space/angle

• Can only shine through the FC gaps (MicroBooNE experience?)

• Structure of the FC (3D drawing to understand geometry considerations)

• In the orange dotted boxes drift region, full field map cannot be extracted.

NORTH

SOUTH

WEST

EAST

All ports “multipurpose”

ports

Page 3: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

• Light blue: inside FC; Dark blue: outside FC; Green: Cryogenic port (could swap or use, to be determined)

• All ports on top of the TPC • Outside ports are 404mm from FT centerline to outside wall of FC (along

support feedthrough line). Field shaping elements another ~70mm away. 3

Current Feedthrough Proposal (for calibration) APA

APA

APA

CPA

CPA

L1

L2

L3

L4

NORTH

SOUTH

WEST

EAST

404 mm

Page 4: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

4

• This may be our final proposal. Do we see any deal breakers or outstanding issues with it?

• Next steps: build a strong case to understand the limitations of this system and if more is needed.

Spacing details for outer ports - Jack Fowler

Limited positions due to maintaining symmetry with other systems (closest to mid-drift achievable)

Same North-South distance on the East side as well

We need to decide North-South distance of these ports NOWouter portsinner ports

Page 5: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

• Two options for Laser:

• Shine laser through FC gaps vs through FC opening (applies to all ports including the ports outside the FC)

• Whatever decision we make should work reasonably well in both cases. Do we have such a case?

• For the ports outside the FC, things are tricky

• Laser head sits on the side of the FC at 404 mm away from FC

• What are our angular limitations, when shining through gaps vs a FC opening at 404 mm distance from the FC? (need drawings)

• What is the desirable North-South distance for these ports? (near mid-drift) vs being closer to APA?

5

Laser port concerns/considerations

Page 6: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

6

Opaqueness of FC: From Bo

FC tubeFC tube

In reality this point sits 404 mm away from the outer wall of the FC

Page 7: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

7

• This may be our final proposal. Do we see any deal breakers or outstanding issues with it?

• Next steps: build a strong case to understand the limitations of this system and if more is needed.

Summary

Page 8: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

BACK UP

8

Page 9: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

9

• This may be our final proposal. Do we see any deal breakers or outstanding issues with it?

• Next steps: build a strong case to understand the limitations of this system and if more is needed.

Spacing details for outer ports - Jack Fowler

Limited positions due to maintaining symmetry with other systems (closest to mid-drift achievable)

Same North-South distance on the East side as well

We need to decide North-South distance of these ports NOW

Page 10: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

Laser Feedthroughs • Bo gave a really nice talk on Drift field distortions due to CPA/FC imperfections:

https://indico.fnal.gov/event/15245/

• Broken resistor case was the most potentially worrisome. We will know a resistor is failed but not where. Unlikely to be able to wait for a cosmic to go through the correct position, need laser or similar system to identify and confirm failure.

• Diagnosing this requires crossing tracks at least on the EAST/WEST sides.

• For the central FT column, need more studies — no conclusion reached. Will address in the coming weeks.

10

Not asking this column

Ports circled in yellow not

possible

Page 11: Laser FT updated (final?) proposal - INDICO-FNAL (Indico)•Outside ports are 404mm from FT centerline to outside wall of FC (along support feedthrough line). Field shaping elements

11

Laser Feedthroughs — A constraint

Along the outer APAs only 3 ports are possible because of space constraints