KC Soccer Stadium

4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities : Storm Sewer installation (Line 1000) is ongoing along Village West Parkway. Storm Line Installation (Line 600 and Sanitary Sewer Line E installation is ongoing on east side of France Family Dive is ongoing. Foundations : Area 3 Field Level – Isolated footing installation is Ongoing and is currently to Column Line 6. Area 4 Mezzanine Level – Excavation for D-Line footing Is ongoing and is currently to Column Line 40. Concrete Flatwork : Area 1 – Mezzanine slab-on deck is complete, Main Concourse structural slab is complete, Suite Level slab on deck is complete, Press Level slab on deck is complete. Preparation for 1 st pour of Field Level Area 1 slab-on-grade is ongoing. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 6.30.2010 Re: Wizards Stadium Project Update – Week of 6.28.2010 Concourse Level Area 2 – Underground plumbing rough-in for the Concourse Buildings is ongoing. Area 1 – Precast concrete treads and riser installation is nearly complete between column lines 32-24. Field Level Area 1 – Vapor barrier installation from column line 32-29 is placed in preparation for slab-on-grade placement.

description

 

Transcript of KC Soccer Stadium

Page 1: KC Soccer Stadium

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 2

and Area 3.

Site Utilities:

Storm Sewer installation (Line 1000) is ongoing along

Village West Parkway.

Storm Line Installation (Line 600 and Sanitary Sewer

Line E installation is ongoing on east side of France

Family Dive is ongoing.

Foundations:

Area 3 Field Level – Isolated footing installation is

Ongoing and is currently to Column Line 6.

Area 4 Mezzanine Level – Excavation for D-Line footing

Is ongoing and is currently to Column Line 40.

Concrete Flatwork:

Area 1 – Mezzanine slab-on deck is complete, Main

Concourse structural slab is complete, Suite Level slab

on deck is complete, Press Level slab on deck is

complete. Preparation for 1st

pour of Field Level Area 1

slab-on-grade is ongoing.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 6.30.2010

Re: Wizards Stadium Project

Update – Week of

6.28.2010

Concourse Level Area 2 – Underground

plumbing rough-in for the Concourse

Buildings is ongoing.

Area 1 – Precast concrete treads and riser

installation is nearly complete between

column lines 32-24.

Field Level Area 1 – Vapor barrier

installation from column line 32-29 is placed

in preparation for slab-on-grade placement.

Page 2: KC Soccer Stadium

Building the Future

Structural Steel Erection:

Area 1 –Detailing and decking in sequence 1-3 is ongoing.

Erection of Steel Sequence 2-1 has started.

Area 1 – Roof deck installation for entire West Building is

nearly complete.

Underground MEP:

Electrical Secondary Distribution is ongoing in Area 3.

MEP Rough-in:

Area 1 – Shallow electrical and plumbing rough-in has

started at Field Level in preparation for 1st

slab-on-grade

pour.

Metal Stud Framing:

Area 1 Suite Level – Metal stud framing for Suites has

started.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue. Storm Line 1000

will continue. Installation of Sanitary Line E will continue.

Deep Underground MEP:

Deep Sanitary and Electrical Distribution installation

in Area 3 will continue.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Area 4 Mezzanine Level – Foundation Wall installation will

continue.

Area 1 – Shot of the West Building from the

southeast.

Roof Level Area 1 – Roof decking is nearly

complete.

Area 1 –Canopy Trusses are being delivered

and staged in the infield.

Page 3: KC Soccer Stadium

Building the Future

Concrete Flatwork:

Area 1 Field Level – Concrete placement for slab-on-grade

will begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 2-1 will

continue.

Delivery of Roof Trusses for sequence 1-7 will continue

throughout the week.

Structural Precast:

Erection of the precast tubs in Area 1 will begin.

Underground MEP:

Deep Sanitary installation will continue in Area 3.

Electrical Secondary will continue in Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in for Area 1 Field Level slab

on grade will continue.

Metal Stud Framing:

Area 1 Suite Level – Metal stud framing for Suites will

continue.

Area 1 Press Level – Metal stud framing for Suites will

begin.

Area 2 – Shot looking south of Terrace Area

taking shape.

Field Level Area 3 – Foundation installation

is ongoing.

Page 4: KC Soccer Stadium

Building the Future

Additional Photos:

Field Level Area 3 – Field wall footing

concrete placed at column line 4.

Field Level Area 1 – Shot of Player’s field

entry.

Suite Level Area 1 – Metal stud framing for

suites has begun.

Area 1 – Subgrade preparation for on-grade

seating risers has started.

Suite Level Area 1 – Duct straps being

installed in preparation for ductwork

installation.

Roof Level Area 1 – Shot of steel framing for

Freight Elevator “High Hat”.