JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company...

45
JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD NO WORK DESCRIPTION OWNER COMMENCEMENT DATE CURRENT STATUS Oct 30, 2019 - (Track Record Updated) 1. SUPPLY OF WELDING ELECTRODE ONGC KG-DWN 98-2 CPP & LQ SAPURA FABRICATION SDN BHD (INDIA PROJECT OFFICE) October 25, 2019 Completed 2. ADDITIONAL SURFACE AREA FOR PFP WORK (FABRICATION OF JAMNAGAR BERTH A2 PROJECT) SAPURA FABRICATION SDN BHD October 23, 2019 In Progress 3. SUPPLY OF WELDING ELECTRODE PEGAGA CPP TOPSIDE SAPURA FABRICATION SDN BHD October 18, 2019 Completed 4. SUPPLY OF BATTERIES ENQUEST October 17, 2019 In Progress 5. PFP MAINTENANCE WORK AT GUMUSUT KAKAP TOPSIDE SABAH SHELL PETROLEUM COMPANY LIMITED October 17, 2019 In Progress 6. SUPPLY OF WELDING ELECTRODE FOR BOKOR PROJECT (ITEM 660-730 ONLY) MMHE October 10, 2019 Completed 7. SUPPLY AND DELIVER WIRELESS KEYBOARD AND LAPTOP STAND FOR PETRONAS LUBRICANTS MARKETING (M) SDN BHD PETRONAS LUBRICANTS MARKETING (M) SDN BHD October 07, 2019 Completed 8. SUPPLY AND DELIVERY OF E&I BULK MTO FOR MEPA INFILL OCTOBER (DELTA WITH AFC) (POWER & INSTRUMENT CABLE) COST PLUS DAYANG ENTERPRISE / MURPHY October 4, 2019 Completed 9. SUPPLY NU BOLT (GRIP/NON-GRIP) FOR SOGT PRESSURE VESSEL REDUDANCY PROJECT EVOLUSI BERSATU SDN BHD / PCSB October 4, 2019 In Progress 10. SUPPLY NU BOLT C/W I-ROD FOR SOGT GTC SEAL GAS LINE EVOLUSI BERSATU SDN BHD / PCSB October 3, 2019 In Progress 11. STRUCTURAL WORKS FOR BOKOR CPP TOPSIDES SVOA NO.4 MMHE October 02, 2019 In Progress 12. SUPPLY OF WELDING ELECTRODE FOR ONGC KG-DWN 98-2 CPP & LQ PROJECT SAPURA FABRICATION SDN BHD September 25, 2019 Completed

Transcript of JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company...

Page 1: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

1. SUPPLY OF WELDING ELECTRODE – ONGC KG-DWN 98-2 CPP & LQ

SAPURA FABRICATION SDN

BHD (INDIA PROJECT OFFICE)

October 25, 2019

Completed

2. ADDITIONAL SURFACE AREA FOR PFP WORK (FABRICATION OF JAMNAGAR BERTH A2 PROJECT)

SAPURA FABRICATION SDN

BHD October 23, 2019

In Progress

3. SUPPLY OF WELDING ELECTRODE – PEGAGA CPP TOPSIDE SAPURA

FABRICATION SDN BHD

October 18, 2019

Completed

4. SUPPLY OF BATTERIES ENQUEST October 17, 2019

In Progress

5. PFP MAINTENANCE WORK AT GUMUSUT KAKAP TOPSIDE SABAH SHELL PETROLEUM

COMPANY LIMITED October 17, 2019

In Progress

6. SUPPLY OF WELDING ELECTRODE FOR BOKOR PROJECT (ITEM 660-730 ONLY) MMHE October 10, 2019

Completed

7. SUPPLY AND DELIVER WIRELESS KEYBOARD AND LAPTOP STAND FOR PETRONAS LUBRICANTS MARKETING (M) SDN BHD

PETRONAS LUBRICANTS

MARKETING (M) SDN BHD

October 07, 2019

Completed

8. SUPPLY AND DELIVERY OF E&I BULK MTO FOR MEPA INFILL OCTOBER (DELTA WITH AFC) (POWER & INSTRUMENT CABLE) – COST PLUS

DAYANG ENTERPRISE /

MURPHY October 4, 2019

Completed

9. SUPPLY NU BOLT (GRIP/NON-GRIP) FOR SOGT PRESSURE VESSEL REDUDANCY PROJECT

EVOLUSI BERSATU SDN BHD / PCSB

October 4, 2019

In Progress

10. SUPPLY NU BOLT C/W I-ROD FOR SOGT GTC SEAL GAS LINE EVOLUSI BERSATU

SDN BHD / PCSB October 3, 2019

In Progress

11. STRUCTURAL WORKS FOR BOKOR CPP TOPSIDES – SVOA NO.4 MMHE October 02, 2019

In Progress

12. SUPPLY OF WELDING ELECTRODE FOR ONGC KG-DWN 98-2 CPP & LQ PROJECT

SAPURA FABRICATION SDN

BHD September 25, 2019

Completed

Page 2: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

13. SUPPLY OF HUMIDUR PAINTS AT MASHHOR OFFSHORE PAINTING SERVICES SDN BHD

BLNG September 24, 2019

In Progress

14. SUPPLY OF WELDING ELECTRODE FOR PEGAGA PROJECT SAPURA

FABRICATION SDN BHD

September 18, 2019

Completed

15. PROCUREMENT OF INSTRUMENT CABLE LOC-PETROFAC MALAYSIA MENARA PRESTIGE

PETROFAC (PM304-MALAYSIA) LIMITED

August 21, 2019

Completed

16. SUPPLY AND DELIVERY OF SURFACE BOOK 2 i7 16GB

PETRONAS LUBRICANTS

INTERNATIONAL SDN BHD

August 21, 2019

In Progress

17. SUPPLY OF WELDING ELECTRODE FOR JX NIPPON LAYANG DEVELOPMENT PROJECT

SAPURA OFFSHORE SDN BHD

August 19, 2019 Completed

18. SSJ - PROVISION OF DRY ICE MACHINE RENTAL BRUNEI LNG SDN

BHD August 7, 2019

In Progress

19. SUPPLY OF WELDING ELECTRODE FOR ENI MERAKES DEVELOPMENT PROJECT

SAPURA OFFSHORE SDN BHD

August 7, 2019

Completed

20. SUPPLY OF WELDING ELECTRODE FOR FABRICATION OF PEGAGA CPP PROJECT

SAPURA FABRICATION SDN

BHD August 2, 2019

Completed

21. SURFACE PREPARATION USING HiCO2 DRY ICE BLASTING FOR C-6942 EO TANK

DIALOG / PCOGD July 28, 2019 In Progress

22. PROVISION OF ELECTRODE FOR KINARUT WEST – BASE SCOPE & LABUAN YARD

SAPURA PINEWELL SDN BHD

July 11, 2019 Completed

23. PURCHASE OF COMPUTER HARDWARE

EXXONMOBIL EXPLORATION AND

PRODUCTION MALAYSIA INC.

July 11, 2019 Completed

24. STRUCTURAL WORKS FOR JACKET, BRIDGE AND APPURTENANCES FOR BOKOR CPP-JACKET

MMHE July 4, 2019 In Progress

Page 3: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

25. PROVISION TO SUPPLY MANPOWER, EQUIPMENTS, TOOLS AND CONSUMABLES FOR PFP COATING FOR RSDV (ADDITIONAL WORK)

SAPURA PINEWELL / KPOC

July 2, 2019 In Progress

26. SUPPLY OF WELDING ELECTRODE FOR PEGAGA CPP TOPSIDE PROJECT SAPURA

FABRICATION SDN BHD

June 25, 2019 Completed

27. SUPPLY OF HUMIDUR FP PLURAL PAINTS TO PT. BREDERO SHAW INDONESIA SHAWCOR

SINGAPORE PTE. LTD

June 25, 2019 Completed

28. SUPPLY AND DELIVERY OF INSTRUMENT BULK MATERIALS FOR MEPA 11 FLOWLINE INTERIM (INSTRUMENT CABLES) – COST PLUS

DAYANG ENTERPRISE /

MURPHY June 20, 2019 Completed

29. SUPPLY OF WELDING ELECTRODE FOR BOKOR PROJECT MMHE June 20, 2019 Completed

30. SUPPLY OF WELDING ELECTRODE FOR BOKOR PROJECT MMHE June 20 , 2019 Completed

31. SUPPLY AND DELIVERY OF KOBE ELECTRODE FOR FSO GOLDEN STAR MMHE June 17, 2019 Completed

32. SUPPLY OF WELDING ELECTRODE FOR ONGC KG-DWN 98-2 SAPURA

FABRICATION SDN BHD

June 14, 2019 Completed

33. SUPPLY AND DELIVERY OF GASKET MALAYSIAN

REFINING COMPANY June 10, 2019 Completed

34. SUPPLY OF HUMIDUR PAINTS TO QESS ENERGY SUPPORT SERVICES SDN BHD BSP May 30, 2019 Completed

35. SUPPLY OF HUMIDUR PAINTS TO MASHHOR OFFSHORE PAINTING SERVICES SDN BHD

BLNG May 30, 2019 Completed

36. SUPPLY AND DELIVERY OF ELECTRICAL CABLE WOODGROUP /

EMEPMI May 29, 2019 Completed

Page 4: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

37. SUPPLY OF WELDING ELECTRODE FOR ONGC KG-DWN 98-2 SAPURA

FABRICATION SDN BHD

May 27, 2019 Completed

38. SUPPLY AND DELIVERY OF MATERIALS FOR WHEATHER SHELTER (INSTRUMENT CABLES) – COST PLUS (GOPA)

DAYANG ENTERPRISE /

MURPHY May 24, 2019 Completed

39. SUPPLY OF HUMIDUR FP BRUSH TRANSFAME SDN

BHD May 24, 2019 Completed

40. REPAIR OF PFP COATING FOR C/01/FB/1039 – EPCC + I FFD HESS PHASE 2 FACILITIES, NMB

SAPURA FABRICATION SDN

BHD / HESS EXPLORATION

May 24, 2019 Completed

41. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTIVE COMPOUND FOR SSB/SSPC

SARAWAK SHELL BERHAD

May 23, 2019 In Progress

42.

FABRICATION AND INSTALLATION OF GRILLAGE, DEAD MAN ANCHOR, LINK BEAMS AND REMOVAL LSF SEAFASTENING AND GRILLAGE FOR BOKOR CPP TOPSIDE

MMHE May 15, 2019 In Progress

43. SUPPLY AND APPLY OF PFP WORKS FOR BOKOR CPP TOPSIDE MMHE May 15, 2019 In Progress

44. SUPPLY OF HUMIDUR PAINTS TO QET BSP May 14, 2019 Completed

45. SUPPLY OF HUMIDUR FP COATING BLACK FOR SS PUTERI INTAN EAGLESTAR

SHIPMANAGEMENT (L) PTE LTD

May 7, 2019 Completed

46. PROVISION TO SUPPLY MANPOWER, EQUIPMENTS, TOOLS AND CONSUMABLES FOR PFP COATING FOR RSDV

SAPURA PINEWELL / KPOC

April 29, 2019 Completed

47. PASSIVE FIRE PROTECTION WORK FOR CONSTRUCTION OF BERTH A2 AT MARINE TERMINAL, JAMNAGAR, INDIA

SAPURA FABRICATION SDN

BHD April 22, 2019 In Progress

48. SUPPLY AND DELIVERY OF CABLE SARAWAK SHELL

BERHAD April 25, 2019 Completed

Page 5: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

49. SUPPLY OF WELDING ELECTRODE FOR BOKOR PROJECT MMHE April 23, 2019 Completed

50. FABRICATION AND INSTALLATION SEAFASTENING AND LOADOUT ACTIVITIES FOR GK PHASE 2

MMHE April 18, 2019 In Progress

51. SUPPLY OF HUMICLEAN TO MASHHOR OFFSHORE PAINTING SERVICES SDN BHD

BLNG April 16, 2019 Completed

52. STRUCTURAL WORKS FOR JACKET, BRIDGE AND APPURTENANCES FOR BOKOR CPP-JACKET

MMHE April 12, 2019 In Progress

53. SUPPLY OF HUMIDUR FP QR SARAWAK SHELL

BERHAD April 5, 2019 Completed

54. SUPPLY OF HUMIDUR ME BRUSH SARAWAK SHELL

BERHAD April 5, 2019 Completed

55. SUPPLY AND DELIVERY OF STUD BOLT FOR DULANG C PIPING UPGRADE (PACKAGE OTHERS)

CARIMIN / PETRONAS CARIGALI

April 4, 2019 Completed

56. SUPPLY AND DELIVERY OF STUD BOLT FOR DULANG C PIPING UPGRADE (PACKAGE FLOWLINE/WELLHEAD)

CARIMIN / PETRONAS CARIGALI

April 3, 2019 Completed

57. SUPPLY OF HUMIDUR FP PAINTS TO QET BSP April 1, 2019 Completed

58. MANPOWER SUPPLY (44 PAX) FOR JACKET BOKOR PROJECT MMHE March 29, 2019 In Progress

59. PURCHASE OF COMPUTER HARDWARE

EXXONMOBIL EXPLORATION AND

PRODUCTION MALAYSIA INC.

March 29, 2019 Completed

60. PROVISION OF TENSILE TEST ON HELIDECK NETTING TRANSFAME SDN

BHD March 29,2019 Completed

Page 6: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

61. PRIMAVERA LICENSE RENEWAL PETRONAS TECHNICAL

SERVICES SDN BHD March 26, 2019 Completed

62. PAN MALAYSIA FIELD JOINT COATING SERVICES SARAWAK SHELL

BERHAD / SAPURA ENERGY

March 21, 2019 In Progress

63. SUPPLY OF WELDING ELECTRODE FOR BOKOR CPP PROJECT SAPURA OFFSHORE

SDN BHD March 22, 2019 Completed

64. CABLING & TV INSTALLATION FOR FGVT WAR ROOMS FELDA GLOBAL

VENTURES HOLDINGS BERHAD

March 20, 2019 Completed

65. SUPPLY OF HUMIDUR TC PAINTS TO QET BSP March 20, 2019 Completed

66. SUPPLY OF HUMIDUR FP PAINTS AND HUMICLEAN TO QET BSP March 20, 2019 Completed

67. SUPPLY AND DELIVERY OF STICKER / STENCIL FOR VESSEL (STATIC PTS-34) PETRONAS CARIGALI

March 19, 2019 Completed

68. PROVISION OF SUPPLY, COMMISSIONING OF HEAT SHIELD AND ROOF SHIELD FOR LIFEBOAT-D

CARIGALI HESS March 7, 2019 Completed

69. SUPPLY AND DELIVERY OF ELECTRICAL CABLE SARAWAK SHELL

BERHAD March 5, 2019 Completed

70. SUPPLY OF HUMIDUR FP BRUSH TO MASHHOR GENERAL CONTRACTOR SDN BHD

BLNG March 5, 2019 Completed

71. SUPPLY OF HUMIDUR PAINTS TO TRANSFAME SDN BHD SARAWAK SHELL

BERHAD March 4, 2019 Completed

72. SUPPLY OF HUMIDUR FP BRUSH TO MASHHOR GENERAL CONTRACTOR SDN BHD

BLNG February 28, 2019 Completed

Page 7: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

73. SUPPLY AND DELIVERY OF WATER SHUT OFF VALVE 5K 125A (KORVAL) CHEE FATT CO. PTE

LTD February 22, 2019 Completed

74. SUPPLY OF HUMIDUR PAINTS TO MASHHOR OFFSHORE PAINTING SERVICES SDN BHD

BLNG February 22, 2019 Completed

75. SUPPLY OF HUMIDUR PAINTS TO MASHHOR OFFSHORE PAINTING SERVICES SDN BHD

BLNG February 20, 2019 Completed

76. SUPPLY OF WELDING ELECTRODE FOR EPCI OF GALLAF SAPURA

FABRICATION SDN BHD

February 20, 2019

Completed

77. SUPPLY OF WELDING ELECTRODE FOR BOKOR TOPSIDE MMHE February 14, 2019 Completed

78. SUPPLY OF HUMIDUR ME COATING FOR SS PUTERI ZAMRUD EAGLESTAR

SHIPMANAGEMENT February 14, 2019 Completed

79. SUPPLY OF HUMIDUR FP COATING FOR SS PUTERI ZAMRUD EAGLESTAR

SHIPMANAGEMENT February 14, 2019 Completed

80. RENTAL OF HAND PORTABLE RADIO PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) February 11, 2019 Completed

81. PASSIVE FIRE PROTECTION RECTIFICATION WORK FOR MALIKAI SABAH SHELL PETROLEUM

COMPANY LIMITED February 11, 2019 Completed

82. PASSIVE FIRE PROTECTION TEST PANEL (EARLY MOB) FOR HESS PHASE 2 PROJECT

SAPURA FABRICATION SDN

BHD / HESS EXPLORATION

February 7, 2019 Completed

83. SUPPLY OF HUMIDUR TC PAINTS AND TO QET BSP February 7, 2019 Completed

84. PASSIVE FIRE PROTECTION TEST PANEL (EARLY MOB) HESS / SAPURA February 7, 2019 Completed

Page 8: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

85. SUPPLY OF IT HARDWARE & CONSUMABLES HESS February 1, 2019 In Progress

86. PROVISION OF ASSAI ONSITE SOFTWARE MAINTENANCE RENEWAL (JANUARY-DECEMBER 2019)

SAPURA EXPLORATION &

PRODUCTION (SARAWAK) INC.

January 31, 2019 In Progress

87. SUPPLY OF WELDING ELECTRODE FOR EPC OF GOREK SAPURA

FABRICATION SDN BHD

January 28, 2019 Completed

88. SUPPLY OF WELDING ELECTRODE FOR EPC OF LARAK SAPURA

FABRICATION SDN BHD

January 28, 2019 Completed

89. SUPPLY OF WELDING ELECTRODE FOR EPC OF BAKONG SAPURA

FABRICATION SDN BHD

January 28, 2019 Completed

90. SUPPLY OF WELDING ELECTRODE FOR HESS PHASE 2 SAPURA

FABRICATION SDN BHD

January 25, 2019 Completed

91. SUPPLY OF WELDING ELECTRODE FOR BOKOR PROJECT MMHE January 25, 2019 Completed

92. SUPLLY OF WELDING ELECTRODE FOR BOKOR PROJECT MMHE January 22, 2019 Completed

93. SUPPLY AND DELIVERY OF INSTRUMENT CABLES – COST PLUS (GOPA) DAYANG

ENTERPRISE / MURPHY

January 16, 2019 Completed

94. SUPPLY OF WELDING ELECTRODE – PEGAGA PROJECT SAPURA

FABRICATION SDN BHD

January 15, 2019 Completed

95. SUPPLY OF FOXIT PHANTOM PDF BUSINESS ADDITION FELDA GLOBAL

VENTURES HOLDINGS BERHAD

January 11, 2019 Completed

96. SUPPLY OF HUMIDUR PAINTS FOR DARAT PROJECT E38 AND E15 TO MASHHOR OFFSHORE PAINTING SERVICES SDN BHD

BLNG December 28, 2018 Completed

Page 9: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

97. SUPPLY OF WELDING ELECTRODE FOR JAMNAGAR PROJECT SAPURA

FABRICATION SDN BHD

December 26, 2018 Completed

98. RENTAL OF HAND PORTABLE RADIO PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) December 24, 2018 Completed

99. SUPPLY OF WELDING ELECTRODE FOR PEGAGA JACKET SAPURA

FABRICATION SDN BHD

November 23, 2018 Completed

100. SUPPLY AND DELIVERY OF CABLE INSTRUMENT (ADDITIONAL) FOR HUC MODIFICATION AT D18MP-A FOR D28 PHASE 1 PROJECT

PETRONAS CARIGALI

December 17, 2018 Completed

101. SUPPLY OF HUMIDUR FP BRUSH TO MASHHOR GENERAL CONTRACTOR SDN BHD

BLNG December 6, 2018 Completed

102. PROVISION OF CISCO HARDWARE & SUPPORT SERVICES TO REFRESH NETWORK SYSTEM

HESS December 6, 2018 In Progress

103. PROVISION OF SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION WORK FOR ZETUNG TOPSIDE – HESS PHASE 2 PROJECT

SAPURA FABRICATION SDN

BHD / HESS EXPLORATION

December 5, 2018 Completed

104. SUPPLY OF WELDING ELECTRODE FOR PEGAGA JACKET SAPURA

FABRICATION SDN BHD

November 23, 2018 Completed

105. PROVISION OF SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION WORK FOR ZETUNG TOPSIDE

HESS / SAPURA November 22, 2018 Completed

106. PROVISION OF SERVER SOFTWARE, LICENSES AND SERVICES FOR MURPHY’S OPERATIONS

MURPHY November 22, 2018 Completed

107. RENTAL OF HAND PORTABLE RADIO PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) November 11, 2018 Completed

108. SUPPLY OF HUMIDUR PAINT FOR MESPLT GUMUSUT DEVELOPMENT AND MALIKAI STORE

SABAH SHELL PETROLEUM

November 9, 2018 Completed

Page 10: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

109. SUPPLY OF WELDING ELECTRODE FOR BOBE PROJECT SAPURA PINEWELL

SDN BHD October 18, 2018 Completed

110. SUPPLY OF WELDING ELECTRODE FOR NOC GALLAF PROJECT SAPURA

FABRICATION SDN BHD

October 17, 2018 Completed

111. MATERIAL FRO TELCO SATELLITE ANTENNA PEDESTAL AT WPPA – COST PLUS (ANTI-SLIP)

DAYANG ENTERPRISE /

MURPHY October 17, 2018 Completed

112. PFP RECTIFICATION WORK FOR ST. JOSEPH SEA HIBISCUS SDN

BHD October 16, 2018 Completed

113. PROVISION OF ELECTRONIC OFFICE APPLICATION LEAVE FOR PTTEP HK OFFSHORE LIMITED

PTTEP HK OFFSHORE LIMITED

October 12, 2018 Completed

114. SUPPLY OF WELDING ELECTRODE FOR BOKOR PROJECT MMHE October 12, 2018 Completed

115. SUPPLY OF WELDING ELECTRODE FOR EPC OF GOREK SAPURA

FABRICATION SDN BHD

October 9, 2018 Completed

116. SUPPLY OF PRIMARY UNIT REGULATOR VALVE 20K 50A WITH GAUGE (KORVAL)

PFLNG October 4, 2018 Completed

117. SUPPLY OF WELDING ELECTRODE FOR EPC OF BAKONG SAPURA

FABRICATION SDN BHD

September 25, 2018 Completed

118. SUPPLY AND DELIVERY ELECTRICAL MATERIAL FOR DULANG V-507 SEPARATOR CONTROL UPGRADE

PETRONAS CARIGALI

September 23, 2018 Completed

119. SUPPLY AND DELIVERY OF CABLE AND ACCESSORIES FOR DULANG WELL FLOW MEASUREMENT B23SL DULANG B PLATFORM

PETRONAS CARIGALI

September 21, 2018 Completed

120. SUPPLY OF SWA CABLE DAYANG

ENTERPRISE September 14, 2018 Completed

Page 11: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

121. SUPPLY OF HUMIDUR PAINTS FOR MESPLT GUMUSUT DEVELOPMENT SABAH SELL PETROLEUM

August 30, 2018 Completed

122. SUPPLY & DELIVERY OF TOOLS AND CONSUMABLE (WELDING ELECTRODE) FOR MAINTENANCE, CONSTRUCTION AND MODIFICATION (MCM)

(SKG) SAPURA FAB-BORNEO

SEAOFFSHORE JV / PETRONAS CARIGALI

August 28, 2018 Completed

123. SUPPLY OF HUMIDUR PAINTS FOR BLNG CSIP USAGE BLNG August 20, 2018 Completed

124. SUPPLY OF INSTRUMENT CABLE FOR SAPA INFILL E & I BULK MATERIAL – COST PLUS

DAYANG ENTERPRISE

August 2, 2018 Completed

125. SUPPLY OF 3M 8515 N95 DISPOSABLE RESPIRATOR PETRONAS GAS

BERHAD July 31, 2018 Completed

126. SUPPLY OF HUMIDUR FP COATING FOR LNG PUTERI NILAM EAGLESTAR

SHIPMANAGEMENT July 27, 2018 Completed

127. RENTAL OF DRY-ICE BLASTING SYSTEM FOR 3 MONTHS EVERSOLVE July 23, 2018 Completed

128. SUPPLY OF HUMIDUR PAINTS FOR U7200 TRESTLE STRUCTURE B/P ACTIVITIES EVERSOLVE July 23, 2018 Completed

129. SUPPLY & DELIVERY OF KOBE ELECTRODE FOR INVENTORY STOCK MMHE July 20, 2018 Completed

130. PROVISION OF PASSIVE FIRE PROTECTIONS (PFP) FOR BR-A PLATFORM REPSOL

REPSOL July 19, 2018 Completed

131. STRUCTURAL WORKS FOR BOKOR CPP TOPSIDES PETRONAS CARIGALI

July 18, 2018 Completed

Page 12: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

132. PROVISION OF SUPPLY OF MANPOWER, MATERIALS AND EQUIPMENT FOR INSTALLATION OF A60 RATED FIRE INSULATION WORK AT SELIGI

ENQUEST July 18, 2018 Completed

133. SUPPLY AND DELIVERY OF CABLES FOR SUMANDAK SELATAN INFILL PROJECT

PETRONAS CARIGALI

July 13, 2018 Completed

134. SUPPLY OF DISPOSABLE RESPIRATOR (REPEAT ORDER) MALAYSIAN

REFINING COMPANY July 13, 2018 Completed

135.

SUPPLY AND DELIVERY OF CABLE INSTRUMENTATION FOR HUC MODIFICATION AT D18MP-A FOR HOST TIE IN DE-BOTTLENECKING FOR D18 PHASE 2 PROJECT

PETRONAS CARIGALI

July 12, 2018 Completed

136. SUPPLY OF SWA CABLE TAI CREST

RESOURCES July 11, 2018 Completed

137. PROVISION OF SUPPLY INSTRUMENT CONTROL CABLE FOR TIONG-A ICP 2.0 PROJECT AT TIONG-A PLATFORM

PETRONAS CARIGALI

July 10, 2018 Completed

138. SUPPLY OF ELECTRODE FOR BOKOR-BETTY – BASE SCOPE

SAPURA PINEWELL SDN BHD / PETRONAS CARIGALI

July 4, 2018 Completed

139. SUPPLY OF DISPOSABLE RESPIRATOR MALAYSIAN

REFINING COMPANY July 3, 2018 Completed

140. PROVISION OF MOXA DEVICES PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) July 2, 2018 Completed

141. PROVISION OF SUPPLY FIBRE OPTIC CABLE FOR TIONG-A ICP 2.0 PROJECT AT TIONG-A PLATFORM

PCSB June 26, 2018 Completed

142. SUPPLY OF ELECTRODE NC36L FOR BOKOR BETTY – BASE SCOPE

SAPURA PINEWELL SDN BHD / PETRONAS CARIGALI

June 13, 2018 Completed

143. PASSIVE FIRE PROTECTION WORKS FOR ANJUNG BDEWC May 30, 2018 Completed

Page 13: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

144. SUPPLY OF DRAKA CABLE PETRONAS CHEMICALS ETHYLENE

May 22, 2018 Completed

145. SUPPLY OF HEAT BARRIER PANEL FOR AHU AND VSAT ANTENNA HEAT PROTECTION AT EAST BELUMUT PLATFORM

NEWFIELD May 17, 2018 Completed

146. RENTAL OF HAND PORTABLE RADIO PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) May 15, 2018 Completed

147. SUPPLY AND RENTAL OF ADDITIONAL DMR HAND PORTABLE RADIO PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) May 15, 2018 Completed

148. PURCHASE ADOBE CREATIVE CLOUD PETRONAS GAS

BERHAD May 2, 2018 Completed

149. SUPPLY & DELIVERY OF DRAKA CABLE FOR FSU NAUTICA MUAR (BENTARA) EPOMS April 27, 2018 Completed

150. SUPPLY OF SPARE PART FOR 2WAY CONTROL VALVE (KORVAL) PFLNG April 26, 2018 Completed

151. SUPPLY OF KOBE ELECTRODE FOR HESS PHRASE II HESS April 17, 2018 Completed

152. PROVISION FOR RENEWAL OF ANNUAL SUBSCRIPTION FOR AUTOCAD COMMERCIAL

PETRONAS TECHNICAL

SERVICES SDN BHD April 23, 2018 Completed

153. SUPPLY OF BREAKING LOAD TENSILE TEST FOR HELIDECK NETTING GK MALIKAI – COST PLUS

PETRA RESOURCES April 12, 2018 Completed

154. CONFIGURATION OF ADDITIONAL CHANNEL AND FREQUENCY FOR LEASING PORTABLE RADIOS

PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) April 11, 2018 Completed

155. PROVISION OF MAINTENANCE RENEWAL (SOLARWINDS AND VEEAM)

EXXONMOBIL EXPLORATION AND

PRODUCTION MALAYSIA INC.

April 11, 2018 Completed

Page 14: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

156. SUPPLY OF ID CARD PRINTER FOR HSE SAPURA

EXPLORATION AND PRODUCTION

April 10, 2018 Completed

157. SUPPLY OF KOBE ELECTRODE FOR HESS PHRASE II HESS April 10, 2018 Completed

158. PROVISION OF MAINTENANCE RENEWAL (PRIMAVERA P6 ENTERPRISE) PETRONAS TECHNICAL SERVICES

March 28, 2018 Completed

159. PROVISION OF LCV ACTUATOR AND PLC NETWORK PETROFAC (PM304-MALAYSIA) LIMITED

March 27, 2018 Completed

160. SUPPLY OF INSTRUMENT CABLE (REPEAT ORDER) AFS-887 – SATELLITES TURNAROUND (SATURN) PROJECT - GuF

EMEPMI March 23, 2018 Completed

161. PROVISION OF IT PERIPHERALS PETRONAS TECH

TRAINING March 19, 2018 Completed

162. SUPPLY OF HUMIDUR FP PAINTS TO QET BSP March 14, 2018 Completed

163.

SUPPLY MATERIALS AND APPLICATION FIRE PROOFING MATERIALS ON NEW LOADING PLATFORM STRICTURES FOR SPR 2 PROJECT FIRE PROOFING APPLICATION ON NEW JETTY PLATFORM STRUCTURES

BLNG March 7, 2018 In Progress

164. SUPPLY OF HUMIDUR PAINTS FOR UNIT 7200 LNG RUNDOWN LINE (GRE CLADDING) PAINTING WORK

BLNG February 26, 2018 Completed

165. PROVISION TO SUPPLY IT HARDWARE & CONSUMABLES HESS EXPLORATION

& PRODUCTION MALAYSIA B.V

February 21, 2018 Completed

166. PROVISION OF ADOBE SOFTWARE PETRONAS

CHEMICALS GROUP BERHAD

February 20, 2018 Completed

167. SUPPLY OF WELDING ELECTRODE FOR STRUCTURAL INSTALLATION FOR SSB PAN MALAYSIA 2018

SSB February 12, 2018 Completed

Page 15: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

168. SUPPLY OF INSTRUMENT CABLE (REPEAT ORDER) GUNTONG PRODUCTION OPTIMIZATION - GuD

EMEPMI February 9, 2018 Completed

169. SUPPLY OF HUMIDUR PAINTS - WESCO SHELL PHILIPPINES EXPLORATION B.V

February 5, 2018 Completed

170. PROVISION OF MOXA DEVICES PETRONAS GAS

BERHAD January 30, 2018 Completed

171. SUPPLY OF HEAT SHIELD PANEL FOR BLUE BRUSKER AT DUYONG LQ PETRONAS CARIGALI

January 24, 2018 Completed

172. PROVISION TO SUPPLY & DELIVER OF PIPELINE TAPE FOR PCSB-SBO PETRONAS

CARIGALI SDN BHD January 23, 2018 Completed

173. ASSAI CALL-OFF MAITENANCE AND SUPPORT SERVICES SAPURA

EXPLORATION & PRODUCTION

January 12, 2018 Completed

174.

PROVISION OF DESIGN, SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION FOR BOD HTI – PROVISION BUNGA PAKMA ACCOMODATION WORK BOAT GANGWAY PROJECT

REPSOL December 12, 2017 Completed

175. SUPPLY OF HUMIDUR PAINTS FOR U7200 TRESTLE STRUCTURE B/P ACTIVITIES BLNG November 29, 2017 Completed

176. SUPPLY OF HUMIDUR FP PAINTS TO MGC BSP November 17, 2017 Completed

177. RENTAL OF HAND PORTABLE RADIO PRPC UTILITIES AND FACILITIES SDN BHD

(PENGERANG) November 11, 2017 Completed

178. FLARE TOWER PFP REINSTATEMENT FOR KIKEH MURPHY September 11, 2017 Completed

179. PROVISION OF PASSIVE FIRE PROTECTION FOR M1 TOPSIDE MAINTENANCE AND STRUCTURAL REPAIR

PETRONAS August 25, 2017 Completed

Page 16: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

180. SUPPLY OF PAINT-MANUFACTURER “ACOTEC & HUMIDUR” SHELL August 24, 2017 Completed

181. PROVISION OF MOTOROLA PORTABLE RADIO AND ACCESSORIES PETRONAS

CARIGALI SND BHD August 24, 2017 Completed

182. PROVISION OF MOTOROLA ACCESSORIES OCEAN MIGHT SDN

BHD August 22, 2017 Completed

183. PROVISION OF MOTOROLA PORTABLE RADIO ACCESSORIES SAPURA

EXPLORATION AND PRODUCTION

August 14, 2017 Completed

184. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION COMPOUND FOR SSB/SSPC – F06

SHELL August 9, 2017 Completed

185. SUPPLY OF MATERIALS AND SPARE PARTS FOR BERGADING-CPP FRESH WATER GENERATOR FOR NORTH MALAY BASIN FULL FIELD DEVELOPMENT

HESS August 7, 2017 In Progress

186. SUPPLY OF AVAYA PABX TELECOMMUNICATION HARDWARE AND ACCESSORIES

HESS August 4, 2017 Completed

187. PROVISION FOR MATLAB SOFTWARE MAINTENANCE SUPPORT FOR 2 YEARS HESS EXPLORATION

& PRODUCTION MALAYSIA B.V

August 3, 2017 Completed

188. PROVISION OF MOTOROLA ACCESSORIES REPSOL OIL AND

GAS MALAYSIA LTD July 24, 2017 Completed

189. PURCHASE OF IT PERIPHERALS

EXXONMOBIL EXPLORATION AND

PRODUCTION MALAYSIA INC.

July 19, 2017 Completed

190. RECTIFICATION OF MISALIGNED STEAM TURBINE PIPING ST 8100 AT ACRYLIC PLANT

BASF July 13, 2017 Completed

191.

PROVISION OF PASSIVE FIRE PROTECTION (PFP) COATING FOR BO-D RISER SPLASH ZONE SECTION FOR BUNGA PAKMA DEVELOPMENT PROJECT – REPSOL 2017

REPSOL July 10, 2017 Completed

Page 17: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

192. HIRING OF DRY ICE BLASTING VENDOR FOR CARRYING OUT DI BLASTING AT BLNG-CSIP FOR TA 2017

BLNG June 24, 2017 Completed

193. PROVISION OF TELWIN ENERGY 650 START BATTERIES SAPURA

EXPLORATION & PRODUCTION

June 22, 2017 Completed

194. PROVISION FOR DESIGN, FABRICATE, SUPPLY AND INSTALLATION ASSISTANCE/SUPERVISION FOR HEAT SHIELD FOR SAPAWI PROJECT

MURPHY June 21, 2017 Completed

195. PROVISION OF HAYAMIM AVA ELECTRONIC WHITEBOARD AND ACCESSORIES HESS EXPLORATION

& PRODUCTION MALAYSIA B.V

June 1, 2017 Completed

196. PURCHASE OF IT PERIPHERALS PETRONAS DAGANGAN BERHAD

May 22, 2017 Completed

197. PURCHASE OF IT PERIPHERALS PETRONAS PENAPISAN (MELAKA)

May 8, 2017 Completed

198. PROVISION OF PASSIVE FIRE PROTECTION SUBCONTRACTING WORK BDEWC April 21, 2017 Completed

199. PROVISION OF MAINTENANCE RENEWAL OF SECURITY SYSTEM (FIREWALL-CYBEROAM)

SAPURA EXPLORATION &

PRODUCTION April 20, 2017 Completed

200. PURCHASE OF IT PERIPHERALS SAPURA

EXPLORATION & PRODUCTION

April 14, 2017 Completed

201. SUPPLY AND DELIVERY OF PRINTER EPOMS April 5, 2017 Completed

202. SUPPLY AND DLEIVERY SAMSUNG MOBILE SMARTPHONES EPOMS March 15, 2017 Completed

203. PROVISIONAL OF SUPERVISION, LABOUR SUPPLY, RENTAL OF MACHINERY AND SCAFFOLDING FOR INSULATION WORK AT LEMONGRASS PROJECT

BASF March 3, 2017 Completed

Page 18: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

204. JUNIPER NETWORK SUPPORT

EXXONMOBIL EXPLORATION AND

PRODUCTION MALAYSIA INC.

February 22, 2017 Completed

205. FIRE PROOFING REPAIR FOR U-7420 c/w ALL MATERIALS EQUIPMENT & MANPOWER FOR U-7420

BLNG January 25, 2017 Completed

206. PURCHASE OF TELECON/NETWORK EXXONMOBIL December 14, 2016 Completed

207. PROVISION TO SUPPLY IT HARDWARE & CONSUMABLES HESS November 25, 2016 Completed

208. RECTIFICATION OF MISALIGNMENT STEAM TURBINE PIPE STAGE 1 BASF November 11, 2016 Completed

209. PURCHASE OF COMPUTER EQUIPMENT EXXONMOBIL November 1, 2016 Completed

210. SUPPLY AND DELIVERY OF SAMSUNG MOBILE SMARTPHONES PETRONAS TECHNICAL

TRAINING SDN BHD October 28, 2016 Completed

211. SUPPLY OF RIBBON ZEBRA

PETRONAS CHEMICAL

DERIVATIVES SDN BHD

October 25, 2016 Completed

212. SUPPLY OF RIBBON ZEBRA

PETRONAS CHEMICAL

DERIVATIVES SDN BHD

October 24, 2016 Completed

213. PASSIVE FIRE PROTECTION WORK FOR SK310 B15 DEVELOPMENT PETRONAS CARIGALI

September 28, 2016 Completed

214. PROVISION VSAT SERVICES SAPURAKENCANA SK GEOTECHNICS

August 22, 2016 In Progress

215. SUPPLY OF KOBE ELECTRODE FOR SK310 B15 DEVELOPMENT - TOPSIDE PETRONAS CARIGALI

August 16, 2016 Completed

Page 19: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

216. PASSIVE FIRE PROTECTION WORKS FOR BNJT-K FOR EPCC TUKAU BARONIA WELLHEAD PLATFORMS (WHP) PROJECT

PETRONAS CARIGALI

June 8, 2016 Completed

217. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION COMPOUND FOR SSB/SSPC – WORKSCOPING AT E11, F23, F13 AND F06

SHELL May 18, 2016 Completed

218. CONTRACT NO: UI50960 - SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION COMPOUND FOR SSB/SSPC

SHELL April 1, 2016 Completed

219. PROVISION OF VIV STRAKES FOR MALIKAI’S PIPELINE SHELL March 16, 2016 Completed

220. PROVISION OF VSAT COMMUNICATION SERVICES & WIRELESS RADIO SERVICES FOR KBM CLUSTER FIELD DEVELOPMENT

COASTAL ENERGY January 28, 2016 In Progress

221.

PROVISION OF NAVAL ARCHITECTURE AND MARINE ENGINEERING FOR PROVISION OF HOOK-UP AND COMMISSIONING FOR BOKOR PHASE 3A PROJECT

PETRONAS CARIGALI November 2, 2015 Completed

222. PASSIVE FIRE PROTECTION WORKS FOR TTJT-K FOR EPCC TUKAU BARONIA WELLHEAD PLATFORMS (WHP) PROJECT

PETRONAS CARIGALI October 23, 2015 Completed

223. PROVISION OF 14” PIPELINE RISER COMPACT FLANGE INSPECTION AND TESTING WORKS FOR KPOC – RM 500,000

KPOC September 18, 2015 Completed

224. PROVISION OF FJC SERVICES FOR SHELL MALIKAI PACK B – USD 700,000 SHELL September 10, 2015 Completed

225. PASSIVE FIRE PROTECTION WORKS FOR EPCIC OF REMOTE WHPS FOR FULL FIELD DEVELOPMENT, NORTH MALAY BASIN PROJECT

HESS September 8, 2015 Completed

226. PROVISION OF VSAT COMMUNICATION SERVICES FOR SKE’S DRILLING RIG SAPURAKENCANA

ENERGY September 1, 2015 Completed

227. PROVISION OF NAVAL ARCHITECTURE SERVICES FOR PROVISION OF HOOK-UP AND COMMISSIONING FOR BARAM HELIDECK PROJECT

PETRONAS CARIGALI

September 1, 2015 Completed

Page 20: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

228.

PROVISION AND SUPPLY OF HDPF WITH SEA SLEEVE & INTRAFUSE FOR PROCUREMENT CONSTRUCTION & COMMISSIONING (PCC) OF REGASTIFICATION TERMINAL 2 PIPELINE PROJECT – USD 35,000

CPM GROUP July 28, 2015 Completed

229. SUPPLY OF STRAKES AND BENDS FOR SHELL GUMUSUT PHASE 2 SHELL July 6, 2015 Completed

230. SUPPLY OF STRAKES AND STRAPS FOR SHELL GUMUSUT PHASE 2 SHELL June 16, 2015 Completed

231. SUPPLY OF PIPELINE FIELD JOINT ANTI-CORROSION COATING SYSTEM FOR BESAR PIPELINE INSTALLATION – PCSB YEAR 2015

PETRONAS CARIGALI May 12, 2015 Completed

232. TO SUPPLY AND DELIVER CORROSION INHIBITOR TOTE TANK (TTJT-A) FOR EPCC OF BNJT-K AND TTJT-A WELLHEAD PLATFORMS (WHP)

PETRONAS CARIGALI May 6, 2015 Completed

233. TO SUPPLY AND DELIVER WASH WATER STORAGE TANK FOR EPCC OF BNJT-K AND TTJT-A WELLHEAD PLATFORM

PETRONAS CARIGALI April 29, 2015 Completed

234. PASSIVE FIRE PROTECTION WORKS FOR PCC OF BESAR-A WHP TOPSIDE PETRONAS CARIGALI April 24, 2015 Completed

235. PROVISION OF VSAT COMMUNICATION SERVICES TOTAL E&P MALAYSIA

October 1, 2014 Completed

236. PROVISION OF WASTE DISPOSAL MANAGEMENT FOR BINTULU OPERATIONS BC PETROLEUM SDN

BHD October 1, 2014 Completed

237. VSAT SATELITE TELECOMMUNICATION SYSTEM AND SERVICES FOR BOKOR PHASE 3A

SCHLUMBERGER September 29, 2014 Completed

238. TO SUPPLY AND DELIVER ATMOSPHERIC TANKS FOR EPCIC OF LAYANG DEVELOPMENT FACILITIES

JX NIPPON September 17, 2014 Completed

239. SUPPLY OF SERVIWRAP PETRONAS CARIGALI

August 8, 2014 Completed

240. PROVISION OF PASSIVE FIRE PROTECTION FOR WELLHEAD PLATFORM BLOCK PM 307 BERTAM FILED DEVELOPMENT

LUNDIN PETROLEUM July 16, 2014 Completed

Page 21: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

241. PROVISION OF COMMUNICATION & ASTRO SERVICE SYSTEM FOR EPV PETRONAS CARIGALI

July 7, 2014 Completed

242. ELECTRODE (KOBELCO) FOR WHEATSTONE PROJECT LNG PLANT – MODULE FABRICATION ISBL

SAPURAKENCANA July 3, 2014 Completed

243. SUPPLY AND DELIVERY OF CABLES & ACCESSORIES FOR HUC FOR CENDOR PHASE 2 DEVELOPMENT PROJECT, BLOCK PM304

KENCANA PETROLEUM

May 28, 2014 Completed

244. VSAT SERVICES FOR TALISMAN MALAYSIA’S OFFSHORE PRODUCTION PLATFORMS

TALISMAN MALAYSIA

May 1, 2014 In Progress

245. PROVISION OF 3RD PARTY SERVICES FOR PASSIVE FIRE PROTECTION AT FIREWALL EAST BELUMUT PLATFORM

MMC OIL & GAS April 30, 2014 Completed

246. DISPOSAL OF SCRAP METAL ITEMS DUE TO MAINTENANCE, DAMAGE METTALIC PARTS, USED SPARE PARTS, OBSOLETE AND EXPIRED MATERIAL

PETRONAS PENAPISAN

(MELAKA) SDN BHD April 21, 2014 Completed

247.

FABRICATION WORKS, SUPPLY OF MATERIAL, EQUIPMENT & MANPOWER AND DELIVERY OF PERMANENT FLANGE PROTECTOR & STUDBOLT FOR SSB PROJECT

TL OFFSHORE SDN BHD

April 16, 2014 Completed

248. PROVISION OF FIXED VSAT SERVICES FOR UMW NAGA JACK-UP RIGS FOR UMW OFFSHORE DRILLING SDN BHD

UMW OFFSHORE DRILLING

April 1, 2014 In Progress

249. PROVISION OF VSAT SYSTEM SERVICES FOR EVA-NMB GAS PIPELINE INSTALLATION

GOM RESOURCES SDN BHD

April 1, 2014 Completed

250. M03PQ-A V-3030 AND 3040 STRUCTURE FRAMING PFP COATING REPAIR (OPTION NO.1)

SHELL February 12, 2014 Completed

251. PROVISION OF FIXED VSAT SERVICES FOR COASTAL ENERGY’S MOBILE PRODUCTION UNIT, THE EP5 AND EP6

COASTAL ENERGY January 1, 2014 In Progress

252. MASTER SERVICE AGREEMENT FOR PROVISION OF VSAT SYSTEM FOR MAIN WORK BARGES / VESSELS 2014 – 2016 – TL OFFSHORE SDN BHD

TL OFFSHORE January 1, 2014 In Progress

253. M03PQ-A VESSEL V-6210 PFP COATING SHELL December 27, 2013 Completed

Page 22: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

254. PASSIVE FIRE PROTECTION SYSTEM ON DIESEL STORAGE TANK COLUMN T-S16270 AT KIKEH UNITL SCOPE COMPLETE

MURPHY November 28, 2013 Completed

255.

SUPPLY AND DELIVERY OF GRATING & ACCESSORIES FOR WAVE ZONE GRATING PHASE 2 FOR GUNTONG C STRUCTURAL AND PIPING SYSTEM REPAIR PROGRAM

EMEPMI November 13, 2013 Completed

256.

SUPPLY AND DELIVERY OF GRATING & ACCESSORIES FOR WAVE ZONE GRATING PHASE 2 FOR GUNTONG B STRUCTURAL AND PIPING SYSTEM REPAIR PROGRAM

EMEPMI November 13, 2013 Completed

257.

SUPPLY AND DELIVERY OF GRATING & ACCESSORIES FOR WAVE ZONE GRATING PHASE 2 FOR TABU A STRUCTURAL AND PIPING SYSTEM REPAIR PROGRAM

EMEPMI October 28, 2013 Completed

258.

SUPPLY AND DELIVERY OF GRATING & ACCESSORIES FOR WAVE ZONE GRATING PHASE 2 FOR PALAS A STRUCTURAL AND PIPING SYSTEM REPAIR PROGRAM

EMEPMI October 28, 2013 Completed

259.

SUPPLY AND DELIVERY OF GRATING & ACCESSORIES FOR WAVE ZONE GRATING PHASE 2 FOR GUNTONG A STRUCTURAL AND PIPING SYSTEM REPAIR PROGRAM

EMEPMI October 25, 2013 Completed

260. PROVISION FOR REMOVAL AND INSTALLATION OF EPOXY-TYPE PASSIVE FIRE PROTECTION FOR HELANG INTEGRATED PLATFORM (HIP)

MMC OIL & GAS October 22, 2013 Completed

261. MODIFICATION AND FABRICATION OF NEW GRILLAGES / SKID RADOIL ONSHORE SUPPORT SYSTEM FOR J-LAY TOWER - SASB

SAPURA ACERGY SDN BHD

September 12, 2013 Completed

262. PROVISION OF FIREWALL UPGRADE (PFP COATING) FOR TAPIS EOR PROJECT FOR GUE TELOK PLATFORM

EMEPMI September 6, 2013 Completed

263. PROVISION OF FIELD JOINT COATING SERVICES FOR EVA PROJECT 2013 HESS August 10, 2013 Completed

264. PROVISION OF FIXED VSAT SERVICES FOR ATWOOD MANTA AND COASTAL ENERGY

ATWOOD August, 2013 Completed

265. SUBCONTRACT WORKS FOR PASSIVE FIRE PROTECTION WORKS FOR DAMAR-A PLATFORM

EMEPMI July 29, 2013 Completed

Page 23: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

266. PROVISION OF FIELD JOINT COATING SERVICES FOR TUKAU PROJECT 2013 HESS July 18, 2013 Completed

267. PROVISION OF VSAT SERVICES FOR BUMI ARMADA AT-300 VESSEL BUMI ARMADA June, 2013 Completed

268. PROVISION OF STABILIZED VSAT SERVICES FOR PERISAI PETROLEUM ON THE PERISAI KAMELIA

PERISAI PETROLEUM June, 2013 Completed

269. SUPPLY AND DELIVER OF SLIDING PLATE FOR FABRICATION OF KBB TOPSIDES (BOAQ) - MMHE

KPOC May 23, 2013 Completed

270. PROVISION OF PASSIVE FIRE PROTECTION FOR SHELL D12 & LAILA FIELD DEVELOPMENT - THHE

SARAWAK SHELL BERHAD

May 9, 2013 Completed

271. PROVISION OF SUPPLY & SERVICE OF HBE COATING APPLICATION FOR 16” X 22KM DAMAR-A TO LAWIT-A CRA PIPELINE – TL OFFSHORE SDN BHD

EMEPMI May 2, 2013 Completed

272.

PROVISION OF RISER CLAMP & FLANGE PROTECTOR FOR 16” X 52KM GAS EXPORT PIPELINE FROM PLEM & LAWIT A PLATFORM – GOM RESOURCES SDN BHD

HESS EXPLORATION & PRODUCTION MALAYSIA B.V

April 29, 2013 Completed

273. PROVISION OF HEAT SHIELD FOR TAPIS EOR PROJECT FOR GUE TELOK PLATFORM – SHAPADU ENERGY & ENGINEERING

EMEPMI April 2013 Completed

274. SUPPLY AND INSTALLATION OF HEAT SHIELD FOR KINABALU KNPG-B - MMHE PETRONAS

CARIGALI SDN BHD April 2013 Completed

275. OFFSHORE CARRY OVER WORKS FOR PIPING OF TAPIS-Q TOPSIDES - MMHE EMEPMI April 2013 Completed

276.

PROVISION FOR PURCHASE OF STRUCTURAL STEEL PIPES FOR TAPIS B WI HTI PIPE SUPPOR TSTOP (AFS003B) – SHAPADU ENERGY & ENGINEERING SDN BHD

EMEPMI April 2013 Completed

277.

PROVISION FOR PURCHASE OF STRUCTURAL STEEL PIPES FOR TAPIS C PLATFORM TOPSIDE (EXCLUDE LER) - SHAPADU ENERGY & ENGINEERING SDN BHD

EMEPMI April 2013 Completed

278.

PROVISION OF FABRICATION AND DELIVERY OF 16” SE-PA RISER LOAD BEARING CLAMP AND SLIDING CLAMP FOR MOC YEAR 2013 PIPELINES INSTALLATION - SAPURA KENCANA PETROLEUM C/O TL OFFSHORE SDN BHD

MURPHY SARAWAK OIL. CO. LTD

April 2013 Completed

Page 24: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

279.

SUPPLY AND DELIVER OF CEILING FINISHES - SUSPENDED CEILING SYSTEM SOUTH ACIS OIL & GAS DEVELOPMENT PROJECT (REPEAT ORDER) - BROOKE DOCKYARD & ENGINEERING WORKS CORPORATION

BROOKE DOCKYARD & ENGINEERING

WORKS CORPORATION

March 18, 2013 Completed

280.

ENGINEERING,SUPPLY OF MATERIAL, MANUFACTURING, FABRICATION, INSTALLATION AND MODIFICATION OF FIBERGLASS GRATINGS, STAIRTREADS AND GRE HANDRAILS FOR DAMAR A SUBSTRUCTURE PROJECT – MMHE

EMEPMI March 13, 2013 Completed

281. PROVISION OF 3LPE FIELD JOINT COATING ON 12” & 10” LINEPIPE SERVICES FOR SIAKAP NORTH PETAI (SNP) DEVELOPMENT PROJECT

MURPHY SNP March 11, 2013 Completed

282. PROVISION OF FIELD JOINT COATING SERVICES FOR EMEPMI 2013 TAPIS & DAMAR OFFSHORE INSTALLATION WORK – TL OFFSHORE

EMEPMI March 8, 2013 Completed

283.

SUPPLY & DELIVERY OF FIELD JOINT ANTI CORROSION COATING SYSTEM HEAT SHRINK SLEEVE (RAYCHEM WPC100) FOR EMEPMI 2013 TAPIS & DAMAR OFFSHORE INSTALLATION WORK – TL OFFSHORE

EMEPMI March 8, 2013 Completed

284. PROVISION OF PIPELINE FIELD JOINT INFILL MATERIAL FOR TAPIS EOR & DAMAR GAS DEVELOPMENT PROJECT Y2013

EMEPMI March 7, 2013 Completed

285. PROVISION OF FIRE PROTECTION (PFP) AND INSULATION WORK FOR WEST DESARU TOPSIDES - THHE FABRICATORS SDN BHD

AQUATERRA ENERGY LIMITED

March 7, 2013 Completed

286. M03 DAMAGED FPF COATING REPAIR - DAYANG ENTERPRISE SDN BHD SHELL March 2013 Completed

287. M01 DAMAGED PFP COATING REPAIR - DAYANG ENTERPRISE SDN BHD SHELL March 2013 Completed

288.

PROVISION OF SUPPLY AND DELIVERY OF MONEL WELDING INTEGRATED TRANSPORTATION AND INSTALLATION OF OFFSHORE FACILITIES FOR EARLY PRODUCTION SCHEME (EPS), INTEGRATED GAS DEVELOPMENT (IGD) PROJECT, NORTH MALAY BASIN (NMB) FIELD – GOM RESOURCES SDN BHD

HESS EXPLORATION & PRODUCTION

MSIA B.V. March 2013 Completed

289. PROVISION OF FIELD JOINT COATING SERVICES FOR HESS 2013 PROJECT – GOM RESOURCES

HESS February 26, 2013 Completed

290. PROVISION TO SUPPLY AND DELIVER CRUDE OIL WASHING MACHINE (COW MACHINE) SUPPLY FOR BERANTAI OPERATION - PETROFAC

PETRONAS January 29, 2013 Completed

Page 25: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

291. SUBCONTRACTOR FOR PASSIVE FIRE PROTECTION WORKS FOR KBB TOPSIDES - MMHE

KPOC January 21, 2013 Completed

292. ARCHITECTURAL INSULATION PACKAGE SUPPLY OF M90 FIRETEX FOR GREATER EKOFISK AREA 2/4 - SMOE

CONOCO PHILIPS January 15, 2013 Completed

293.

PROVISION OF 3RD CAMPAIGN SEA-FASTENING WORKS OF J-LAY AND PES TOWER ON BOARD SAPURA 3000 – SAPURA ACERGY SDN BHD

SHELL January 11, 2013 Completed

294.

PROVISION OF SUPPLY AND DELIVERY OF CEILING FINISHES – SUSPENDED CEILING FOR SOUTH ACIS PROJECT – BROOKE DOCKYARD AND ENGINEERING WORKS.

MURPHY January 10, 2013 Completed

295. DESIGN, FABRICATION & DELIVERY OF FIREWALL FOR DAMAR-A TOPSIDE MMHE

EMEPMI January 08, 2013 Completed

296. SUPPLY OF PAINT EMEPMI December 27, 2012 Completed

297.

E & I WORKS-FABRICATION AND INSTALLATION FOR F14DR-A TOPSIDES & F14/F29 PROCESS MODULE – MALAYSIA MARINE AND HEAVY ENGINEERING SDN. BHD.

SHELL December 17, 2012 Completed

298. STRUCTURE WORKS FOR DAMAR-A PLATFORM (TOPSIDE) - MMHE EMEPMI November 12, 2012 Completed

299. SUPPLY OF INSULATION MATERIALS FOR FABRICATION OF KEBABANGAN TOPSIDES (5.12M003C) – MALAYSIA MARINE HEAVY ENGINEERING SDN. BHD.

KPOC October 18, 2012 Completed

300.

SUPPLY, DELIVERY, AND INSTALLATION SUPERVISION OF COMPOSITE MATERIALS (FIBERGLASS) & ACCESSORIES FOR WAVE ZONE GRATING FOR GUNTONG A STRUCTURAL AND PIPING SYSTEM REPAIR PROGRAM, EMEPMI EPCM BROWNFIELD PROJECT.

EMEPMI October 5, 2012 Completed

301. SUPPLY AND DELIVER OF OFFICE EQUIPMENT (HS1146630X FIRE FIGHTING SUIT) HS1146630X FIRE FIGHTING SUIT

UNIVERSITI TELNOLOGI

PETRONAS, TRONOH PERAK

October 2012 Completed

Page 26: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

302.

SUPPLY OF INSULATION MATERIALS FOR FABRICATION OF KEBABANGAN TOPSIDES (BOAQ)(5.12M002B) – MALAYSIA MARINE HEAVY ENGINEERING SDN. BHD.

KPOC September 24, 2012 Completed

303. SUPPLY OF INSULATION MATERIALS FOR FABRICATION OF KEBABANGAN TOPSIDES (5.12M003C) – MALAYSIA MARINE HEAVY ENGINEERING SDN. BHD.

KPOC September 24, 2012 Completed

304.

PROVISION OF FABRICATION 18” AND 12” FLEXIJOINT BODY SUPPORT ON ERECTOR FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD

SHELL September 13, 2012 Completed

305.

PROVISION OF FABRICATION 8” AND 10” STRESSJOINT BODY SUPPORT ON ERECTOR FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD

SHELL September 12, 2012 Completed

306. PROVISION OF FIELD JOINT COATING SERVICES FOR 8" AND 10" MALIKAI PIPELINE – GOM RESOURCES

SHELL September 11, 2012 Completed

307.

PROVISION OF FABRICATE AND SUPPLY OF WS2 UPPER MAST ELEMENT 2 LIFTING PAD EYE FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISIHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD

SHELL September 5, 2012 Completed

308.

PROVISION OF FABRICATE AND SUPPLY OF NEW 18” ESCALATOR TROLLEY INSERTS, ACCESS TO HPU BOOST PUMPS, WS2 LOWER MAST ELEMENT 2, WS2 HINGE HATCH COVER, WS1 RAIN PROTECTION IMPROVEMENT FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISIHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD

SHELL September 5, 2012 Completed

309. PROVISION OF STABILIZED VSAT SATELLITE COMMUNICATIONS FOR SAPURAACERGY ON THE SAPURA3000

SAPURAACERGY September, 2012 Completed

310. PROVISION OF TELECOMMUNICATION SYSTEM (VSAT) – SCOPETEL SDN. BHD SCOPETEL August 30, 2012 Completed

311. PROVISION OF DISPOSAL OF DAMAGED KOSMO, IVECO AND MAN BUSES AND ITS COMPONENTS – SYARIKAT PRASANA NEGARA BERHAD

SPNB August 29, 2012 Completed

312. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION (PFP) FOR TAPIS Q TOPSIDE – MMHE SDN BHD

EMEPMI August 28, 2012 Completed

313. SUPPLY AND DELIVERY OF HSS (WPC100M) FOR MALIKAI PIPELINE – GOM RESOURCES

SHELL August 18, 2012 Completed

Page 27: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

314. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION (PFP) FOR TELOK A TOPSIDES – MMHE SDN BHD

EMEPMI August 9, 2012 Completed

315. PROVISION OF VSAT SERVICES IN GULF OF MEXICO – SAPURA ACERGY SDN BHD

SAPURA ACERGY August 9, 2012 Completed

316.

PROVISION OF FIELD JOINT COATING SERVICES AND SUPPLY OF ANTICORROSSION TAPE (SERVIWRAP M30B) FOR 6" X 7.6KM BEKOK-A TO TIONG-A PIPELINE INSTALLATION – GOM RESOURCES

PETRONAS August 2, 2012 Completed

317. SUPPLY OF VINYL COATED CHAIN LINK FABRIC FOR EMEPMI’S TABU A STRUCTURAL REPAIR PROJECT – PERUNDING RANHILL WORLEY

EMEPMI July 31, 2012 Completed

318. SUPPLY AND DELIVER OF HEAVY DUTY ANTI SLIP STEP COVER – TALISMAN MALAYSIA LIMITED

TALISMAN July 12, 2012 Completed

319. PROVISION OF TELECOMMUNICATION SYSTEM FOR TOISA PALADIN – FUGRO GEODETIC (M) SDN BHD

FUGRO GEODETIC July 12, 2012 Completed

320. FABRICATION AND INSTALLATION OF STRUCTURE WORKS FOR PACKAGE 1, DECK NORTH AND MISC FOR TAPIR R TOPSIDES PROJECT - MMHE SDN BHD

EMEPMI July 10, 2012 Completed

321.

SUBCONTRACT FOR PIPING WORKS FOR PACKAGE B: B-193 A-Q (LIVING QUARTERS, POWER GENERATION & WATER INJECTION) AND PACKAGE B: B-193 A-P FOR (PGC & AGRU) – SIME DARBY ENGINEERING SDN BHD

OIL AND NATURAL GAS CORPORATION

LTD (ONGC) July 07, 2012 Completed

322.

SUBCONTRACT FOR PIPING WORKS FOR PACKAGE B: B-193 A-Q (LIVING QUARTERS, POWER GENERATION & WATER INJECTION) – SIME DARBY ENGINEERING SDN BHD

OIL AND NATURAL GAS CORPORATION

LTD (ONGC) July 04, 2012 Completed

323. SUPPLY OF VINYL COATED CHAIN LINK FABRIC FOR EMEPMI’S PALAS A STRUCTURAL REPAIR PROJECT – PERUNDING RANHILL WORLEY

EMEPMI July 04, 2012 Completed

324. SUPPLY AND DELIVER OFSLIDING PLATE FOR FABRICATION ON KBB TOPSIDES (BOAQ) - MMHE

KPOC July 02, 2012 Completed

325.

TO SUPPLY MATERIALS, EQUIPMENT, CONSUMABLES, TOOLS AND MANPOWER FOR COOLING MANIFOLD RELOCATION FOR GUMUSUT KAKAP, J LAY TOWER REFURBISHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD

SHELL June 12, 2012 Completed

326. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES IN SUPPORT OF VESSEL DLB264 – GOM RESOURCES

GOM RESOURCES June 11, 2012 Completed

Page 28: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

327. PROVISION OF PULLING & REMOVE CABLE FOR LNGC SERI ALAM – MMHE SDN. BHD.

MISC May 21, 2012 Completed

328. SUPPLY, FABRICATE AND DELIVERY SEA FASTENING FOR CARGO BARGE FOR LAN DO DEVELOPMENT PROJECT – SAPURA ACERGY SDN BHD

TNK VIETNAM BV May 17, 2012 Completed

329.

PROVISION OF FIELD JOINT COATING SERVICES FOR MOC TRANSPORTATION AND INSTALLATION OF OFFSHORE PIPELINES AND FACILITIES FOR YEAR 2012 – TL OFFSHORE SDN BHD

MURPHY OIL May 9, 2012 Completed

330. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION AT PM318-PUTERI FWS PIPELINE REPLACEMENT PROJECT - NEWFIELD

NEWFIELD April 9, 2012 Completed

331. PROVISION OF VSAT TELECOMMUNICATION AND SERVICES FOR PETRONAS CARIGALI SDN BHD – IPERINTIS SDN BHD

IPERINTIS April 6, 2012 Completed

332. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES - SCHLUMBERGER GROUP

SCHLUMBERGER April 4, 2012 Completed

333. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES - HALLIBURTON ENERGY SERVICES (M) SDN BHD

HALLIBURTON April 4, 2012 Completed

334. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES IN SUPPORT OF HEAVY LIFT PIPE LAY VESSEL LTS3000

L & T SAPURA April 1, 2012 Completed

335. DESIGN, FABRICATION AND DELIVERY OF FIREWALL FOR TELOK A & B PROJECT – MMHE SDN BHD

SHELL March 23, 2012 Completed

336. COMMISSIONING OF STABILISED VSAT SERVICES AND VPN ONBOARD MV. WANGSAMAJU – OCEANTECH GEOMATICS

OCEANTECH GEOMATIC

March 14, 2012 Completed

337.

PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION TAPE (SERVIWRAP M30B) FOR KEBABANGAN DEVELOPMENT PROJECT – GLOBAL OFFSHORE MALAYSIA

KPOC March 13, 2012 Completed

338.

SUPPLY AND DELIVERY OF HANGER FLANGE, RISER GUARD AND RISER CLAMP FOR PROVISION OF HOOK-UP AND COMMISSIONING FOR PETRONAS CARIGALI SKO PIPELINE REJUVENATION PROJECT. – CARIMIN ENGINEERING SERVICES

PETRONAS March 12, 2012 Completed

339. PROVISION OF TELECOMMUNICATION SYSTEM (VSAT) – SCOPETEL SDN. BHD SCOPETEL March 5, 2012 Completed

Page 29: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

340.

SUPPLY AND DELIVERY OF ELECTRICAL FITTINGS AND ACCESSORIES FOR TCOT PWSU TAIL END & REMEDIAL WORK FOR EMEPMI EPCM BROWNFIELD PROJECT – PERUNDING RANHILL WORLEY

EMEPMI March 1, 2012 Completed

341. PROVISION OF FIELD JOINT COATING FOR SOGT PROJECT – ALAM SWIBER PETRONAS February 27, 2012 Completed

342.

PROVISION OF FIELD JOINT COATING AND SUPPLY OF HSS (RAYCHEM WPC100M) FOR EMEMPI’S TAPIS EOR REJUVENATION AND TELOK DEVELOMENT PROJECT. – TL OFFSHORE SDN BHD

EMEPMI February 24, 2012 Completed

343. DESIGN, ENGINEERING, AND DELIVERY OF FAIRINGS & THRUST COLLARS FOR DRILLING RISERS – SONGA OFFSHORE

PETRONAS February 22, 2012 Completed

344. PROVIDING STABILISED VSAT SYSTEM FOR SEMI-SUBMERSIBLE RIG, OCEANROVER FOR DEEPWATER PROJECT, KIKEH – DIAMOND OFFSHORE

MURPHY OIL February 14, 2012 Completed

345. PROVISION OF VSAT SYSTEM AND PROVIDING VPN RENTAL SERVICES FOR DLB264 – GLOBAL OFFSHORE MALAYSIA

GLOBAL OFFSHORE February 09, 2012 Completed

346. PIPELINE AND SPOOLS FIELD JOINT COATING SERVICES FOR LAN DO DEVELOPMENT PROJECT VIETNAM – SAPURA ACERGY SDN BHD

TNK VIETNAM BV January 20, 2012 Completed

347.

PROVISION FOR DETAILED DESIGN ENGINEERING SERVICES FOR PACKAGE THIRD PARTY VERIFICATION OF GUE H RATED FIREWALL TO WITH STAND 30-MINUTES JET FIRE FOR TELOK GAS DEVELOPMENT PROJECT – PERUNDING RANHILL WORLEY SDN BHD

EMEPMI December 29, 2011 Completed

348. PROVISION OF INSTALLATION AND MAINTENANCE OF VPN INTERNET SERVICES – ASIAN SUPPLY BASE SDN BHD

ASIAN SUPPLY BINTULU

December 21, 2011 Completed

349. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION AT M01 AND E11 FOR TI-FIX AND IR PROJECT - SHELL

SHELL December 21, 2011 Completed

350. SUPPLY MANPOWER, EQUIPMENTS AND MATERIALS FOR PM329 EAST PIATU TOPSIDES – KENCANA HL SDN BHD

NEWFIELD December 1, 2011 Completed

351. E & I FABRICATION, INSTALLATION, TESTING, PRE-COMMISSIONING WORK, FOR TAPIS EOR PROJECT (PACKAGE B AND PACKAGE C) – MMHE SDN BHD

EMEPMI December, 2011 Completed

352. PIPING FABRICATION AND INSTALLATION FOR TAPIS Q LIVING QUARTERS – MMHE SDN BHD

EMEPMI November, 2011 Completed

Page 30: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

353. SUPPLY OF H120 FIRE/BLAST WALL FOR KEBABANGAN TOPSIDES – SIME DARBY ENGINEERING SDN BHD

KPOC November 25, 2011 Completed

354. PROVISION OF FIELD JOINT COATING FOR BCOT PROJECT – ALAM SWIBER PETRONAS October 10, 2011 Completed

355.

PROVISION OF REMOVAL, REPAIR, & REINSTATEMENT OF PASSIVE FIRE PROTECTION CASTING FOR SDV ON BUNGA RAYA-B – APEX ENERGY SDN. BHD.

TALISMAN September 27, 2011 Completed

356.

PROVISION OF PASSIVE FIRE PROTECTION (PFP) SERVICES FOR PCC OF TOPSIDES AND PIPELINE FOR PM318 PUTERI PIPELINE RESTORATION PROJECT – KENCANA HL SDN BHD

NEWFIELD September 15, 2011 Completed

357.

PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION MATERIAL (SERVIWRAP) FOR 14” AND 24” EXPORT PIPELINE SHORE APPROACH INSTALLATION FOR KEBABANGAN NORTHERN HUB DEVELOPMENT – PBJV GROUP SDN BHD

PETRONAS CARIGALI SDN BHD

September 15, 2011 Completed

358.

PROVISION OF PASSIVE FIRE PROTECTION (PFP), TOOLS/ EQUIPMENT & MATERIALS TO REMOVE THE DEGRADED PFP & APPLICATION OF NEW PFP AT M3PQ-A LIVING QUARTER WEST WALL – SARKU ENGINEERING SERVICES SDN. BHD.

SHELL September 15, 2011 Completed

359.

PROVISION OF REMOVAL, REPAIR, & REINSTATEMENT OF PASSIVE FIRE PROTECTION SYSTEM FOR HELANG TOPSIDES (E-9550 & E-9650) – MONT TRINITY

NIPPON OIL September 12, 2011 Completed

360.

PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION MATERIALS (SERVIWRAP) FOR INTRAGRATED TRANSPORTATION & INSTALLATION OF OFFSHORE FACILITIES (TIONG A) PROJECT – GLOBAL OFFSHORE MALAYSIA SDN BHD

NEWFIELD August 17, 2011 Completed

361. PROVISION OF REMOVAL, REPAIR & REINSTATEMENT OF BLASTWALL ON M3P-Q PLATFORM – DAYANG ENTERPRISE & SSB

SHELL August 5, 2011 Completed

362.

DESIGN, MANUFACTURE AND SUPPLY OF VIV SUSPRESSION STRAKES FOR BLOCK 06.1 PHASE III PROJECT – LAN DO DEVELOPMENT PROJECT – RANHILL WORLEYPARSONS SDN BHD

BP EXPLORATION OPERATING CO. LTD

August 3, 2011 Completed

Page 31: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

363.

PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION MATERIALS (SERVIWRAP) FOR TRANSPORTATION AND INSTALLATION OF OFFSHORE FACILITIES FOR SKO PIPELINE REPLACEMENT PROJECT – TARGET ENERGY CO. (M) SDN. BHD.

PETRONAS CARIGALI SDN BHD

July 25, 2011 Completed

364.

FABRICATION AND INSTALLATION OF TAPIS-R DECK (NORTH) TAPIS-R DECK (SOUTH), TAPIS-R LIVING QUARTERS & BRIDGES SKID BEAM AND TAPIS-Q DECK – MMHE SDN. BHD.

EMEPMI July 15, 2011 Completed

365. FABRICATION AND INSTALLATION OF TAPIS-R DECK (NORTH), TAPIS-Q DECK, MISCELLANEOUS WORKS TAPIS-Q – MMHE SDN. BHD.

EMEPMI July 3, 2011 Completed

366. SUPPLY, DELIVERY AND INSTALLATION OF STRAKES FOR GUMUSUT KAKAP JUMPERS - FMC

SHELL June 17,2011 Completed

367. PROVISION OF PIPELINE FIELD JOINT COATING WORKS FOR THE FABRICATION SERVICES OF FLOWLINE JUMPER – LABUAN SHIPYARD

SAPURA ACERGY/ SHELL

April 14, 2011 Completed

368.

PROVISION OF PIPELINE INFIELD FIELD JOINT COATING FOR PETRONAS CARIGALI INTERGRATED TRANSPORTATION INSTALLATION OF OFFSHORE FACILITIES FOR YEAR 2010-2012 – GLOBAL OFFSHORE MALAYSIA SDN BHD

PETRONAS CARIGALI SDN BHD

April 12, 2011 Completed

369.

PROVISION OF PIPELINE ANTI CORROSION MATERIAL (SERVIWRAP) FOR PETRONAS CARIGALI INTERGRATED TRANSPORTATION INSTALLATION OF OFFSHORE FACILITIES FOR YEAR 2010-2012 – GLOBAL OFFSHORE MALAYSIA SDN BHD

PETRONAS CARIGALI SDN BHD

March 31, 2011 Completed

370. PROVISION OF FIELD JOINT COATING SERVICES FOR F28DR-A/F6K-A PIPELINE PROJECT – TL OFFSHORE SDN BHD

SHELL March 18, 2011 Completed

371.

FABRICATION AND INSTALLATION OF STRUCTURAL WORKS FOR TOPSIDES A-Q COMPRISING PART OF SURVEY, DESIGN, ENGINEERING, PROCUREMENT, FABRICATION, LOAD OUT, TIE-DOWN/SEAFASTENING, TRANSPORTATION, INSTALLATION, HOOK-UP, TESTING, COMMISSIONING (EPCIC) OF PROCESS PLATFORM FOR B-193 PROJECT – SIME DARBY ENGINEERING

OIL AND NATURAL GAS CORPORATION

LTD (ONGC) February 25, 2011 Completed

372. PROVISION OF PIPELINE MATERIALS WITH SEA SLEEVES C/W EQUIPMENT FOR NEWFIELD’S EAST PIATU INSTALLATION – TL OFFSHORE SDN BHD

NEWFIELD February 24, 2011 Completed

373. PROVISION OF PASSIVE FIRE PROTECTION SERVICES) FOR NEWFIELD'S EAST PIATU'S JACKET & TOPSIDES - KENCANA HL

NEWFIELD February 11, 2011 Completed

Page 32: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

374. PROVISION OF FIELD JOINT COATING AND INFILL MATERIALS FOR PUTERI PIPELINE RESTORATION PROJECT – TL OFFSHORE SDN BHD

NEWFIELD February 11, 2011 Completed

375.

PROVISION OF REMOVAL, REPAIR, & REINSTATEMENT OF PASSIVE FIRE PROTECTION SYSTEM FOR CAKERWALLA OFFSHORE - SHAPADU ENERGY & ENGINEERING SDN BHD

CARIGALI HESS February 1, 2011 Completed

376.

PROVISION OF FIELD JOINT COATING, SUPPLY AND INSTALLATION OF CANUSA GTS-PP WRAPID SLEEVE FOR CILIPADI PIPELINE PROJECT – TL OFFSHORE SDN BHD

SHELL January 17, 2011 Completed

377. REPAIR WORKS OF BLASTWALL AND FIREWALL FOR MODULE 3 KUMANG TOPSIDE - OFFSHORE WORKS

PETRONAS CARIGALI SDN BHD

December 13, 2010 Completed

378.

DESIGN, CONSTRUCT, SUPPLY AND DELIVERY OF NOISE ATTENUATORS AND EXPANSION SPOOLS FOR F13 PROCESSING MODULE GLYCOL REBOILER SKID AT E11P-B PLATFORM

SARAWAK SHELL BERHAD

November 24, 2010 Completed

379.

FABRICATION AND INSTALLATION OF THE MOORING PORCHES, CHAIN JACK GANTRIES AND ASSOCIATED PLATFORMS, AND INSTALLATION OF FAIRLEAD FOUNDATIONS FOR GUMUSUT KAKAP FPS HULL (36010863) AT MALAYSIA MARINE AND HEAVY ENGINEERING

SHELL / MISC November 12, 2010 Completed

380. SUBCONTRACT FOR STRUCTURAL WORKS FOR PROCESS PLATFORM FOR B -193 PROJECT AT SIME DARBY ENGINEERING

OIL AND NATURAL GAS CORPORATION

LTD (ONGC) October 22, 2010 Completed

381. DESIGN, FABRICATE AND SUPPLY FIRE RATED ROLLER SHUTTER FOR KINABALU NAG DEVELOPMENT PROJECT (KNPG-B) - MMHE

PETRONAS CARIGALI SDN BHD

October 21, 2010 Completed

382. SUPPLY AND DELIVERY OF SAFETY EQUIPMENTS FOR SAMARANG (PHASE 1 – ACCELERATED DRILLING) DEVELOPMENT PROJECT – KENCANA PETROLUEM

PETRONAS CARIGALI SDN BHD

October 6, 2010 Completed

383. PROVISION OF BR-B REPLACEMENT – RISER PIPE, CLAMP AND I-TUBE – FIELD JOINT COATING

TALISMAN September 20, 2010 Completed

384. DESIGN, FABRICATE AND SUPPLY OF BLASTWALL FOR LIVING QUARTERS FOR JACKETS OF PM329 EAST PIATU DEVELOPMENT PROJECT – KENCANA HL

NEWFIELD September 17, 2010 Completed

385.

PROVISION OF PIPELINE FIELD JOINT COATING SERVICES AND INFILL MATERIALS FOR PETRONAS CARIGALI’S SKO PIPELINE PROJECT – TL OFFSHORE

PETRONAS CARIGALI SDN BHD

September 7, 2010 Completed

386. PROVISION OF FLOWLINE AND RISER FIELD JOINT COATING SERVICES FOR GUMUSUT KAKAP PROJECT – SAPURA ACERGY

SHELL August 6, 2010 Completed

Page 33: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

387. UMBRELLA CONTRACTS FOR SALE OF SSB/SSPC SCRAP METAL (600865) SARAWAK SHELL

BERHAD August 3, 2010 Completed

388.

PROVISION OF THE SERVICE FOR DISPOSAL OF SURPLUS MATERIALS FOR PETRONAS GROUP OF COMPANIES FOR YEAR 2010-2013 (UMBRELLA CONTRACT)

PETROLIAM NASIONAL BERHAD

July 28, 2010 Completed

389. SUPPLY AND DELIVERY OF INSTRUMENT FIRE & GAS CABLES FOR MRU - BUNGA ORKID DEV. PROJECT FOR SDE

TALISMAN MALAYSIA LIMITED

July 23, 2010 Completed

390. PROVISION OF PIPELINE FIELD JOINT COATING AND INFILL MATERIAL FOR ST. JOSEPH PIPELINE INSTALLATION ON E3 – TL OFFSHORE

SABAH SHELL PETROLUEM CO. LTD

July 22, 2010 Completed

391. SUPPLY AND DELIVER OF INSTRUMENT CABLES & GLANDS FOR EMEMPI’S SELIGI AND SEMANGKUK PIPELINE REPLACEMENT PROJECT

RANHILL WORLEY PARSONS

June 29, 2010 Completed

392. STRUCTURAL WORK ~(5-TOPSIDES) - EPCIC OF (5) WELLHEAD PLATFORM FOR B-193 PROJECT – SDE

OIL AND NATURAL GAS CORP. LTD

(ONGC) June 12, 2010 Completed

393. SUPPLY OF ELECTRICAL FITTINGS AND ACCESSORIES FOR GUNTONG E AIR UTILITY SYSTEM UPGRADE PROJECT

RANHILL WORLEY PARSONS

May 27, 2010 Completed

394. SUPPLY OF CABLES FOR INTERGRATED PROCUREMENT AND CONSTRUCTION DEVELOPMENT PROJECT (PHASE 1)

SIME DARBY May 18, 2010 Completed

395. PROVISION OF FIELD JOINT COATING SERVICES FOR DEVIL’S CREEK DEVELOPMENT PROJECT

SAPURA ACERGY May 15, 2010 Completed

396. SUPPLY OF SERVI-WRAP ANTI-CORROSION MATERIALS SARAWAK SHELL May 13, 2010 Completed

397. SUPPLY OF INSTRUMENT CABLES & CABLE GLANDS FOR TAPIS PUMP FIRE AND GAS SYSTEM UPGRADE PROJECT - EMEPMI

RANHILL WORLEY PARSONS

May 4, 2010 Completed

398. MASTER SERVICE AGREEMENT FOR PROVISION OF VSAT SYSTEM INCLUDING LAN/WAN – TL OFFSHORE SDN BHD

TL OFFSHORE May 1, 2010 Completed

399. SUPPLY, FABRICATE, INSTALL AND PRE-COMMISSION ONE UNIT OF GYM ROOM FOR BRE

TALISMAN MALAYSIA LIMITED

April 29, 2010 Completed

400. DESIGN, SUPPLY, APPLICATION AND INSTALLATION OF PASSIVE FIRE PROTECTION (PACKAGE NO.SF03) FOR GUMUSUT KAKAP SEMI-FPS PROJECT

MMHE April 21, 2010 Completed

401. APPLICATION OF FOAM INSULATION FOR CAMERON INTERNATIONAL (M) SYSTEM SDN BHD

CAMERON INTERNATIONAL (M)

SDN BHD April 10, 2010 Completed

Page 34: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

402. FIELD JOINT COATING WORK AT TLO FOR 2010 MURPHY PIPELINE PROJECT MURPHY OIL CORP March 16, 2010 Completed

403. FIELD JOINT COATING WORK AT GLOBAL OFFSHORE MALAYSIA FOR 2010 PETRONAS PIPELINES PROJECT

PETRONAS CARIGALI

March 16, 2010 Completed

404. SUPPLY OF CABLES FOR F23R-A CILIPADI GAS FIELD DEVELOPMENT PROJECT PFCE March 15, 2010 Completed

405. PASSIVE FIRE PROTECTION FOR SARAWAK SHELL E-8 PLATFORM SARAWAK SHELL March 15, 2010 Completed

406. DISPOSAL & REMOVAL OF SCRAP MATERIALS FROM MMHE SARAWAK SHELL March 15, 2010 Completed

407. SALE OF USED/SCRAP MATERIALS AND EQUIPMENT MLNG March 10, 2010 Completed

408. THERMOCOUPLE CABLE FOR BUNGA ORCHID-A TALISMAN MALAYSIA

March 9, 2010 Completed

409. HEAT SHIELD PANELS FOR ABU FIELD PETRONAS CARIGALI

March 3, 2010 Completed

410. SUPPLY AND APPLICATION OF PFP FOR F23DR-A CILIPADI PROJECT AT RFSB FOR PFCE

SARAWAK SHELL BERHAD

February 28, 2010 Completed

411. J-LAY TOWER REFURBISHMENT PROJECT (STRUCTURAL WORKS) FOR SAPURA ACERGY

SHELL / MISC February 25, 2010 Completed

412. SUPPLY OF LIGHT WATER STATION PETRONAS CARIGALI

February 5, 2010 Completed

413. BLASTING AND PAINTING FOR JLT STRUCTURE SERVICES FOR GUMUSUT AT SAPURA ACERGY

SHELL/ MISC January 28 2010 Completed

414. SUPPLY OF HEATSHIELDS TO CILIPADI PROJECT AT RFSB FOR PFCE SARAWAK SHELL December 28 2009 Completed

415. DISPOSAL OF EXXON MOBIL OBSOLETE, PROJECT SURPLUS, AND USED MATERIALS

EMEMPI December 8, 2009 Completed

416. S-LAY FIELD JOINT COATING CONTRACT FOR GUMUSUT PIPELINE AT SAPURA ACERGY

SHELL / MISC November 26, 2009 Completed

417. SUPPLY AND APPLICATION OF PFP FOR TANGGA BARAT CPP TOPSIDE @ MMHE

PETRONAS CARIGALI

November 3, 2009 Completed

Page 35: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

418. DISPOSAL OF TML SLOW MOVING AND OBSOLETE GOODS AT KSB (SCRAP METAL)

TALISMAN October 30, 2009 Completed

419. SUPPLY OF BLASTWALL FOR F23 (CILIPADI) AT RAMUNIA YARD @ PFCE SARAWAK SHELL October 21, 2009 Completed

420. SUPPLY OF BLASTWALL TO J.R MCDERMOTT FOR THE KIPPER TUNA PROJECT ESSO AUSTRALIA August 25, 2009 Completed

421. SUPPLY OF INSTRUMENT, FIRE & GAS, ELECTRICAL AND TELECOM CABLES TO PFCE AT RAMUNIA FABRICATION YARD FOR 23 TOPSIDE PROJECT

SARAWAK SHELL August 24, 2009 Completed

422. SUPPLY OF AIMS RFP MUDMAT SYSTEM FOR NEWFIELD’S WEST BELUMUT WELLHEAD JACKET AT KENCANA HL

NEWFIELD July 31, 2009 Completed

423. SUPPLY OF CHEMICALS – TRIETHYLENE GLYCOL – 99.9%, 235 KGS DRUM UNDER PRICE AGREEMENT WITH PETRONAS CARIGALI

PETRONAS CARIGALI

July 15, 2009 Completed

424.

ELECTRICAL AND INSTRUMENTATION FABRICATION & HOST TIE & HOOK-UP COMMISSIONING OF GUA FLAREBOOM REPLACEMENT AT BOUSTEAD PENANG SHIPYARD S/B

EXXON MOBIL June 22, 2009 Completed

425. FABRICATION OF INSTRUMENT GAS SKID FOR KUMANG PROJECT AT SDE PETRONAS CARIGALI

June 15, 2009 Completed

426. FIELD JOINT COATING WORK AT TLO FOR 2009 PETRONAS PIPELINE PROJECT PETRONAS CARIGALI

June 8, 2009 Completed

427. SUPPLY OF SERVIWRAP TO TLO FOR 2009 PETRONAS PIPELINE PROJECT PETRONAS CARIGALI

May 15 , 2009 Completed

428. FIELD JOINT COATING WORK AT TLO FOR BEKOK-DULANG PROJECT FOR PETRONAS PIPELINE PROJECT

PETRONAS CARIGALI

April 17, 2009 Completed

429. FIELD JOINT COATING WORK AT TLO FOR WEST LUTONG PROJECT FOR PETRONAS PIPELINE PROJECT

PETRONAS CARIGALI

March 6, 2009 Completed

430. FIELD JOINT COATING WORK AT TLO FOR BETTY BAKAU PROJECT FOR PETRONAS PIPELINE PROJECT

PETRONAS CARIGALI

February 12, 2009

Completed

431. PASSIVE FIRE PROTECTION FOR B11 LQ & HELIDECK AT BDEWC, SARAWAK SARAWAK SHELL

BERHAD February 11, 2009 Completed

432. PASSIVE FIRE PROTECTION FOR PC-4 RISER AT BD11 DR-A PLATFORM FOR MMHE

PETRONAS CARIGALI

January 19, 2009 Completed

Page 36: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

433. SUPPLY OF ELECTRICAL AND INSTRUMENTATION CABLES FOR F23 VLAP COMPRESSION AT SDE

SARAWAK SHELL BERHAD

January 5, 2009 Completed

434. MARK AND CUT STEEL STRUCTURAL WORKS FOR MCR-A PROJECT AT MMHE MMHE JV WITH

TECHNIP January 2, 2009 Completed

435. FABRICATION OF STRUCTURAL WORKS FOR EAST MODULE TOPSIDES OF GUMUSUT KAPAP AT MMHE

SHELL AND MISC December 31, 2008 Completed

436. E & I AND PIPING WORK AT MMHE FOR TANGGA BARAT CPP TOPSIDES PETRONAS CARIGALI

December 24, 2008 Completed

437. PASSIVE FIRE PROTECTION FOR B-11 TOPSIDES AT BROOKE DOCK YARD SARAWAK SHELL

BERHAD December 19, 2008 Completed

438. SUPPLY OF KOBE ELECTRODES FOR F23-RA TOPSIDES AT RFSB SARAWAK SHELL

BERHAD December 19, 2008 Completed

439. INSTRUMENTATION & FGS & TELECON JUNCTION BOX – DULANG B AT KENCANA HL

PETRONAS CARIGALI

November 4, 2008 Completed

440. SUPPLY OF TOTE TANKS PETRONAS CARIGALI

October 29, 2008 Completed

441. SUPPLY OF FIRE RATED WINDOWS FOR KUMANG AND TANGGA BARAT AT SDE PETRONAS CARIGALI

October 21, 2008 Completed

442. SUPPLY OF INSTRUMENT CABLES FOR FPSO RUBY AT MMHE MISC October 15, 2008 Completed

443. STRUCTURAL FABRICATION WORK FOR TANGGA BARAT AT MMHE PETRONAS CARIGALI

October 13, 2008 Completed

444. SUPPLY AND INSTALL KUMANG BLASTWALL/ FIREWALL COMPLETE SYSTEM INCLUDING PFP AT SDE TO MEET FIRE RATINGS

PETRONAS CARIGALI

October 10, 2008 Completed

445. SUPPLY OF ELECTRICAL AND INSTRUMENTATION (E&I) CABLES FOR KUMANG AND TANGGA BARAT AT SDE

PETRONAS CARIGALI

September 27, 2008 Completed

446. PIPING FABRICATION WORK FOR B11 KA TOPSIDE @ MMHE SARAWAK SHELL

BERHAD September 16, 2008 Completed

447. SUPPLY OF PERSONNEL TRANSFER BASKET AND CABLE GLAND / FITTINGS TO MURPHY OIL

MURPHY SARAWAK OIL CO. LTD

September 15, 2008 Completed

Page 37: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

448. FIELD JOINT COATING WORK FOR CPOC PIPELINES AT TLO PETRONAS CARIGALI

September 10, 2008 Completed

449. PASSIVE FIRE PROTECTION FOR PLUTO PROJECT @ RFSB WOODSIDE ENERGY August 15, 2008 Completed

450. FIELD JOINT COATING WORK AT TLO FOR SCDR-A / E11K-A 12” & 14” PIPELINE PROJECT

SARAWAK SHELL BERHAD

August 1, 2008 Completed

451. SUPPLY OF CANUSA HSS TO TLO FOR SCDR-A / E11K-A 12” & 14” PIPELINE PROJECT

SARAWAK SHELL BERHAD

July 22, 2008 Completed

452. SUPPLY OF DOUBLE SKIN HEAT SHIELDS FOR B11 KA PROJECT AT MMHE SARAWAK SHELL

BERHAD June 30, 2008 Completed

453. PASSIVE FIRE PROTECTION OF ANDP-D AT RFSB PETRONAS CARIGALI

June 30, 2008 Completed

454. SUPPLY OF SERVIWRAP FOR CPOC PIPELINE TO TLO PETRONAS CARIGALI

June 26, 2008 Completed

455. E&I, PIPING, MECHANICAL & STRUCTURAL FABRICATION FOR KUMANG CLUSTER DEVELOPMENT / TANGGA BARAT PROJECT @ SDE

PETRONAS CARIGALI

June 11, 2008 Completed

456. DESIGN, SUPPLY, FABRICATION AND INSTALL NEW FIRE AND BLASWALL FOR BR-A

TALISMAN MALAYSIA LIMITED

May 23, 2008 Completed

457. PASSIVE FIRE PROTECTION OF GOPA-GOPB AT KHL MURPHY SARAWAK

OIL CO. LTD May 8, 2008 Completed

458. SUPPLY AND DELIVERY OF CONCRETE MATRESSES, SLEEPERS, LIFTING FRAME FOR 24” ANDR-A/TCOT PIPELINE FOR TLO

PETRONAS CARIGALI

April 30, 2008 Completed

459. ELECTRICAL AND INSTRUMENTATION FABRICATION WORK AT RFSB ON ANGSI –D PLATFORM

PETRONAS CARIGALI

April 24, 2008 Completed

460. PFP for F23 AND F6 AT BROOKE DOCKYARD, KUCHING, SARAWAK SARAWAK SHELL

BERHAD April 11, 2008 Completed

461. SUPPLY OF POWER & INSTRUMENTATION CABLES MURPHY SARAWAK

OIL CO. LTD April 10, 2008 Completed

462. SUPPLY OF HEATSHIELDS TO CLOUGH FOR MONTARA PROJECT IN THAILAND CLOUGH (THAILAND)

CO. LTD April 10, 2008 Completed

Page 38: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

463. FIELD JOINT COATING SERVICES FOR TALISMAN PIPELINE INSTALLATION TALIMAN MALAYSIA

LIMITED April 10, 2008 Completed

464. FIELD JOINT COATING FOR PETRONAS CARIGALI 2008 PIPELINE INSTALLATION AT TLO FOR 5 PIPELINES

PETRONAS CARIGALI

April 10, 2008 Completed

465. SUPPLY AND APPLICATION OF WET AND CASTING PFP FOR TALISMAN RISERSAND ESDVS

TALIMAN MALAYSIA LIMITED

April 8, 2008 Completed

466. SUPPLY OF FIRE RATED DOORS TO MMHE PETRONAS CARIGALI

April 5, 2008 Completed

467. SUPPLY OF RADIANT HEATSHIELD, LOUVERS AND MISC ITEMS FOR PC 4 @ MMHE

PETRONAS CARIGALI

March 31, 2008 Completed

468. FIELD JOINT COATING FOR KEA- TIA @ PBJV

PETRONAS CARIGALI

March 7, 2008 Completed

469. SUPPLY OF ELECTRICAL OPERATED MONORAIL TROLLEY HOIST, 5 MT – MMHE

MMHE March 7, 2008 Completed

470. SUPPLY OF MANUAL OPERATED GANTRY CRANE TO MMHE MMHE March 7, 2008 Completed

471. ENGINEERING, DESIGN, FABRICATION AND INSTALLATION OF SHELTER CABIN FOR PC4 AT MMHE

PETRONAS CARIGALI

February 28, 2008 Completed

472. SUPPLY OF LINE PIPES SMLS API TYPE OF VARIOUS SIZES TO MMHE PETRONAS CARIGALI

January 17, 2008 Completed

473. SUPPLY OF FIRE RATED DOORS TO TURKMENISTAN GAS DEVELOPMENT PROJECT

MITCO JAPAN SDN BHD

January 11, 2008 Completed

474. PASSIVE FIRE PROTECTION FOR BUNGA ORKID @ SDE TALISMAN

MALAYSIA LIMITED January 3, 2008 Completed

475. FABRICATION OF GUMUSUT-KAKAP SEMISUBMERSIBLE HULL (PACKAGE 2) SHELL AND MISC December 5, 2007 Completed

476. STRUCTURAL FABRICATION FOR CPOC PROJECT AT MMHE PETRONAS CARGALI

SDN BHD November 30, 2007 Completed

477. SUPPLY OF FIRE RATED WINDOWS FOR BUNGA ORKID PROJECT AT SDE TALISMAN

MALAYSIA LIMITED October 23, 2007 Completed

Page 39: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

478. SUPPLY OF TOTE TANKS TO EMEPMI EXXON MOBIL September 30, 2007 Completed

479. MULTI DISCIPLINE WORKS (STRUCTURE, PIPING, E& I AND BLASTING/ PAINTING FOR PC 4 TOPSIDE WORK @ MMHE

PETRONAS CARGALI SDN BHD

July 26, 2007 Completed

480. FIELD JOINT COATINGS FOR VASAI EAST DEVELOPMENT PROJECT AT RAMUNIA FABRICATORS SDN BHD

OIL & NATURAL GAS CORPORATION,

INDIA August 27, 2007 Completed

481. SUPPLY & APPLICATION OF PASSIVE FIRE PROTECTION -TALISMAN NORTHERN FIELD

TALISMAN MALAYSIA LIMITED

August 23, 2007

Completed

482. FIELD JOINT COATINGS FOR JERNEH PIPELINES AT TLO EXXONMOBIL August 8, 2007 Completed

483. FABRICATE BEAM HAUNCH, CROSS OVER SPOOL FOR HIGH PRESSURE MUD LINE AND CRANE BEAM

SAAG DRILLING & WELL SERVICES SDN

BHD August 7, 2007 Completed

484. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR BELUMUT AT RAMUNIA FABRICATORS SDN BHD

PETRONAS CARIGALI SDN BHD

August 5, 2007 Completed

485. FIELD JOINT COATINGS FOR SEMARANG PIPELINES AT TLO PETRONAS CARGALI

SDN BHD July 28, 2007

Completed

486. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR INTRALINE RESOURCES

TALISMAN MALAYSIA LIMITED

July 16, 2007 Completed

487. FIELD JOINT COATINGS FOR ANDR-A PIPELINES AT TLO PETRONAS

CARIGALI SDN BHD June 25, 2007

Completed

488. FIELD JOINT COATINGS FOR 18 “ GUE PIPELINE AT TLO EXXONMOBIL June 20, 2007 Completed

489. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR SUMANDAK TOPSIDES

PETRONAS CARIGALI

June 13, 2007 Completed

490. SUPPLY OF SPARES FOR CLOSURE DOOR TO MMHE SARAWAK SHELL

BERHAD June 6, 2007

Completed

491. FIELD JOINT COATINGS FOR BETTY– BORONIA 18” P/L SARAWAK SHELL

BERHAD June 1, 2007 Completed

492. ENGINEERING, PROC, CONSTRUCTION & COMMISSIONING OF FIRE PROTECTION SYSTEM

PETRONAS DAGANGAN BERHAD

May 28, 2007 Completed

Page 40: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

493. FIELD JOINT COATING FOR TAPM-3 CAA NORTHEN FIELD DEVELOPMENT TALISMAN

MALAYSIA LIMITED May 22, 2007

Completed

494. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR SCDR-A TOPSIDES

SARAWAK SHELL BERHAD

May 4, 2007 Completed

495. SUPPLY OF SAFETY EQUIPMENT AND LIFE RAFT TO MDFT FOR KIKEH PROJECT M.D.F.T (KIKEH) LTD May 2, 2007

Completed

496. FIELD JOINT COATINGS FOR ALL SUMANDAK PIPELINES AND SUPPLY OF SERVIWRAP TO TL OFFSHORE

PETRONAS CARIGALI

(PETRONAS CARIGALI)

April 6, 2007 Completed

497. 2007-2009 OFFSHORE FACILITIES TRANSPORT AND INSTALLATION OF FIELD JOINT COATINGS FOR MCDERMOTT

SARAWAK SHELL BERHAD

March 27, 2007 Completed

498. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF BLASTWALL FOR PETRONAS CARIGALI’S BELUMUT PROJECT AT RFSB

PETRONAS CARIGALI

(PETRONAS CARIGALI)

March 19, 2007 Completed

499. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR ANGEL GAS TOPSIDE PROJECT AT MMHE

WOODSIDE ENERGY March 15, 2007 Completed

500. FIELD JOINT COATING OF 10” BAP-AA TO BADP-G PIPELINE FOR TL OFFSHORE

PETRONAS CARIGALI

(PETRONAS CARIGALI)

March 1, 2007 Completed

501. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF BLASTWALL FOR SHELL’S SCDR-A AT MMHE

SARAWAK SHELL March 1, 2007 Completed

502. FABRICATION, INSTALLATION, TESTING AND PRE-COMMISSIONING OF PIPINGAND MECHANICAL WORKS FOR SCDR-A TOPSIDES AT MMHE

SARAWAK SHELL February 14, 2007 Completed

503. DESIGN, ENGINEERING AND FABRICATION OF END CLOSURE FOR SHELL’S SCDR-A PROJECT AT MMHE

SARAWAK SHELL February 6, 2007 Completed

504. ENGINEERING, DESIGN & FABRICATION OF PFP CASTINGS FOR METERING RUN - BR-B PLATFORM OFFSHORE

TALISMAN MALAYSIA LIMITED

January 29, 2007 Completed

505. FABRICATE GUMUSUT-KAKAP SEMI-SUBMERSIBLE HULL SHELL January 25, 2007 Completed

506. MULTI DISCIPLINE WORKS (STRUCTURE, PIPING, E&I AND BLASTING/PAINTING FOR F6 REJUVENATION WORKS

SARAWAK SHELL January 23, 2007

Completed

Page 41: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

507. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF HEATSHIELDS FOR MAARI FIELD DEVELOPMENT AT KENCANA HL ENGINEERING

CLOUGH PROJECT INTERNATIONAL PTY

LTD, AUSTRALIA January 17, 2007 Completed

508. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF HEATSHIELDS FOR ANGEL GAS PROJECT AT MMHE

WOODSIDE ENERGY LTD, AUSTRALIA

January 15, 2007 Completed

509. SUPPLY OF ANTI-SKID BRE STAIRWAYS TALISMAN

MALAYSIA LIMITED January 4, 2007 Completed

510. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF HEATSHIELDS FOR SCDR-A PROJECT AT MMHE

SARAWAK SHELL December 27, 2006 Completed

511. SUPPLY OF INSTR. CABLE CONNECTING BRA AND BRE PAGA SYSTEM TALISMAN

MALAYSIA LIMITED November 15, 2006 Completed

512. FIELD JOINT COATING FOR PBJV GROUP SDN BHD FOR WEST LUTONG PROJECT

PETRONAS CARIGALI

November 11, 2006 Completed

513. CONTRACT FOR CIVIL WORKS PACKAGE FOR KUANTAN – KERTEH RAILWAY PROJEC, INCL. VEHICULAR, DRAINAGE & UTILITY BOX CULVERTS

PERCON BABENA JOINT VENTURE

October 15, 2006 Completed

514. STRUCTURAL STEEL FABRICATION FOR SUMANDAK SELATAN TOPSIDES AND HOST

PETRONAS CARIGALI

September 27, 2006 Completed

515. FJ COATING FOR TLO PETRONAS

CARIGALI AND SHELL

August 10, 2006 Completed

516. PIPING WORKS FOR KIKEH FPSO AT MMHE MURPHY OIL August 2, 2006 Completed

517. SUPPLY OF HEATSHIELDS FOR F13W PROJECT AT RAMUNIA FABRICATORS SARAWAK SHELL June 15, 2006 Completed

518. SUPPLY OF END CLOSURE DOORS- F13W AT RFSB SARAWAK SHELL June 09, 2006 Completed

519. PASSIVE FIRE PROTECTION FOR KIKEH DTU TOPSIDES MURPHY OIL

May 3, 2006 Completed

520. FIELD JOINT COATINGS AT BARMADA MCDERMOTT TALISMAN

MALAYSIA LIMITED March 14, 2006 Completed

521. FIELD JOINT COATINGS FOR BARMADA MCDERMOTT S/B EXXON MOBIL March 14, 2006 Completed

Page 42: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

522. PASSIVE FIRE PROTECTION FOR ARTHIT PFP AT Mc DERMOTT YARD IN BATAM INDONESIA

PTTEP and KBR February 27, 2006 Completed

523. PIPING WORKS FABRICATION FOR MURPHY KIKEH PROJECT @ MMHE MURPHY OIL January 14, 2006 Completed

524. ELECTRICAL AND INSTRUMENTATION FOR MODEC RJS-409 MODULE FABRICATION @ SDE

PETROBRAS December 1, 2005 Completed

525. PIPELINE FIELD JOINT COATING FOR BARAM (MCOT) 16” AND 10” PETRONAS

CARIGALI – TLO November 30, 2005 Completed

526. STRUCTURAL FABRICATION FOR MODEC RJS-409 ESPADARTE MODULE FABRICATION @ SDE

PETROBRAS November 1, 2005 Completed

527. SPECIAL STRUCTURAL SPECIAL FABRICATION FOR MURPHY KIKEH PROJECT MURPHY OIL September 9, 2005 Completed

528. SUPPLY AND INSTALL OF FIRESEAL FOR AMENAM KPONO PROJECT TOTAL ELF September 9, 2005 Completed

529. ARCHITECTURAL FITTINGS FOR CLIFF HEAD A PLATFORM AT HL ENGINEERING ROC OIL, AUSTRALIA August 6, 2005 Completed

530. PFP FOR SHELL E11 –PB SARAWAK SHELL August 3 2005 Completed

531. SUPPLY OF BARUNIA PROTECTIVE RELAYS PETRONAS

CARIGALI SDN BHD August 3, 2005 Completed

532. MAJOR STRUCTURAL FABRICATION FOR MURPHY KIKEH DTU SPAR HULL MURPHY OIL May 3, 2005 Completed

533. PFP FOR BARAM TOPSIDE AT BDEWC PETRONAS

CARIGALI SDN BHD April 2005 Completed

534. DESIGN, ENGINEERING AND FABRICATION OF BARAM HEATSHIELD AT BDEWC PETRONAS

CARIGALI SDN BHD April 2005 Completed

535. BLASTING AND PAINTING WORKS AT SSE FOR GUE EXXONMOBIL March 2005 Completed

536. DESIGN, ENGINEERING AND FABRICATION OF E11 P-B BLASTWALL AT MSE SARAWAK SHELL

BERHAD March 2005 Completed

Page 43: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

537. PFP FOR SHELL’S E8-DR-A AT RAMUNIA FABRICATORS SARAWAK SHELL

BERHAD March 2005 Completed

538. PFP FOR SHELL’S F13 SARAWAK SHELL February 2005 Completed

539. PFP FOR BR-E JACKET AND TRIPOD PROJECT AT MSE TALISMAN ENERGY February 2005 Completed

540. PFP FOR BR-E CO2 REMOVAL PROJECT AT SSE TALISMAN ENERGY February 2005 Completed

541. PFP FOR GUNTONG E PROJECT AT SIME SEMBCORP ENGINEERING EXXONMOBIL

EXPLORATION & PRODUCTION INC

January 2005 Completed

542. DESIGN, ENGINEERING AND FABRICATION OF SCKA & SF 13 HEATSHIELDS SARAWAK SHELL

BERHAD October 2004 Completed

543. DESIGN, ENGINEERING AND FABRICATION OF GUNTONG- E BLASTWALL EXXONMOBIL

EXPLORATION & PRODUCTION INC

July 2004 Completed

544. STRUCTURAL STEEL FABRICATION & WELDING AT MSE FOR MOAB TALISMAN ENERGY July 22, 2004 Completed

545. BLASTWALL REINSTAMENT TO H60 RATING – PFP TALISMAN ENERGY July 5, 2004 Completed

546. SUPPLY OF VESSELS UNDER MASTER SPOPT CHARTER PARTY FCF653 EXXONMOBIL

EXPLORATION & PRODUCTION INC

June 26, 2004 Completed

547. PASSIVE FIRE PROTECTION SUPPLY AND APPLY FOR AMENAM PROJECT AT SSE TOTAL ELF FINA @

NIGERIA June 2004 Completed

548. SUPPLY OF PRODUCTION & TEG CHEMICALS - 3 YEARS SARAWAK SHELL/

PETRONAS CARIGALI / NIPPON

June 23, 2004 Completed

549. CASTINGS FOR BUNGA RAYA-A PLATFORM TALISMAN ENERGY March 3, 2004 Completed

550. PFP FOR YOHO PROJECT PROTECTION EXXON MOBIL

NIGERIA March 2004 Completed

551. CASTINGS FOR SDV on BUNGA RAYA-A TALISMAN ENERGY December 2003 Completed

Page 44: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

552. PFP FOR SERAI PROJECT SARAWAK SHELL September 2003 Completed

553. PFP FOR JINTAN PROJECT PROTECTION SARAWAK SHELL

BERHAD July 2003 Completed

554. INFIELD JOINT COATING FOR NIPPON STEEL (NSC) PETRONAS CARIGALI

May 8, 2003 Completed

555. YOHO PLATFORM ELECTRODE EXXON MOBIL

NIGERIA February 2003 Completed

556. BUNGA RAYA 24” Riser PFP PETRONAS

CARIGALI/TALISMAN February 2003 Completed

557. SHELL M3 BLASTWALL SARAWAK SHELL January 11, 2003 Completed

558. HELANG’s RISER / SDV/ FLANGE / VALVE PFP CASTING NIPPON OIL

EXPLORATION January 2003 Completed

559. MLNG SPHERE PFP MLNG SDN BHD December 2002 Completed

560. LUNDIN RISER / SDV PFP TALISMAN December 2002 Completed

561. HALFDAN HEATSHIELDS ENGINEERING DESIGN SEMBCORP ENGRG

SINGAPORE September 6, 2002 Completed

562. SHELL M1 BLASTWALL ENGINEERING DESIGN SARAWAK SHELL

BERHAD September 2002 Completed

563. PASSIVE FIRE PROTECTION USING LEIGH’S PAINTS PFP NIPPON OIL

(HELANG) AT MSE July 15, 2002 Completed

564. MODIFICATION & INSTALL ELECTRICAL WORK FOR SWITCHGEARS (KNDP-A) SARAWAK SHELL

BERHAD November 18, 2001 Completed

565. PASSIVE FIRE PROTECTION FOR MLNG3 SLUGCATCHER PETRONAS CARIGALI

October 29, 2001 Completed

566. PASSIVE FIRE PROTECTION USING LEIGH’S PAINTS PFP MALAYSIA LNG

SDN BHD October 20, 2001 Completed

Page 45: JURUNATURE SDN. BHD COMPANY CURRENT TRACK RECORD · 2019-11-04 · jurunature sdn. bhd. - company current track record no work description owner commencement date current status oct

JURUNATURE SDN. BHD. - COMPANY CURRENT TRACK RECORD

NO WORK DESCRIPTION OWNER COMMENCEMENT

DATE CURRENT STATUS

Oct 30, 2019 - (Track Record Updated)

567. PASSIVE FIRE PROTECTION USING LEIGH’S PAINTS PFP PETRONAS CARIGALI

October 15, 2001 Completed

568. SUPPLY/ INSTALL E & I SWITCHGEAR SARAWAK SHELL

BERHAD August 20, 2001 Completed

569. INSULATION CONTRACT WITH PETRA RESOURCES ESSO PRODUCTION

MALAYSIA INC. July 6, 2001 Completed

570. SUPPLY OF ELECTRODES DOTANAH ENGRG &

CONSTRUCTORS July 2, 2001 Completed

571. ELECTRODE SUPPLY FOR NIPPON OIL (HELANG) MALAYSIA

SHIPYARD (MSE) June 15, 2001 Completed

572. ELECTRODE SUPPLY FOR PETRONAS CARIGALI (ANGSI-A) SIME SEMBCORP

ENGINEERING June 15, 2001 Completed

573. ELECTRODE SUPPLY FOR ESSO (SATELIT) AND LARUT MSE February 2001 Completed

574. SUPPLY OF ELECTRODES FOR ESSO (LARUT-A) SIME SEMBCORP

ENGINEERING July 6, 2000 Completed

575. SUPPLY OF ELECTRODES PETRONAS FERTILIZER

TENDER Completed

576. SUPPLY OF CONSUMABLES FOR PETRONAS PETRONAS

AMMONIA SDN BHD TENDER Completed

577. SUPPLY OF CONSUMABLES FOR PETRONAS CARIGALI PETRONAS CARIGALI

TENDER Completed