Jeres l-410 design of pipelines

28

Click here to load reader

description

 

Transcript of Jeres l-410 design of pipelines

Page 1: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Design of Pipelines

Revision 3

Responsibility JER Engineering Division

13 May 2009

Page 2: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 2 of 28

Revision Tracking

Revision Revision Date Scope of Revision

3 13 May 2009 Revised to update paragraphs: 18.4.3.

2 10 September 2008 Revised to update page numbering.

1 15 May 2008 Updating Issued for bid package Rev. 0 to incorporate technical comments.

0 29 April 2008 Issued for bid package.

02 31 March 2008 Issued for bid package only for review

01 24 April 2007 First official JERES-L-410 is issued.

00 15 February 2007 First draft issued is based on Saudi Aramco SAES-L-410 “Design of Pipelines” issue date April 28, 2004. Document was modified to incorporate amendments and modifications.

Page 3: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 3 of 28

Table of Contents

Section Contents Page

1 Scope 5

2 Conflicts, Deviations and Clarifications 5

3 References 5

4 Definitions 7

5 Applicable Code and Standards 7

6 Design Package and Project Records 8

7 Pipeline Optimization Study 8

8 Limitations on Design Factor and Stress Level 9

9 Limitations on Materials 11

10 Design Temperature 11

11 Design Pressure and Wall Thickness 12

12 Construction Types 13

13 Corridors and Pipelines Layout 14

14 Anchors and Pipe Supports 16

15 Sectionalizing Valves 18

16 Check Valves 20

17 System Appurtenances 20

Page 4: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 4 of 28

Section Contents Page

18 Pipelines Scraping Requirements 21

19 Corrosion Control 23

Appendix

A

Wall Thickness Selection of Transportation Pipelines

24

Page 5: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 5 of 28

1 Scope

1.1 This standard covers the additional requirements for designing onshore and near shore pipelines including cross-country pipelines, transfer line, etc.

1.2 This standard supplements ASME B31.4 and ASME B31.8 requirements for designing pipelines.

1.3 This standard is applicable to existing pipelines that will be converted from one specific service to another type of service. Examples of pipelines in this category are pipelines converted from stabilized oil to sales gas, from sales gas to NGL and so on.

2 Conflicts, Deviations and Clarifications

2.1 Any conflicts between this standard and other applicable Company Engineering Standards (JERES), Material Specifications (JERMS), Standard Drawings (JERSD), Engineering Procedures (JEREP), Company Forms or Industry standards, specifications, Codes and forms shall be brought to the attention of Company Representative by the Contractor for resolution.

Until the resolution is officially made by the Company Representative, the most stringent requirement shall govern.

2.2 Where a licensor specification is more stringent than those of this standard, the Licensor’s specific requirement shall apply.

2.3 Where applicable Codes or Standards are not called by this standard or its requirements are not clear, it shall be brought to attention of Company Representative by Contractor for resolution.

2.4 Direct all requests for deviations or clarifications in writing to the Company or its Representative who shall follow internal Company procedure and provide final resolution.

3 References

The selection of material and equipment, and the design, construction, maintenance, and repair of equipment and facilities covered by this standard shall comply with the latest edition of the references listed below as of the CUT-OFF DATE as specified in the Contract unless otherwise noted.

3.1 Company References

Page 6: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 6 of 28

Company Engineering Standards

JERES-B-064 Onshore and Nearshore Pipeline Safety

JERES-H-001 Coating Selection & Application Requirements for Industrial Plants & Equipment

JERES-L-100 Applicable Codes and Standards for Pressure Piping Systems

JERES-L-105 Piping Materials Specifications

JERES-L-108 Selection of Valves

JERES-L-109 Selection of Pipe Flanges, Stud Bolts and Gaskets

JERES-L-110 Limitations on Pipe Joints and Components

JERES-L-120 Piping Flexibility Analysis

JERES-L-125 Safety Instruction Sheet for Piping and Pipelines

JERES-L-131 Fracture Control of Carbon Steel Line Pipe

JERES-L-132 Velocity Criteria and Basic Material Selection of Process Piping

JERES-L-133 Corrosion Protection Requirements for Pipelines, Piping and Process Equipment

JERES-L-136 Selection and Restrictions of Carbon Steel Pipe

JERES-L-140 Thermal Expansion Relief in Piping

JERES-L-150 Pressure Testing of Plant Piping and Pipelines

JERES-L-315 Steam Tracing and Jacketed Piping

JERES-L-420 Scraper Trap Station and Appurtenances

JERES-L-440 Anchors for Buried Pipelines

JERES-L-450 Construction of On-Land and Near-Shore Pipelines

JERES-L-460 Pipeline Crossings under Roads and Railroads

JERES-P-315 Electrical Tracing for Piping and Equipment

JERES-X-400 Cathodic Protection of Buried Pipelines

Company Standard Drawings

JERSD-X-0037 Cathodic Protection, Pipeline KM Market and Test Station

JERSD-M-0014 Market Plates for Pipeline Kilometer Market

Page 7: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 7 of 28

3.2 Industry Codes and Standards

American Society of Mechanical Engineers

ASME B31.3 Process Piping

ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids

ASME B31.8 Gas Transmission and Distribution Piping Systems

3.3 Saudi Government

SSD-29 Saudi Security and Safety Directives

4 Definitions

4.1 Definitions presented in this Standard and other JER documents have precedence over other definitions. Conflicts between various definitions shall be brought to the attention of Company Representative by the Contractor for resolution.

Company: Jubail Export Refinery.

Company Representative: A designated person from the Company or an assigned third party representative.

Company Inspector: A designated person or an agency responsible for conducting inspection activities on behalf of the Company.

4.2 List of Definitions

All definitions listed in JERES-L-100 shall apply to this standard, including the following:

− Cross Country Pipelines

− Design Factor

− MAOP

SMYS: Specified minimum yield strength.

5 Applicable Code and Standards

5.1 In addition to referenced Codes and Standards within the context of this standard, the applicable Codes and standards in accordance with JERES-L-100 shall apply.

Page 8: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 8 of 28

5.2 Piping systems designed and constructed in accordance with ASME B31.3 are acceptable to be considered as ASME B31.4 or B31.8 piping subject to the approval of the Company Representative.

6 Design Package and Project Records

The pipeline design shall include, as a minimum, the preparation of the documents listed below and shall be given Company engineering drawing numbers. These documents shall be prepared in accordance with Jubail Export Refinery Drafting Manual and will become permanent plant records:

− Piping and Instrument Diagram (P&ID).

− Process Flow Diagram (PFD).

− Calculation sheets supporting flow and pressure drop data, surge analysis in liquid services, stress analysis of restrained and unrestrained pipelines, anchor design, supports for above ground and minimum cover for buried pipelines, etc., as applicable, (calculation sheets are not required for flowlines).

− Safety Instruction Sheets (SIS) per JERES-L-125.

− Pipeline route/corridor drawing.

− As-built pipeline Plan and Profile drawings including pipeline data and appurtenance information such as topography, area classification and design factors, MAOP, station location of all accessories along the pipeline presented in a tabular form along the route of pipeline.

− Piping detail drawings for end connections, branches, crossings, etc.

− Hydrostatic Test Diagram and pressure testing plans per JERES-L-150.

− Pipe support and anchor detail drawings.

− Project Scope of Work or Project Specifications covering the installation and highlighting any special features or precautions, tie-in temperature range, procedures for testing, lay-up, and commissioning as applicable.

7 Pipeline Optimization Study

7.1 Each new pipeline shall be thoroughly studied to evaluate its technical and economical feasibility. The economic analysis shall include a Life Cycle Cost Analysis (i.e., optimizing the installation cost and operating cost). The study shall be conducted no later than the Project Proposal stage and shall address the following as a minimum:

Page 9: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 9 of 28

a) Pipe diameter, wall thickness and material type and grade.

b) Pipeline routing, construction method (i.e., aboveground or buried) and their impact on initial capital, operation, and maintenance expense.

c) Pipeline area classification.

d) The maximum allowable operating pressure, the available inlet pressure and the minimum required delivery pressure.

e) Requirements for future expansion.

f) Constructability of the pipelines.

g) Design flow rate (and future needs), velocity limitations (upper and lower) imposed by the fluid composition and flow pattern for multi-phase fluid.

h) Pipeline material selection, with regard to potential corrosion and erosion affects.

7.2 Production pipelines in gas or crude may not require detailed pipeline optimization study. For pipelines in this category, consult the Company Representative for a determination of whether a detailed study is required.

8 Limitations on Design Factor and Stress Level

8.1 Each pipeline shall have an area classification per JERES-B-064. The design factors specified by this Standard, shall overrule those stipulated in ASME B31.4 and/or ASME B31.8.

8.2 For pipelines in hydrocarbon service, the design factors, F shall not exceed values listed in Table 1.

Commentary Note:

ASME B31.4 has no location classes with different design factors for populated areas. This is a Jubail Export Refinery requirement to minimize potential damage to liquid carrying pipelines caused by the activities of people along the route of the pipelines.

Table 1 – Design Factor for Pipelines in Hydrocarbon, Toxic and Flammable Services

Pipeline Type Service Class 1 Class 2 Class 3 Class 4

Cross country pipelines Gas 0.72 0.60 0.50 0.40

Cross-country pipelines NGL, LPG 0.72 0.60 0.50 0.40

Cross country pipelines Crude Oil sour 0.72 0.60 0.50 0.40

Page 10: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 10 of 28

Cross country pipelines Crude Oil sweet 0.72 0.60 0.50 0.50

Cross country pipelines Refined products 0.72 0.60 0.50 0.50

Pipelines over Open Water all services 0.60 0.60 0.50 0.40

8.3 For pipelines in non-hydrocarbon, nontoxic and non-flammable services, the design factor, F shall not exceed values listed in Table 2.

Table 2 – Design Factor for Pipelines In-Services other than Hydrocarbon

Service Class 1 Class 2 Class 3 Class 4

Sea Water 0.72 0.72 0.72 0.72

Water disposal 0.72 0.72 0.72 0.72

8.4 Any buried pipeline in hydrocarbon service within 150 m of process plant SSD fence, the design factor, F, shall not exceed F = 0.50.

However, for flowlines in hydrocarbon service the distance is 50 m from the GOSP SSD fence but not less than 150 m from the inlet manifold header.

8.5 For cross country pipelines designed to ASME B31.4 and/or ASME B31.8, Area Class I (F=0.72), piping assemblies such as jump-over between pipelines or laterals, and main line valve bypasses, the design factor, F, shall be F = 0.60.

Commentary Note:

The requirement for the lower design factor is per paragraph 841.121 of ASME B31.8 code to take into consideration the additional mechanical stresses due to fabrication and operation.

8.7 Limitations on Stresses

8.7.1 Crude Oil Service Lines

In calculating the combined stress in production pipelines in crude oil service designed to shut-in wellhead pressure requirements, the following metal temperatures shall be assumed: 38°C for buried lines, 27°C for underwater lines, and 65°C for above ground lines.

8.7.2 For liquefied hydrocarbon gas services, the nominal hoop stress calculated for the vapor pressure of the liquid at flowing design conditions shall not exceed 25% of SMYS, unless the pipe material has adequate crack arrest capability at a higher hoop stress caused by the vapor pressure of the liquid. (Refer to JERES-L-131).

Page 11: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 11 of 28

8.7.3 Welded Attachments

If the piping is designed to operate at a hoop stress in excess of 50% of the SMYS of the pipe material, all structural attachments which transfer loads to the pipe through welds, shall be welded to full encirclement sleeves or saddle pads of at least 90 degrees with rounded corners. ASME B31.4 paragraph 421.1(d) and ASME B31.8 paragraph 834.5(b), if applicable, shall not be waived. All welds to the pipe shall be continuous.

8.7.4 Stresses Due to Soil Pressures

The sum of the hoop stress due to internal pressure and the calculated circumferential bending stress due to external loading by soil pressure shall not exceed the maximum value provided by the applicable Code for hoop stress excluding joint, quality or other de-rating factors (E = 1).

9 Limitations on Materials

The following limitations shall apply to the line pipes and piping components:

9.3 Material specifications shall be in accordance with JERES-L-105.

9.4 Selection of valves shall be in accordance with JERES-L-108.

9.5 Selection of pipe flanges shall be in accordance with JERES-L-109.

9.6 Limitations on pipe joint per JERES-L-110 shall apply.

9.7 Carbon steel line pipe shall comply with JERES-L-131 for fracture control requirement.

9.8 Selection of the basic material shall be in compliance with JERES-L-132.

9.9 JERES-L-136 shall apply for pipe material selection and restrictions

10 Design Temperature

10.1 The design temperature shall be selected based on the maximum anticipated flowing conditions.

Page 12: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 12 of 28

Commentary Note:

This is to avoid arbitrary selection of design temperature. Design temperature has significant cost impact on pipeline thickness and construction requirements.

10.2 Tie-In Temperature

For fully restrained pipelines (buried and above-ground), a tie-in temperature shall be defined during the Project Proposal stage. The construction location and expected ambient conditions during construction activities are major factors for defining the tie-in temperature.

10.3 Temperature Excursions

Heat excursions caused by unforeseen operational upsets may be used to determine the type and quality of coating or tape wrapping used on the pipeline. The Company Representative shall be consulted for a coating recommendation. These excursions should not be the basis for selecting the design temperature of the pipeline.

11 Design Pressure and Wall Thickness

11.1 General Requirements

The design pressure of the pipelines required to achieve design capacity shall be normally equal to the MAOP of the pipeline.

Exception:

Exception to this is that when the diameter to wall thickness or minimum wall thickness requirements are the limiting factors.

Commentary Note:

This is to avoid arbitrary or over-conservative selection of design pressure. Design pressure has significant cost impact on pipeline thickness and construction requirements.

11.2 Liquid Service Cross-Country Pipelines

For cross-country pipelines in liquid service, the design pressure is the pump shutoff pressure plus the static head of the liquid column.

Page 13: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 13 of 28

11.3 Gas Pipelines

For cross-country pipelines in gas service, the design pressure shall not be less than the compressor shut off pressure, unless the piping system is protected by full process relief system.

11.4 Line Pipe Wall Thickness

11.4.1 For carbon steel piping, the minimum nominal wall thickness shall not be less than the values listed in Table 3.

Table 3 – Limitation on Wall Thickness of Carbon Steel Line Pipe

Nominal Size (Inches) Hydrocarbon Service Water Service

2 and smaller SCH 80 SCH 40 3 through 5 SCH 40 SCH 40 6 through 32 6.35 mm (0.25 inch) 6.35 mm (0.25 inch) 34 and larger Diameter/135 Diameter/135

11.4.2 For non-metallic line pipe the Company Representative shall be consulted to determine the proper wall thickness.

12 Construction Types

12.1 General

Unless it is limited by this standard or the governing code and SSD-29 requirements, an economic feasibility study shall be conducted to determine the most cost effective type of construction. All construction options shall be evaluated such as whether it should be buried, above ground unrestrained or above ground fully restrained.

12.2 Buried Pipelines

Cross-country pipelines shall be buried and the original ground surface shall be restored by using suitable fill, or graded to suit the surrounding terrain (e.g., sand dune areas) in accordance with JERES-L-450. If requested by the Company Representative a bermed over construction may be used for pipeline demarcation and restriction of vehicular crossing. However, the top of pipe shall be buried at a minimum depth of 450 mm below finished grade.

Page 14: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 14 of 28

12.3 Bermed-Over Pipelines

Where, because of the soil conditions, it is not feasible or economical to restore the original grade, such as in rocky areas and in landfill in subkhas or tidal flats, buried cross-country pipelines shall have a stabilized berm per JERES-L-450.

12.4 Above-Ground Restrained Pipelines

Where the terrain or other considerations, such as cost of construction, or corrosion preclude burial, the pipeline should be designed for above ground installation.

These lines shall be fully restrained by means of ring girders and end anchors as detailed in section 14 below. The pipeline shall be supported off the natural or graded ground surface per JERES-L-450.

12.5 Above-Ground Non-Restrained Pipelines

12.5.1 This construction type is recommended for production pipelines in crude oil service and water injection pipelines up to 16" sizes. This is due to the simplicity of the design, construction, and cost effectiveness and availability of construction contactors.

12.5.2 Above-Ground Non-Restrained construction may also be a cost effective alternative for services other than that specified in 12.5.1, subject to the approval of the Company Representative.

Above-ground non-restrained pipelines shall have expansion loops or offsets to accommodate for thermal expansion. Stress analysis shall be performed for these lines per JERES-L-120.

12.6 Heat Tracing Pipelines

12.6.1 In case the pipeline will be provided with heat tracing, JERES-L-315 shall apply for steam tracing and JERES-P-315 shall apply for electrical tracing.

13 Corridors and Pipelines Layout

13.1 Corridors

Parallel lines shall be routed within a common corridor. Pipelines serving an onshore plant shall make the approach within one or more designated corridors or pipeways.

Page 15: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 15 of 28

Parallel pipelines with scraper traps shall terminate in a common scraper trap area and have tie-lines to the plant placed in a pipeway.

13.2 Vehicle Crossings

Above-ground pipelines and bermed over pipelines shall have crossings, at selected locations, suitable for the passage of people, vehicles and animals as dictated by local conditions. These crossings shall be in accordance with JERES-L-460. When both feasible and practical, the location of new crossings should match with those installed on existing parallel pipelines.

13.3 Spacing of Parallel Pipelines

13.3.1 The clear distance (OD to OD) between parallel pipelines shall be such that the installation and eventual repairs can be done with minimum risk of damage to or interference with the operation of adjacent pipelines. Consideration shall be given to requirements for future pipelines in corridors and above grade pipeways with limited space.

13.3.2 Cross Country Buried Pipeline

The minimum centerline spacing of buried parallel pipelines, each built at different times, shall be 15 m to allow access for construction or maintenance equipment. The minimum clear distance between two parallel buried pipelines, built at the same time, shall be minimum 3 m, except where this clearance cannot be provided over a relatively short length (such as in a road crossing) not to exceed a maximum of 150 m. Vehicles and equipment access to each pipeline needs to be made from only one side.

13.3.3 Cross-Country Above-Ground Pipelines

The minimum centerline spacing of above-ground, restrained, parallel pipelines on individual supports shall be 3 m with 15 m access for maintenance equipment from one side.

Exception:

Within 450 m of the plant SSD fence, requirements for maintenance vehicle access shall be reviewed and approved by the Company Representative.

Page 16: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 16 of 28

13.4 Clearances between Pipelines and Others

The minimum clearance between buried cross-country pipelines and an adjacent structure not used to support the pipeline shall be 1 m. If for any reason this clearance can not be provided, approval must be obtained from the Company Representative.

For oil flowlines, trunklines, testlines, water supply lines, water injection lines, and GOSP water disposal lines, this minimum clearance shall be 0.3 m (1 ft) over a short length up to 3 pipe diameters or a minimum of 0.6 m (2 ft) if the length is longer.

13.5 Pipeline Markers

In addition to the requirements of ASME B31.4, Section 434.18 and JERES-B-064 for markers in populated areas, kilometer markers similar to those illustrated on Standard Drawings JERSD-X-0037 and JERSD-M-0014 shall be installed at every kilometer station of the pipeline, at road crossings (within 10 meters of the road on both sides of the road), and near appurtenances, deflections, junctions and transitions where needed to identify the approximate location of such features. Additional markers are not required for appurtenances at the end points of the pipeline.

Commentary Notes:

For example, a block valve can be referred to as the block valve at KM 18.6 with the name of the pipeline.

Kilometer markers, per Standard Drawing AA-036907 referred to above, do not require a cathodic protection one-pin test station, other than at every kilometer station, or at those locations listed in JERES-X-400.

14 Anchors and Pipe Supports

14.1 End Anchors

14.1.1 Above-ground fully restrained pipelines shall be provided with end anchors designed to withstand the full thrust and pull forces due to thermal expansion and contraction and due to internal fluid pressure considering Poisson's ratio, with a maximum anchor deflection of 6 mm unless it can be shown that larger movement be accommodated by the piping system.

14.1.2 All buried cross-country pipelines of 0.5 km in length and longer shall be provided with a full thrust or drag anchor at each end of the pipelines.

Page 17: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 17 of 28

14.1.3 A full thrust anchor shall be provided at the onshore end and close to the shoreline at the transition points between onshore and subsea offshore pipelines.

14.1.4 The end anchor shall be designed per JERES-L-440.

14.2 Deflection Anchors

Any change in direction in the horizontal and/or vertical plane of above-ground restrained pipelines shall require one or more deflection anchors designed to resist the resultant force of the full thrust forces. Deflection anchors may be required on buried pipelines if the passive soil restraint against the pipe is not sufficient to fully restrain the line.

14.3 Intermediate Anchors

Differential thrust anchors shall be provided for above ground restrained pipelines where there is a change in thrust, e.g., due to a change in pipe diameter or wall thickness. This requirement is exempted if the associated local axial movement of the line can be shown to be less than 6 mm.

Intermediate anchors or axial line stops shall be provided for above-ground unrestrained pipelines between and/or at the center of expansion loops or offsets. The design load for such intermediate anchors shall include the effect of friction forces.

14.4 Camel Crossings

Camel crossings are considered as equalizing anchors between expansion loops or offsets and shall not be considered as end anchors without appropriate design analysis.

Commentary Note:

Equalizing anchors usually will be subjected to minimal thrust force. In fact calculation could show that the may be under zero axial loads.

14.5 Ring Girders Pipe Supports

14.5.1 Above ground restrained pipelines shall be supported on ring girders, or 180-degree saddles with top strap, designed to prevent lateral buckling of the pipeline. Suitable electrical insulation strips shall be provided between the pipe and the support if required to prevent dissipation of cathodic protection current.

Page 18: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 18 of 28

14.5.2 If the ring girder supports of the above ground piping sections interfere with the cathodic protection of the buried sections (if some sections of the line are buried), electrical insulation between the pipe and the supports is required per JERES-X-400.

14.5.3 The pipe surface covered by the ring girder or saddle and top strap shall be coated in accordance with JERES-H-001 to prevent corrosion of the pipe. Coating is not required if a fiberglass insulating spacer is epoxy bonded to the pipe after abrasive blasting the pipe surface to Sa 2-½ (near white metal blast).

14.6 Clearance from Grade

For above-grade pipelines the clearance between bottom of the pipe and the finished grade shall not be less than the following:

a) Inside plant areas and where the grade under 300 mm the pipe is hard surfaced

b) Outside plant areas with nearby stabilized 450 mm sand dunes

c) In areas with moving sand dunes 900 mm

14.7 Support Spacing (Restrained)

To mitigate wind-induced resonance vibration of the above-ground cross-country pipelines with diameters larger than 12 inch that are supported at regular intervals, every seventh span length shall be reduced by 20%. The basic support spacing shall be selected so that the natural frequency of the pipeline in operating condition is outside the range of wind induced frequencies plus or minus 10% for wind speed above 9 m/s (20 MPH) which will cause vortex shedding.

Commentary Note:

The Company Engineering Report SAER-1714 "Wind Induced Vibration of Pipelines" or any other reliable engineering source could be used to perform these calculations.

14.8 Guides and Stops

The free movement of unrestrained piping, both in axial and lateral directions, shall be controlled and limited by properly located guides and anchoring points to within acceptable bounds. The restraints shall be designed to withstand any shock loads which may occur due to start-up, surges or slug flow. The design force due to liquid slugs shall be conservatively estimated (density times the square of the maximum expected velocity times the cross-sectional flow area of the pipe) and applied at all changes in direction of the pipe.

Page 19: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 19 of 28

14.9 Low Friction Supports

Low friction supports by use of Teflon sheets or equivalent should be avoided. In case they are not avoided, low friction supports shall be designed such that sand or other debris cannot accumulate on sliding surfaces (by making the top surface larger than the bottom surface). Sliding surfaces shall be protected during all construction activities including painting and sandblasting.

15 Sectionalizing Valves

15.1 Sectionalizing Valves

In addition to the requirements of Section 434.15 of ASME B31.4 and Section 846 of ASME B31.8, the maximum spacing between sectionalizing block valves shall be as follows:

a) Table 4 as a function of service and class locations, as defined in JERES-B-064.

b) Additional valves for emergency isolation shall be provided as required by JERES-B-064. A sectionalizing valve may be used as an emergency isolation valve if the valve complies with the requirements of JERES-B-064.

c) Additional operational valves may be required by the Operating Department in order to operate and maintain the pipeline, associated equipment, and facilities.

Table 4 – Sectionalizing Valve Spacing

Class 1 Class 2 Class 3 Class 4

Hydrocarbon and Flammable Pipelines

Abs. vapor pres. >450 kPa (65 psia) Note 1 Note 1 16 km 8 km

Abs. vapor pres. <450 kPa (65 psia) Note 1 Note 1 16 km 16 km

Gas 32 km 24 km 16 km 8 km

Non-Hydrocarbon Pipelines

Note 2 32 km 24 km 16 km 16 km

Other than Note 2 32 km 32 km 32 km 32 km

Notes:

1) Install valves upstream and downstream of environmentally sensitive areas as identified in the Environmental Assessment portion of the Project.

2) Sour water, seawater, brine, and other contaminated or chemically treated water.

Page 20: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 20 of 28

Exception:

If the proposed spacing exceeds these limits, the valve locations shall be jointly reviewed and approved by a Company Representative..

15.2 Void

15.3 For liquid service sectionalizing valve every 16 km are not required under the following conditions: a) Liquid having a TVP less than 450 kPa (65 psia), b) The pipelines is above grade, c) The pipelines has vertical expansion loops installed at distances which will create

a natural retention of the liquid and limitation of spillage in case of pipelines rupture.

16 Check Valves

16.1 General Requirement

A check valve shall be installed in each branch near the intersection point, and near the upstream end of cross-country pipelines in hazardous service, such that backflow is prevented in case of an upstream line rupture or emergency in the plant which feeds the pipeline.

16.2 Bi-directional Scrapable Pipelines

If the pipeline is designed for bi-directional flow service, a check valve and a parallel block valve shall be installed. If a check valve was installed on an existing outgoing pipeline which will be converted to bi-directional flow, the block valve can be installed on the by-pass and the check valve left on the main line. For the design of a new pipeline in bi-directional flow, the check valve shall be installed on the by-pass.

17 System Appurtenances

17.1 Vents and Drains

Permanent vents and drains with plugged or blinded valves, or other appurtenances provided for the blow-down of pipeline sections at selected locations, shall be installed only as required by the Operating Department for emergency conditions. Temporary vent valves, if required during the initial filling of the pipeline for hydrostatic test, shall be removed and the connection plugged and seal welded after the test.

Page 21: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 21 of 28

17.2 Instruments and Control

Pressure gauges, thermowells, and any controlling or recording instruments, surge protection equipment, telemetry and other remote monitoring and control shall be provided as required by the Operating Department and be installed per applicable instrumentation standards.

17.3 Other Appurtenances

Pipeline appurtenances covered by other JERESs include the following:

Vessels such as for separation of liquid slugs from gas lines and for sand removal at water supply wells per applicable vessel standards;

Devices for internal pipeline corrosion monitoring and control, injection of inhibitors and other chemicals, gas blanketing of water wells, etc., per JERES-L-133;

Cathodic protection equipment, test and bonding stations, insulating joints or flanges, etc., per JERES-X-400;

Thermal relief valves on lines in liquid service per JERES-L-140;

Scraper traps and associated piping per JERES-L-420;

Concrete anchors for buried pipelines shall comply to JERES-L-440; and

Roads and railroad crossings per JERES-L-460.

18 Pipelines Scraping Requirements

18.1 Responsibilities

18.2 Unless specifically identified below, designing pipelines to allow the passage of scraper and the installation of permanent scraping facilities that are capable of accepting instrument scraping tools should be evaluated for its economical and operational justification. Following are general guidelines that could be used to justify such installation:

a) for corrosion control and monitoring of the pipeline,

b) pipelines passing through populated areas classified as area class,

c) for removal of liquid build-up in gas lines,

Page 22: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 22 of 28

d) when routine hydrostatic revalidation tests must be made (onshore oil and gas flowlines are excluded),

e) when required and justified by the Operating Organization.

18.3 Cross Country Pipelines

All new cross country pipelines shall be designed to allow passage of instrument scraper tool and should have permanent scraping facilities.

18.4 Design Requirements

The following requirements shall apply for pipelines designed to allow passage of scrapers, instrumented type as well as cleaning type.

18.4.1 The Project Proposal should identify the specific type of scrapers to be used to assess in designing scraper trap size and minimum bend radius.

18.4.2 Additional design requirements for permanent scraping facilities, including the scraper traps, appurtenances and associated piping shall be in accordance with JERES-L-420.

18.4.3 Pipeline Bends

Long radius bends shall be used in pipelines which will be subject for scraping. This is required whether the pipeline is equipped with permanent or temporary scraping facilities.

The bend radius shall be not less than eight diameters (8D) for lines up to 8-inch NPS, 5D for lines of 10-inch NPS through 14-inch NPS, and 3D (either bends or forged elbows) for lines of 16-inch NPS and larger if 5D cannot be used because of space limitation, or difficulty in procurement, subject to review and approval by the Company Representative.

18.4.4 Valves and Tees

The valves shall be full bore type to allow for the passage of scrapers. Tee shall be barred-tees type where needed.

18.4.5 The pipeline shall not be multi-diameter.

18.4.6 Markers for Subsea Pipelines

Page 23: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 23 of 28

Subsea pipelines shall be equipped with visible markers that will assist in identifying defects location during instrument scraping runs. This could be accomplished by:

a) Installing short pipe joints 4 feet in length with separation distances no greater than 2 kilometers along the pipeline length. These short pipe joints shall be externally permanently marked so as to be visible to the divers. For example, Monel plates may be attached to these pipe joints using a polypropylene rope or Monel banding.

b) Presence of permanent, readily identifiable features, such as line break valves, tees, flanged tie-in risers, etc., are acceptable markers and should be taken into account as placements of pup pieces.

18.5 Instrument Run Baseline

PMT (Project Management Team) shall provide a baseline instrument scraper survey when ILI-capable scraping facilities are required. The baseline survey shall be completed prior to the commissioning or just after that with agreed on schedule with the Operating Organization.

19 Corrosion Control

Internal and external corrosion protection requirements for pipelines within the scope of this standard shall be in accordance with JERES-L-133.

Page 24: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 24 of 28

Appendix A: Wall Thickness Selection of Transportation Pipelines A.1 General

A.1.1 The pipe wall thickness is calculated by using the equation for internal pressure thickness (Barlow’s Equation).

A.1.2 The allowances, if required, are added to the calculated wall thickness for internal pressure.

A.1.3 The wall thickness calculated based on internal pressure must be checked to be adequate for external loads as well as structural rigidity.

A.1.4 The wall thickness selected shall be either the next higher standard size of ANSI/API standard wall thicknesses or the exact calculated thickness.

Commentary Note:

Selection of the exact calculated wall thickness will reduce the steel tonnage and result in cost savings if the quantity of pipe ordered is significant (large diameter long pipelines). The project engineer shall evaluate the cost of both options as early as possible in the design stage and before material procurement.

A.2 Pipeline Wall Thickness for the Internal Design Pressure

A.2.1 Company Standard calls for applying the design factor formula of ASME B31.8 for all transportation piping systems regardless of the nature of the service. The differences will be in the design factors and de-rating factors as discussed below.

2SETFPDt=

(Eq. 1)

Where:

T = Internal pressure design wall thickness, inches.

P = Design pressure, psig.

D = Outside diameter of pipe, inches.

S = Specified Minimum Yield Strength (SMYS), psi.

E = Longitudinal-joint quality factor.

T = Temperature de-rating factor.

Page 25: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 25 of 28

F = Design factor.

A.2.2 The design pressure [P] should be selected to match process needs and will normally be equal to the Maximum Allowable Operating Pressure (MAOP). Selecting a design pressure higher than the required operating pressure increases the required pipe wall thickness, and thus, increases the capital cost considerably.

A.2.3 Pressure surge in liquid lines must be considered. If pressure surges exceeding 110% of MAOP are not avoidable, and it is not practical to install surge relief systems, then increasing the wall thickness of the line to withstand these pressure surges is required.

The ASME B31.4, paragraph 402.2.4 states that the MATP, maximum allowable transient pressure due to the pressure surges, shall not exceed 110% of the design pressure (MAOP) in the line.

A.2.3 High Integrity Pipeline Protection System (HIPS) might be installed to protect the pipeline against overpressure in lieu of increasing the wall thickness or installing mechanical relief system. However, such decision must be taken based on full engineering study as described in Company Engineering Report SAER-6043.

A.3 The parameter [S] is the Specified Minimum Yield Strength (SMYS) of the material. The ASME codes B31.4 & B31.8 specify the acceptable materials together with their SMYS. Using high strength steel decreases the required pipe wall thickness and steel tonnage, and thus the overall project cost. However, economical and technical evaluation must be conducted before making the final wall thickness selection.

Commentary Note:

Higher grade steels (X 70 and higher) are not suitable for sour services because hardness values in the field welds may exceed those permitted by NACE to avoid sulfide stress cracking.

A.3.1 The lower thickness resulting from using higher strength steel must be sufficient to withstand other failure criteria like buckling. Company Standards require that the minimum thickness be greater than diameter/135.

A.3.2 Higher strength steel requires special welding procedures which are usually more expensive and technically more difficult compared to lower grade.

A.4 The temperature de-rating factor [T] accounts for the fact that the yield strength of materials is reduced as the metal temperature increases. This factor is only

Page 26: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 26 of 28

applicable for pipelines designed to ASME B31.8 with design temperature more than 250ºF.

A.5 The design factor [F], sometimes called DF, is a safety factor that accounts for the relative hazard created by the presence of the pipeline to the surrounding population, environment, and facilities. This design factor is selected based on area classification shown in Table 1 (refer to JERES-B-064 for more details).

Table 1: Location Class and Design Factors for Transportation Piping Location Class Design Factor

F Population Density

Index PDI Commentary and Examples

1 0.72 10 Desert area non developed areas Water service lines.

2 0.60 11-29 Hydrocarbon service, in populated areas or parallel to highways

3 0.50 30 and above Plant piping designed to B31.4 / B31.8

4 0.40 Special Cases Highly populated complexes such as hospitals and malls.

A.6 Corrosion Allowance and Mill Tolerance

A.6.1 Additional pipe wall thickness to allow for metal loss due to internal or external corrosion is not normally applicable for cross country pipelines.

Commentary note:

Adding corrosion allowance as an extra corrosion protection to coating and cathodic protection increases the project cost without any added value. If the coating or cathodic protection fails at a location, the corrosion will be localized and aggressive, and the additional thickness will not last for long and its additional cost is not justified. Internal corrosion will normally be controlled by corrosion inhibitor injection.

A.6.2 Manufacturer mill tolerance shall NOT be considered for transportation pipelines. The Code considers the mill tolerance in the design factor [F].

A.7 Traffic and Soil Loads over Buried Pipeline

A.7.1 The required thickness of the buried sections of pipelines should be checked for soil and traffic loads, in addition to the design pressure. These loads cause a circumferential bending stress in the pipe.

A.7.2 If analysis shows that pipeline thickness must be increased under road crossing, the

Page 27: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 27 of 28

wall thickness of the pipe under the road crossing shall be increased NOT the whole pipeline.

A.7.3 Casing shall be used for rail road crossing, as required by the Saudi Arabian Government, instead of increasing the pipe thickness.

A.7.4 Installation of concrete slab over the pipe to redistribute the stresses is an alternative to increasing the pipe thickness, if needed, under road crossing.

Commentary Note:

Consulting Serviced Department completed a technology item which showed that in many occasions, the buried pipe does not need additional reinforcement by casing under the road crossing. Consulting Services Department owns a software called “Analysis and Design of Buried Pipeline” to perform the stress calculation. The software was developed through a Technology Research Item and it is designed to run analysis for road/highway crossing and sand overburden.

A.8 Typical Mistakes in Wall Thickness Selection

Even though the calculation for wall thickness is relatively simple and straight forward, unintentional mistakes and/or inappropriate assumptions cost the company more capital investment than necessary. These typical mistakes are summarized but not limited to the following:

A.8.1 Specifying a design pressure that is higher than what is required to fulfill the operational requirement.

A.8.2 Selecting the higher wall thickness to match the flange pressure rating. The wall thickness of the pipeline might be less than of the mating flange.

A.8.3 Setting the design pressure based on a pre-selected or existing flange rating that exceeds the MAOP required for operation.

A.8.4 Applying the wrong Code.

A.8.5 Specifying the wrong allowable stresses in the formula.

A.8.6 Adding the manufacturer mill tolerance to the calculated wall thickness.

A.8.7 Adding corrosion allowance to pipelines where it is not needed.

Page 28: Jeres l-410 design of pipelines

Jubail Export Refinery Engineering Standard

JERES-L-410 Rev. 3 Design of Pipelines 13 May 2009

This document is the property of Jubail Export Refinery and no parts of this document shall be reproduced by any

means without prior approval by the Company.

Page 28 of 28

A.8.8 Selecting exact calculated wall thickness rather than standard ANSI/API pipe thickness to reduce the cost of steel tonnage, but on the expense of extra cost of special manufacturing.

A.8.9 Selecting higher grade of pipe material to reduce the cost of steel tonnage, but on the expense of handling and installation cost.

A.8.10 Overestimating of the RER/PDI, and thus, increasing the area classification.

A.8.11 Making pure mathematical mistakes in the calculations which are reflected in possibly unsafe designs or costly material.