J. Wenninger LNF Spring School, May 2010 1 LHC : construction and operation Part 2: Machine...
-
Upload
emery-hoover -
Category
Documents
-
view
219 -
download
2
Transcript of J. Wenninger LNF Spring School, May 2010 1 LHC : construction and operation Part 2: Machine...
J. Wenninger LNF Spring School, May 2010 1
LHC : construction and operationLHC : construction and operation
Part 2:•Machine protection•Incident and energy limits•Commissioning and operation
Jörg Wenninger
CERN Beams Department / Operations group
LNF Spring School 'Bruno Touschek' - May 2010
J. Wenninger LNF Spring School, May 2010
Machine protection
2
J. Wenninger LNF Spring School, May 2010
The price of high fields & high luminosity…
3
When the LHC is operated at 7 TeV with its design luminosity & intensity,
the LHC magnets store a huge amount of energy in their magnetic fields:
per dipole magnet Estored = 7 MJ
all magnets Estored = 10.4 GJ
the 2808 LHC bunches store a large amount of kinetic energy:
Ebunch = N x E = 1.15 x 1011 x 7 TeV = 129 kJ
Ebeam = k x Ebunch = 2808 x Ebunch = 362 MJ
To ensure safe operation (i.e. without damage) we must be able to dispose of all that energy safely !
This is the role of machine protection !
J. Wenninger LNF Spring School, May 2010
Stored Energy
4
Increase with respect to existing accelerators :
• A factor 2 in magnetic field
• A factor 7 in beam energy
• A factor 200 in stored energy
J. Wenninger LNF Spring School, May 2010
Comparison…
5
The energy of an A380 at 700 km/hour corresponds to the energy stored in the LHC
magnet system :
Sufficient to heat up and melt 15 tons of Copper!!
The energy stored in one LHC beam corresponds
approximately to…
• 90 kg of TNT
• 10-12 litres of gasoline
• 15 kg of chocolate
It’s how easily/quickly the energy is released that matters most !!
J. Wenninger LNF Spring School, May 2010
Machine protection: beam
6
J. Wenninger LNF Spring School, May 2010
To set the scale..
7
Few cm long groove of an SPS vacuum chamber after the impact of ~1% of a nominal LHC beam (2 MJ) during an ‘incident’:
Vacuum chamber ripped open.
3 day repair.
The same incident at the LHC implies a shutdown of > 3 months.
>> Protection of the LHC must be much stricter and much more reliable !
J. Wenninger LNF Spring School, May 2010
Beam impact in a target
8
Courtesy N. Tahir / GSI
20 bunches 180 bunches
100 bunches 380 bunches
The 7 TeV LHC beam can drill a hole through
~35 m of Copper
Simulation of a 7 TeV LHC beam impact into a 5 m long Copper target
J. Wenninger LNF Spring School, May 2010
From a real 450 GeV beam…
9
A B D C
Shot Intensity / p+
A 1.2×1012
B 2.4×1012
C 4.8×1012
D 7.2×1012
~0.1% nominal LHC beam
Cu plate ~20 cm inside the ‘target’.
30 cm
108 plates
6 cm
6 cm
Shoot a 450 GeV beam into a target…
J. Wenninger LNF Spring School, May 2010
‘Safe’ beams at the LHC…
10
L ~ 21028 cm-2s-1
LHC 2010
‘Safe beam’
‘Un-safe beam’
2011
J. Wenninger LNF Spring School, May 2010
Schematic layout of beam dump system in IR6
11
Q5R
Q4R
Q4L
Q5L
Beam 2
Beam 1
Beam dump block
Kicker magnets to paint (dilute)
the beam
700 m
500 m
15 fast ‘kicker’ magnets deflect the beam to the
outside
When it is time to get rid of the beams (also in case of emergency!), the beams are ‘kicked’ out of the ring by a system of kicker magnets and send into a dump block !
Septum magnets deflect the
extracted beam vertically
quadrupoles
The 3 ms gap in the beam gives the kicker time to reach
full field.
Ultra-high reliability system !!
J. Wenninger LNF Spring School, May 2010
The dump block
12
Approx. 8 m
concrete shielding
beam absorber (graphite)
The ONLY element in the LHC that can withstand the impact of the full beam !
The block is made of graphite (low Z material) to spread out the showers over a large volume.
It is actually necessary to paint the beam over the surface to keep the peak energy densities at a tolerable level !
Measurement
Simulation
J. Wenninger LNF Spring School, May 2010
Dump line in IR6
13
J. Wenninger LNF Spring School, May 2010
Dump line
14
J. Wenninger LNF Spring School, May 2010
Dump installation
15
J. Wenninger LNF Spring School, May 2010
‘Unscheduled’ beam loss due to failures
16
Beam loss over multiple turns
(~millisecond to many seconds) due to many types of failures.
Passive protection - Failure prevention (high reliability systems).- Intercept beam with collimators and absorber
blocks.
Active Protection- Failure detection (by beam and/or equipment monitoring)
with fast reaction time (< 1 ms).
- Fire beam dumping system.
Beam loss over a single turn
during injection, beam dump.
In the event a failure or unacceptable beam lifetime, the beam must be dumped immediately and safely into the beam dump block
Two main classes for failures (with more subtle sub-classes):
Because of the very high risk, the LHC machine protection system is of unprecedented complexity and size.
A general design philosophy was to ensure that there should always be at least 2 different systems to protect against a given failure type.
J. Wenninger LNF Spring School, May 2010
Failure detection example : beam loss monitors
17
Ionization chambers to detect beam losses:– N2 gas filling at 100 mbar over-pressure, voltage 1.5 kV
– Sensitive volume 1.5 l– Reaction time ~ ½ turn (40 ms)– Very large dynamic range (> 106)
There are ~3600 chambers distributed over the ring to detect abnormal beam losses and if necessary trigger a beam abort !
J. Wenninger LNF Spring School, May 2010
Beam loss monitoring
J. Wenninger LNF Spring School, May 2010
Machine protection
and quench prevention:
collimation
19
J. Wenninger LNF Spring School, May 2010
Operational margin of SC magnet
20
Temperature [K]
App
lied
field
[T]
Superconductingstate
Normal state
Bc
Tc
9 K
Applied Field [T] Bc critical field
1.9 K
quench with fast loss
of ~few 109 protons
quench with fast loss of ~106-7 protons
8.3 T / 7 TeV
0.54 T / 450 GeV
QUENCH
Tc critical
temperature
Temperature [K]
The LHC is ~1000 times more critical than
TEVATRON, HERA, RHIC
J. Wenninger LNF Spring School, May 2010
Quench levels
21
Example of the energy (mJ/cm3) required to quench an LHC dipole magnet with an instantaneous loss.
Steep energy dependence.
Models are confirmed at 0.45 TeV.
The phase transition from the super-conducting to a normal conducting state is called a quench.
Quenches are initiated by an energy in the order of few milliJoules– Movement of the superconductor by several m (friction and heat dissipation).– Beam losses.– Cooling failures.– ..
J. Wenninger LNF Spring School, May 2010
Beam lifetime
22
Consider a beam with a lifetime :
Number of protons lost per second for different lifetimes (nominal intensity):
t = 100 hours 109 p/s
t = 25 hours 4x109 p/s
t = 1 hour 1011 p/s
While ‘normal’ lifetimes will be in the range of 10-100 hours (in collisions most of the protons are actually lost in the experiments !!), one has to anticipate short periods of low lifetimes, down to a few minutes !
To survive periods of low lifetime we must intercept the protons that are lost with very high efficiency before they can quench a magnet : collimation!
/)()(
)( /0 tN
dt
tdNeNtN t
Quench level ~ 106-7 p
J. Wenninger LNF Spring School, May 2010
Collimation
23
A 4-stage halo cleaning (collimation) system is installed to protect the LHC magnets from beam induced quenches.
A cascade of more than 100 collimators is required to prevent the protons and their debris to reach the superconducting magnet coils.
The collimators will also play an essential role for protection by intercepting the beams.
the collimators must reduce the energy load into the magnets due to particle lost from the beam to a level that does not quench the magnets.
in front of the exp.Exp.
Detectors
Courtesy C. Bracco
J. Wenninger LNF Spring School, May 2010
Collimator settings at 7 TeV
24
1 mm
The collimator opening corresponds roughly to the size of Spain !
At the LHC collimators are essential for machine operation as soon as we have more than a few % of the nominal beam intensity at injection !
Opening ~3-5 mm
Carbon jaw
RF contact ‘fingers’
J. Wenninger LNF Spring School, May 2010 25
Collimation performance
IR8IR8 IR1IR1IR2IR2 IR5IR5
Momentum
Cleaning
Momentum
Cleaning
Dump Protection
Dump Protection
Measurements of the collimation efficiency from beam loss maps confirms the excellent performance : > 99.9% efficiency !
Collimation team
CleaningCleaning
J. Wenninger LNF Spring School, May 2010
Machine protection: magnets
26
J. Wenninger LNF Spring School, May 2010 27
Powering Sector
LHC powering in sectors
Sector 1
5
DC Power feed
3 DC Power
2
4 6
8
7LHC27 km Circumference
To limit the stored energy within one electrical circuit, the LHC is powered by sectors.
The main dipole circuits are split into 8 sectors to bring down the stored energy to ~1 GJ/sector.
Each main sector (~2.9 km) includes 154 dipole magnets (powered by a single power converter) and 47 quadrupoles.
This also facilitates the commissioning that can be done sector by sector !
J. Wenninger LNF Spring School, May 2010
Powering from room temperature source…
28
Water cooled 13 kA Copper cables! Not superconducting !
6 kA power converter
J. Wenninger LNF Spring School, May 2010
…to the cryostat
29
Feedboxes (‘DFB’) : transition from Copper cable to super-conductor
Cooled Cu cables
J. Wenninger LNF Spring School, May 2010
Quench detection
30
When part of a magnet quenches, the conductor becomes resistive, which can lead to excessive local energy deposition (tT rise !!) due to Ohmic losses.
To protect the magnet:– The quench must be detected: this is done by monitoring the voltage that appears
over the coil (R > 0).– The energy release is distributed over the entire magnet by force-quenching the
coils using quench heaters (such that the entire magnet quenches !).– The magnet current is switched off within << 1 second.
18/04/10
Example of the voltage signals over 5 quenching dipole magnets (beam induced at injection).
Threshold of quench protection system (QPS)
J. Wenninger LNF Spring School, May 2010
Quench - discharge of the energy
31
Magnet 1 Magnet 2
Power Converter
Magnet 154
Magnet i
Protection of the magnet after a quench:• The quench is detected by measuring the voltage increase over coil.• The energy is distributed in the magnet by force-quenching using quench heaters.• The current in the quenched magnet decays in < 200 ms.• The current flows through the bypass diode (triggered by the voltage increase over the
magnet).• The current of all other magnets is dischared into the dump resistors.
Discharge resistor
J. Wenninger LNF Spring School, May 2010
Dump resistors
32
Those large air-cooled resistors can absorb the 1 GJ stored in the dipole magnets (they heat up to few hundred degrees Celsius).
J. Wenninger LNF Spring School, May 2010
Machine protection philosophy
33
Power permit
Power Converters
QPS
Cryo
→ Authorises power on→ Cuts power off in case of fault
→ Authorises beam operation→ Requests a beam dump in case of problems
Collimators
access
RF
Beam permit
Experiments
vacuum
BLMs
Warm Magnets
Software interlocks
Stored magnetic energy
Stored beam
energy
Power Permit Beam Permit
J. Wenninger LNF Spring School, May 2010
Beam interlock system
34
Beam Interlock System
Beam Dumping System
Injection BIS
PIC essential+ auxiliary
circuitsWIC
QPS(several 1000)
Power Converters
~1500
AUG
UPS
Power Converters
Magnets
FMCM
CryoOK
RFSystem
Movable Devices
Experiments
BCMBeam Loss
Experimental Magnets
CollimationSystem
CollimatorPositions
Environmentalparameters
Transverse Feedback
Beam Aperture Kickers
FBCMLifetime
BTV
BTV screens Mirrors
Access System
Doors EIS
VacuumSystem
Vacuumvalves
AccessSafetyBlocks
RF Stoppers
BLM BPM in
IR6
Monitorsaperture
limits(some 100)
Monitors in arcs
(several 1000)
Timing System (Post Mortem)
CCC Operator Buttons
SafeMach.Param.
SoftwareInterlocks
LHCDevices
SEQ
LHCDevices
LHCDevices
Tim
ing
SafeBeamFlag
Over 20’000 signals enter the interlock system of the LHC that will send the beam into the dump block if any input signals a fault !
Isn’t it a miracle that it works !
J. Wenninger LNF Spring School, May 2010
Incident of September 19th 2008
& Consequences
35
J. Wenninger LNF Spring School, May 2010
Event sequence on Sept. 19th
36
Introduction: on September 10th when the first beam made it around the LHC, not all magnets had not been fully commissioned for 5 TeV.
A few magnets were missing their last commissioning steps.
The last steps were finished the week after Sept. 10th.
Last commissioning step of the dipole circuit in sector 34 : ramp to 5.5 TeV.
At ~5.1 TeV an electrical fault developed in the dipole bus bar (the bus bar is the cable carrying the current that connects all magnet of a circuit).
Later traced to an anomalous resistance of 200 n (should be 0.3 n).
An electrical arc developed which punctured the helium enclosure.
Secondary arcs developed along the arc.
Around 400 MJ were dissipated in the cold-mass and in electrical arcs.
Large amounts of Helium were released into the insulating vacuum.
In total 6 tons of He were released.
J. Wenninger LNF Spring School, May 2010
Pressure wave
37
PTQVQV QV QVQV SVSV
Cold-massVacuum vesselLine ECold support postWarm JackCompensator/BellowsVacuum barrier
Q D D QD D D QD D D QD D D QD
Pressure wave propagates in both directions along the magnets inside the insulating vacuum enclosure.
Rapid pressure rise :– Self actuating relief valves could not handle the pressure.
designed for 2 kg He/s, incident ~ 20 kg/s.– Large forces exerted on the vacuum barriers (every 2 cells).
designed for a pressure of 1.5 bar, incident ~ 10 bar.– Several quadrupoles displaced by up to ~50 cm.– Connections to the cryogenic line damaged in some places.– Beam vacuum to atmospheric pressure.
J. Wenninger LNF Spring School, May 2010 38
One of ~1700 bus-bar connections
Dipole busbar
J. Wenninger LNF Spring School, May 2010
Incident location
39
Dipole bus bar Dipole bus bar
J. Wenninger LNF Spring School, May 2010
Collateral damage : displacements
40
Quadrupole-dipole interconnection
Quadrupole support
Main damage area ~ 700 metres. 39 out of 154 dipoles, 14 out of 47 quadrupole short straight
sections (SSS)
from the sector had to be moved to the surface for repair (16) or replacement (37).
J. Wenninger LNF Spring School, May 2010
Collateral damage : beam vacuum
41
Beam Screen (BS) : The red color is characteristic of a clean copper
surface
BS with some contamination by super-isolation (MLI multi layer
insulation)
BS with soot contamination. The grey color varies depending on the thickness of the soot, from grey to
dark.
Clean Copper surface.Contamination with multi-layer magnet insulation
debris.Contamination with sooth.
60% of the chambers 20% of the chambers
The beam vacuum was affected over entire 2.7 km length of the arc.
J. Wenninger LNF Spring School, May 2010
Quench - discharge of the energy
42
Magnet 1 Magnet 2
Power Converter
Magnet 154
Magnet i
Discharge resistor
In case of a quench, the individual magnet is protected (quench protection and diode). Resistances are switched into the circuit: the energy is dissipated in the resistances (current
decay time constant of 100 s).
>> the bus-bar must carry the current until the energy is extracted !
The bus-bar must carry the current for some minutes, through interconnections
J. Wenninger LNF Spring School, May 2010
Bus-bar joint
43
24’000 bus-bar joints in the LHC main circuits.
10’000 joints are at the interconnection between magnets.
They are welded in the tunnel.
Nominal joint resistance:
•1.9 K 0.3 nΩ
•300K ~10 μΩ
For the LHC to operate safely at a certain energy, there is a limit to maximum value of the joint resistance.
J. Wenninger LNF Spring School, May 2010
Joint quality
44
The copper stabilizes the bus bar in the event of a cable quench (=bypass for the current while the energy is extracted from the circuit).
Protection system in place in 2008 not sufficiently sensitive.
A copper bus bar with reduced continuity coupled to a superconducting cable badly soldered to the stabilizer can lead to a serious incident.
During repair work in the damaged sector, inspection of the joints revealed systematic voids caused by the welding procedure.
X-ray of joint
bus U-profile bus
wedge
Solder No solder
J. Wenninger LNF Spring School, May 2010
superconducting cable with about 12 mm2 copper
copper bus bar 280 mm2copper bus bar 280 mm2
Magnet Magnet
Everything is at 1.9 Kelvin. Current passes through the superconducting cable.
For 7 TeV : I = 11’800 A
Normal interconnect, normal operation
Interconnection joint (soldered)
This illustration does not represent the real geometry
current
45
Helium bath
J. Wenninger LNF Spring School, May 2010
copper bus bar 280 mm2copper bus bar 280 mm2
Magnet Magnet
Quench in adjacent magnet or in the bus-bar. Temperature increase above ~ 9 K. The superconductor becomes resistive. During the energy discharge the current passes for few minutes
through the copper bus-bar.
superconducting cable interconnection
Normal interconnect, quench
46
J. Wenninger LNF Spring School, May 2010
copper bus bar 280 mm2copper bus bar 280 mm2
Magnet Magnet
Interruption of copper stabiliser of the bus-bar. Superconducting cable at 1.9 K Current passes through superconductor.
Non-conform interconnect, normal operation
superconducting cable interconnection
47
J. Wenninger LNF Spring School, May 2010
copper bus bar 280 mm2copper bus bar 280 mm2
Magnet Magnet
Interruption of copper stabiliser. Superconducting cable temperature increase to above ~9 K and
cable becomes resistive. Current cannot pass through copper and is forced to pass
through superconductor during discharge.
superconducting cable interconnection
Non-conform interconnect, quench.
48
J. Wenninger LNF Spring School, May 2010
copper bus bar 280 mm2copper bus bar 280 mm2
Magnet Magnet
The superconducting cable heats up because of the combination of high current and resistive cable.
superconducting cable interconnection
Non-conform interconnect, quench.
49
J. Wenninger LNF Spring School, May 2010
copper bus bar 280 mm2copper bus bar 280 mm2
Magnet Magnet
Superconducting cable melts and breaks if the length of the superconductor not in contact with the bus bar exceeds a critical value and the current is high.
Circuit is interrupted and an electrical arc is formed.
superconducting cable interconnection
Non-conform interconnect, quench.
Depending on ‘type’ of non-conformity, problems appear : at different current levels. under different conditions (magnet or bus bar quench etc).
50
J. Wenninger LNF Spring School, May 2010
copper bus bar 280 mm2copper bus bar 280 mm2
Magnet Magnet
Anomalous resistance at the joint heats up and finally quenches the joint – but quench remains very local.
Current sidesteps into Copper that eventually melts because the electrical contact is not good enough.
September 19th hypothesis
superconducting cable quench at the interconnection
51
>> A new protection system will be installed this year to anticipate such incidents in the future:
new Quench Protection System (‘nQPS’)
J. Wenninger LNF Spring School, May 2010
LHC repair and consolidation
52
14 quadrupole magnets replaced
39 dipole magnets replaced
204 electrical inter-connections repaired
Over 4km of vacuum beam tube cleaned
New longitudinal restraining system for 50 quadrupoles
Almost 900 new helium pressure release ports
6500 new detectors and 250km cables for new Quench Protection System to protect busbar joints: nQPSCollateral damage mitigation
J. Wenninger LNF Spring School, May 201053
Mechanical clamping (not present in Tevatron
and Hera …)
A glimpse in the future: the consolidated connection
In the next long (> 1 year) shutdown all the connections will be re-done.
Latest design:o Better electrical contacto Mechanical clamping
Courtesy F. Bertinelli
J. Wenninger LNF Spring School, May 2010
LHC energy target - way down
2002-20077 TeV
Summer 20085 TeV
Spring 2009
3.5 TeV
Nov. 2009
450 GeV
Detraining
nQPS2 kA
6 kA
9 kA
When Why
12 kA
Late 2008 Joints
1.18 TeV
DesignAll main magnets commissioned for 7TeV operation before installation
Detraining found when hardware commissioning sectors in 2008
o 5 TeV poses no problemo Difficult to exceed 6 TeV
Machine wide investigations following S34 incident showed problem with joints
Commissioning of new Quench Protection System (nQPS)
54
J. Wenninger LNF Spring School, May 2010
LHC energy target - way up
Train magnetso 6.5 TeV is within reacho 7 TeV will take time
Repair jointsComplete pressure relief system
Commission nQPS system
2014 ?
2010
Training
Joint repair
nQPS
When What
7 TeV
3.5 TeV
1.18 TeV
450 GeV
2011
2013
2009
6 TeV
55
J. Wenninger LNF Spring School, May 2010
Beam operation
56
J. Wenninger LNF Spring School, May 2010
Goals for 2010-2011
Repair of Sector 341.18TeV
nQPS6kA
3.5 TeVIsafe < I < 0.2 Inom
β* ~ 2 mIons
3.5 TeV~ 0.2 Inom
β* ~ 2 mIons
20092009 20102010 20112011
No Beam B Beam Beam
Ambitious goal for the run: collect 1 fm-1 of data/exp at 3.5 TeV/beam.
To achieve this goal the LHC must operate in 2011 with
L ~ 2×1032 Hz/cm2 ~ Tevatron Luminosity
which requires ~700 bunches of 1011 p/bunch(stored energy of ~ 30 MJ – 10% of nominal)
Implications:Strict and clean machine setup.Machine protection systems at near nominal performance.
β*inj β*
min
IP1 / IP5 11 m 2 m
IP2/IP8 10 m 2 m
IP5-TOTEM 11 m 90 m
Mininum β* in various IP’s
57
J. Wenninger LNF Spring School, May 2010
LHC schedule
58
Proton run until November.
Lead ion setup and run November and Decenber.
J. Wenninger LNF Spring School, May 2010 59
2010 commissioning milestones
27th Feb First injection
28th Feb Both beams circulating
5th March Canonical two beam operation
8th March Collimation setup at 450 GeV
12th March Ramp to 1.18 TeV
15th - 18th March Technical stop – dipoles magnets good for 3.5 TeV
19th March Ramp to 3.5 TeV
30th March First 3.5 TeV collisions in all experiments (media event)
4th - 5th April 19h-long physics fill with * 10/11 m - L ~ 1027 cm-2s-1
7th April *squeeze to 2 m in IP1 and IP5
24th April 30h-long physics fill with * of 2 m - L ~ 1.31028 cm-2s-1
J. Wenninger LNF Spring School, May 2010
LHC machine cycle
60
energy ramp
preparation and access
beam dump
injection phase
collisions
collisions
450 GeV
7 TeV
start of the ramp Squeeze
3.5 TeV
J. Wenninger LNF Spring School, May 2010
LHC cycle
61
Ramp-down/pre-cycle: 1 ½ - 2 hourso Depending on initial conditions, the magnets must either be ramped down (3.5 TeV
injection) or cycled (from access). Injection: > 15 minutes
o Probe beam: low intensity bunch (≤ 1010 p) that must be first injected when a ring is empty (safety !). Used to verify that beam parameters are OK for higher intensity.
o Nominal bunch sequence follows when beam parameters have been adjusted. Ramp: 40 minutes
o Machine energy is increase at constant optics (b-function) from 450 to 3.5 TeV. For the moment the ramp rate is limited to ~1 GeV/s.
o Ramp rate to nominal value ~5 GeV/s in June >> ramp will become a lot faster! Squeeze: ~30 minutes
o Injection * is larger (10 m in IR1/5, 11 m in IR2/8) because more aperture is needed to accommodate the larger beam emittance (triplet magnets).
o In the squeeze * is reduced to its nominal physics value (presently 2 m in all IRs). This implies gradient changes of most quadrupoles in the straight sections and first part of the arc.
J. Wenninger LNF Spring School, May 2010
Beam squeeze
62
10 m to 2 m10 m to 2 m
30 min 30 min
11 m to 2 m11 m to 2 m
Duration will soon be reduced to ~ 20 minutes
Duration will soon be reduced to ~ 20 minutes
J. Wenninger LNF Spring School, May 2010
How equal are the IPs?
63
The -function can be measured by exciting (shaking) the beams.
After correction of optics errors, the residual error is in a band of around +- 20% (specification).
>> * may vary from IP to IP by up to 20% !
Example of optics errors along the ring for * 2 m (beam1) Horizontal
Vertical
J. Wenninger LNF Spring School, May 2010
LHC cycle : physics
64
Stable beams: 10’s of hours and more…o Period with quiet running conditions for the experiments (with HV ON, etc).o Beam tuning activity reduced to the minimum (to keep good lifetimes…).o Collimators in fixed positions (they move during ramp and squeeze).o Note however that abrupt beam loss can occur in any phase due to powering
problems, cooling etc etc – even in stable beams. Experiments are protected by the collimators (shadowing), the LHC machine
protection system and by their own protection system (BCM : Beam Condition Monitors).
[1030 cm-2s-1]
J. Wenninger LNF Spring School, May 2010
Beam overlap
65
Because the beams circulate most of the time in different vacuum chambers, they also see slightly different magnetic fields.
>> no guarantee that they collide at the IP ! Small beam sizes !!
To optimize the beam overlap (hor. and vert. planes) the beams are scanned across one another until the peak luminosity if found (typical +- 2 sigma).
>> settings are quite reproducible – more experience needed.
J. Wenninger LNF Spring School, May 2010
Beam operation at 3.5 TeV
Luminosity (head on case, no crossing angle) :
**
2
4 yx
fkNL
The beam size s depends on * and on beam emittance n:
n** Everywhere in the ring the beam
size scales with 1/ ~ 1/E.
Aperture margins are reduced wrt 7 TeV !
The quench levels at 3.5 TeV are a factor ~10 higher wrt 7 TeV and the stored beam energy is lower: advantage in the early days.
J. Wenninger LNF Spring School, May 2010
Peak luminosity at 3.5 TeV A consequence of the small beam size at the IP (small *) is a large beam
size in the triplet magnets. The physical aperture in the triplet quadrupoles defines the minimum of *.
o Limits * to ~2 m at 3.5 TeV (instead of 0.5 m at 7 TeV)
Beam size * increase by: Factor 2 (‘naturally’ larger size)
Factor ~2 (* limit)
Luminosity loss wrt 7 TeV of: Factor ~22 per plane (*)
>> overall factor ~8
for same beam intensity
Lower limit on * (with crossing angle)
Present operating conditions(no crossing angle) @ 2 m
J. Wenninger LNF Spring School, May 2010
Intensity increase plan
68
Stage N (protons) k Stored E (kJ) Peak L (Hz cm-2)
3 fat pilots 1.00E+10 3 17 1.34E+28
4 bunches 2.00E+10 4 44.8 7.63E+28
4 bunches 5.00E+10 4 112.0 4.77E+29
8 bunches 5.00E+10 8 224.0 9.54E+29
4x4 bunches 5.00E+10 16 448.0 1.91E+30
8x4 bunches 5.00E+10 32 896.0 3.81E+30
43x43 5.00E+10 43 1204.0 5.13E+30
8 trains of 6 b 8.00E+10 48 2150.4 1.33E+31
50 ns trains 8.00E+10 96 4300.8 2.67E+31
Assumption:
* = 2 m
nominal
To gain experience with the machine protection system, 2 weeks of running time (~10 fills, 40 h of physics) must be integrated before proceeding to the next step.
Some steps require additional (machine protection) commissioning.
Present phase
Next step (coming days)
Beams become rather dangerous
J. Wenninger LNF Spring School, May 2010
Performance estimate
69
charm, D’s, J/Psicharm, D’s, J/Psi
Weak bosons (W, Z)Weak bosons (W, Z)
30.3 - 19.4 * 10m 1.1e10 p/bch
30.3 - 19.4 * 10m 1.1e10 p/bch
23.4 - ... * 2m 1.1e10 p/bch
23.4 - ... * 2m 1.1e10 p/bch
November 7November 7
4 coll pairs2e10 p/bch4 coll pairs2e10 p/bch
Apr 23Apr 23
4 coll pairs5e10 p/bch4 coll pairs5e10 p/bch
If all goes well, we could reach
L 1032 cm-2s-1
by November!
J. Wenninger LNF Spring School, May 2010
Integrated luminosity projections
70
If maintain the high availability 100 pb-1 could be integrated
until November
Apr 23Apr 23
Apr 23Apr 23
J. Wenninger LNF Spring School, May 2010
LHC operation today
71
So far LHC operation is amazingly stable and efficient (we are still in commissioning !!).
But we are working with ‘tiny’ beams (on the nominal LHC scale).
In physics at the moment:
* = 2 m at IPs * 45 m
N 1.81010 p/bunch k = 2 bunches
1 colliding pair / IP L 1.31028 cm-2s-1
The next step in intensity is most likely:
N 41010 p/bunch k = 2 bunches
1 colliding pair / IP L 6.81028 cm-2s-1
We have been able to collide bunches with nominal population (N = 1011) at 450 GeV: this is a good omen for 3.5 TeV (cross fingers…)
o We may be able to push luminosity faster than anticipated (L N2)
J. Wenninger LNF Spring School, May 2010
To observe the LHC
72
http://op-webtools.web.cern.ch/op-webtools/vistar/vistars.php?usr=LHC1
J. Wenninger LNF Spring School, May 2010
Outlook
73
The LHC beam commissioning has been progressing smoothly and rapidly so far – even we are sometimes surprised !!
o But the LHC remains a very complex machine, so far we operate under rather simple conditions.
The problem of the LHC: to reach ‚interesting‘ luminosities we must store very dangerous beams at a very early stage of the commissioning.
o We have little operational experience.
o We are still consolidating beam control software, debugging systems...
o We must be sure that they are no unexpected flaws in the machine protection system (or totally unexpected situations).
>> for this reason we increase the intensity/L in rather modest steps.
Assuming there are no surprises, and once we have passed the main hurdle of the initial machine protection commissioning (soon !), progress should be faster:
>> so far the target of 1031 – 1032 cm-2s-1 by November is within reach !
J. Wenninger LNF Spring School, May 2010
From darkness… …to light
74
Sept 2008
April 2010