ISIS operational update
David FindlayAccelerator DivisionISIS DepartmentRutherford Appleton Laboratory / STFC
DL-RAL Joint Accelerator Workshop, RAL20–21 January 2009
2
ISIS Second Target Station now operational
3
ISIS Second Target Station now operational
70 MeV H– linac
800 MeV proton synchrotronTS-1
4
ISIS Second Target Station now operational
70 MeV H– linac
800 MeV proton synchrotronTS-1
5
Dec. 2007: first protons to TS-2
Aug. 2008: first neutrons from TS-2
First beam — 340 V double pulse into 25 ohms1 hour 17 minutes to get beam from synchrotron to TS-2
First neutrons
7
Spallation neutron sources:
for investigating structure and dynamics of molecular matter
Currently operating spallation neutron sources:
PSI (Villigen, Switzerland)
SNS (Oak Ridge)
ISIS (RAL, Oxon.)
LANSCE (Los Alamos)
J-PARC (Tokai-mura)
Decreasing power
Guinness Book of Records — can no longer show this photo
9
ISIS — world’s most productive spallation neutron facility
ISISJ-PARC, LANSCE, PSI, SNS
ISIS: 800 MeV protons on to tungsten targets, 0.2 MW
TS-1, 0.16 MW, 40 pps; TS-2, 0.04 MW, 10 pps
~800 neutron experiments per year
~1600 visitors/year (~5000 visits)
ISIS accelerators wholly for neutron factories
Also muon factory
Decreasing number of target stations
Rutherford Appleton Laboratory, looking north
ISIS Diamond
Rutherford Appleton Laboratory, looking north-east
ISIS
70 MeV H– linac
800 MeV proton synchrotron
TS-1
ISIS from air
View down north side of ISIS 70 MeV H– MeV linac
Inside Tank 1
Inside Tank 4
Tanks 2 and 3 — built in 1954
Superperiods 9, 0 and 1 of the ISIS 800 MeV synchrotron
1RF cavity 9
2RF cavity 6
MICE pion beam line in synchrotron
room
ISIS TS-1 experimental hall
ISIS TS-2 experimental hall
Proton beam line EPB2 to TS-2 — 1
Proton beam line EPB2 to TS-2 — 2
Proton beam line EPB2 to TS-2 — 3
Overall target system schematic — 1
Overall target system schematic — 2
Target in operational position
Target withdrawn into remote handling cell
Target, reflectors and moderator assembly
TS-2 tungsten target, tantalum coated, heavy water cooling
Solid tungsten cylinder, tantalum coated, surface cooled, 68 mm dia., 307 mm long — exploded view
Moderators
Reflector
Target, reflectors and moderator assembly — 2
Solid methane moderators — containing aluminium foam for heat
conduction
Target services trolley — 1
Target services trolley — 2
35
TS-2 optimised for cold neutrons
Long wavelengths, big molecules
TS-2 runs at 10 pps — 100 ms between pulses
10 pps stolen from 50 pps from synchrotron
Only 40 pps left for TS-1
Beam current × 50/40
Dual harmonic RF — JWGT later
Commissioning TS-2
Difficult while running full programme to TS-1
Also CDM restrictions
36
ISIS 70 MeV H– linac 0.2 MW + 800 MeV H+ synchrotron
J-PARC 180 MeV H– linac 0.2 MW1
+ 3 GeV + 50 GeV synchrotrons
LANSCE 800 MeV H+ /H– linac 0.8 MW + accumulator ring
PSI 590 MeV cyclotron 1.2 MW + 72 MeV injector cyclotron
SNS 1 GeV H– linac 0.6 MW2
+ accumulator ring
1: For limited time during commissioning; ultimate design 1 MW with 400 MeV linac.
2: Still commissioning; 1 MW design operation.
J-PARC
LANSCE
PSI — Villigen, Switzerland
PSI cyclotron
PSI target station
SNS — Oak Ridge
45
Trip rates / High power proton accelerators
0.01
0.1
1
10
100
1000
0.1 1 10 100 1000 10000 100000 1000000
Trip length (seconds)
Tri
ps
pe
r d
ay
lo
ng
er
tha
n t
rip
le
ng
th
ISIS
LANSCE
PSI
SNS
2/3 power law
46
Other accelerator work
H– ion sources
Front ends
DHRF, ring R&D
ISIS upgrades
Electrical engineering
Letchford
Thomason
Glover
47