Inventory Optimization Report Final

download Inventory Optimization Report Final

of 20

Transcript of Inventory Optimization Report Final

  • 7/31/2019 Inventory Optimization Report Final

    1/20

    1

    1

    CPE Inventory Optimization Project

    July 30, 2008Javier Sanchez

  • 7/31/2019 Inventory Optimization Report Final

    2/20

    2

    2

    Inventory Optimization Report

    Points of Discussion

    Definition of the Problem

    Root Causes

    Current Process Map

    Improvement Opportunities

    Suggestions for opportunities found

    Financial Benefits

  • 7/31/2019 Inventory Optimization Report Final

    3/20

    3

    3

    Problem Definition

    Shipping costs in May increased $61k due toexcessive overnight shipments of CPE

    Stock requirement analysis is manual, timeconsuming, and cumbersome

    Suspect we may retain excessive stock in some

    products (See Annex # 2 for Details)

  • 7/31/2019 Inventory Optimization Report Final

    4/20

    4

    4

    Root Causes

    Shipping costs in May increased $61k due to excessive overnight

    shipments of CPE Stock-out due to:

    > Delay in approving PO

    > Delay from Vendor in getting the PO in their system

    > Delay in normal vendor shipping time frame

    Re-Stocking analysis is manual, time consuming, and cumbersome Systems provide pieces of data that must be manually manipulated in

    Excel to obtain:

    > Field shipment orders

    > Stock replenishment quantity

    Suspect we may retain excessive stock Lack of generally accepted stocking methodology to manage stock

  • 7/31/2019 Inventory Optimization Report Final

    5/20

    5

    5

    Start

    InventoryInformation Systems

    Inventory Gets the reportOf products needed for

    two week period

    SalesSales Person enter

    info. on MSS

    Inv. Ships the productto Market Site

    Inventory depletes stockfrom Warehouse Using

    the Replenishment System

    Inv. Package the Product

    Market Sites Receiveequipment

    Distribution to differentsites

    Market Sites enters equipment intoMSS as equipment Available

    Sites Receive OrdersTo install equipmentField Tech. Change MSS

    Equipment from Available to In Service

    Field Tech. Goes and InstallEquipment Field Tech. Deletes Equipment

    From MSS.

    Nuvox Bills the customer

    $

    Nuvox Bank

    RICH PICTURE OFINVENTORY SYSTEM

    (System # 1 )

    Sub- System 2

    Sub System# 3

    Current Process High Level

  • 7/31/2019 Inventory Optimization Report Final

    6/20

    6

    6

    Current Process

    INVENTORY HANDLING PROCESS

    Inventory goesto MSS and pullReports in order

    to find what'sneeded to be

    shipped tomarket sites

    Not Installed Report(NIR)

    TSP ScheduleDrillable Report

    Installed YTD Report(IR)

    Cleaning Reports

    Combine all TSP Reportsinto one

    Called Total TSP

    Conbine Total TSP intoNIR

    Combine IR into NIR

    Rename NIR to CPESummary Report

    CPESummaryReport issent to

    warehouseElectronically

    Warehouseverifies reportwith currentinventory(Manually)

    Warehouseprepares

    material to beshipped

    WarehousecreatesPOs of

    inventorythat will beshipped.

    Warehouseships the

    product/s tomarketsites

    Marketsites

    receiveequipmentand enter it

    into thesystem

    Financialreceives

    POs

    electronically

    POs

    approved?

    Yes

    No

    Request ofinstallation isneeded andMarket site

    assigns serial #to customer POand change theclassifications

    Market siteinstalls

    equipment

    FieldTechnicianreturn to thesystem anddelete partfrom thesystem.

    End

    Warehousereceives

    confirmationelectronically

    Warehousefax the POs

    to Supplier

    SupplierreceivesPOs and

    send back aconfirmationemail with

    delivery time

    Supplierprepares

    and sendsequipment

    Warehousereceives

    equipmentand store it

    Warehousekeeps

    copies ofopen POs

    Confirmationnotice is store

    on thecorresponding

    Open PO

    Warehouseattached

    closes thePO with the

    receiverfrom

    supplier.

    End

    Delay Process

    3 .1 .5 2 40 1 .5 3 .25

    .5 .25 40 .1 .25 40 160 2

    50.35hours/6.3 Days

    261.72hours/32.71

    Days

    Non Valueactivities

    Chance forImprovement

    Non Value, but notaffecting the

    process

    NVA= 3TNVA=3

    VA=0TVA=0

    NVA= 1.5TNVA=247.1

    VA=.5TVA=1.6

    NVA= 160TNVA=245.6

    VA=0TVA=1.1

    NVA= 40TNVA=85.6

    VA=0TVA=1.1

    NVA= 0TNVA=45.6

    VA=.25TVA=1.1

    NVA= 40TNVA=45.5

    VA=0TVA=.85

    NVA= .25TNVA=5.5

    VA=0TVA=.85

    NVA= .1TNVA=45.6

    VA=0TVA=.85

    NVA= 1.75TNVA=5.25

    VA=.75TVA=.85

    NVA= .5TNVA=3.5

    VA=0TVA=.1

    NVA= 0TNVA=3VA=.1TVA=.1

  • 7/31/2019 Inventory Optimization Report Final

    7/20

    77

    Improvement Opportunities

    Less Regimented PO approval process

    Automatic re-stocking analysis

    Utilize bar code scanners to integrate withinventory system

    Decrease supplier lead time

  • 7/31/2019 Inventory Optimization Report Final

    8/20

    88

    Improvement Actions

    Develop fully automated daily report to provide re-stock amounts and field shipping details. Field Shipping detail:

    > Order #> CLLI> TSP Date> Market> Equipment

    Re-Stock Amounts> Part Number> Quantity

    .

    Develop process to incorporate scanning devices to place inventory data into inventory system.

    Enhance CPE approval process. Provide Harold with unilateral authority to replenish stock to system-driven stock level Generate daily/weekly reports to advise executive management of capital commitment Special capital purchase circumstances, such as TitleMax, will be handled ICB

    Pursue new vendor supply strategy to reduce lead time to delivery. Vendor retain 2 months of stock on hand Commit to next day shipping Will probably have to guarantee payment for on hand stocked items

  • 7/31/2019 Inventory Optimization Report Final

    9/20

    99

    New Process

    Sub-System # 3

    Start

    Inv. Goes to the

    System and gets areport of what is

    needed to ship forthe market sites

    Inv. Open the R.S.

    model 100004-LG-XX and goes to

    the Data BaseSheet.

    On the Data Base,

    update what isgoing to be

    shipped as out ofstock.

    Verify each

    product on theupdatable

    demand sheet

    Does the productsays order Now

    Create a PO for

    what is indicatedto order on the

    Updatable

    Demand Sheet

    Save thedocument and exit.

    No

    Yes

    Fax PO to VendorAnd notify

    Financial ofpurchases made.

    Monitor POs for

    fast delivery.

    ReceivedEquipment using

    Bar Code andstore it.

    Update R.S onData Base Sheet

    End

    NOTES:

    RECONCILIATION AND DEMAND MUST BEMONITORED ON A DAILY BASES

  • 7/31/2019 Inventory Optimization Report Final

    10/20

    1010

    Mathematical Model

  • 7/31/2019 Inventory Optimization Report Final

    11/20

    1111

    Daily Data Base

  • 7/31/2019 Inventory Optimization Report Final

    12/20

    1212

    Updatable Demand

  • 7/31/2019 Inventory Optimization Report Final

    13/20

    1313

    Financial Benefits

  • 7/31/2019 Inventory Optimization Report Final

    14/20

    1414

    Financial Benefits 1 Day

  • 7/31/2019 Inventory Optimization Report Final

    15/20

    1515

    Financial Benefits 5 Days

  • 7/31/2019 Inventory Optimization Report Final

    16/20

    1616

    Example of Calculation

    Note:There is potential of 10 Extra Days of Savings if we negotiate a win winstrategy with our supplier.

    Potential Savings off an additional $468,994

    Based on the 16 CPE productssavings are:

    One Day= $46,630

    5 Days= $233,703

  • 7/31/2019 Inventory Optimization Report Final

    17/20

    1717

    Annex 1

    ABC Classification

    $0

    $500,000

    $1,000,000

    $1,500,000

    $2,000,000

    $2,500,000

    $3,000,000

    $3,500,000

    $4,000,000

    2431-16 2431-8 2432-24 2431-T1E1 VWIC-1MFT-T1 VWIC-2MFT-T1 2821 PVDM2-64 3845

    Products

    2007/2008

    UnitCost

    0

    20

    40

    60

    80

    100

    120

    Items

    Accumulative %

  • 7/31/2019 Inventory Optimization Report Final

    18/20

    1818

    Summary

    Enhance PO approval process

    Immediate one-time savings of $233,703

    Automate Field distribution reporting Eliminate manual labor increasing accuracy

    Automate the re-stock analysis system

    Immediate one-time savings of $326,180~ Optimizes stock levels Minimizes capital commitment

    Potentially decrease supplier lead time Additional potential savings of $ 468,994

  • 7/31/2019 Inventory Optimization Report Final

    19/20

    1919

    Annex # 2

  • 7/31/2019 Inventory Optimization Report Final

    20/20

    2020

    0

    200

    400

    600

    800

    1000

    1200

    2431-8 2431-

    T1E1

    2821 VWIC-

    1MFT-

    T1

    PV

    DM2-64

    NM-

    1T3/E3

    VIC2-

    2FXS

    VIC2-

    4FXS

    HN-

    404-

    CP-1E-I

    MinInv based on lead time/product

    Current Inventory

    Annex # 3 Current Inventory Levels