Integer Linear Programming (ILP) Prof KG Satheesh Kumar Asian School of Business.
-
Upload
elijah-reynolds -
Category
Documents
-
view
217 -
download
0
Transcript of Integer Linear Programming (ILP) Prof KG Satheesh Kumar Asian School of Business.
Integer Linear Programming (ILP)
Prof KG Satheesh Kumar
Asian School of Business
Types of ILP Models
ILP:
A linear program in which some or all variables are restricted to integer values.
Types: 1. All-integer LP or a pure ILP
2. Mixed-Integer LP
3. 0-1 integer LP
An All-Integer IP or Pure ILP
Maximise 2 x1 + 3 x2
Subject to
3 x1 + 2 x2 ≤ 12
¼ x1 + 1 x2 ≤ 4
1 x1 + 2 x2 ≤ 6
x1, x2 ≥ 0 and integer
Illustration of All-Integer LP
Sweeny: Eastborne Reality is considering investing in townhouses (T) and apartments(A). Determine the number of T’s and A’s to be purchased. (Integers)
Funds available: $2 million.Cost: $282k per T and $400k per ANumbers available: 5 T’s and any number of A’s.
Management time available: 140 h/moTime needed: 4 hrs/mo for T and 40 h/mo for A.
Contribution: $10k for T and $15k for A.
Sweeny Eastborne: ILP Model
Maximise 10T + 15A
Subject to: 282T + 400A ≤ 2000
4T + 40A ≤ 140
T ≤ 5
T, A ≥ 0 and integer
Sweeny Eastborne Relaxed LP: Rounded Solution
If we relax the integer restriction, the optimum solution is
T=2.48, A = 3.25, Z = 73.57This is not acceptable because townhouses and
apartments cannot be purchased in fractions!
Rounding down gives integer solution with T = 2, A = 3 and Z = 65
Such rounding down may sometimes yield an optimum solution, but one cannot be sure!
Sweeny Eastborne ILPOptimal Integer Solution
The optimal solution is T = 4, A = 2, Z = 70 and not the rounded-down solution which
gives Z = 65.
ILP Algorithms
The ILP algorithms are based on exploiting the tremendous computational success of LP. The strategy involves three steps:
1. Relax the ILP: Remove integer restrictions; replace any binary variable y with continuous range 0 y 1.
2. Solve the relaxed LP as a regular LP.
3. Starting with the relaxed optimum, add constraints that iteratively modify the solution space to satisfy the integer requirements.
B&B and Cutting Plane Methods
The two commonly used methods are:
1. Branch and bound method
2. Cutting Plane Method
Neither method is consistently effective; but B&B is far more successful.
Branch-and-Bound (B&B)
• Developed in 1960 by A Land and G Doig
• Relax the integer restrictions in the problem and solve it as a regular LP. Let’s call this LP0 (to imply node-zero LP)
• Test if integer requirements are met. Else branch to get sub-problems LP1 and LP2.
Branching
• If LP0 (in general LPi) fails to yield integer solution, branch on any variable that fails to meet this requirement. The process of branching is illustrated below.
If LPi yields x1 = 3.5 and x1 is taken as the branching variable, we get two sub-problems, LPi+1 = LPi & (x1 3) and LPi+2 = LPi & (x1 4).
Note: In mixed integer problems, a continuous variable is never selected for branching.
Bounding / Fathoming
• Select LP1 (in general LPi) and solve. Three conditions arise.
– Infeasible solution, declare fathomed (no further investigation of LPi).
– Integer solution. If it is superior to the current best
solution update the current best. Declare fathomed.
– Non-integer solution. If it is inferior to the current best, declare fathomed. Else branch again.
Best Bound
• In maximisation, the solution to a sub-problem is superior if it raises the current lower bound.
• In minimisation, the solution to a sub-problem is superior if it lowers the current upper bound.
• When all sub-problems have been fathomed, stop. The current bound is the best bound.
B&B Tree for Eastborne
LP0 T = 2.48, A = 3.25, Z = 73.57
Non-integer, non-inferior to current best, branch on T
LP1 = LP0 & T ≤ 2 T = 2, A = 3.3, Z = 69.5
Non-integer, can’t give better solution than LP5, fathomed
LP2 = LP0 & T ≥ 3 T = 3, A = 2.89 Z = 73.28 Non-integer, non-inferior to current best, branch on A
LP3 = LP0 & T ≥ 3 & A ≤ 2 T = 4.26, A = 2, Z = 72.55 Non-integer, non-inferior to current best, branch on T
LP4 = LP0 & T ≥ 3 & A ≥ 3
Infeasible, fathomed
LP5 = LP0 & T [3,4] & A ≤ 2 T = 4, A = 2, Z = 70
Integer, Lower (best) bound
LP6 = LP0 & T ≥ 5 & A ≤ 2 T = 5, A = 1.48, Z = 72.13 Can’t give better solution than LP5, fathomed
Note: Z is a multiple of 5 and hence only Z ≥ 75 can be better than z = 70
LP2 = LP0 & T ≥ 3
T = 3, A = 2.89 Z = 73.28
Non-integer, non-inferior to current best, branch on A
LP1 = LP0 & T ≤ 2
T = 2, A = 3.3, Z = 69.5
Non-integer, can’t give better solution than LP5, fathomed
LP0
T = 2.48, A = 3.25, Z = 73.57
Non-integer, non-inferior to current best, branch on T
LP4 = LP0 & T ≥ 3 & A ≥ 3Infeasible, fathomed
LP3 = LP0 & T ≥ 3 & A ≤ 2
T = 4.26, A = 2, Z = 72.55
Non-integer, non-inferior to current best, branch on T
LP6 = LP0 & T ≥ 5 & A ≤ 2
T = 5, A = 1.48, Z = 72.13
Can’t give better solution than LP5, fathomed
LP5 = LP0 & T [3,4] & A ≤ 2
T = 4, A = 2, Z = 70
Integer, Lower (best) bound
See more illustrations of Branch-and-Bound
algorithm in the Excel sheet
0-1 Integer LP
“0 -1” decision variables are used in problems where an Yes-No decision is to be taken regarding multiple choices.
If the variable is 1, the corresponding choice is selected; if the variable is 0, it is not selected.
0-1 ILP: Capital BudgetingFive projects are being evaluated over a three year planning horizon. The table gives the expected returns for each project and associated yearly expenditures. Which project should be selected over the 3-year horizon?
Expenditure in million $/year Returns, million $
Project Year 1 Year 2 Year 3
1 5 1 8 20
2 4 7 10 40
3 3 9 2 20
4 7 4 1 15
5 8 6 10 30
Available funds, million $
25 25 25
0-1 ILP Model
Maximise: 20 P1 + 40 P2 + 20 P3 + 15 P4 + 30 P5
subject to:
5 P1 + 4 P2 + 3 P3 + 7 P4 + 8 P5 <= 25
1 P1 + 7 P2 + 9 P3 + 4 P4 + 6 P5 <= 25
8 P1 + 10 P2 + 2 P3 + 1 P4 + 10 P5 <= 25
P1, P2, P3, P4, P5 = [0,1]
The Ice –Cold refrigerator Company is considering investing in several projects that have varying capital requirements over the next 4 years. Faced with limited capital each year, management would like to select the most profitable projects. The estimated net present value for each project, the capital requirements, and the available capacity over the four year period are shown:
Projects
Plant expansion
Warehouse expansion
New
Machinery
New product research
Total capital available
Present value 90000 40000 10000 37000
Yr1 15000 10000 10000 15000 40000
Yr2 20000 15000 10000 50000
Yr3 20000 20000 10000 40000
yr4 15000 5000 4000 10000 35000
Fixed Cost
Three raw materials are used for a company to produce three products: a fuel additive, a solvent base, a carpet cleaning. The profit contribution are $40 per ton for the fuel additive, $30 per ton for the solvent base, and $50 per ton for the cleaning fluid. Each ton of fuel additive is a blend of 0.4 tons of material 1 and 0.6 tons of material 3. Each ton of solvent base is a blend of 0.5 of material 1, 0.2 of material 2, 0.3 of material 3, Each ton of carpet cleaning fluid is a blend of 0.6 of material 1, 0.1 of material 2, 0.3 of material 3.
F = tons of fuel additive usedS = tons of solvent base usedC = tons of carpet cleaning used. Max 40F+30S+50Cs.t. 0.4F+0.5S+0.6C<=20 0.2S+0.1C<=5 0.6F+0.3S+0.3C<=21 F,S,C>=0
product Set up cost Maximum
Production
Fuel additive $200 50 tons
Solvent base $50 25 tons
Carpet cleaning fluid
$400 40 tons
SF = 1 if fuel additive is produced ,0 elseSS = 1 if fuel additive is produced ,0 elseSC = 1 if fuel additive is produced ,0 else
Max 40F+30S+50C-200SF-50SS-400SC (net profit)s.t . F<=50SF or F-50SF <=0 Maximum F S<=25SS or S-25SS <=0 Maximum S C<=40SC or C-40SC <=0 Maximum C
Distribution Systems Design
The Martin-Beck Company operates a plant in
St. Louis with an annual capacity of 30,000 units. Product is shipped to regional centers located in Boston, Atlanta, Houston. Bcos of an anticipated increase in demand, Martin-Beck plans to increase the capacity by constructing a new plant in one or more of the following cities : Detroit, Toledo, Denver or Kansas City. The estimated annual fixed cost and the annual capacity for the 4 proposed plants is as follows:
Proposed plant Annual fixed cost
Annual Capacity
Detroit 175000 10000
Toledo 300000 20000
Denver 375000 30000
Kansas city 500000 40000
Annual Demand of the Distribution Centers:
Distribution Centers Annual Demand
Boston 30000
Atlanta 20000
Houston 20000
Plant size Boston Atlanta Houston
Detroit 5 2 3
Toledo 4 3 2
Denver 9 7 5
Kansas city 10 4 2
St.louis 8 4 3
Max:5x11+2x12+3x13+4x21+3x22+4x23+9x31+7x32+5x33+10x
41+4x42+2x43+8x51+4x52+3x53+175y1+300y2+375y3+500y4
y1=1 if a plant is constructed in Detroit, 0 else y2=1 if a plant is constructed in Toledo, 0 else
y3=1 if a plant is constructed in Denver, 0 else y4=1 if a plant is constructed in Kansas city, 0 else
s.t. x11+x12+x13<=10y1 or x11+x12+x13-10y1<=0
x21+x22+x23<=20y1 or x21+x22+x23-20y1
x31+x32+x33<=30y1 or x31+x32+x33-30y1
x41+x42+x43<=40y1 or x41+x42+x43-40y1
x51+x52+x53<=30
x11+x21+x31+x41+x51=30
x12+x22+x32+x42+x52=20
x13+x23+x33+x43+x53=20
Branch Location
• The long-range planning department for the Ohio Trust Company is considering expanding its operation into a 20-county region in NE Ohio. Currently, Ohio Trust does not have a principal place of business in any of the 20 counties. According to the banking laws in Ohio, if a bank establishes a principal place of business (PPB) in any county, branch banks can be estd in that county and in any adjacent county. However, to establish a new PPB, Ohio Trust must either obtain approval for a new bank from the state’s superintendent of banks or purchase an existing bank.
COUNTIES IN THE OHIO TRUST EXPANSION REGION
COUNTIES UNDER CONSIDERATION ADJACENT COUNTIES
1 Ashtabula 2,12,16
2 Lake 1,3,12
3 Cuyahoga 2,4,9,10,12,13
4 Lorain 3,5,7,9
5 Huron 4,6,7
6 Richland 5,7,17
7 Ashland 4,5,6,8,9,17,18
8 Wayne 7,9,10,11,18
9 Medina 3,4,7,8,10
10 Summit 3,8,9,11,12,13
11 Stark 8,10,13,14,15,18,19,20
12 Geauga 1,2,3,10,13,16
13 portage 3,10,11,12,15,16
14 Columbians 11,15,20
15 Mahoning 11,13,14,16
16 Trumbull 1,12,13,15
17 Knox 6,7,18
18 Holmes 7,8,11,17,19
19 Tuscarawas 11,18,20
20 Carroll 11,14,19
• Decision variables Let xi= 1 if a PBB is estd in county i; 0 otherwise
• Objective Function Minimise: Z= x1+x2+x3.,.,.x20
• Subject to: x1 + x2 + x12 + x16 >= 1 (Ashtabula)
x1 + x2 + x3 + x12 >= 1 (Lake) .,.,,.,.,.,(20 constraints)
• Non-negativity Xi = 0,1 i = 1,2,.,., 20
See more illustrations of
0-1 ILP
and solution using
Excel Solver
Reference
• Hamdy A Taha, “Operations Research: An Introduction”; Pearson
• Anderson, Sweeny and Williams, “An Introduction to Management Science”; Thomson
Thank you for listening