Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review

19
Extraction Michael Bevins May 17, 2007 12GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review

description

12GeV Upgrade - Beam Transport. Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review. Extraction Michael Bevins May 17, 2007. Outline. Introduction & Scope Requirements & Specifications New/Modified Extraction Elements/Girder Count Beam Transport Layouts - PowerPoint PPT Presentation

Transcript of Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review

Page 1: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction

Michael BevinsMay 17, 2007

12GeV Upgrade - Beam Transport

Injection, Linac, Extraction, & Correctors

Preliminary Design and Safety Review

Page 2: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Outline

• Introduction & Scope• Requirements & Specifications• New/Modified Extraction Elements/Girder Count• Beam Transport Layouts• Safety Considerations• Cost Estimates• Risk Assessment• Summary

Page 3: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Introduction & Scope• The extraction region must be upgraded to support

transport of higher energy beam to halls A, B, & C and 5th pass beam to the new arc 10 to support 12GeV operations

• Songsheet level machine layouts will be presented along with cost estimates

Extraction Region

Page 4: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Requirements & Specifications • Alignment specs

– Quads & dipoles positioned to +/-0.5mm in x & y, +/- 1.0mm in z• Vacuum specs

– Beam line partial pressure of hydrogen <10-6 torr– Total average pressure of all other constituents less than 5x10-7 torr

• Fabrication, welding, cleaning & handling, and leak checking specs still apply – 22631-S-001 Fabrication of Ultra-High Vacuum Equipment– 22632-S-001 Cleaning and Handling of U.H.V. Components– 22633-S-001 Welding Specification For U.H.V. Components– 22634-S-001 Helium Leak Test For U.H.V. Components – Note an update and modernization of our vacuum specs is underway

Page 5: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

New/Modified Extraction Elements/Girder Count

• Preliminary - pending CASA review and more detailed vacuum study

Element Qty Element QtyQuads 4 Diagnostics

QB 1 BPM 5QC 3 Harp 1

Correctors 6 Viewer 1BM Horizontal 3 VacuumBM Vertical 3 Ion Pump 10

Dipoles 7 Beam Valves 1BP 7 Roughing Valve 5

Septa 7YA 4YR 3

RF Separators 5

QtyNew Quad Girders 3

Double Quad Girders 1QB/QC 1

Single Quad Girders 2QC 2

• Elements in red are part of I&C WBS

Page 6: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Beam Transport Layout - Extraction

Page 7: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – RF Separators

12GeV Configuration

Current Configuration

Relocated

New

Two new pedestal stands

Existing supports

New quad girder

New double quad girder

Page 8: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – RF Separators

Page 9: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – Septa Magnet Stacks

12GeV Configuration

Current Configuration

Relocated

New

Two new pedestal stands YA Septa Stacks YB/YR Septa Stack

New quad girder

Two YBs

Three YRs

One relocated and one new support stand

Two new support stands

Page 10: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – Septa Magnet Stacks

Existing YA Septa Stack Existing YB Septa Stack

Page 11: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – Dipole Magnet Stacks

12GeV Configuration

Current Configuration

New Two new support stands

New BP Dipole Stack

Three BPs

Page 12: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – Dipole Magnet Stacks

12GeV Configuration

Current Configuration

New

Page 13: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – Dipole Magnet Stacks

New

New support stand

BQ/BP Dipole Stack

Three new BPs

12GeV Configuration

New pedestal for 5th pass BP downbeam support

Two existing BQs

BP Dipole Stack

New BP

Two new pedestal supports for 5th pass BP

Page 14: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Extraction Layouts – Dipole Magnet Stacks

Existing BP Dipole Stack Existing BQ Dipole Stack

BP Stack BQ Stack

Page 15: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Safety Considerations

• Personnel Training– Jlab & sub-contractor

• Radiation– Designated areas for containment and radiation survey

of material that will be removed from the tunnel• Material handling

– Provide provisions for lifting• Electrical Hazards

– Package and support electronics, power leads and terminal blocks to control electrical hazards

Page 16: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Cost Estimates –Extraction WBS Rollup

WBS Elements I have covered today

D/PM & J Material

1.3.5 EXTRACTION 38.9 12.8 65.0 114.0 21.1 465.7 122.8 45.0 0.0 4.0

1.3.5.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.01.3.5.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.01.3.5.4 LAMBERTSON 12.9 4.0 6.4 23.3 5.4 43.2 10.0 6.0 0.0 4.01.3.5.5 CHICANE 20.6 8.1 4.0 32.7 8.1 350.9 94.3 39.0 0.0 0.01.3.5.6 STANDS 5.4 0.7 54.6 58.0 7.6 71.6 18.6 0.0 0.0 0.0

TotalContingency

Total Contingency

LABOR [Man Wks] PROCUREMENTS [$k] EXPENSES [$k]

WBS ELEMENT ME MD MT Total Contingency

*

* Septa and dipole vacuum chambers

Page 17: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Cost Estimates - Highlighted WBS

Stands - Procurements

WBS ELEMENT /Activity ID ACTIVITY DEFINITION / SCOPE ITEMS Basis D/PM J D/PM & J

Total [$k]1.3.5.6 STANDS 71.6 18.6

3 Proc Stands Matls (Stands) 11.3 3.2m Procure brackets to support (2) YAs rotated 90 degrees 800 2 1.6 eng jud 0.35 0.6m Procure brackets to support new YBs in YB/YR stack 800 2 1.6 eng jud 0.35 0.6m Procure brackets to support new YRs in YB/YR stack 1500 3 4.5 eng jud 0.35 1.6

mProcure alignment cartridges for (5) new BPs, (1) RF sep, & (2) YAs 150 24 3.6 eng jud 0.15 0.5

5 Fab Stands (Stands) 47.8 12.0m Procure pedestal stands for RF seperators 900 2 1.8 eng jud 0.25 0.5m Procure pedestal stand for new 5th pass YA 900 1 0.9 eng jud 0.25 0.2

mProcure vertical spt stands and floor and ceiling plates for new YA stack 5360 2 10.7 eng jud 0.25 2.7

mProcure vertical spt stands and floor and ceiling plates for YB/YR stack 5360 2 10.7 eng jud 0.25 2.7

mProcure vertical spt stands and floor and ceiling plates to replace upbeam stand at MQXXA01 5360 1 5.4 eng jud 0.25 1.3

mProcure pedestal style spt stands for 5th pass BP under existing BP stack 750 2 1.5 eng jud 0.25 0.4

mProcure vertical spt stands and floor and ceiling plates for new BP stack 5360 2 10.7 eng jud 0.25 2.7

mProcure vertical spt stands and floor and ceiling plates for upstream support of new 3rd, 4th, &5th pass BPs 5360 1 5.4 eng jud 0.25 1.3

mProcure pedestal style spt stand for downbeam end of 5th pass BP in BP/BQ stack 750 1 0.8 eng jud 0.25 0.2

7 Install RF Separators, Septa & Dipoles (Stands) 8.5 3.0m Procure beamline drifts, bellows,flgs for modified tubes etc. 5000 1 5.0 eng jud 0.35 1.8m Procure CF flange pair gaskets & hardware 3500 1 3.5 eng jud 0.35 1.2

ContingencyQTY Total

[$k]

PROCUREMENTS

Unit Cost [$]

Page 18: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Risk Assessment

• Technical - Low– Girders & Supports – very similar designs exist and are

already proven– Vacuum - existing designs already proven, detailed

vacuum analysis TBD– Alignment - same as existing machine

• Procurement Schedule - Low– No long-lead items identified

• Cost – Low– Good cost estimates for machined parts

• Vendor & Jlab shop budgetary estimates

Page 19: Injection, Linac, Extraction, & Correctors  Preliminary Design and Safety Review

Summary

• Preliminary extraction beam transport layouts and cost and installation estimates are complete based on present scope

• We are in a good position to support our DOE External Project Reviews this summer

• We will continue to work closely with our friends throughout the lab (safety, CASA, installation, vacuum, alignment, RadCon, I&C, magnet measurement, operations, procurement & facilities) as we move forward

• Detailed design will be completed to support assembly and installation schedules

• We look forward to comments & recommendations from the committee