INDUSTRY BRIEFING #2

76
INDUSTRY BRIEFING #2 LARRAKEYAH DEFENCE PRECINCT REDEVELOPMENT PROGRAM (LDPRP)

Transcript of INDUSTRY BRIEFING #2

Page 1: INDUSTRY BRIEFING #2

INDUSTRY BRIEFING #2

LARRAKEYAH DEFENCE PRECINCT REDEVELOPMENT PROGRAM

(LDPRP)

Page 2: INDUSTRY BRIEFING #2

2

Industry Briefing – Acknowledgement of Country

I respectfully acknowledge the past and present Traditional Custodians ofthis land on which we are meeting, the Larrakiapeople. It is aprivilege to be standing on Larrakia country.

Page 3: INDUSTRY BRIEFING #2

3

Industry Briefing - Introduction

• Introductions & Acknowledgement of Country Steve Shenfield, Laing O’Rourke Construction Manager

• Department of Defence Commentary Maj Anneke Jamieson

• Project Scope & Programme Graeme Maclean, Laing O’Rourke Project Director

• Safety Differently Winnie Robertson, Laing O’Rourke Next Gear Champion

• Procurement Alex Panomarenko, Laing O’Rourke Procurement Lead

• ICN Charmaine Barrett, ICN

• ABCC and the Building Code Rob Northey, ABCC

• Close and Post-Presentation Networking Graeme Maclean, Laing O’Rourke Project Director

Page 4: INDUSTRY BRIEFING #2

MAJOR ANNEKE JAMIESON

Page 5: INDUSTRY BRIEFING #2

GRAEME MACLEAN

Page 6: INDUSTRY BRIEFING #2

6

Industry Briefing – Scope and Programme

Page 7: INDUSTRY BRIEFING #2

7

Industry Briefing – Scope and Programme

Page 8: INDUSTRY BRIEFING #2

8

Industry Briefing – Site Access and Surrounds

Page 9: INDUSTRY BRIEFING #2

9

Scope of Works

Larrakeyah Barracks Redevelopment (Previously: J0109-Component 1)

Upgrade existing or replace with new, engineering infrastructure

Replace or refurbish existing working accommodation and associated facilities

Increase the capacity of engineering services to accommodate currently planned future work

Facilities to Support Naval Operations in the North (Previously: N2238-Component 2)

Deliver new berthing facilities to accommodate varying combinations of major surface combatants

and submarines

Deliver ‘ready use’ refuelling capabilities to meet current and future projected demands

The new facilities and infrastructure capability must meet the needs of RAN and visiting allied

naval vessel

Industry Briefing – Scope of Works

• Strategically important Base servicing the Royal Australian Navy (RAN), Army and Joint Task Force units in the Darwin Area

• Base covers approximately 80ha and is situated on a headland 2km west of Darwin CBD

• Greenfield and brownfield works

Page 10: INDUSTRY BRIEFING #2

10

Industry Briefing – Contractual Arrangement

• 18 March 2019 – Planning Phase Approval achieved

SubcontractorsDelivery Phase Consultants

Design Consultants

Larrakeyah Defence Precinct Redevelopment Program is a merging of the two former projects:

Component 1J0109 Larrakeyah Barracks Redevelopment

Component 2N2238 Facilities to Support Naval Operations in the North

Commonwealth

Page 11: INDUSTRY BRIEFING #2

11

Industry Briefing – The Project So Far

• 18 March 2019 Planning Phase Approval

• November 2016 “MPFR” 5% Design

• May 2017 “CDR” 30% Design

• November 2017 “SDR” 70% Design

• May 2018 “DDR” 90% Design

• 28 June 2018 Parliamentary Approval

• 1 May 2018 PWC Hearing

• Imminent “FDR” 100% Design

Page 12: INDUSTRY BRIEFING #2

12

Industry Briefing – The Project So Far

• Total no. TBE work packages let: 14

• Total value of TBE work packages let: $11,616,035

• TBE work packages let to local business: 12

• Value of TBE work packages let to local business: $11,489,535

99% of TBE work packages let to local businesses

(by value)

200+ workers inducted into EIFY

Page 13: INDUSTRY BRIEFING #2

13

Industry Briefing – 3D Model Fly-Through

Page 14: INDUSTRY BRIEFING #2

14

Industry Briefing – Group 3 Work Packages

C018 – Incoming HV Power Supply

Works include:• All HV electrical works to supply, construct, test, commission and handover the HV supply from Mitchell

St to the Larrakeyah switching stations.

• Includes any (as required): directional drilling, trenching, excavations, pits, conduits, cables and

associated equipment.

• Works also include management of work area (outside of base), traffic management and liaison with

local authorities.

Approx. $3,500,000

Approximate Commencement Date Q2 2020

Approximate Duration 1 Year

Page 15: INDUSTRY BRIEFING #2

15

C020 – Bulk Earthworks & Civil Infrastructure (Hardstand and Access Road)

Industry Briefing – Group 3 Work Packages

Works include:• Construction of the second access road,

retaining wall and hardstand pavements,

including:

• Demolition of buildings, clearing and

grubbing;

• Construction of the retaining wall, ramp

and second access road;

• Earthworks including pavements for the

hardstand area;

• Installation of in-ground infrastructure

including ducts and drainage;

• Installation of barricades, fencing and

road furniture; and

• Removal of underground fuel tanks

Approx. $8,000,000

Approximate Commencement Date Q2 2020

Approximate Duration 1 Year

Page 16: INDUSTRY BRIEFING #2

16

J007 – Site Wide Electrical incl. Street Lighting, HV & LV

Industry Briefing – Group 3 Work Packages

Works include:

• Supply and installation of site wide electrical services, including:

• Street lighting;

• High Voltage (HV) within the Larrakeyah Defence Precinct perimeter;

• Site wide Low Voltage (LV) distribution network;

• Includes terminations, connections, cable pulling and testing and commissioning

• Includes interfaces with Base Entry Precinct and excludes HV supply from the local authority.

Approx. $6,000,000

Approximate Commencement Date Q2 2020

Approximate Duration 2 Years

Page 17: INDUSTRY BRIEFING #2

17

J014 – NORFORCE Precinct

Industry Briefing – Group 3 Work Packages

• Includes construction of the following facilities:• Regimental Headquarters• Operational Support Squadron Building• Two vehicle shelters to suit Defence heavy

and light vehicles• Hazardous goods store

Approx. $32,000,000

Approximate Commencement Date Q2 2020

Approximate Duration 2 Years

• Works also include:• All services above & below ground inside the NORFORCE compound

• Demolition of existing buildings

• All civil works, foundations, hardstand areas, roads and landscaping

• Tying in of roads and services at battery limits

• Building fit-out (including all material supply)

Page 18: INDUSTRY BRIEFING #2

18

J017B – Ancillary Building (ICTCN)

Industry Briefing – Group 3 Work Packages

Works Include:• Construction of a single 20 x 15m

building

• The building is primarily an ICT

building also houses a generator.

• Decommission and removal of

existing storm drain and pit.

• Supply and construct raft

foundation, internal/external

blockwork walls, and steel frame to

support external wall and roof

cladding.

• Supply, install and commission all

electrical, hydraulic, fire and

mechanical services (including in-

ground services).

• Supply and construct all FF&E as

noted in consultant schedules.

Approx. $2,000,000

Approximate Commencement Date Q1 2020

Approximate Duration 7 Months

Page 19: INDUSTRY BRIEFING #2

19

J022 – Communications Infrastructure (Site Wide)

Industry Briefing – Group 3 Work Packages

Approx. $6,000,000

Works include:• Site wide communications services, including:

• Cables into new and existing buildings (including pit and pipe);

• Telecommunications devices/equipment (non CIOG equipment only);

• BMS, security and fire interfaces;

• Works include all supply, terminations, testing and commissioning

Approximate Commencement Date Q2 2020

Approximate Duration 2 Years

Page 20: INDUSTRY BRIEFING #2

20

N002 – Bulk Earthworks & Civil Infrastructure (Fuel Farm)

Industry Briefing – Group 3 Work Packages

Approx. $3,000,000

Works include:• Complete the bulk earthworks and preparation for

the construction of the Fuel Farm, including:

• Demolition of existing facilities;

• Clearing, grubbing & bulk earthworks;

• Installation of in ground infrastructure including

drainage, conduits and hydraulic services;

• Buildings, tanks and apron foundations; and

• Concrete aprons, pavement and bunds.

Approximate Commencement Date Q2 2020

Approximate Duration 1 Year

Page 21: INDUSTRY BRIEFING #2

21

N003 – Defence Fuel Infrastructure – Marine (Tanks, Civil, SMP & E&I)

Industry Briefing – Group 3 Work Packages

Approx. $17,500,000

Works include:• All piping supply fabrication and installation including all inline equipment;

• Supply and installation of mechanical equipment;

• Construction of new tanks including supply, fabrication and installation;

• Supply of all reinforcing, concrete and any required fill materials;

• All civil works including foundations and any cast in elements (excluding bulk earthworks);

Approximate Commencement Date Q2 2020

Approximate Duration 1 Year

Page 22: INDUSTRY BRIEFING #2

22

N003 – Defence Fuel Infrastructure – Marine (Tanks, Civil, SMP & E&I)

Industry Briefing – Group 3 Work Packages

Approx. $17,500,000

Approximate Commencement Date Q2 2020

Approximate Duration 1 Year

Works include:• Decommissioning and demolition of existing

infrastructure and tanks;

• Supply installation and commissioning of control

systems/SCADA including all cabling;

• Supply installation of all electrical equipment, lighting

and cabling;

• Construction of control room including all material

supply (excludes FQCC);

• All structural steel supply, fabrication and erection.

Page 23: INDUSTRY BRIEFING #2

23

Industry Briefing – Base Operations

SAFEBASE System Revised 25 March 2019

AWAREThreat advice of a violent act

against Defence bases is generalised. No specific time of

location is notified.

ALERTThreat advice indicates a specific timeframe for a violent act against

specific bases.

ACTA violent act on the base is either

happening or imminent

Page 24: INDUSTRY BRIEFING #2

WINNIE ROBERTSON

Page 25: INDUSTRY BRIEFING #2

LOOK AT SAFETY DIFFERENTLY

• HSE is our:

• Core value

• Number one priority

• Lead the industry

• Accredited systems

• Focus on High Risk works

• Remove control and constraint

behaviour

• Simplify our systems (Next Gear)

• Build resilience and accountability

Standard Approach Different Approach

Page 26: INDUSTRY BRIEFING #2

FOCUS ON HIGH RISK WORK ACTIVITIES

FSR 01 Temporary Works and Services

FSR 02 Plant and Equipment FSR 10 Demolition

FSR 03 Cranes and Lifting

FSR 04 Working at Heights

FSR 11 Asbestos

FSR 12 Precast and Tilt-Up Concrete

FSR 05 Scaffolding

FSR 06 Energised Plant, Isolations and Lockout

FSR 07 Electrical Safety

FSR 08 Confined Spaces

FSR 14 Rail Operations

FSR 15 Traffic Operations

FSR 16 Piling

FSR 13 Work over Water

FSR 09 Formwork and Falsework

Please visit: www.nextgearsms.com

Page 27: INDUSTRY BRIEFING #2

REMOVE CONTROL & CONSTRAINT BEHAVIOUR

Page 28: INDUSTRY BRIEFING #2

“NEXT GEAR” – SIGNATURE SAFETY PROGRAM

• Disrupts traditional ways of thinking and doing Safety.

• Places individuals at the centre of creating the solution.

• Relies on and encourages a strong safety leadership capability.

• Recognises positive safety indicators using a simple framework.

Page 29: INDUSTRY BRIEFING #2

SIMPLIFIED HSE SYSTEM – THE 3 NEXT GEAR PRINCIPLES

People are the solution instead of the problem.

Safety is the presence of positives instead of the absence of negatives.

Safety is an ethical responsibility instead of a bureaucratic activity.

Page 30: INDUSTRY BRIEFING #2

TACTICS THAT BUILD RESILIENCE

• Empower workforce through

engagement and trust.

• Focus on high consequence risks.

• Learn from our normal work and

investigate success.

• Reduce bureaucracy and simplify

systems.

• Leadership that challenges traditional thinking.

Page 31: INDUSTRY BRIEFING #2

YOUR PART TO PLAY

• Implement our HSE Management and

understand the contract requirements.

• Identify controls required to manage High

Risk work activities.

• Get involved to ensure we understand our

work and resource the required controls.

• Challenge the process and keep it simple.

Let’s step out from the crowd so we can

position ourselves at the forefront of HSE leadership and the construction industry.

Page 32: INDUSTRY BRIEFING #2

WE LOOK FORWARD TO WORKING WITH YOU

Page 33: INDUSTRY BRIEFING #2

ALEX PANOMARENKO

Page 34: INDUSTRY BRIEFING #2

34

Maximising Opportunities for Local Industry

“At present, the typical arrangements are for sub-

contracts to be based on ‘trade packages’.

Defence has considered feedback from Northern

Territory enterprises and will instead trial the use of

smaller ‘work packages’ for the upcoming

Larrakeyah Redevelopment and Naval Operations in

the North projects,” Minister Payne said.

Under this approach, buildings or work elements may

be tendered separately, rather than by individual

trade. It is expected that this initiative will provide

greater opportunity to local industry in the Northern

Territory.

Australian Government Department of Defence Website, 31 August 2017

(former)

Page 35: INDUSTRY BRIEFING #2

35

Industry Briefing – Procurement Processes

SubcontractorsDelivery Phase Consultants

Commonwealth

Page 36: INDUSTRY BRIEFING #2

36

Industry Briefing – Procurement Processes

• Invite Expressions of Interest – advertise Packages• in the NT News and Weekend Australian• at lbrandfsnon.icn.org

• Shortlist Tenders

• Potential Tenderers upload completed “EOI’s” to ICN

• Request for Tenders issued (RFTs)

• Shortlisted Tenderers submit proposals

• Tenders assessed, recommendation made to Defence and Subcontractor appointed

Page 37: INDUSTRY BRIEFING #2

37

Industry Briefing – Procurement Processes

Group 1 and 2 Packages

lbrandfsnon.icn.org.au

Package

Group

Package

IDWork Package Name

Group 1 C004 Cadastral (Land) Surveyor

Group 1 J001 Base Entry Precinct

Group 1 J002 Civil Services Infrastructure

Group 1 J004 Stormwater Tunnelling

Group 1 J015 Decanting - NORFORCE (Stage 1)

Group 1 J020 Sewer Infrastructure (Sitewide)

Group 1 N022 Wharf Structure

Group 1 N023 Containerised Fuel Storage Tank

Group 2 C012 Environmental Monitoring

Group 2 C016 Arborist

Group 2 C022 Hardstand Bulk Earthworks and Revetment Wall Upgrade

EOI CLOSED 9 June 2018

EOI Close Date

EOI CLOSED 10 May 2019

Page 38: INDUSTRY BRIEFING #2

38

Industry Briefing – Procurement Processes

Group 3 Packages

lbrandfsnon.icn.org.au

Package

Group

Package

IDWork Package Name

Release Date of

EOIEOI Close Date

Group 3 C018 Incoming HV Power Supply

Group 3 C020 Bulk Earthworks & Civil Infrastructure (Hardstand and Access Road)

Group 3 J007 Site Wide Electrical incl. Street Lighting, HV & LV

Group 3 J014 NORFORCE Precinct

Group 3 J017B Ancillary Building (ICTCN)

Group 3 J022 Communications Infrastructure (Site wide)

Group 3 N002 Bulk Earthworks & Civil Infrastructure (Fuel Farm)

Group 3 N003 Defence Fuel Infrastructure - Marine (Tanks, Civil, SMP & E&I)

27 Jul 19 26 Aug 19

Page 39: INDUSTRY BRIEFING #2

39

Industry Briefing – Procurement Processes

Group 4, 5 and 6 Packages

lbrandfsnon.icn.org.au

Package

Group

Package

IDWork Package Name

Approx Release

Date of EOI

Group 4 N004 Wharf - Shore-to-Ship Power (D&C)

Group 4 N005 Electrical Infrastructure and Street Lighting (Hardstand)

Group 4 N006 Wharf - Power and Lighting

Group 4 N007 Wharf - Hydraulics

Group 4 N008 Wharf - Communications and Security

Group 4 N017B Warehouse

Group 5 J016 SUF

Group 5 N009 Wharf - Sundry Metalwork

Group 5 N015 Wharf - Mobile Spill Kit

Group 5 N017A Ancillary Building (Wharf Substation)

Group 5 N018 Fuel Quality and Control Centre

Group 5 N020 Wharf - Aluminium Gangways

Group 6 C009 Landscaping and Remediation Works

Group 6 J003 Junior Sailors Carpark and SUF Civil incl landscaping

Group 6 J019 Junior Sailors Carpark Access Tower and Bridge

14 Dec 19

07 Nov 20

14 Aug 21

Page 40: INDUSTRY BRIEFING #2

40

Industry Briefing – Procurement Processes

• WHEN SUBMITTING EOI’S AND TENDERS, THEY MUST:

• BE SUBMITTED ON TIME• EOI’S – UPLOADED VIA ICN GATEWAY• TENDERS – UPLOADED VIA ASITE

• INCLUDE ALL RETURNABLE SCHEDULES

• OTHERWISE THE SUBMISSION MAY NOT BE CONSIDERED

• IF YOU’RE NOT SURE, JUST ASK

• DOUBLE CHECK ALL ATTACHMENTS ARE INCLUDED

[email protected]

Page 41: INDUSTRY BRIEFING #2

41

Industry Briefing – Procurement Processes

• DO:

• ENSURE SUFFICIENT DETAIL PROVIDED IN TENDER/EOI RESPONSES

• ENSURE RESPONSES, ATTACHMENTS AND EXPERIENCE PROVIDED IS

APPLICABLE/RELEVANT TO THE WORK PACKAGE SCOPE

• ANSWER EVERY QUESTION IN THE EOI AND THE TENDER DOCUMENT

• DON’T:

• PROVIDE NON-CONFORMING SUBMISSIONS WITHOUT JUSTIFICATION

• SAVE TENDER QUERIES UNTIL THE LAST MINUTE

• SUBMIT TENDER QUERIES INFORMALLY VIA EMAIL OR PHONE

Page 42: INDUSTRY BRIEFING #2

CHARMAINE BARRETT

Page 43: INDUSTRY BRIEFING #2

Industry Briefing – ICN

ICN is an information source

43

Page 44: INDUSTRY BRIEFING #2

Industry Briefing – ICN

44

• Business Promotions (NT) Pty Ltd t/a ICN (NT) with a Board of 8 Directors

• Shareholders

• Chamber of Commerce NT

• Master Builders Association NT (MBA NT)

• Supported by NT Dept. of Trade, Business & Innovation (DTBI)

• Independent and Unbiased

• Public and Private sector procurement processes

Part of a national and NZ network

Page 45: INDUSTRY BRIEFING #2

Industry Briefing – ICN

45

Page 46: INDUSTRY BRIEFING #2

Industry Briefing – ICN

46

• Promote the capability of Northern Territory and Australian

business and Industry

• Promote business opportunities that arise from private and

public sector projects at both construction and operation

phases

ICN assists and encourages buyers of goods, services &

equipment to source locally

Page 47: INDUSTRY BRIEFING #2

Industry Briefing – ICN

47

LBRandFSNON.icn.org.au

Page 48: INDUSTRY BRIEFING #2

Industry Briefing – ICN

48

LBRandFSNON.icn.org.au

Page 49: INDUSTRY BRIEFING #2

Industry Briefing – ICN

49

LBRandFSNON.icn.org.au

Page 50: INDUSTRY BRIEFING #2

Industry Briefing – ICN

50

LBRandFSNON.icn.org.au

Page 51: INDUSTRY BRIEFING #2

Industry Briefing – ICN

51

LBRandFSNON.icn.org.au

Page 52: INDUSTRY BRIEFING #2

Industry Briefing – ICN

52

Page 53: INDUSTRY BRIEFING #2

Industry Briefing – ICN

You must communicate effectively with ICN so ICN can communicate

effectively with you.

53

1. Create an ICN profile

2. Review your ICN profile

3. Enable your NOTIFICATIONS

1. Submit an EOI against GENERAL

UPDATES

2. Submit EOIs and complete

documentation for INDIVIDUAL

PACKAGES

ICN Gateway

gateway.icn.org.au

Project Page

LBRandFSNON.icn.org.au

Thank you

Page 54: INDUSTRY BRIEFING #2

ROB NORTHEY

Page 55: INDUSTRY BRIEFING #2

ABCC & the Building Code 2016

Rob NortheyMat Thomson Tammil ToombsMitchell Sonter

Page 56: INDUSTRY BRIEFING #2

Overview

•Key Terms

•Role of the ABCC

•Building Code 2016 –application of the Building Codes

–what it means to be ‘hooked’

–subcontractor obligations

•Reporting Requirements

Page 57: INDUSTRY BRIEFING #2

Key Terms

• Building Code 2016 – the Code for the Tendering and Performance of

Building Work 2016 – commenced 2 December 2016

• Code Covered Entity – the term we use to describe a contractor

that has tendered for or expressed interest in Commonwealth funded building work from 2 December 2016.

Page 58: INDUSTRY BRIEFING #2

Key Terms cont.

• Enterprise Agreement - Enterprise agreements are collective agreements

made at an enterprise level between employers and employees about terms and conditions of employment. They are registered with the Fair Work Commission and continue to operate until terminated.

• Modern Award - Modern awards cover a whole industry or occupation and provide

a safety net of minimum pay rates and employment conditions. (e.g. Building and Construction General On-Site Award 2010)

Page 59: INDUSTRY BRIEFING #2

The role of the Australian Building and Construction Commission (ABCC)

• Purpose: “…to ensure that building work is carried out fairly, efficiently and productively…”

• Two key areas of responsibility

– Compliance with the Fair Work Act 2009 & the BCIIP Act

– Compliance with the Building Codes

Page 60: INDUSTRY BRIEFING #2

Education• On site activities;

• Presentations

• 1800 Hotline

• Direct contact from Industry

• Website

• Industry Updates

Compliance• Right of entry

• Unprotected industrial action

• Freedom of association

• Coercion, discrimination and adverse action

• Sham contracting

• Building Code

• Wage and entitlements;

Page 61: INDUSTRY BRIEFING #2

What is the Building Code 2016?

• It is the Code for the Tendering and Performance of Building Work 2016 established under the Building and Construction (Improving Productivity) Act 2016.

• It sets out the Australian Government’s expected standards for building industry participants who wish to be involved in Commonwealth-funded construction projects.

Page 62: INDUSTRY BRIEFING #2

Building Code 2016

Compliance with the Building Code 2016

• Building Code 2016 applies to contractors who submit an EOI or tender for Commonwealth funded building work on or after 2 December 2016.

– This will make you a ‘code covered entity’

Page 63: INDUSTRY BRIEFING #2

I’m a Code Covered entity…what now

• This means, you will be required to also comply with the Building Code on all new privately funded projects.

• Except, you are not required to ensure sub contractor compliance on privately funded projects.

Page 64: INDUSTRY BRIEFING #2

Subcontractor responsibilities during tender process

On Commonwealth funded building work:

– require compliance with Code

– ensure section 23 eligibility requirements are met.

Page 65: INDUSTRY BRIEFING #2

Eligibility Requirements

• The Building Code 2016 sets out two eligibility requirements to tender for Commonwealth funded building work:

– The code covered entity and its related entities must meet the requirements of section 11; and

– Must not be subject to an exclusion sanction.

Page 66: INDUSTRY BRIEFING #2

Section 11 Compliance• To demonstrate compliance with section 11 of the

Code, contractors require either :– a Letter of Compliance or – an appropriate Self-Declaration.

• The evidence required of each contractor is different depending on the type of industrial arrangement(s) the contractor operates under, when the arrangement was made, and when the contractor has/is tendering for Commonwealth funded building work.

• You are not required to have an Enterprise Agreement in order to tender for Commonwealth funded building work

Page 67: INDUSTRY BRIEFING #2

Letters of Compliance

• The ABCC issues Letters of Compliance for enterprise agreements made on or after 25 April 2017 that meet the requirements of the Building Code 2016 (an ABCC Determination).

• The ABCC also provides advice on whether individual clauses and proposed agreements meet the requirements of the Building Code 2016.

The ABCC has published:• Extensive guidance material containing advice on the

compliance of hundreds of clauses.

Page 68: INDUSTRY BRIEFING #2

Subcontractor responsibilities on site

On Commonwealth funded building work:

– as far as reasonably practicable, ensure subcontractors take action to remedy non-compliant behaviour.

Page 69: INDUSTRY BRIEFING #2

What are the requirements of the Building Code 2016?

The Building Code contains a range of requirements for code covered entities: – eligibility requirements for engaging contractors on Commonwealth funded building work– compliance with certain laws, including designated building laws, WHS laws, Competition and

Consumer Act and Migration Act;– security of payment compliance, including specific Building Code requirements;– unregistered agreements– prohibited content for enterprise agreements– sham contracting– collusive tendering practices– above-entitlement payments– labour market testing– protecting freedom of association– right of entry– reporting and notification requirements– managing drug and alcohol issues in the workplace

Page 70: INDUSTRY BRIEFING #2

What if we identify a Breach of Building Code?

Reporting obligations – no later than 2 working days

Must notify ABCC of a breach or a suspected breach of the Building Code and advise the steps proposed to be taken to rectify the breach.

Rectification – notify of steps within 14 days

After initial notification, must notify the ABCC of the steps taken to rectify the breach.

Page 71: INDUSTRY BRIEFING #2

Consequences of breaching the Code

If the non-compliance is with WHS laws or the Fair Work Act re: underpayment of wages or entitlements, the Minister must impose an

exclusion sanction unless satisfied not appropriate.

Minister may issue a formal warning or impose an exclusion sanction.

Refer the breach to the Minister for Employment, with a recommendation for sanction.

Page 72: INDUSTRY BRIEFING #2

General responsibilities: What do we need to do?

Comply with the Building Codes

Understand which Code applies to your project

Comply with any WRMP that applies on Commonwealth funded building work

Respond to requests for information from the ABCC relating to the Code

Understand reporting obligations

Page 73: INDUSTRY BRIEFING #2

Questions?

ABCC Hotline:

1800 003 338

Website:

www.abcc.gov.au

Email:

[email protected]

[email protected]

Page 74: INDUSTRY BRIEFING #2

GRAEME MACLEAN

Page 75: INDUSTRY BRIEFING #2

Industry Briefing - Key Issues For Tenderers

• Building Code 2016

• Defence Common Access Card

• Restricted timings for deliveries

• Cannot Interfere with Base Operations or Operational Tempo

• Must be cognisant of 149 Defence families on Base

• Conforming Bids must answer the questions and submit all schedules

• lbrandfsnon.icn.org.au

• http://www.defence.gov.au/EstateManagement/

75

Page 76: INDUSTRY BRIEFING #2

www.laingorourke.com

Thank you

76

All materials contained in this presentation are copyright of Laing O’Rourke