InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning...

21
Reston, VA / San Diego, CA / Mexico City Phone: 703-476-8999 www.gtechassociates.net InBuilding Wireless & Our Solutions/Services

Transcript of InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning...

Page 1: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Reston, VA / San Diego, CA / Mexico City Phone: 703-476-8999

www.gtechassociates.net

InBuilding Wireless

& Our Solutions/Services

Page 2: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

• Why Inbuilding wireless?

• What is InBuilding wireless?

• What is the market for InBuilding wireless?

• Market Players

• Challenges

• Sample deliverable

• Our solution/services

1

Agenda

Page 3: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Proprietary and Confidential 2

Why Inbuilding?

• Mobile trend continues

• People love their phones

• Shift in cell phone use

• 70% of mobile traffic is inside

buildings

• 80% of mobile data is inside buildings

• 4G speeds rival WiFi

• Carrier build plans have changed• Macro builds largely complete

• Increased focus on user density

• Large buildings are revenue sources

• Bottom line: Inbuilding coverage

will remain a focal point for

carriers. https://www.youtube.com/watch?v=3wRPOV-H8lY

Page 4: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

• Extension of coverage in the

building.

• Small Cell / DAS / WiFi• Small Cell- Low powered base stations with limited

coverage/ capacity.

• Distributed Antenna System (DAS)- Network of antennas

in a venue connected to a single source

• WiFi- Local area wireless networking.

3

What is InBuilding?

• RF Source• Donor antenna/repeater- Collects RF from nearby macro

cell.

• Base station/eNodeB- Separate source from carrier, installed in headend or as part of a small cell network.

• Active DAS• Dedicated RF source, leveraging fiber for building distribution.

• Passive DAS• No dedicated source; RF signal may be amplified and

distributed via coax.

Page 5: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

4

What is the InBuilding market worth?

$8B

$19B

$9B

$11B

>500,000

100,000 – 500,000

50,000 – 100,000

<50,000

Square Footage

8,000(Active DAS/Small Cell)

128,000(Active DAS/Small Cell)

199,000(Active DAS/Small Cell)

5,222,000(Passive DAS/Small Cell)

Total Commercial Bldgs.

Source: EAI 2012 Survey; Skyline Marketing Est

2015 – 2020, US Market

Page 6: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

5

InBuilding Wireless Players

• Carriers- Verizon, AT&T, T-Mobile,

Sprint• Verizon and AT&T, having the most presence

• Neutral host or dedicated

• Operator Owner (Neutral Host)• Crown Castle

• Extenet

• American Tower

• Boingo

• Myriad of consultants, integrators, and

IT shops

• OEMs• Traditional

• DAS-focus

• Venue Owners

• Cable Companies (WiFi)

• Yes• Vz- Region-by-region, only penetration is in

Philly.

• AT&T- Recent staff red.; only penetration is with

BAWA.

• Sprint- Focus is on small cells.

• Yes• Minimal traction with CC.

• Initial conversations with Extenet

• Yes• Oceus

• Yes• ALU, Nokia in Mexico

• JMA, Viavi (JDSU)

• Yes• Ronald Reagan Bldg.

• Yes• Some relationships, minimal traction

Player Potential Customer

Page 7: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

• Fragmented/diverse market

• Approaches vary, resulting in no specific recipe for business and

project development

• Flexibility is key

• Plug and play nature of certain small cell solutions

• Umbrella services as the best approach?

• Partnerships

• Need to establish/finalize

• HP Communications, Bemis, and others

• Client penetration

• Old rules still apply: need to understand client drivers

• Need to know before RFQ is released.

6

Our Challenges

Page 8: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

7

Sample Deliverable

Page 9: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

End-to-End DAS Solutions

Key Tasks

Pre-Design

and Survey

System

Design

Installation /

Integration

Optimization

Coverage assessment

Site walk

Data collection

Capacity planning

Link budget analysis

iBwave design and cov. prediction

Equipment procurement

Installation and commissioning

Test and acceptance

System and parameter audit

RF and performance measurement

Network optimization

8

Pro

gra

m M

an

ag

em

en

t

Page 10: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Partnership Responsibilities

GTA

JMA

• Coverage assessment

• Site walk

• CW propagation

analysis

• Data gathering (e.g.

floor plan, equipment

rooms, cable routing,

telco, existing fiber

runs, etc.)

• Competitive

benchmarking

• Report generation

• Equipment specs.

• Vex files

• Product info

• Training

• Capacity analysis

• Link budget

calculations Use

software analysis tool

(e.g. iBwave) to design

system

• Conform design to

architectural and

operational constraints

• Create Bill of Material

(BOM) and cost

analysis

• Design guidelines and

standards

• Equipment

procurement

• Warehousing

• Installation and

commissioning

• Architectural and

Engineering drawings

• Integration with other

systems and trades

(WiFi, in-house

communications, etc.)

• Installation verification

• Final Acceptance and

reporting

• Installation/

commissioning

processes and docs.

• Integration support and

training

• Audit parameters

• Measure power output

RSSI and RSRP,

throughput testing, etc.

• Measure losses

• Validate coverage and

cell overlap

• Integrate with macro

system

• Perform and verify

adjustment to the

system if necessary

• Capacity optimization

• Handover to customer

• Guidelines for

Optimization

• Report templates

Pre-Design

And Survey

System

Design

Installation And

Commissioning

Optimization

9

Page 11: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Comprehensive Data Collection Across All Venue Types

Coverage assessment

Site walk

Indoor/outdoor CW propagation analysis

Data gathering of critical information of

design (e.g. floor plan, equipment room,

cable routing, telco, existing fiber runs,

etc.)

Establish objectives: coverage, capacity,

application, technology, etc.

Competitive benchmarking

If required, Optimize existing Macro

and/or DAS

Final reporting of existing environment

with recommendations of improvements

Pre-Design /

SurveySystem Design

Installation

/ IntegrationOptimization

10

Page 12: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Design Experience Across All Technologies and

Equipment Vendors

Define the most suitable in- building

solution

Incorporate present and future

capacity requirements

Link budget calculations based on

estimates of feeders, power splitters

and couplers to be deployed

Use software analysis tool (e.g.

iBwave) to design system

Conform design to architectural and

operational constraints

Create Bill of Material (BOM) and cost

analysis

Pre-Design /

SurveySystem Design

Installation

/ IntegrationOptimization

11

Page 13: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Vendor-specific and Neutral Host Integration and

Commissioning

Support in Equipment procurement

Warehousing of equipment and delivery of system

components/ancillary material

Manage installation and commissioning of the

system

Structured cabling installation: CAT5, Coaxial

cable and Fiber Optic

Architectural and Engineering drawings

Integration with other systems and trades (WiFi,

in-house communications, etc.)

Verify proper interconnect and configuration

of access points

Final Acceptance and reporting

Pre-Design /

SurveySystem Design

Installation

/ IntegrationOptimization

12

Page 14: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Network Optimization to Meet and Exceed KPI Targets

CS drops were reduced

after parameter changes

implementation

Improved CS DCR

after parameter changes

implementation

Audit system parameters

Measure power output RSSI and RSRP,

throughput testing, etc.

Measure losses through distribution system

Validate coverage and cell overlap

Integrate with macro system

Perform field measurement after system deployed

Perform and verify adjustment to the system if

necessary

Capacity optimization and review

Handover the system to customer, with sign off

acceptance

Pre-Design /

SurveySystem Design

Installation

/ IntegrationOptimization

13

Page 15: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Robust Equipment and Tool Expertise

MobileAccess/Corning

Solid Technologies

Commscope/Andrew

JMA Wireless/Teko

ADRF

PCTEL

Ascom

JDSU

Alcatel-Lucent

Ericsson

Huawei

Airspan

PCTEL

Ascom

JDSU

Ruckus

Cisco

Belair

Airmagnet

Netstumbler

Ekahuau

Forsk

DAS Small Cells Wi-Fi

14

Page 16: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

Diverse Experience Across a Range of Venues

Survey Design Integration Optimization

Over 100 Venues

Equipment: PCTel,

JDSU, TEMS, etc.

Project Examples:

Philly Airport (PA)

Fair Oaks Mall (VA)

The Westin

Philadelphia (PA)

Boeing Plant (PA)

Over 150 Venues

IBWave certified

Project Examples:

INOVA Fairfax

Hospital (VA)

Potomac Mills Mall

(VA)

Marriot Downtown NH

DAS (PA)

Over 45 Venues

Trained & certified

personnel in DAS

commissioning

Project Examples:

Wheaton Mall

(WESTFIELD

WHEATON MALL)

(MD)

Robinson Nature

Center. (MD)

Thyssen Krupp. (SC)

Over 50 Venues

Significant

optimization

experience on all

technologies (i.e.

LTE, VoLTE, etc.)

Project Examples:

Shore Hotel (CA)

Apple City Creek (UT)

Pepsico Winston

Salem (NC)

15

Page 17: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

OEM Certified

6

• GTA has a range integration and commissioning

experience, with in-house DAS-certified engineers:

• Corning Mobile Access

• SOLiD Technologies

• TE Connectivity - CDIU

• Andrew/Commscope

Page 18: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

• Verizon Wireless- Survey/data collection and design

experience

• AT&T- Survey/data collection, design, optimization, and 5-

step commissioning experience

• Neutral host design support across AT&T, Verizon, Sprint

and T-Mobile.

17

Experience with multiple wireless carriers

Page 19: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

18

Robust Project Management Approach

Phase I: Venue Cont. Negotiation

Project Kickoff Call (PM, DAS Engineer, Construction Team and Venue Personal)

Site Survey Scheduling

BTS / Head End / GPS antenna construction drawing (NSB, Green Field, LTE Overlay, carrier add etc.)

Preliminary RFDS, Plumbing diagram, Capacity Calculator and A&E drawings sent to client for Approval.

Phase II: Design Package

Final Design Package (Schematic Design, BOM, Datafill (RNDCIQ/ NDER), DAS cost details, RF coverage and Prediction Plots)

Obtain final design approval from Client DAS/Small Cell RF team.

Handoff to Construction Team

Phase III: Construction

Receive BOM and final approval copy from DAS Engineer

Equipment order process

Installation Kickoff call ( PM, Construction Team and Venue Personal)

BTS / DAS Installation

5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement)

Handoff reports GTA DAS engineering team to validate

Construction complete signoff

Phase IV: Optimization

DAS site integration and On-Air process (Client RF and GTA DAS engineer)

RF Validation and data throughput testing

Post process data collection report and E911 call verification

Handoff Post processing results to client RF team

Site On-Air Signoff

Page 20: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

• In-depth knowledge of Macro, DAS, Small Cell, and WiFi deployment

• One-stop shop with end-to-end project implementation

• Experienced and trained staff across multiple technologies

• Ability to scale to meet demand

• Price competitive

• Responsive customer-focused management team

• Corporate commitment to exceeding customer expectations

• iBwave-certified engineers

• Over 70 venues designed with Teko gear

• End-to-end process knowledge for all carriers.

GTA’s Value Proposition for InBuilding Support

19

Page 21: InBuilding Wireless & Our Solutions/Services · BTS / DAS Installation 5 step Commissioning Procedure ( Report : Alarm Free OSS / EMS, Coax cable sweep, PIM, OTDR measurement) Handoff

AT&T 5-Step Commissioning Certified (OEM/carrier

experience slide)

Engineers are certified for AT&T’s 5-step commissioning

process

• Step 1 – Validation of Construction Complete

• Validation of Standalone Commissioned RAN Equipment

• Validation of PIM Results

• Validation Cable Sweeps (Spectrum and DTF based Return Loss)

• Validation Optical Test Results (OTDR and Link Loss)

• Step 2 – Baseline Noise floor Measurement (BTS / DAS)

• Step 3 – RF Continuity and Loss Measurement- CW Testing

• DL/UL Head-end

• DL/UL Remote end

• Step 4 - Calibrate/Minimize UL Noise (Maximize Sensitivity)

• Step 5 - Integration of DAS/RAN Equipment, Post Integration

Baseline Measurements and Basic Call Testing

20