FORM -1
MINING PLAN &
PRE-FEASIBILITY REPORT
TO OBTAIN ENVIRONMENTAL CLEARANCE
FOR QUARRYING OF BLACK GRANITE
(Extent: 2.93.0Ha)-B2 Project
IN
S.F.Nos: 248/2 (P), 248/1A (P), 248/1B(P)
and 248/1C (P)
Village: Marasandiram
Taluk: Krishnagiri
District: Krishnagiri
State: Tamilnadu
SUBMITTED TO
State Level Environment Impact Assessment Authority (SEIAA),
Government of Tamilnadu
Chennai
SUBMITTED BY
M/s. Laksa Granites and Exports Pvt. Ltd.,
No. 10G, 2nd Cross,
Co – Operative Colony,
Krishnagiri District – 635 001
INDEX FILE
S.No DESCRIPTION PAGE
NOS
1 To Obtain Environmental clearance 3
2 Environmental clearance Format 5-9
3 Declaration letter 11
4 Demand Draft 13
5 Form-1 15-53
6 Approved Mining Plan Along With
Approval Letter 55-163
7 Pre-Feasibility Report 165-221
8 VAO signed for quarry site 205
9 Baselines Studies 223-247
10 Affidavit Document 249-251
11 Copy of Explosive License 253-255
12 Consolidated Above Document In
PDF Format (DVD)
257
Checklist for receiving the application of Minor Mineral Proposals
S. No Documents/Information required for Initial Scrutiny Yes/No Page No
1. Processing fee in the form of DD as per GO Yes 13
2. Duly filled and signed by both RQP/Consultant & Proponent
in Mining of Minor Minerals Checklist
Yes 1-(f)
3. Duly filled and signed by both RQP/Consultant & Proponent
in Form- 1
Yes 15
4. Duly Prepared and Signed by both RQP / Consultant &
Proponent Pre Feasibility report
Yes 141
5. Approved Mining Plan duly attested with seal by Assistant /
Deputy Director / Commissioner of Geology and Mining
Yes 107
6. Precise area communication letter from District Collector /
Principal Secretary to Government
Yes 109
7. Certificate from the VAO /Tashildhar stating details of
habitation located within 500m radius from the boundary of
the proposed site along with FMB sketch
No -
8. Acknowledgement copy of the application submitted to
NBWL if applicable
Not applicable -
9. Letter from the AD/DD mines about the details (Name of the
Owner, S.F.No, Extent & distance from the boundary of this
quarry) of other quarries
(Proposed/Existing/Abandoned quarries) within a radius of
500m from the boundary of the proposed quarry site
(Applicable for Rough stone/Granite)
Not applicable -
10. Affidavit from the applicant regarding all the general
conditions stipulated in the EIA notification 2006
Yes 203
11. Affidavit from the applicant stating the habitation, details of
other quarry permanent structures within 500m, child labour
etc
Yes 203
12. Documents of village records, FMB, Combined Sketch,
Patta, Chitta, Adangal, consent letter, etc., and also 1km & 10
km radius map, surface plan duly attested by the
AD/DD/Commissioner of Geology and Mining and signed
by concerned authorities
Yes 111-
123,131,1
35
Verified By
To consider the proposal for the grant of Environmental Clearance for Black Granite for over an extent of
2.93.0Ha in S.F.No: 248/2 (P), 248/1A (P), 248/1B (P) and 248/1C (P) at Marasandiram Village of
Krishnagiri Taluk, Krishnagiri District by M/s. Laksa Granites and Exports Pvt. Ltd,
The salient features of the proposal are as follows:
S.No: Details of the proposal : Data furnished Page No:
1.
Name of the owner/Firm
:
M/s. Laksa Granites and Exports Pvt. Ltd.,
No. 10G, 2nd Cross,
Co – Operative Colony,
Krishnagiri District – 635 001
Mobile No: 9952145095
3,19,55,1
23,165
2.
Type of quarrying
(Savudu/Rough stone/
Sand/Granite)
:
It is a Black Granite quarry Project in Marasandiram
Village
3,19,55,1
23,167
3.
S.F.No of the quarry site with
area break up :
S.F.No. 248/2 (P), 248/1A (P), 248/1B (P) and 248/1C
(P) at Marasandiram Village of Krishnagiri Taluk,
Krishnagiri District
3,19,55,1
23,165
4. Village in which situated
: Marasandiram Village 3,19,55,1
23,165
5. Taluk in which situated
: Krishnagiri Taluk 3,19,55,1
23,165
6. District in which situated
: Krishnagiri District 3,19,55,1
23,165
7. Extent of quarry (in ha)
2.93.0Ha 3,19,55,1
23,165
8. Period of quarrying proposed
: Mining license applied for period of twenty years only.
Mining plan period for the first five years
57,83,123
9. Production (Quantity in m
3)
: The proposed quantity of reserves (10%) is 4560m
3 of
Black Granite for a period of five years.
17,97,169
10. Latitude and Longitude of all
corners of the quarry site :
12°37’51’’N to 12°37’57’’N
78°09’58’’ E to 78°10’06’’ E
17,83,169
11. Topo sheet No : 57 L/02 17,83,169
12.
Precise area communication
approved by the District
Collector with date
: Letter No: 18527/MME2/2015-1 Dated: 18.01.2015 123
13.
Mining plan approved by the
Assistant Director of the District
with date
: Letter. No: 8857/MM5/2015 Dated: 09.02.2016 55
14.
Water Requirement:
1. Drinking & Domestic
purpose (in KLD)
2. Dust suppression & Green
Belt (in KLD)
;
Purpose Quantity
KLD
Source
Drinking 0.3KLD Water vendors
Domestic purpose 0.3KLD From Existing bore hole nearby quarry area
Dust suppression and
Afforestation
0.4KLD From Existing bore hole
nearby quarry area
33,171
15.
Depth of quarrying
:
The applicant proposed up to a depth of 8m (1m top soil
+ 2m weathered rock + 5m Black Granite) for a period
of five years.
16.
Project cost (including EMP
cost) :
The project cost including EMP cost is about
Rs. 46,65,000/- (Rupees forty six lakhs and sixty five
thousand only)
113,173
17. EMP cost
: The total EMP cost is about Rs. 2,65,000/- (Rupees two
lakhs sixty five thousand only)
113,173
Checklist for Mining of Minor Mineral 2.93.0Ha mine lease area
S.No Details of the proposal : Data furnished Page No
1. Name of the owner/Firm : M/s. Laksa Granites and Exports Pvt. Ltd., 3,19,55,
123,165
2.
Correspondence Address with Pin
Code :
No. 10G, 2nd Cross,
Co – Operative Colony,
Krishnagiri District – 635 001
3. Email Address : [email protected]
4. Mobile Number : 9952145095
5. Type of quarrying
(Earth/ Rough stone/Sand/Granite) :
It is a Black Granite quarry Project in Marasandiram Village 3,19,55,
123,167
6.
S.F. No of the Quarry site
:
S.F.No. 248/2 (P), 248/1A (P), 248/1B (P) and 248/1C (P) at
Marasandiram Village of Krishnagiri Taluk, Krishnagiri
District
3,19,55,
123,165
7.
Village in which situated, Town
Panchayat/ Panchayat Union in
which the village is situated
:
Village Panchayat : Marasandiram
Panchayat Union : Krishnagiri
3,19,55,
123,165
8. Taluk in which situated
: Krishnagiri Taluk 3,19,55,
123,165
9. District in which situated
: Krishnagiri District 3,19,55,
123,165
10. Extent of quarry (in Ha)
: 2.93.0Ha 3,19,55,
123,165
11. New or existing quarry
: It is New proposal Black Granite Quarry Project in
Marasandiram Village.
3,19,55,
123,169
12.
If in case of existing Rough Stone/
Blue Metal/ Granite Quarry, the
length, width and depth to which
quarrying has already been done
(below the ground level/ above the
ground level)
:
It is New proposal Black Granite Quarry Project in
Marasandiram Village.
3,19,55,
123,169
13.
If quarrying had been done below
the ground level/above the Ground
level, the height of quarrying
: It is New proposal Black Granite Quarry Project in
Marasandiram Village.
3,19,55,
123,169
14.
Name of the owner who had earlier
undertaken the quarrying & a copy
of mining lease issued with date
:
It is New proposal Black Granite Quarry Project in
Marasandiram Village.
3,19,55,
123,169
15.
Proof of land ownership.
If owned patta copy.
If not own patta land agreement/
lease copy entered with the owner
(to be enclosed)
:
It is a Patta land vide patta No: 1440, 2507, 83,129
16. Period of quarrying
: Mining license applied for period of twenty years only.
Mining plan period for the first five years
57,83,12
3
17.
Production (quantity in m3)
:
The proposed quantity of reserves (10%) is 4560m3 (or) 806
Lorry Loads of Black Granite for a period of five years.
Per year for lorry loads = 806 lorry loads/5 years =161 lorry
loads per years.
Total number of effective working days = 280days per year
Per months for lorry loads = 161 lorry loads/12 months
(280days)= Maximum 13 lorry loads per months
The quarry operation is proposed up to depth for 28m (1m top
soil + 2m weathered rock + 25m Black Granite) at present
scenario considering for the entire lease period. The applicant
proposed Black Granite up to a depth of 8m (1m top soil + 2m
weathered rock + 5m Black Granite) for a period.
Descriptio
n
ROM
(m3)
Recove
ry10%
(m3)
Granit
e
waste
90%
(m3)
Top soil
(m3)
Weathe
red rock
(m3)
Side
burden
(m3)
Total
waste
(m3)
Geological
reserves
392000
39200
352800
33600
67200
358400
778400
Mineable
Reserves
184625
18463
166162
16182
31110
17500
214773
Year wise
reserves 45600 4560 41040 11457
21840
-
62880
17,91,93
,97,169
18.
Method of Mining
:
The quarrying operation will be carried out by Open cast semi
mechanized mining method with 5.0m vertical bench with a
bench width of 5.0m is being proposed.
23,95,16
9
19. Top soil/ Overburden in case of
Rough Stone/ Blue Metal :
The thickness of top soil is about 1m. The generation of top
soil is about 11457m3 during the five years period.
97,107
20.
Quantity of rejects in m3 in case of
Granite Mining.
:
Total waste is 214773m3 (166162m
3 of Granite waste @
90% + 31110m3 of Weathered Rock + 17500m
3 of Side
burden) for entire life period.
Total waste is 62880m3 (41040m
3 of Granite waste @ 90% +
21840m3 of Weathered Rock) for a period of five years;
93,97
21.
Length, Width, Depth & Proposed
Quarry in meters.
:
Dimension of the year wise: L (m) Max W(m) Max D (m) Max
172 68 8
Ultimate pit dimensions Length (m) Width (m) Depth (m)
187 87 28
22.
Land use pattern for a radius of 1Km
around the quarry site such as
Agriculture, Habitation etc., :
Description Percentage %
Road – 3%
Agricultural land – 65%
Barren land / trees – 28%
Habitations - 4%
149
23.
Details of other quarries for a radius
of 1Km, around the quarry site. :
The village Topo sketch map showing the quarry proposed
site.
There is no quarry within the radius of 500m
149
24. Aerial distance from periphery of the
site to the nearest habitation : The Nearest habitation Pandijuruki is 2.0km on North eastern
side.
49,1112
09
25.
Aerial distance to the interstate
borders, in case of Rough Stone/
Blue Metal/ Granite quarry to be
obtained from IRS, Anna University.
:
The interstate boundary is situated 5km away from the
eastern side of the area.
49,173,2
07
26.
In case of Rough Stone/ Blue Metal/
Granite quarry no objection
certificate from the concerned
district Forest Officer/ Wild Life
Sanctuaries/ National Parks/ HACA/
Western Ghats region if the quarry
site is within 15 Kms of these areas.
:
There are no wild life sanctuaries, National parks, HACA,
Western Ghats, within the radius of 15km.
The forest is situated within the radius of 5km away from the
eastern side.
49,173,2
07
27.
Aerial distance to the nearest eco-
sensitive areas, CRZ, Forests,
Monuments etc., within 15Kms of
these areas.
:
There is no CRZ, Monuments, forest and sensitive areas
within the radius of 15km.
49,173,2
07
28. Latitude and Longitude of all corners
of the quarry site. : 12°37’51’’N to 12°37’57’’N
78°09’58’’ E to 78°10’06’’ E
17,83,16
9
29. Topo Sheet No
: 57 L/02 17,83,16
9
30.
Copy of explosives license and a
consent letter/ agreement of
competent recognized person who
has agreed to handle explosive for
the blasting, in case of Rough Stone/
Blue Metal/ Granite quarry.
:
A copy of consent letter and license copy enclosed.
253,255
31.
Brief details of APC measures
proposed to be proposed to be
implemented. :
The granite stones are quarried as undamaged dimensional
stones without involving deep hole drilling and heavy blasting,
fragmentation and generation of lumps, fines or dust is
negligible. Water will be sprinkled for the suppression air
borne dust from mine approach roads waste dumps on regular
intervals using water tankers.
32.
Mine Closure Plan to be furnished in
Mining plan.
:
In the Black Granite quarry operations the maximum depth
about 28m (1m top soil + 2m weathered rock + 25m Black
Granite) for the entire lease period this is based on the market
potential at present scenario.
After completion of quarry operation the quarried out land will
be land will be fenced and maintained with barbed wire to
prevent inherent entry of the Public and cattle. Garland drains
will be constructed around the quarry to prevent the surface
run off rain water.
33.
Scheme of Mining prepared by
(Xerox copy of certificate to be
attached)
:
M.Ifthikhar Ahmed, M.Sc., F.G.S., M.B.A., M.M.E.A,
RQP/MAS/183/2004/A
59,121,1
41
34.
Precise area communication
approved by the District Collector :
The Precise area communication letter was issued by the
Additional Chief Secretary, Industries (MME.2) Department
Government of Tamilnadu, Chennai vide Letter No:
18527/MME2/2015-1 Dated: 18.01.2015
123
35.
Mining plan approved by the
Deputy/ Assistant Director of the
District. :
The Mining Plan was Approved by the Commissioner of
Geology and Mining, Chennai vide Letter. No:
8857/MM5/2015 Dated: 09.02.2016
55
36.
Water requirement :
a) Drinking & domestic
purposes in KLD.
b) Dust suppression (in KLD)
:
Drinking Water –0.3 KLD
& Domestic purpose
Dust Suppression – 0.3 KLD
Green belt -0.4 KLD
33,171
c) Green belt (in KLD) Total – 1.0 KLD
37.
Source of water
:
Purpose Sources
Drinking &
Domestic Purpose
Packaged drinking water is available
from the nearby approved water vendors
Dust suppression From Existing Borehole on nearby quarry
Green belt
development
From Existing Borehole on nearby quarry
33,171
38. Ground water table
: The Ground water is about 45mt depth from ground level. 29,85,16
9
39.
Project Cost (excluding EMP Cost)
:
The Project cost:
A. Fixed Asset cost = Rs. 6,50,000/-
B. Operational cost = Rs. 37,50,000/-
C. EMP cost = Rs. 2,65,000/-
Total cost = Rs. 46,65,000/-
The project cost including EMP cost is about
Rs. 46,65,000/- (Rupees forty six lakhs and sixty five
thousand only)
113,173
40. EMP Cost
: The total EMP cost is about Rs. 2,65,000/- (Rupees two lakhs
sixty five thousand only)
113,173
41. Disclosure RQP
:
M.Ifthikhar Ahmed, M.Sc., F.G.S., M.B.A., M.M.E.A,
RQP/MAS/183/2004/A
59,121,1
41
42.
Soft copy of the Form–1,
Pre –feasibility report and Mining
plan in CD.
:
There is enclosed Soft copy for form –1, Pre – feasibility
report and mining plan in CD.
257
43.
Key map showing the approach
roads to the site to be attested by the
Deputy/ Assistant Director of
Geology and Mining of the
concerned District.
:
The Route map showing with approach roads to the site is
enclosed Plate No: IC
147
44.
Village map with S.F. Nos& salient
features such as vegetation,
habitations etc., for a radius of 500m
around the quarry site.
:
Village map with S.F.No and Salient features such as
vegetation, habitation etc., for 500mt radius is enclosed as
Plate no. VIII & Annexure - III
149
45.
If lakes, Ponds, river, nallah, odai
etc. are situated near the quarry site
permission from the concerned PWD
authorities for mining
There is no Rivers/Stream, Lakes, and Reservoir within the
500m distance to the lease applied area.
Krishnagiri Dam is situated 12km away from the South side of
the area.
49,173,2
07
46.
Section map for mining to be
attested by the Deputy/ Assistant
Director of Geology and Mining of
the concerned District.
:
The Geological Plan and section in 1:1000 & 1:500 scale is
enclosed: IV.
47.
Photograph of the proposed Mining
site with S.F.No and attested by at
least VAO.
:
The Photo of the quarry site is enclosed. 205
48. Form –I To be signed by applicant : I am hereby signed 53
49.
Pre- Feasibility Report to be signed
by applicant. :
Pre-feasibility report has been signed by the applicant
221
50. First and last page and the page at
which quantity of mining has been :
First page and last page and the quantity proposed in the plan
have been signed by the Commissioner of Geology and
worked out to be signed by the
Deputy/Assistant Director of
Geology and Mining of the
concerned District.
Mining.
51.
Affidavit from the applicant that
child labor is not being employed in
the mining activity. :
It is been ensured that the labor will not be employed less than
18 years, No child labor will engaged or entertained for any
kind of quarrying operations. All the labor engaged for
quarrying operations will be insured during the quarry lease
period.
249,251
52.
Affidavit from the applicant
regarding planting of trees around
the quarry site in fulfillment of the
Green belt commitment furnished.
:
Affidavit from the applicant regarding the proposal for
planting trees around the quarry and fulfillment of greenbelt
commitment is enclosed
249,251
53.
Details (POD) Regarding
communicating the proposal to the
members of the committee.
:
1. Signature of the applicant
For M/s. Laksa Granites and Exports Pvt. Ltd.,
G.G. Gokul
(Managing Director)
2. Signature of the Recognized qualified person
M.Ifthikhar Ahmed, M.Sc., F.G.S., M.B.A., M.M.E.A,
RQP/MAS/183/2004/A
MARASANDIRAM BLACK GRANITE QUARRY LEASE APPLIED AREA (2.93.0Ha)
The proponent M/s. Laksa Granites and Exports Pvt. Ltd has applied for Environmental clearance for
the proposed quarry Black Granite for over an extent of 2.93.0Ha in S.F.No: 248/2 (P), 248/1A (P),
248/1B (P) and 248/1C (P)at Marasandiram Village of Krishnagiri Taluk, Krishnagiri District.
Salient features of the proposal are as follows:
S. No
Details of the proposal :
Data furnished Page No
1. Name of the Owner + Firm
: M/s. Laksa Granites and Exports Pvt. Ltd., No. 10G, 2nd Cross,
Co – Operative Colony,
Krishnagiri District – 635 001 Mobile No: 9952145095
3,19,55,123,165
2. Location of the
quarry-S.F.No.
: S.F.No. 248/2 (P), 248/1A (P), 248/1B (P) and 248/1C (P) at
Marasandiram Village of Krishnagiri Taluk, Krishnagiri
District
3,19,55,
123,165
3. Purpose of
Application
: It is a Black Granite quarry Project in Marasandiram Village. 3,19,55,
123,167
4. Extent of quarry in
Ha-
: 2.93.0Ha 3,19,55,
123,165
5. Land use planning
a) Mining b) Storage of Topsoil
over burden
c) Infrastructure Road
d) Utilized Area
Total
:
Description
Present
Area
(Ha.)
Area to be
Required
during the
mining plan
period (Ha)
Area at the
end of life
of quarry
(Ha)
Area under quarry Nil 1.13.0 1.54.0
Waste dump Nil 0.50.0 Backfilling
Infrastructure Nil 0.01.0 0.01.0 Roads Nil 0.01.0 0.02.0
Green Belt Nil 0.18.0 0.72.0
Stocking Blocks 2.93.0 1.10.0 0.64.0
Grand Total 2.93.0 2.93.0 2.93.0
23,119,2
11
6. Production (quantity in m3)
: The proposed quantity of reserves (10%) is 4560m3 (or) 806
Lorry Loads of Black Granite for a period of five years.
Per year for lorry loads = 806 lorry loads/5 years =161 lorry
loads per years. Total number of effective working days = 280days per year
Per months for lorry loads = 161 lorry loads/12 months
(280days)= Maximum 13 lorry loads per months The quarry operation is proposed up to depth for 28m (1m top
soil + 2m weathered rock + 25m Black Granite) at present
scenario considering for the entire lease period. The applicant
proposed Black Granite up to a depth of 8m (1m top soil + 2m
weathered rock + 5m Black Granite) for a period.
Descriptio
n
ROM
(m3)
Recove
ry10%
(m3)
Granit
e waste
90%
(m3)
Top soil
(m3)
Weather
ed rock
(m3)
Side
burden
(m3)
Total
waste
(m3)
Geological
reserves
392000
39200
352800
33600
67200
358400
778400
Mineable
Reserves
184625
18463
166162
16182
31110
17500
214773
Year wise
reserves 45600 4560 41040 11457
21840
-
62880
17,91,93,97,169
7. Top soil & overburden
(quantity in m3)
: The thickness of top soil is about 1m. The generation of top
soil is about 11457m3 during the five years period.
97,107
8. Method of Mining : The quarrying operation will be carried out by Open cast semi mechanized mining method with 5.0m vertical bench with a
bench width of 5.0m is being proposed.
23,95,169
9. Life of Mine as per
approved mining plan
: Mining license applied for period of twenty years only.
Mining plan period for the first five years
57,83,12
3
10. Height / width of the
bench
: Height 5.0m & Width 5.0m
23,95,16
9
11. Source of water / quantity required
:
Quantity
required
(in litres)
Source
33,171
a. Drinking &
Domestic Purpose
0.3 KLD Packaged drinking water is available from the approved water
vender
b. Dust Suppression 0.3KLD From Existing bore hole on nearby quarry
C. Afforestation 0.4 KLD From Existing bore hole on nearby quarry
12. Waste water
Sewage water
Mode of disposal
:
:
There is no waste water. 37,213
The septic tank is constructed on permanent structure with in
the quarry lease area.
To local Panchyat Authority
13. APC Measures : 1.Mist Spray using water tankers,
2. Enclosed covered system. (Tarpaulin) for transportation.
39,
14. Ariel distance of
nearest habitation
: S.
No Name of the Village
Approximate
distance &
Direction from
lease applied area
Approximate
population
1. Pandijuruki 2.0km - NE 500
2. Marasandiram 3.0km - NW 600
3. Kodipalli 3.0km - SE 650
4. Lakkabathalapalli 4.0km-SW 650
49,1112
09
15. Ariel distance from
Reserve forest,
Sensitive areas, Forest,
Bird sanctuaries, Wild
life sanctuaries,
National parks, Monuments etc.,
within 15km
: The forest is situated within the radius of 5km away from the
eastern side.
Bird Sanctuaries – Nil
Wild life sanctuaries - Nil
National Park – Nil
Monuments – Nil
49,173,2
07
16. Land owner ship
document
Own patta land
Lease
Govt. Poromboke
:
:
:
It is a Patta land vide patta No: 1440, 2507, 83,129
17. Land use classification : It is New proposal Black Granite Quarry Project in
Marasandiram Village.
3,19,55,
123,169
18. Mining plan prepared
by
:
M.Ifthikhar Ahmed, M.Sc., F.G.S., M.B.A., M.M.E.A,
RQP/MAS/183/2004/A
59,121,1
41
19. Approved by : The Mining Plan was Approved by the Commissioner of
Geology and Mining, Chennai vide Letter. No:
8857/MM5/2015 Dated: 09.02.2016
55
20 Precise area statement
Approved by
: The Precise area communication letter was issued by the
Additional Chief Secretary, Industries (MME.2) Department
Government of Tamilnadu, Chennai vide Letter No:
18527/MME2/2015-1 Dated: 18.01.2015
123
21. Nearby quarries : There is no quarry within the radius of 500m 149,
22. Nearby lake / river/
odai / channel etc.
: There is no Rivers/Stream, Lakes, and Reservoir within the
500m distance to the lease applied area.
Krishnagiri Dam is situated 12km away from the South side of the area.
49,173,2
07
23. Latitude / Longitude : 12°37’51’’N to 12°37’57’’N
78°09’58’’ E to 78°10’06’’ E
17,83,169
24. GI Sheet No. : 57 L/02 17,83,16
9
25. Project Cost(Project
cost +EMP cost)
: The Project cost:
A. Fixed Asset cost = Rs. 6,50,000/-
B. Operational cost = Rs. 37,50,000/-
C. EMP cost = Rs. 2,65,000/-
Total cost = Rs. 46,65,000/-
The project cost including EMP cost is about
Rs. 46,65,000/- (Rupees forty six lakhs and sixty five
thousand only)
113,173
26. EMP Cost (Capital
and recurring)
: The total EMP cost is about Rs. 2,65,000/- (Rupees two lakhs
sixty five thousand only)
113,173
27. Water table : The Ground water is about 45mt depth from ground level. 29,85,169
28. Interstate boundary : The interstate boundary is situated 5km away from the eastern
side of the area.
49,173,2
07
29. Western Ghats : There is no Western Ghats region within the radius of 15km. 49,173,2
07
From:
M/s. Laksa Granites and Exports Pvt. Ltd.,
No. 10G, 2nd Cross,
Co – Operative Colony,
Krishnagiri District – 635 001
Mobile No: 9952145095
To:
THE CHAIRMAN,
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY,
PANAGAL BUILDING, SAIDAPET,
CHENNAI
Sir,
Sub: Submission of Form–1 and Pre-feasibility report and Mining plan (Ref: Letter. No:
8857/MM5/2015 Dated: 09.02.2016) for obtaining Environmental Clearance for
our Marasandiram Black Granite Quarry Lease applied area- Reg.,
****************
I am here by submitting the processing fee in the form of demand draft for rupees one
lakh, along with Form-I and Pre-feasibility report and mining plan to your good office for
obtaining clearance from SEIAA, Chennai, for our Marasandiram Black Granite quarry Lease
applied area for over an extent of 2.93.0Ha in S.F.No. 248/2 (P), 248/1A (P), 248/1B (P) and
248/1C (P) at Marasandiram Village of Krishnagiri Taluk, Krishnagiri District, Tamilnadu.
I have submitted all the relevant documents to your good office to the best of our
knowledge. If any clarifications are required, we are ready to submit the same to your office at
your convenient time. Also we are ready to present the project in front of the committee.
Hence we request your good office to kindly process our application and allow us to
present our project at the earliest.
Thanking you.
Yours sincerely
For M/s. Laksa Granites and Exports Pvt. Ltd.,
G.G. Gokul
(Managing Director)
Place: Krishnagiri
Dated: 13.02.2016