Implementation of MICE at RAL
description
Transcript of Implementation of MICE at RAL
MICE Mtg Oct 2002 Elwyn Baynham RAL 1
Implementation of MICE at RAL
Work done in
Engineering and ISIS Departments
Rutherford Appleton Laboratory
ContributorsIouri Ivaniouchenkov
Tom Bradshaw Jim Rochford Tony Jones
Paul Drumm Elwyn Baynham
MICE Mtg Oct 2002 Elwyn Baynham RAL 2
Aims of the Work
Establish the feasibility to install MICE at RAL Basic questions
» Can it fit in the proposed experimental hall» Can the requirements for services infrastructure
be met– Use of existing services – Space for installation of new services
» Can the safety requirements of RAL/ISIS be met
Impact on cost
MICE Mtg Oct 2002 Elwyn Baynham RAL 3
Scope of Presentation
Overview of the Experimental Hall» MICE layout
MICE Infrastructure needs » Global estimates» Specific assessments - schematic/quantitative
Hydrogen system Cryogenic plant Chilling water plant Electrical power services
MICE installation» Alignment , rails, support structure
Safety Issues
MICE Mtg Oct 2002 Elwyn Baynham RAL 4
Experimental Hall
Inside Bld R5.2
Hall:
L = 47 m W = 12 m H = 8 m
S = 564 m2 V = 4512 m3
Two overhead cranes (8 tonnes each)
MICE Mtg Oct 2002 Elwyn Baynham RAL 5
MICE Layout
MICE Mtg Oct 2002 Elwyn Baynham RAL 6
MICE Layout
MICE Mtg Oct 2002 Elwyn Baynham RAL 7
MICE Layout
MICE Mtg Oct 2002 Elwyn Baynham RAL 8
MICE global services needs
Current status of global audit of services Cryogenic
» Helium– Effective cooling power at 4K min 300W - max 600W
» Liquid Nitrogen– min 90 L/hr - max 120L/hr
Electrical– min 250kW - max 350kW
Water cooling– min - 100kW
MICE Mtg Oct 2002 Elwyn Baynham RAL 9
Hydrogen System: Hydrogen Module
Drawing by E. Black
MICE Mtg Oct 2002 Elwyn Baynham RAL 10
Hydrogen System schematic layout
Igloo Igloo Igloo
Hydrogen buffer tankHydrogen vent
Hydrogen supply bottles
MICE Mtg Oct 2002 Elwyn Baynham RAL 11
Cryogenic Plant - cooling requirements
Systems requiring cryogenic cooling » Muon decay channel magnet
4K supercritical
» MICE Instrument – Sc magnets
4 K 2 phase
– H2 absorber 14-18K gas
– He absorber 4K liquid
– Sci Fi detector 4K
MICE Mtg Oct 2002 Elwyn Baynham RAL 12
Cryogenic Plant - cooling requirements
Proposed configuration of refrigeration plant and interface to MICE is described in the paper of Mike Green» Concept of 2 phase for magnet coil cooling» Shields , stops and lead cooling by 14-18K gas» LH2 cooling by 14 - 18K He gas» Estimates of refrigerator power based on this
arrangement
Additional requirements » Scintillating Fibre detector - LHe as absorber
MICE Mtg Oct 2002 Elwyn Baynham RAL 13
Cooling requirements - Sci Fibre Detector
Scintillating fibre detector option will require substantial refrigeration power
Initial estimates » 150W at 4K» 1100W at 77K ( liquid nitrogen)
Impact on the installed refrigeration capacity
MICE Mtg Oct 2002 Elwyn Baynham RAL 14
Refrigerator Requirements - power audit
Equivalent cooling power @4K Elec Powerbasic power + margin
W W kW
MICE magnets +absorbers 140(MG paper)
Decay Solenoid 35
Sc magnets 175 263 150-250
Sci Fi detector 150
Sc Magnets + Sci Fi Det 325 488 250
Absorbers with Lhe 100
Sc magnets with LHe absorber 275 413 250
All systems 425 638 250+
MICE Mtg Oct 2002 Elwyn Baynham RAL 15
Cryogenic Plant - schematic layout
He tank Compressor room
Cold box
Cold box
Refrigerator
Buffer dewar
MICE Mtg Oct 2002 Elwyn Baynham RAL 16
Cooling requirements - Liquid Nitrogen
Refrigerator» to get the full power rating from the refrigerator will
require LN2 cooling – consumption - 90 L/hr
Sci Fibre detector will require approx 25 L/hr Total consumption approx 115 L/hr
(3000L/day) Dedicated cooler may be the best solution
MICE Mtg Oct 2002 Elwyn Baynham RAL 17
Cooling Plant implementation
Implementation will need to take into account » staging of MICE
– to allow modularity and flexibility
» quench requirements» effects of magnetic fields
– pneumatic operation
» location of compressor plant– provision of building and power for compressors
» if He is to be used in the absorbers
MICE Mtg Oct 2002 Elwyn Baynham RAL 18
Cryogenic Plant Location Schematic
MICE Mtg Oct 2002 Elwyn Baynham RAL 19
Cryogenic Plant Proposed Location
Site Proposed for MICE Plant
Proposed route for services
Alternative route for services
Proposed site for controls & control room (presently the cable store and under the ISIS control room).
Proposed new linac cooling plant room
MICE Mtg Oct 2002 Elwyn Baynham RAL 20
Chilled water plant and Electrical power
Chilled water » New 1MW water plant will be built for ISIS
– we are negotiating with ISIS to upgrade this to 1.5MW
» Status– planning permission is granted agreement with ISIS to
fund this should be reached by Spring 2003
Electrical Power– 240V system - we have enough power in the hall– 3.3kV system new installation will be required
MICE Mtg Oct 2002 Elwyn Baynham RAL 21
Experiment support infrastructure
Requirements for mounting of MICE experiment » Beam height assumed 1.8-2m
– Increased to avoid cutting of trench in the hall floor
» Alignment– requirement – not yet defined – rail system will be required to mount elements of the
experiment
» Careful planning for the modular build up and testing will be necessary to ensure matching of all components and their services
MICE Mtg Oct 2002 Elwyn Baynham RAL 22
Support Structure
Guiding railSupporting rail
Support system specs:
- max load – 5 Tonnes ?- alignment precision along the beam – 5 mm ? transverse the beam – 1 mm ? vertical – 1 mm ?- max movement along the beam – 5 m ?
Questions: 4 or more wheels ? Material – austenitic stainless steel (non magnetic) for example 304-S12
MICE Mtg Oct 2002 Elwyn Baynham RAL 23
Support Structure: Forces
Solenoid coils: J=71.96 A/mm2
Focusing coils: J=105.88 A/mm2
Coupling coils: J=95.07 A/mm2
Correction coils: J=128.89 A/mm2
Transition coils: J=86.95 A/mm2
Transition coils: J=44.40 A/mm2
Correction coils: J=93.33 A/mm2
1357 1357 3232
153
554
137
2162
1554
861550
153
554
137
2162
1554
86
1550
All forces are in kN !
755
86
608
MICE Mtg Oct 2002 Elwyn Baynham RAL 24
Safety at RAL
Objectives» define the hazards specific to the engineering,
installation and operation of MICE
» confirm the applicable RAL rules for implementation
» review implications and feasibility
note these are summarised in the note of Paul Drumm
MICE Mtg Oct 2002 Elwyn Baynham RAL 25
Hazards identified for the engineering of MICE
» Pressure vessels/vacuum vessels» Hydrogen» X-ray and radiation» Magnetic fields» Cryogenic liquids» RF radiation» Toxic substances (beryllium)
MICE Mtg Oct 2002 Elwyn Baynham RAL 26
Safety at RAL
» RAL Safety Rules and Protocols will apply to all aspects of MICE Implementation
– special requirements for ISIS
» The MICE safety case (hazard assessment) should identify the most credible accidents, analysing probability and consequence and the steps needed to reduce the risks to be as low as reasonably achievable.
– An independent Safety Review Committee will review the hazard assessment
MICE Mtg Oct 2002 Elwyn Baynham RAL 27
Safety at RAL
The principle regulations that will need to be addressed are:» The new explosive gas regulations (ATEX).
– A document explaining the explosion protection will be required
» Pressure vessel regulations: – Vacuum vessels are classed as pressure vessels
and must be designed as such to an agreed International Code.
» RAL codes of Practice and Safety Policy» Quality Control Systems
MICE Mtg Oct 2002 Elwyn Baynham RAL 28
Hydrogen Safety Issues
The most significant hazard from liquid hydrogen is an explosion » Cold surfaces can cryo-pump oxygen
leading to a hazardous situation with the potential for explosion.
» Care must be taken to manage faults to ensure that a “chain” of events does not lead to an uncontrolled dangerous situation.
MICE Mtg Oct 2002 Elwyn Baynham RAL 29
Hydrogen Safety Issues
Implementation / experience at ISIS » Liquid Hydrogen is currently used in a hydrogen
moderator on ISIS although the volume is somewhat different from that expected for MICE.
– ISIS uses about 20L, MICE will use around 120L.
» The rules and codes of practice for design, installation and operation of a liquid hydrogen system on ISIS are established for this moderator
“These will be the benchmark for MICE”
MICE Mtg Oct 2002 Elwyn Baynham RAL 30
Hydrogen Absorber Design
Benchmark design rules» “design must take steps to prevent the
condensation of oxygen on any surface that could come into contact with a hydrogen leak”.
– This is the defining statement for the engineering of the MICE absorbers.
» In essence the design must prevent the ingress of air in normal operation or fault conditions
– the oxygen in the system could come from long term cryopumping
MICE Mtg Oct 2002 Elwyn Baynham RAL 31
ISIS benchmark design vs MICE
H2
VacVacVac
Air
MICE ISIS
H2
Vac
He
Air
MICE Mtg Oct 2002 Elwyn Baynham RAL 32
Hydrogen Safety Issues
Implications for MICE design and installation» MICE design of the absorber system must
be identical to the ISIS benchmark or at least equivalent
» Preliminary designs (schematics) must be produced which will allow a first stage assessment and comparison with ISIS for the MICE Proposal
MICE Mtg Oct 2002 Elwyn Baynham RAL 33
Safety Issues - Radiation protection
X-rays from Cavities» 800MHz cavities in a magnetic field will produce
large dark currents . The level of radiation from this source is difficult to predict with accuracy. A 60cm concrete wall is included in the layout to reduce the radiation level to 0.5 microSV/hr
From ISIS beam» extensive shielding will be required where the
beamline passes into B 5.2 - addressed by Paul Drumm
MICE Mtg Oct 2002 Elwyn Baynham RAL 34
Safety Issues - Magnetic fields
» Limits for the public:– Stray magnetic fields in a normally accessed area must
not exceed 0.5 mT(5G - pacemaker issues).
» Where work must be carried out in a magnetic fields, the following limits are used:
– Partial body exposure (arms, hands and feet: 2T (20,000 gauss) for short periods (minutes) 0.2T (200mT/2,000 gauss) for long periods (hours).
– Exposure of whole body 0.2T (200mT/2,000 gauss) for short periods 0.02T (20mT/200 gauss) for long periods.
» Limits for ISIS– injector /control room
MICE Mtg Oct 2002 Elwyn Baynham RAL 35
Safety Issues: Magnetic Field
At the moment the 5Gauss line is outside the building – some shielding may have to be used.
MICE Mtg Oct 2002 Elwyn Baynham RAL 36
ISIS Linac is close to MICE. First indications are that the field is low enough without shielding
Field on ISIS Linac
MICE Mtg Oct 2002 Elwyn Baynham RAL 37
Safety Issues: Magnetic Field
Volume in blue: 1 kGauss field
Volume in orange: 5 Gauss field
MICE Mtg Oct 2002 Elwyn Baynham RAL 38
Aims of the Work
Establish the feasibility to install MICE at RAL Basic questions
» Can it fit in the proposed experimental hall» Can the requirements for services infrastructure
be met– Use of existing services – Space for installation of new services
» Can the safety requirements of RAL/ISIS be met
Impact on cost
MICE Mtg Oct 2002 Elwyn Baynham RAL 39
Work for Proposal
Continue to develop layout in hall Audit of services
» final iteration for proposal
Safety» absorber design to ISIS benchmark
– initial internal review
» magnetic field worst case
Impact on cost» continue to develop the cost model with MICE