IEMR Session 3 d

download IEMR Session 3 d

of 36

Transcript of IEMR Session 3 d

  • 8/12/2019 IEMR Session 3 d

    1/36

  • 8/12/2019 IEMR Session 3 d

    2/36

  • 8/12/2019 IEMR Session 3 d

    3/36

    Why M&V

    Measurement and verification:

    Is needed to confirm project energy savings and validatethat anticipated or guaranteed performance has beenachieved

    Presents common definitions, terminology and proceduresfor energy-efficiency projects

    Improves communication and understanding among projectimplementing partners

    Provides a risk management tool to financing entitiesMinimizes disagreements and disputes

    Facilitates persistence of energy savings

  • 8/12/2019 IEMR Session 3 d

    4/36

    Key Considerations in M&V

    Who pays for the M&V?

    Who should conduct the M&V?

    How much does M&V cost?

    What should be included in the M&V plan?

    What methodologies are available?

    How are baseline adjustments to be addressed?

  • 8/12/2019 IEMR Session 3 d

    5/36

    Who Should Conduct M&V?

    M&V

    Project Host ESCO

    Third Party

  • 8/12/2019 IEMR Session 3 d

    6/36

    How much does M&V cost?

    The costs of M&V depend on the energy efficiencytechnologies and measures to be implemented andthe approach and methodology to be utilized

    M&V costs 5 to 10% of project investmentsTrade off between

    accuracy of the M&V

    cost of M&V

    Simple approaches are preferred to reduce costs andminimize potential for disputes

  • 8/12/2019 IEMR Session 3 d

    7/36

    Who Pays for M&V Costs?

    If the project host conducts or engages a third partyto conduct M&V, the host directly pays the M&Vcosts

    If the ESCO conducts or engages a third party toconduct M&V, the M&V costs are part of ESCOs costs

    In either case, the M&V costs are an integral elementof project cost and an allowance needs to be made inthe project budget and financing plan for these costs

    While the M&V is specified in the Energy ServicesAgreement, the lender needs to understand andapprove the M&V approach and costs

  • 8/12/2019 IEMR Session 3 d

    8/36

    Key Elements of an M&V Plan

    Key Elementsof M&V Plan

    Description of energy efficiency measures.

    Documentation of the base conditions & energy data.

    Identification of any planned changes.

    Identification of the post-retrofit period conditions.

    Specification of M&V options & analysis procedures,algorithms, and assumptions.

    Specification of software, budget, and resource needs.

    Documentation and data available to verify reportedsavings.

    Methods for making relevant baseline adjustments.

  • 8/12/2019 IEMR Session 3 d

    9/36

    Basic M&V Concept

    Equation 1:

    Savings = Baseline Energy Use Post-installation Energy Use+/- Adjustments

    Equation 2:

    Cost Savings = Rate Baseline (Baseline Energy use)

    Rate Baseline (Post Energy use)

    +/- Adjustments

    First Step Establish the Baseline Energy Use

  • 8/12/2019 IEMR Session 3 d

    10/36

  • 8/12/2019 IEMR Session 3 d

    11/36

    M&V Methodologies

    Deemed or Stipulated Savings

    Bill data analysis

    Metering

    Hours of use

    Individual equipment

    Energy systems or processes

    Time of use meteringBuilding or process modeling

    Increasingcomplexity

    Increasingcost

  • 8/12/2019 IEMR Session 3 d

    12/36

    M&V methodologies

    METHODOLOGY CHARACTERISTICS

    Deemed Savings Participants agree to the unit energy savingsfrom new equipment and savings calculationsare based on simple formulas

    Bill Data Analysis Utility bills before and after installation areused to determine the savings

    Metering Meters are installed to measure the actualenergy consumption of specific equipment orsystems (before and after implementation)

    Modeling In complex systems where energy use isinfluence by a wide range of factors, modelingapproaches are used to estimate energyconsumption and savings

  • 8/12/2019 IEMR Session 3 d

    13/36

    M&V Protocols

    Deemed orStipulated

    Savings

    Protocolsfor M&V

    IPMVP

    AustralasianESPC

    M&V GuideU.S. FEMP

    M&VGuidelines

    California PublicUtilities Commission

    Energy EfficiencyEvaluation

    Protocols

    CDM MethodologiesApproved by

    UNFCCC

  • 8/12/2019 IEMR Session 3 d

    14/36

    IPMVP

    Developed by a coalition of researchers and practitioners

    Managed by independent organization (EVO) dedicated to provisionof tools to quantify the results of EE projects and programs.

    Provides flexible framework of M&V options that allowspractitioners to craft the right M&V Plan for their project

    Internationally recognized and acceptedCertification program for M&V professionals

    Introduced in India - Alliance for Energy-Efficient Economy (AEEE)

    International Performance Measurement andVerification Protocol

  • 8/12/2019 IEMR Session 3 d

    15/36

    M&V Approaches in IPMVP

    Retrofit Isolation Methods

    Option A Partially measured or one timemeasurement

    Option B Longer or continuousmeasurements

    Whole Facility Methods

    Option C Whole facility energy analysisOption D Computer simulation

  • 8/12/2019 IEMR Session 3 d

    16/36

    Illustration of IPMVP Options

    Options A & B areretrofit isolation methods.

    Options C & D arewhole-facility methods.

    The difference iswhere theboundary lines aredrawn.

  • 8/12/2019 IEMR Session 3 d

    17/36

    17

    IPMVP M&V Options

    M&V Option How savings arecalculated

    Option A: Based on measured equipmentperformance, measured or stipulated operationalfactors, and annual verification of potential to

    perform.

    Engineering calculations.

    Option B: Based on periodic or continuousmeasurements taken throughout the term of thecontract at the device or system level.

    Engineering calculations usingmeasured data.

    Option C: Based on whole-building or facility levelutility meter or sub-metered data adjusted for

    weather and/or other factors.Analysis of utility meter data.

    Option D: Based on computer simulation of buildingor process; simulation is calibrated with measureddata.

    Comparing different models.

  • 8/12/2019 IEMR Session 3 d

    18/36

    18

    Option ASimple approach (and low cost)

    Performance parameters are measured (before andafter), usage parameters may be estimated

    Used where the potential to perform needs to beverified but accurate savings estimation is notnecessary

    Key features

    Lower costSimple procedure

    Requires agreement among parties

  • 8/12/2019 IEMR Session 3 d

    19/36

    19

    Option BUnder Option B, some or all parameters are measuredperiodically or continuously

    Applicable where accurate savings estimation isnecessary and long-term performance needs tracking

    Reduced uncertainty, but requires more effort

    Key featuresReal M&V

    Improved O&M

    Ongoing Commissioning

    Remote monitoring

  • 8/12/2019 IEMR Session 3 d

    20/36

    20

    Option C

    Option C looks at energy use and cost of entire facility,not at specific equipment

    Conceptually simple, may be difficult in practice

    Key features:Can consider weather, occupancy, etc.

    Useful where total savings need to be valued butcomponent savings do not

    Commercial software is available that simplifiesimplementation

    May require baseline adjustments

  • 8/12/2019 IEMR Session 3 d

    21/36

    21

    Option DOption D treats building as computer model

    Flexible, but requires significant effort

    Applications:

    New constructionEnergy management & control systemsBuilding use changesBuilding envelope modifications & additions

    Uses specialized software that requires substantialexperience

    Requires measurements for calibration

  • 8/12/2019 IEMR Session 3 d

    22/36

    Lighting Project M&V - Option A

    Baseline is 100 W light bulb and new lamp is25 Watt compact fluorescent

    Wattage verified by measurements/specifications

    Assume 3,000 operating hours per year:

    Previous experience

    Estimate by owner

    Calculated Savings are:3,000 hr/yr * (0.1 - 0.025 kW) =225 kWh/year

  • 8/12/2019 IEMR Session 3 d

    23/36

  • 8/12/2019 IEMR Session 3 d

    24/36

    Lighting Project M&V - Option C

    Used when lighting is the dominant load

    Document baseline utility bill

    Obtain post-installation utility Bills

    Calculate savings

  • 8/12/2019 IEMR Session 3 d

    25/36

    Lighting Project -Option D

    Used when interactive effects need to be estimated

    Input lighting and HVAC system into simulationprogram.

    Calibrate model and calculate pre- and post-installation lighting and interactive HVAC energyuse for determining savings.

  • 8/12/2019 IEMR Session 3 d

    26/36

    M&V Options with Multiple End-Uses

    1. Lighting Efficiency and Controls2. Motor and Drive Efficiency Improvements

    3. Variable-Speed Drives4. Boiler Improvements

    5. Chiller Improvements6. Air, Water, and Steam DistributionSystems

    7. Thermal Energy Recovery8. Controls

    Option A: One-time metering Option B: Continuous metering

    Option C: Utility Bill AnalysisOption D: Computer Simulation

    1 2 3 4 5 6 7 8

  • 8/12/2019 IEMR Session 3 d

    27/36

    Adjusting for Changes in Baseline

    Measurementand

    Verification Process

    Definition of the BaselineSpecifies the pre-implementation

    conditions against which the savingsare measured

    Changes May Affect

    Equipment Performance

    andLevel of Energy Savings

  • 8/12/2019 IEMR Session 3 d

    28/36

    Adjusting for Changes in Baseline

    PossibleChanges

    in Baseline

    Facility Use or Operating Conditions

    Occupancy

    Equipment Operating Schedules

    Environmental Conditions

    Additions to Energy-Using Equipment

    Facility Refurbishment or Rehabilitation

  • 8/12/2019 IEMR Session 3 d

    29/36

    Common M&V Issues

    Factors affecting saving performancePredictability, measurability, factors such as weather,occupancy, equipment intensity, ability of EEMs todeliver savings, implementation effectiveness, occupant

    operator cooperation, equipment deterioration and lifeEvaluating saving uncertainty

    Instrumentation error, modeling error, sampling error,planned and unplanned changes

    Minimum energy StandardsMinimum operating conditions

  • 8/12/2019 IEMR Session 3 d

    30/36

    Common M&V Issues (continued)

    Energy Prices

    For simplification, price is specified

    Verification by a third party

    Third party can resolve issues

    Baseline adjustments

    Routine and non-routine

    CostCost to owner against benefits

  • 8/12/2019 IEMR Session 3 d

    31/36

  • 8/12/2019 IEMR Session 3 d

    32/36

    M&V Information Document (continued)

    5. Post-installation equipment and conditionsPlan for defining new equipment and spaceconditions, assumptions and stipulations

    6. MeteringSchedule of metering (duration/when), who willprovide, data validation, sampling

    7. Measurement and verification activitiesWho conducts M&V, analysis and prepare report,quality assurance, reports defined and postinstallation energy use relative to production

    8. Initial and annual cost

  • 8/12/2019 IEMR Session 3 d

    33/36

    Case Studies of M&V Plans

    1. Fuel switching in textile SME

    2. Large public sector hospital

    3. Municipal street-lighting control

  • 8/12/2019 IEMR Session 3 d

    34/36

    Fuel Switching in SME

    Project: Efficiency improvement of thermic fluidheating system by switching to saw-dust fuelautomatically fed in the heaters

    M&V Boundary: Drawn around the thermic fluidsystem using Option A: Retrofit Isolation with KeyParameters Measured

    Pre and post-installation energy use calculatedusing the equation

    Annual Energy Cost =Fuel Rs/kg * Avg. fuel consumption kg /day* Days/year

  • 8/12/2019 IEMR Session 3 d

    35/36

    EE Retrofits at a Large Hospital

    Project: Efficiency improvement in water pumping,indoor and outdoor lighting, hot water and air-conditioning systemsM&V Boundary:

    Power factor improvement Entirefacility/utility metering (Option C: whole facilitymeasurement)Lighting retrofits number of lights replaced;spot-checks on lighting source retrofitted (OptionA retrofit isolation/key parameter measured)Raw water pump efficiency (Option A retrofitisolation/key parameter measured)

  • 8/12/2019 IEMR Session 3 d

    36/36