IEMR Session 3 d
-
Upload
debabrata-tantubai -
Category
Documents
-
view
216 -
download
0
Transcript of IEMR Session 3 d
-
8/12/2019 IEMR Session 3 d
1/36
-
8/12/2019 IEMR Session 3 d
2/36
-
8/12/2019 IEMR Session 3 d
3/36
Why M&V
Measurement and verification:
Is needed to confirm project energy savings and validatethat anticipated or guaranteed performance has beenachieved
Presents common definitions, terminology and proceduresfor energy-efficiency projects
Improves communication and understanding among projectimplementing partners
Provides a risk management tool to financing entitiesMinimizes disagreements and disputes
Facilitates persistence of energy savings
-
8/12/2019 IEMR Session 3 d
4/36
Key Considerations in M&V
Who pays for the M&V?
Who should conduct the M&V?
How much does M&V cost?
What should be included in the M&V plan?
What methodologies are available?
How are baseline adjustments to be addressed?
-
8/12/2019 IEMR Session 3 d
5/36
Who Should Conduct M&V?
M&V
Project Host ESCO
Third Party
-
8/12/2019 IEMR Session 3 d
6/36
How much does M&V cost?
The costs of M&V depend on the energy efficiencytechnologies and measures to be implemented andthe approach and methodology to be utilized
M&V costs 5 to 10% of project investmentsTrade off between
accuracy of the M&V
cost of M&V
Simple approaches are preferred to reduce costs andminimize potential for disputes
-
8/12/2019 IEMR Session 3 d
7/36
Who Pays for M&V Costs?
If the project host conducts or engages a third partyto conduct M&V, the host directly pays the M&Vcosts
If the ESCO conducts or engages a third party toconduct M&V, the M&V costs are part of ESCOs costs
In either case, the M&V costs are an integral elementof project cost and an allowance needs to be made inthe project budget and financing plan for these costs
While the M&V is specified in the Energy ServicesAgreement, the lender needs to understand andapprove the M&V approach and costs
-
8/12/2019 IEMR Session 3 d
8/36
Key Elements of an M&V Plan
Key Elementsof M&V Plan
Description of energy efficiency measures.
Documentation of the base conditions & energy data.
Identification of any planned changes.
Identification of the post-retrofit period conditions.
Specification of M&V options & analysis procedures,algorithms, and assumptions.
Specification of software, budget, and resource needs.
Documentation and data available to verify reportedsavings.
Methods for making relevant baseline adjustments.
-
8/12/2019 IEMR Session 3 d
9/36
Basic M&V Concept
Equation 1:
Savings = Baseline Energy Use Post-installation Energy Use+/- Adjustments
Equation 2:
Cost Savings = Rate Baseline (Baseline Energy use)
Rate Baseline (Post Energy use)
+/- Adjustments
First Step Establish the Baseline Energy Use
-
8/12/2019 IEMR Session 3 d
10/36
-
8/12/2019 IEMR Session 3 d
11/36
M&V Methodologies
Deemed or Stipulated Savings
Bill data analysis
Metering
Hours of use
Individual equipment
Energy systems or processes
Time of use meteringBuilding or process modeling
Increasingcomplexity
Increasingcost
-
8/12/2019 IEMR Session 3 d
12/36
M&V methodologies
METHODOLOGY CHARACTERISTICS
Deemed Savings Participants agree to the unit energy savingsfrom new equipment and savings calculationsare based on simple formulas
Bill Data Analysis Utility bills before and after installation areused to determine the savings
Metering Meters are installed to measure the actualenergy consumption of specific equipment orsystems (before and after implementation)
Modeling In complex systems where energy use isinfluence by a wide range of factors, modelingapproaches are used to estimate energyconsumption and savings
-
8/12/2019 IEMR Session 3 d
13/36
M&V Protocols
Deemed orStipulated
Savings
Protocolsfor M&V
IPMVP
AustralasianESPC
M&V GuideU.S. FEMP
M&VGuidelines
California PublicUtilities Commission
Energy EfficiencyEvaluation
Protocols
CDM MethodologiesApproved by
UNFCCC
-
8/12/2019 IEMR Session 3 d
14/36
IPMVP
Developed by a coalition of researchers and practitioners
Managed by independent organization (EVO) dedicated to provisionof tools to quantify the results of EE projects and programs.
Provides flexible framework of M&V options that allowspractitioners to craft the right M&V Plan for their project
Internationally recognized and acceptedCertification program for M&V professionals
Introduced in India - Alliance for Energy-Efficient Economy (AEEE)
International Performance Measurement andVerification Protocol
-
8/12/2019 IEMR Session 3 d
15/36
M&V Approaches in IPMVP
Retrofit Isolation Methods
Option A Partially measured or one timemeasurement
Option B Longer or continuousmeasurements
Whole Facility Methods
Option C Whole facility energy analysisOption D Computer simulation
-
8/12/2019 IEMR Session 3 d
16/36
Illustration of IPMVP Options
Options A & B areretrofit isolation methods.
Options C & D arewhole-facility methods.
The difference iswhere theboundary lines aredrawn.
-
8/12/2019 IEMR Session 3 d
17/36
17
IPMVP M&V Options
M&V Option How savings arecalculated
Option A: Based on measured equipmentperformance, measured or stipulated operationalfactors, and annual verification of potential to
perform.
Engineering calculations.
Option B: Based on periodic or continuousmeasurements taken throughout the term of thecontract at the device or system level.
Engineering calculations usingmeasured data.
Option C: Based on whole-building or facility levelutility meter or sub-metered data adjusted for
weather and/or other factors.Analysis of utility meter data.
Option D: Based on computer simulation of buildingor process; simulation is calibrated with measureddata.
Comparing different models.
-
8/12/2019 IEMR Session 3 d
18/36
18
Option ASimple approach (and low cost)
Performance parameters are measured (before andafter), usage parameters may be estimated
Used where the potential to perform needs to beverified but accurate savings estimation is notnecessary
Key features
Lower costSimple procedure
Requires agreement among parties
-
8/12/2019 IEMR Session 3 d
19/36
19
Option BUnder Option B, some or all parameters are measuredperiodically or continuously
Applicable where accurate savings estimation isnecessary and long-term performance needs tracking
Reduced uncertainty, but requires more effort
Key featuresReal M&V
Improved O&M
Ongoing Commissioning
Remote monitoring
-
8/12/2019 IEMR Session 3 d
20/36
20
Option C
Option C looks at energy use and cost of entire facility,not at specific equipment
Conceptually simple, may be difficult in practice
Key features:Can consider weather, occupancy, etc.
Useful where total savings need to be valued butcomponent savings do not
Commercial software is available that simplifiesimplementation
May require baseline adjustments
-
8/12/2019 IEMR Session 3 d
21/36
21
Option DOption D treats building as computer model
Flexible, but requires significant effort
Applications:
New constructionEnergy management & control systemsBuilding use changesBuilding envelope modifications & additions
Uses specialized software that requires substantialexperience
Requires measurements for calibration
-
8/12/2019 IEMR Session 3 d
22/36
Lighting Project M&V - Option A
Baseline is 100 W light bulb and new lamp is25 Watt compact fluorescent
Wattage verified by measurements/specifications
Assume 3,000 operating hours per year:
Previous experience
Estimate by owner
Calculated Savings are:3,000 hr/yr * (0.1 - 0.025 kW) =225 kWh/year
-
8/12/2019 IEMR Session 3 d
23/36
-
8/12/2019 IEMR Session 3 d
24/36
Lighting Project M&V - Option C
Used when lighting is the dominant load
Document baseline utility bill
Obtain post-installation utility Bills
Calculate savings
-
8/12/2019 IEMR Session 3 d
25/36
Lighting Project -Option D
Used when interactive effects need to be estimated
Input lighting and HVAC system into simulationprogram.
Calibrate model and calculate pre- and post-installation lighting and interactive HVAC energyuse for determining savings.
-
8/12/2019 IEMR Session 3 d
26/36
M&V Options with Multiple End-Uses
1. Lighting Efficiency and Controls2. Motor and Drive Efficiency Improvements
3. Variable-Speed Drives4. Boiler Improvements
5. Chiller Improvements6. Air, Water, and Steam DistributionSystems
7. Thermal Energy Recovery8. Controls
Option A: One-time metering Option B: Continuous metering
Option C: Utility Bill AnalysisOption D: Computer Simulation
1 2 3 4 5 6 7 8
-
8/12/2019 IEMR Session 3 d
27/36
Adjusting for Changes in Baseline
Measurementand
Verification Process
Definition of the BaselineSpecifies the pre-implementation
conditions against which the savingsare measured
Changes May Affect
Equipment Performance
andLevel of Energy Savings
-
8/12/2019 IEMR Session 3 d
28/36
Adjusting for Changes in Baseline
PossibleChanges
in Baseline
Facility Use or Operating Conditions
Occupancy
Equipment Operating Schedules
Environmental Conditions
Additions to Energy-Using Equipment
Facility Refurbishment or Rehabilitation
-
8/12/2019 IEMR Session 3 d
29/36
Common M&V Issues
Factors affecting saving performancePredictability, measurability, factors such as weather,occupancy, equipment intensity, ability of EEMs todeliver savings, implementation effectiveness, occupant
operator cooperation, equipment deterioration and lifeEvaluating saving uncertainty
Instrumentation error, modeling error, sampling error,planned and unplanned changes
Minimum energy StandardsMinimum operating conditions
-
8/12/2019 IEMR Session 3 d
30/36
Common M&V Issues (continued)
Energy Prices
For simplification, price is specified
Verification by a third party
Third party can resolve issues
Baseline adjustments
Routine and non-routine
CostCost to owner against benefits
-
8/12/2019 IEMR Session 3 d
31/36
-
8/12/2019 IEMR Session 3 d
32/36
M&V Information Document (continued)
5. Post-installation equipment and conditionsPlan for defining new equipment and spaceconditions, assumptions and stipulations
6. MeteringSchedule of metering (duration/when), who willprovide, data validation, sampling
7. Measurement and verification activitiesWho conducts M&V, analysis and prepare report,quality assurance, reports defined and postinstallation energy use relative to production
8. Initial and annual cost
-
8/12/2019 IEMR Session 3 d
33/36
Case Studies of M&V Plans
1. Fuel switching in textile SME
2. Large public sector hospital
3. Municipal street-lighting control
-
8/12/2019 IEMR Session 3 d
34/36
Fuel Switching in SME
Project: Efficiency improvement of thermic fluidheating system by switching to saw-dust fuelautomatically fed in the heaters
M&V Boundary: Drawn around the thermic fluidsystem using Option A: Retrofit Isolation with KeyParameters Measured
Pre and post-installation energy use calculatedusing the equation
Annual Energy Cost =Fuel Rs/kg * Avg. fuel consumption kg /day* Days/year
-
8/12/2019 IEMR Session 3 d
35/36
EE Retrofits at a Large Hospital
Project: Efficiency improvement in water pumping,indoor and outdoor lighting, hot water and air-conditioning systemsM&V Boundary:
Power factor improvement Entirefacility/utility metering (Option C: whole facilitymeasurement)Lighting retrofits number of lights replaced;spot-checks on lighting source retrofitted (OptionA retrofit isolation/key parameter measured)Raw water pump efficiency (Option A retrofitisolation/key parameter measured)
-
8/12/2019 IEMR Session 3 d
36/36