Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20...

22
Page 1 of 20 9 August 2006 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim August 9, 2006 Brian D. James Julie Perez Peter Schmidt (703) 243 – 3383 [email protected] Directed Technologies, Inc.

Transcript of Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20...

Page 1: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 1 of 209 August 20062006-8-9 DOE Transition Workshop

Hydrogen Transition Sensitivity Studies

using H2SimAugust 9, 2006

Brian D. JamesJulie Perez

Peter Schmidt(703) 243 – 3383

[email protected] Technologies, Inc.

Page 2: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 2 of 209 August 20062006-8-9 DOE Transition Workshop

Project OverviewObjectives / Goals

• Create a tool robust enough to test the impact of different assumptions on the development of hydrogen infrastructure

• Exercise the tool under different assumptions to understand the infrastructure’s sensitivity to different scenarios

• Suggest to DOE areas of further research based on the parameters most influential in the infrastructure development

Page 3: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 3 of 209 August 20062006-8-9 DOE Transition Workshop

Model EnhancementsFeature

H2Sim 1.0“Old”

H2Sim 2.0“New”

Pathways in Each Year

One pathway built in a given year.

Multiple build rounds considered, allows multiple

pathways

Delivery Evolution Delivery method is fixed to production plant

“Pathway’s can’t change”

Production plant can change delivery methods (eg. Central plant that trucks H2

initially, then switches to pipeline)

Stranding Entire pathways Strands individual portions (eg. Prod., Del., Disp.)

Dispensing Stations Build-Out

Disp. stations capacity = Prod. Capacity,

all built in same year

Dispensing stations built as required by demand

Page 4: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 4 of 209 August 20062006-8-9 DOE Transition Workshop

Model Enhancements, cont.Feature

H2Sim 1.0“Old”

H2Sim 2.0“New”

Dispensing Cost Algorithm

Lookup tables populated with H2A

data

Discounted Cash Flow within model

Delivery Cost Algorithm

Lookup tables populated with city-specific H2A data

Delivery cost computed within model. Allows rapid modeling of different size

cities.Pipelines Optimized Ring

Structure used in HDSAM (Rev. 22 Apr 06)

Minimum Spanning Tree Approach as suggested by

UC DavisEthanol Not an available

production optionIncludes Forecourt Ethanol

(1.5tpd)

Page 5: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 5 of 209 August 20062006-8-9 DOE Transition Workshop

Review of “Old” ResultsBaseline Build-Out Plot

Evaluation & Selection Process is repeated for each year of the analysis. Forecourt SMR is seen to win every year.

Legend defines which

pathways are built in each year.

1.5tpd NG Forecourt SMR was selected

every year.(Demand: Los Angeles 15%

Penetration in 10 yrs.)

Page 6: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 6 of 209 August 20062006-8-9 DOE Transition Workshop

Forecourt Sensitivity (1,500kg/day station)

…”Upper Bound” Forecourt SMR has ahigher cost than leading pathways and thus…

Forecourt SMR with “Upper Bound” capital cost raises

cost substantially

Forecourt SMR (1.5tpd)

Coal/Pipeline

Coal/Pipeline/CO2 Seq.

Biomass/Pipeline

SMR/GT

SMR/Pipeline

Coal/LT

SMR/GT/CO2 Seq.

SMR/Pipeline/CO2 Seq.

Assuming “Upper Bound”Forecourt SMR, Central

Coal with Pipeline became lowest cost pathway.

1.5 tpd NG Forecourt SMR beat all other

options by >$0.50/kg.

Review of “Old” Results, cont.

Page 7: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 7 of 209 August 20062006-8-9 DOE Transition Workshop

Baseline Case and SensitivitiesUsing the “New” Model

(H2Sim 2.0)

Page 8: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 8 of 209 August 20062006-8-9 DOE Transition Workshop

Baseline Assumptions• City of Choice: Los Angeles• DOE LA Demand Scenario

– LA Scenario 1 is baseline (Scenario 2 examined in sensitivity analysis)– Curve has Vehicle Penetration of 5.8% in 10 yrs, 99% by 2050– Assumes MTA Population & Vehicles

• Initial Dispensing Station Penetration set at 0.5% (20 stations)• Forecourt SMRs at “Lower Bound” capital cost estimates

– “Upper Bound” capital cost assessed in sensitivity analysis• Central Coal plants must use sequestration

– CA: No power plant emissions greater than that from IGCC plants– Limited number of sequestration sites in California

• Coal plant in Wyoming becomes available in 2020– 1,000 mile pipeline from Power River Basin to LA (~$700k/mile)– Not fully optimized: will examine larger production/pipelines

• Urban Pipelines are not allowed until 2025 (Modeling practicality). – Costs are set at $1M/mi. (to represent urban pipeline cost)

Page 9: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 9 of 209 August 20062006-8-9 DOE Transition Workshop

Baseline Assumptions, continued

• Step change in Dispensing Technology in 2020 (“DOE 2017 Delivery”)– Increase compressor efficiency from 65% to 80%– Decrease # of purchased compressors from 3 to 1– Compressor cost factor decreases from $6300 to $4100/(kg/hr)– Decrease storage tank costs from $818/kg to $300/kg– Maintenance & Repair cost factor drops from 1.8% to 1.5%– Output pressure increases to 10kpsi

• New Delivery option in 2020– Cold Compressed Gas Truck (CCGT) carries 1100 kg (previous HPGT

carried 657kg)– Also applies to gaseous storage at Dispensing Stations & Terminals

• Step change in Terminal Technology in 2020– Decrease # of purchased compressors from 3 to 2– Decrease storage compressors from 2 to 1– Decrease storage tank costs from $818/kg to $300/kg– Compressor cost factor (NG to H2 compressors) decreases from 130% to

80%

Page 10: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 10 of 209 August 20062006-8-9 DOE Transition Workshop

Sensitivity StudiesIncrease the initial #

of dispensing stationsto 2% of city total

Increase ForecourtSMR Capital Costs to

Upper BoundEstimates

Same as previous butwith higher pipeline

costs ($2M/mi)

Increase ForecourtSMR Capital Costs to

Upper BoundEstimates

View Baseline Caseout to 2050

BaselineCase

(Los AngelesDemand Scenario 1)

View Scenario 2 buildout to 2050

Increase Demand(Los Angeles

Demand Scenario 2)

Page 11: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 11 of 209 August 20062006-8-9 DOE Transition Workshop

Baseline

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 20250

50

100

150

200

250

300

350

400

450

Year

Volu

me

(TPD

)

Buildout (Pro.)

20 20 20 205

20527

20527

36

20527

36

47

20527

36

47

56

20527

36

47

56

60

20527

36

47

56

60

68

20527

36

47

56

60

68

78

(2015) FC,NG-SMR,1.5 @ 33 x 20(2018) FC,NG-SMR,1.5 @ 33 x 5(2019) FC,NG-SMR,1.5 @ 33 x 27(2020) FC,NG-SMR,1.5 @ 33 x 36(2021) FC,NG-SMR,1.5 @ 33 x 47(2022) FC,NG-SMR,1.5 @ 33 x 56(2023) FC,NG-SMR,1.5 @ 33 x 60(2024) FC,NG-SMR,1.5 @ 33 x 68(2025) FC,NG-SMR,1.5 @ 33 x 78CapacityDemand

ForecourtNG-SMR (lower

bound)wins every time

Page 12: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 12 of 209 August 20062006-8-9 DOE Transition Workshop

Displays profited cost of H2 if build new for entire demandStatic Price Plot- Baseline

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 20252

2.5

3

3.5

4

4.5

5

5.5

Year

Prof

ited

Cos

t (ne

w fa

cilit

ies)

NG Forecourt SMR (0.100 tpd)

Forecourt Ethanol(1.5 tpd) – DOE Target ~$3.00

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 20252

2.5

3

3.5

4

4.5

5

5.5

Year

Prof

ited

Cos

t (ne

w fa

cilit

ies)

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 20252

2.5

3

3.5

4

4.5

5

5.5

Year

Prof

ited

Cos

t (ne

w fa

cilit

ies)

NG Forecourt SMR (1.5 tpd) Upper Bound

NG Forecourt SMR (1.5 tpd)

WY: 2015 Coal+SEQPL to CCGT

NG City Gate SMR(15 tpd) with HPGT

Central (Bio/SMR/Coal)

with CCGT

Central (Bio/SMR/Coal)

with HPGT

Central (Bio/SMR/Coal)

with LT

In general:Biomass < SMR < Coal+Seq.

*◊

Existing LAwith LT

Existing LAwith HPGT

Page 13: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 13 of 209 August 20062006-8-9 DOE Transition Workshop

Scenario 1: Upper Bound SMR

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 20250

50

100

150

200

250

300

350

400

450

Year

Volu

me

(TPD

)Buildout (Pro.)

1 1 1 11

1

1

1

1

1

1

1

1

1

1

1

1

(2015) CG,EX @ 46 x 1(2020) C,NG-SMR @ 19 x 1(2015) CG,EX => 48CapacityDemand

Existing LA gaseous capacity + New

Liquefier w/ liquid truck delivery (but HPGT is only slightly more

expensive)

Central NG-SMR w/ cold

compressed gas truck (CCGT)

Existing LA capacity

switches to CCGT

Liquid truck technology stranded!

Page 14: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 14 of 209 August 20062006-8-9 DOE Transition Workshop

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 20250

50

100

150

200

250

300

350

400

450

Year

Volu

me

(TPD

)

1 1 1 11

1

12

1

12

47

1

12

47

56

1

12

47

56

60

1

12

47

56

60

68

1

12

47

56

60

68

78

(2015) CG,EX @ 48 x 1(2020) FC,NG-SMR,1.5 @ 33 x 12(2021) FC,NG-SMR,1.5 @ 33 x 47(2022) FC,NG-SMR,1.5 @ 33 x 56(2023) FC,NG-SMR,1.5 @ 33 x 60(2024) FC,NG-SMR,1.5 @ 33 x 68(2025) FC,NG-SMR,1.5 @ 33 x 78CapacityDemand

Scenario 1 with 78 Disp. Stations in 2015(2% initial station penetration)

Existing LA gaseous capacity +

New Liquefier w/ liquid truck delivery

Forecourt NG-SMR

Page 15: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 15 of 209 August 20062006-8-9 DOE Transition Workshop

2010 2015 2020 20250

100

200

300

400

500

600

700

800

900

1000

Year

Volu

me

(TPD

)Buildout (Pro.)

1 1 1 1 1 1

48

1

48

66

1

48

66

79

1

48

66

79

86

1

48

66

79

86

94

1

48

66

79

86

94

99

1

48

66

79

86

94

99

107

1

48

66

79

86

94

99

107

126

1

48

66

79

86

94

99

107

126

138

(2012) CG,EX @ 47 x 1(2017) FC,NG-SMR,1.5 @ 33 x 48(2018) FC,NG-SMR,1.5 @ 33 x 66(2019) FC,NG-SMR,1.5 @ 33 x 79(2020) FC,NG-SMR,1.5 @ 33 x 86(2021) FC,NG-SMR,1.5 @ 33 x 94(2022) FC,NG-SMR,1.5 @ 33 x 99(2023) FC,NG-SMR,1.5 @ 33 x 107(2024) FC,NG-SMR,1.5 @ 33 x 126(2025) FC,NG-SMR,1.5 @ 33 x 138CapacityDemand

Scenario 2: Lower Bound SMR (13.3% vehicle penetration in 2025)

ForecourtNG-SMR

wins every time (just like

baseline scenario)

2012 – 2017: Existing LA

gaseous capacity + New Liquefier w/

liquid truck delivery

Page 16: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 16 of 209 August 20062006-8-9 DOE Transition Workshop

2010 2012 2014 2016 2018 2020 2022 2024 20260

200

400

600

800

1000

1200

Year

Volu

me

(TPD

)

Buildout (Pro.)

1 1 1 1 1 11

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

(2012) CG,EX @ 46 x 1(2017) C,BIO-G @ 40 x 1(2019) C,BIO-G @ 40 x 1(2020) C,NG-SMR @ 19 x 1(2019) C,BIO-G => 42(2021) C,BIO-G @ 40 x 1(2021) C,BIO-G => 42(2022) C,BIO-G @ 42 x 1(2023) C,BIO-G @ 42 x 1(2024) C,BIO-G @ 42 x 1(2025) C,BIO-G @ 42 x 1CapacityDemand

(13.3% vehicle penetration in 2025)

Scenario 2: Upper Bound SMR

Existing LA gaseous capacity + New Liquefier w/ liquid truck

delivery

Central Biomass/ NG-SMR w/ cold compressed gas

truck (CCGT)

Liquid truck technology stranded!

Page 17: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 17 of 209 August 20062006-8-9 DOE Transition Workshop

Scenario 1: Baseline out to 2050

2010 2015 2020 2025 2030 2035 2040 2045 2050 20550

1000

2000

3000

4000

5000

6000

7000

8000

Year

Volu

me

(TPD

)Buildout (Pro.)

20 20 20 205 20527 2052736 205273647 205273647562052736475660

20527364756606820527364756606878

20527364756606878103

20527364756606878103126

20527364756606878103126155

20527364756606878103126155187

20527364756606878103126155187223

20527364756606878103126155187223262

20527364756606878103126155187223262301

20527364756606878103126155187223262301

3

20527364756606878103126155187223262301

3

3

527364756606878103126155187223262301

3

3

3

527364756606878103126155187223262301

3

3

3

3

527364756606878103126155187223262301

3

3

3

3

3

27364756606878103126155187223262301

3

3

3

3

3

3

364756606878103126155187223262301

3

3

3

3

3

3

4

4756606878103126155187223262301

3

3

3

3

3

3

4

3

56606878103126155187223262301

3

3

3

3

3

3

4

3

2

606878103126155187223262301

3

3

3

3

3

3

4

3

2

3

6878103126155187223262301

3

3

3

3

3

3

4

3

2

3

2

78103126155187223262301

3

3

3

3

3

3

4

3

2

3

22

103126155187223262301

3

3

3

3

3

3

4

3

2

3

222

126155187223262301

3

3

3

3

3

3

4

3

2

3

2222

155187223262301

3

3

3

3

3

3

4

3

2

3

22222

187223262301

3

3

3

3

3

3

4

3

2

3

222222

223262301

3

3

3

3

3

3

4

3

2

3

2222222

262301

3

3

3

3

3

3

4

3

2

3

22222222

(2015) FC,NG-SMR,1.5 @ 33 x 20(2018) FC,NG-SMR,1.5 @ 33 x 5

(2019) FC,NG-SMR,1.5 @ 33 x 27(2020) FC,NG-SMR,1.5 @ 33 x 36(2021) FC,NG-SMR,1.5 @ 33 x 47(2022) FC,NG-SMR,1.5 @ 33 x 56

(2023) FC,NG-SMR,1.5 @ 33 x 60(2024) FC,NG-SMR,1.5 @ 33 x 68

(2025) FC,NG-SMR,1.5 @ 33 x 78(2026) FC,NG-SMR,1.5 @ 33 x 103(2027) FC,NG-SMR,1.5 @ 33 x 126(2028) FC,NG-SMR,1.5 @ 33 x 155

(2029) FC,NG-SMR,1.5 @ 33 x 187(2030) FC,NG-SMR,1.5 @ 33 x 223

(2031) FC,NG-SMR,1.5 @ 33 x 262(2032) FC,NG-SMR,1.5 @ 33 x 301(2033) C,BIO-G @ 43 x 3(2034) C,BIO-G @ 43 x 3

(2035) C,BIO-G @ 43 x 3(2036) C,BIO-G @ 43 x 3(2037) C,BIO-G @ 43 x 3(2038) C,BIO-G @ 43 x 3

(2039) C,BIO-G @ 43 x 4(2040) C,BIO-G @ 43 x 3

(2041) C,BIO-G @ 43 x 2(2042) C,BIO-G @ 43 x 3(2043) C,BIO-G @ 43 x 2(2044) C,BIO-G @ 43 x 2

(2045) C,BIO-G @ 43 x 2(2046) C,BIO-G @ 43 x 2

(2047) C,BIO-G @ 43 x 2(2048) C,BIO-G @ 43 x 2(2049) C,BIO-G @ 43 x 2(2050) C,BIO-G @ 43 x 2

CapacityDemand

…then Central (Biomass/SMR/

Coal)w/ Pipeline($1M/mile)

Forecourt NG-SMR to

2032…

Page 18: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 18 of 209 August 20062006-8-9 DOE Transition Workshop

Scenario 2: Build out to 2050

2010 2015 2020 2025 2030 2035 2040 2045 2050 20550

1000

2000

3000

4000

5000

6000

7000

8000

Year

Volu

me

(TPD

)Buildout (Pro.)

1 1 1 1 1 148148661486679148667986

148667986941486679869499

1486679869499107

1486679869499107126

1486679869499107126138

1486679869499107126138185

1486679869499107126138185215

1486679869499107126138185215245

1486679869499107126138185215245276

14866798694991071261381852152452763

486679869499107126138185215245276312

4866798694991071261381852152452763123

48667986949910712613818521524527631233

486679869499107126138185215245276312332

4866798694991071261381852152452763123323

48667986949910712613818521524527631233233

6679869499107126138185215245276312332333

798694991071261381852152452763123323333

86949910712613818521524527631233233332

9499107126138185215245276312332333323

991071261381852152452763123323333232

10712613818521524527631233233332322

126138185215245276312332333323223

1381852152452763123323333232232

18521524527631233233332322321

215245276312332333323223213

2452763123323333232232132

27631233233332322321322

312332333323223213223

312332333323223213223

(2012) CG,EX @ 47 x 1(2017) FC,NG-SMR,1.5 @ 33 x 48(2018) FC,NG-SMR,1.5 @ 33 x 66(2019) FC,NG-SMR,1.5 @ 33 x 79(2020) FC,NG-SMR,1.5 @ 33 x 86(2021) FC,NG-SMR,1.5 @ 33 x 94(2022) FC,NG-SMR,1.5 @ 33 x 99(2023) FC,NG-SMR,1.5 @ 33 x 107(2024) FC,NG-SMR,1.5 @ 33 x 126(2025) FC,NG-SMR,1.5 @ 33 x 138(2026) FC,NG-SMR,1.5 @ 33 x 185(2027) FC,NG-SMR,1.5 @ 33 x 215(2028) FC,NG-SMR,1.5 @ 33 x 245(2029) FC,NG-SMR,1.5 @ 33 x 276(2030) C,BIO-G @ 42 x 3(2012) CG,EX => 48(2031) C,BIO-G @ 42 x 2(2032) C,BIO-G @ 42 x 3(2033) C,BIO-G @ 42 x 3(2034) C,BIO-G @ 42 x 2(2035) C,BIO-G @ 42 x 3(2036) C,BIO-G @ 42 x 3(2037) C,BIO-G @ 42 x 3(2038) C,BIO-G @ 42 x 3(2039) C,BIO-G @ 42 x 2(2040) C,BIO-G @ 42 x 3(2041) C,BIO-G @ 42 x 2(2042) C,BIO-G @ 42 x 2(2043) C,BIO-G @ 42 x 3(2044) C,BIO-G @ 42 x 2(2045) C,BIO-G @ 42 x 1(2046) C,BIO-G @ 42 x 3(2047) C,BIO-G @ 42 x 2(2048) C,BIO-G @ 42 x 2(2049) C,BIO-G @ 42 x 3CapacityDemand

Forecourt NG-SMR

from 2017 to 2030…

…then Central

(Biomass/SMR/Coal)

w/ Pipeline($1M/mile)

2012 – 2017: Existing LA

gaseous capacity + New Liquefier w/

liquid truck delivery

Page 19: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 19 of 209 August 20062006-8-9 DOE Transition Workshop

Scenario 1: Higher Pipeline Costs

2010 2015 2020 2025 2030 2035 2040 2045 2050 20550

1000

2000

3000

4000

5000

6000

7000

Year

Volu

me

(TPD

)Buildout (Pro.)

202020205205272052736205273647205273647562052736475660

20527364756606820527364756606878

20527364756606878102

20527364756606878102128

20527364756606878102128154

20527364756606878102128154188

20527364756606878102128154188221

20527364756606878102128154188221264

20527364756606878102128154188221264300

20527364756606878102128154188221264300339

20527364756606878102128154188221264300339373

527364756606878102128154188221264300339373

425

527364756606878102128154188221264300339373

425

417

527364756606878102128154188221264300339373

425

417

418

27364756606878102128154188221264300339373

425

417

418

422

364756606878102128154188221264300339373

425

417

418

422

419

4756606878102128154188221264300339373

425

417

418

422

419

401

56606878102128154188221264300339373

425

417

418

422

419

401360

606878102128154188221264300339373

425

417

418

422

419

401360369

6878102128154188221264300339373

425

417

418

422

419

401

360369295

78102128154188221264300339373

425

417

418

422

419

401360369295277

102128154188221264300339373

425

417

418

422

419

401

360369295277260

128154188221264300339373

425

417

418

422

419

401360369295277260259

154188221264300339373

425

417

418

422

419

401360369295277260259232

188221264300339373

425

417

418

422

419

401360369295277260259232259

221264300339373

425

417

418

422

419

401

360369295277260259232259266

264300339373

425

417

418

422

419

401360369295277260259232259266273

(2015) FC,NG-SMR,1.5 @ 33 x 20(2018) FC,NG-SMR,1.5 @ 33 x 5(2019) FC,NG-SMR,1.5 @ 33 x 27(2020) FC,NG-SMR,1.5 @ 33 x 36(2021) FC,NG-SMR,1.5 @ 33 x 47(2022) FC,NG-SMR,1.5 @ 33 x 56(2023) FC,NG-SMR,1.5 @ 33 x 60(2024) FC,NG-SMR,1.5 @ 33 x 68(2025) FC,NG-SMR,1.5 @ 33 x 78(2026) FC,NG-SMR,1.5 @ 33 x 102(2027) FC,NG-SMR,1.5 @ 33 x 128(2028) FC,NG-SMR,1.5 @ 33 x 154(2029) FC,NG-SMR,1.5 @ 33 x 188(2030) FC,NG-SMR,1.5 @ 33 x 221(2031) FC,NG-SMR,1.5 @ 33 x 264(2032) FC,NG-SMR,1.5 @ 33 x 300(2033) FC,NG-SMR,1.5 @ 33 x 339(2034) FC,NG-SMR,1.5 @ 33 x 373(2035) FC,NG-SMR,1.5 @ 33 x 425(2036) FC,NG-SMR,1.5 @ 33 x 417(2037) FC,NG-SMR,1.5 @ 33 x 418(2038) FC,NG-SMR,1.5 @ 33 x 422(2039) FC,NG-SMR,1.5 @ 33 x 419(2040) FC,NG-SMR,1.5 @ 33 x 401(2041) FC,NG-SMR,1.5 @ 33 x 360(2042) FC,NG-SMR,1.5 @ 33 x 369(2043) FC,NG-SMR,1.5 @ 33 x 295(2044) FC,NG-SMR,1.5 @ 33 x 277(2045) FC,NG-SMR,1.5 @ 33 x 260(2046) FC,NG-SMR,1.5 @ 33 x 259(2047) FC,NG-SMR,1.5 @ 33 x 232(2048) FC,NG-SMR,1.5 @ 33 x 259(2049) FC,NG-SMR,1.5 @ 33 x 266(2050) FC,NG-SMR,1.5 @ 33 x 273CapacityDemand

ForecourtNG-SMR

wins every time

Page 20: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 20 of 209 August 20062006-8-9 DOE Transition Workshop

Questions?

Page 21: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 21 of 209 August 20062006-8-9 DOE Transition Workshop

(15% initial station penetration)

Scenario 1 with 576 Disp. Station in 2015

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 20250

50

100

150

200

250

300

350

400

450

500

Year

Volu

me

(TPD

)( )

1 1 1 11

1

1 1

1

1

1

1

1

1

1

1

1

1

1

1

1

(2015) CG,EX @ 48 x 1(2020) C,BIO-G @ 40 x 1(2015) CG,EX => 46(2023) C,BIO-G @ 40 x 1(2025) C,BIO-G @ 40 x 1CapacityDemand

Existing LA

capacity w/ liquid truck

Liquid truck technology stranded over a 2-yr. period

Existing LA capacity w/

CCGT Central biomass w/ CCGT

15% penetration

still not reached in

2025!

Page 22: Hydrogen Transition Sensitivity Studies using H2Sim · 2014. 3. 13. · 9 August 2006 Page 1 of 20 2006-8-9 DOE Transition Workshop Hydrogen Transition Sensitivity Studies using H2Sim

Page 22 of 209 August 20062006-8-9 DOE Transition Workshop

2010 2015 2020 2025 2030 2035 2040 2045 2050 20550

1000

2000

3000

4000

5000

6000

7000

Year

Volu

me

(TPD

)Buildout (Pro.)

20 20 20 205 20527 2052736 205273647 205273647562052736475660

205273647566068

20527364756606878

20527364756606878103

20527364756606878103126

20527364756606878103126155

20527364756606878103126155187

205273647566068781031261551872

2052736475660687810312615518722

20527364756606878103126155187222

20527364756606878103126155187222

3

20527364756606878103126155187222

3

3

527364756606878103126155187222

3

3

3

527364756606878103126155187222

3

3

3

3

527364756606878103126155187222

3

3

3

3

3

273647566068781031261551872

22

3

3

3

3

3

3

364756606878103126155187222

3

3

3

3

3

3

4

4756606878103126155187222

3

3

3

3

3

3

4

3

566068781031261551872

22

3

3

3

3

3

3

4

3

2

606878103126155187222

3

3

3

3

3

3

4

3

2

3

687810312615518722

2

3

3

3

3

3

3

4

3

2

3

2

78103126155187222

3

3

3

3

3

3

4

3

2

3

22

1031261551872

22

3

3

3

3

3

3

4

3

2

3

22

2

12615518722

2

3

3

3

3

3

3

4

3

2

3

2

222

155187222

3

3

3

3

3

3

4

3

2

3

222

22

18722

2

3

3

3

3

3

3

4

3

2

3

2222

22

22

2

3

3

3

3

3

3

4

3

2

3

2222

222

2

22

3

3

3

3

3

3

4

3

2

3

2

22

222

2

(2015) FC,NG-SMR,1.5 @ 33 x 20(2018) FC,NG-SMR,1.5 @ 33 x 5

(2019) FC,NG-SMR,1.5 @ 33 x 27(2020) FC,NG-SMR,1.5 @ 33 x 36(2021) FC,NG-SMR,1.5 @ 33 x 47

(2022) FC,NG-SMR,1.5 @ 33 x 56(2023) FC,NG-SMR,1.5 @ 33 x 60

(2024) FC,NG-SMR,1.5 @ 33 x 68(2025) FC,NG-SMR,1.5 @ 33 x 78

(2026) FC,NG-SMR,1.5 @ 33 x 103(2027) FC,NG-SMR,1.5 @ 33 x 126(2028) FC,NG-SMR,1.5 @ 33 x 155

(2029) FC,NG-SMR,1.5 @ 33 x 187(2030) C,BIO-G @ 43 x 2(2031) C,BIO-G @ 43 x 2(2032) C,BIO-G @ 43 x 2

(2033) C,BIO-G @ 43 x 3(2034) C,BIO-G @ 43 x 3(2035) C,BIO-G @ 43 x 3

(2036) C,BIO-G @ 43 x 3(2037) C,BIO-G @ 43 x 3(2038) C,BIO-G @ 43 x 3(2039) C,BIO-G @ 43 x 4

(2040) C,BIO-G @ 43 x 3(2041) C,BIO-G @ 43 x 2(2042) C,BIO-G @ 43 x 3

(2043) C,BIO-G @ 43 x 2(2044) C,BIO-G @ 43 x 2

(2045) C,BIO-G @ 43 x 2(2046) C,BIO-G @ 43 x 2

(2047) C,BIO-G @ 43 x 2(2048) C,BIO-G @ 43 x 2(2049) C,BIO-G @ 43 x 2

CapacityDemand

Scenario 1: Lower Pipeline Costs

Forecourt NG-SMR to

2029…

…then Central (Biomass/SMR/

Coal)w/ Pipeline

($700K/mile)

Transition is 2 years earlier with $700K/mile

pipeline than with $1M/mile