High Voltage Distribution System-A Lasting Solution For The ILLs of
the Last Mile of the Power Chain
-
8/10/2019 HVDS basic
2/67
High Voltage Distribution System
Distribution is called the last mile in the power supply chainbeing closest to the consumer.
Its quality controls / governs the consumer satisfaction
However it is the most neglected segment of the power sector formany years due to paucity of funds
Major challenge of reforms process is the up gradation ofDistribution system
-To maintain the Standards of performance fixed by the
Regulator.
--To achieve the targets set Under National Electricity policy.
-- To meet the stipulations of various codes like Supply Codes,Grid code etc., in all its functioning
-
8/10/2019 HVDS basic
3/67
High Voltage Distribution System
National Electricity Policy stipulates achieving thefollowing targets, among others, by 2012
- Extension Power supply of quality , continuity and reliability
to all areas including rural areas as per the standards fixed
by the respective Commission, meeting the demand in full,all at affordable price.
- Bringing down AT&C losses to 15.5%
Both the targets are of a very tall order, requiring adoptingof every conceivable method of system improvement.
-
8/10/2019 HVDS basic
4/67
High Voltage Distribution System
Parameters for assessing supply quality Voltage Frequency, Harmonics
Parameters for assessing Reliability Power CutsNo Supply Periods Interruptions - Frequency & Duration
---Measured variables
Number of interruptionsDuration of interruptions
-
8/10/2019 HVDS basic
5/67
MAX. TOLERABLE TARGET LEVEL
TRANSMISSION 4 4.00 2.00
SUB TRANSMISSION 4 4.50 2.25HIGH VOLTAGE DISTRIBUTION 6 5.00 3.00
LOW VOLTAGE DISTRIBITION 8 2.00 1.00
TOTAL 22 15.50 8.25
SYSTEM COMPONENTSEXISTING
LEVELS
INTERNATIONAL NORMS
NORMS FOR TECHNICAL LOSSES
REVIEW OF SYSTEM LOSSES
Source:World Bank Energy Department Paper No 6-July 1982 on
"Energy Efficiency:Optimization of Electrical Power Distribution System losses"
-
8/10/2019 HVDS basic
6/67
Objectives of a power utility
Supplying of Power of quality, continuity andReliability
Extending supply network to all parts in the area
under its jurisdiction
Meeting the demand in full
Operating plants and network at Optimum
efficiency
Keeping the losses at bare minimumProviding effective consumer services
Supplying power at affordable price
-
8/10/2019 HVDS basic
7/67
PRESENT STATUS OF DISTRIBUTION SYSTEM
Power supply for few hours on any day. Number of interruptions even during the hours of supply due to
the bad condition of net work.
Poor quality of power supply with low voltages
Growing consumer dissatisfaction. Poor revenue realization
Comparatively higher losses.
Financial status which permits only little investment in the systemimprovement.
Achieving targets set in NEP by 2012, against the above back
ground, calls for drastic changes in the set up.
-
8/10/2019 HVDS basic
8/67
Low Voltage Distribution System
The two widely prevalent distribution practices invogue across the world are:
Low Voltage Distribution System (LVDS):
It is based on European practice. A Three phase transformer of considerable capacity,
say 63kVA and above, is installed and a large group
of loads are fed through longer LV lines .
This system is best suited to meet the concentratedloads of high load density.
-
8/10/2019 HVDS basic
9/67
Low Voltage Distribution System
This system is widely adopted in our power sector despitethe contrasting status, particularly in rural areas, of
scattered loads with low load density.
This has resulted in system losses well beyond the tolerablelimits, poor Voltage profile and host of other ills, many a
times compounding in nature
-
8/10/2019 HVDS basic
10/67
Problems of Existing Distribution
As Power is drawn through longer L.T. lines with higher current,
there is increased power and energy losses
Higher voltage drop in lengthy LT lines resulting in Low Voltages atconsumer end.
Frequent motor burning outs due to low voltage at consumer end andconsequent expenditure on repairsHigher rate of transformer failures due to commonly ocuring defectsin L.T. network and over loading increased expenditure on repairs-increased interruptions to the consumer.
For any transformer failure large number of consumers gettingaffected.
For any delays in replacing failed transformers , damages to standingcrops
-
8/10/2019 HVDS basic
11/67
Problems of Existing Distribution
As more number of consumers are connected under eachtransformer , more fluctuations.
Higher possibilities for theft of energy by direct hooking to thebare L.T. lines, running in remote areas
More number of interruptions due to the defects in the lengthyL.T net work. lesser reliability
As bare L.T network has only fuse protection ,without anybreaker, Chances for accidents are more by coming in to contact
with snapped bare wires.
Poor quality of supply resulting in lesser end use efficiencyThe above drawbacks are automatically call for adopting a
different distribution system devoid of these defects
-
8/10/2019 HVDS basic
12/67
High Voltage Distribution System (HVDS):
It is the best remedy for all the prevailing ills in the existing LowVoltage Distribution System (LVDS)
It is based on North American practice.
A Three phase or single phase HV line is taken as near to a smallgroup of loads as possible, and a distribution transformers of smaller
capacities , single phase or three phase transformer as the case may
be , are installed to feed a small group of loads through AB cables
and service wire , such that the length of the LV lines is minimum or
is eliminated altogether.
To the extent LV lines are permitted, they are with insulated ABcables only
This system is best suited to meet the scattered loads of low loaddensity.
-
8/10/2019 HVDS basic
13/67
Different Types of High Voltage
Distribution System
There are three types of High Voltage distribution system in vogue:
Phase Neutral HVDS (PN-HVDS)
Phase Phase HVDS (PP-HVDS)
Phase-Ground HVDS (PG HVDS)
-
8/10/2019 HVDS basic
14/67
Phase-Neutral HVDS
-
8/10/2019 HVDS basic
15/67
Phase-Neutral HVDS
It is widely adopted in North America. Under this system:
- the main line from substation is three-phase 4 wire (3 phases +
Neutral)
-- laterals are single-phase 2 wire line or two-phase 3-wire line orthree-phase 4-wire line depending upon the loads and feeding
arrangement.
Unique feature of the system lies in providing the neutral rightthrough the system, viz from substation to all nodes on the network.
Single-phase Loads:11 KV single phase line (phase neutral) branch isextended from main line and 1 No. 6350/230-0-230 V distribution
transformer is erected to feed single phase loads as shown in Part (A)
of Fig.
-
8/10/2019 HVDS basic
16/67
Phase-Neutral HVDS
Three-phase loads: Three alternative arrangements for feeding threephase loads are described.
11 KV two-phase 3-wire branches are extended from the main lineand 2 Nos. of single-phase 6350/230-0-230 V distribution transformer
is connected, star on HV side and open delta on LV side to feed three-
phase loads, as shown in part (B) of Fig. Effective capacity of thetransformer bank is 86.6% of the total capacity of 2 transformers. Ie.
. if 2 No.s 10 kVA, transformers are used ,maximum 3 ph. load that
Can be fed is 17.32 kVA
11 KV three-phase, 4-wire line is extended and 3 Nos. 6350/230-0-230 V single phase transformers are connected, star- delta to feedthree-phase loads as shown in Part (C)of Fig.
Existing 11 KV three-phase 4-wire line is extended and three-phaseDelta/Star distribution transformer is used as shown in art D of Fi .
-
8/10/2019 HVDS basic
17/67
Phase - Phase HVDS
-
8/10/2019 HVDS basic
18/67
Phase - Phase HVDS
Three-Phase loads: Three alternate arrangements for feeding three-phase loads are described.
11 KV three-phase 3-wire branches are extended from main line and 2Nos. of single phase 11000/230-0-230 V distribution transformer is
connected HV side/ LV side V-V (Open delta ) to feed three phase
loads as shown in Part (F) of Fig. Effective capacity -86.6%
11 KV three-phase 3-wire line is extended and 3 Nos. 11000/230-0-230 V single phase distribution transformer are connected delta on
HV side and delta on LV side, as shown in Part (G) of Fig.
11 KV three-phase, 3-wire line is extended and existing three-phase11000/415V delta / star distribution transformer is used as shown inPart (H) of Fig.
-
8/10/2019 HVDS basic
19/67
Phase - Ground HVDS
It is similar to Phase- Neutral HVDS in all respects exceptthat ground is used as return path and neutral wire is notprovided all along the system.
The transformer HV neutral or star point on HV side (when
more than one transformer is used) is earthed solidly atevery location, and thereby ground is used as return path.
This system is used in certain parts of North America andAustralia.
Since ground forms return path, soil resistivity plays a keyrole.
Good quality of earthing is required for the safety of
-
8/10/2019 HVDS basic
20/67
Phase - Ground HVDS
It is unsuitable to Indian conditions due to technical and practical reasonslike :
Since ground is used for return path of the current, the soil resistivityof the area plays a vital role. The system may be hazardous in areas
where soil resistivity is high.
Good quality Earthing is required for the safety of personnel andanimals. The code of practice stipulates that the voltage rise ie., Load
current x and resistance of HV earthing system, at the point of
Earthing shall not exceed 20 V.
Providing effective Earthing and ensuring its maintenance throughoutthe period at a number of locations in rural areas is beset with severalpractical problems.
Interference with telecommunication lines.
-
8/10/2019 HVDS basic
21/67
Advantages under HVDS
All the ills of LVDS get eliminated under HVDS
a)Drastic Reduction in system losses, both Power and energy losses
(In S.ph.HVDS energy losses are 13% of that in LVDS)
b) Improvement in system voltage profile (In S.ph.HVDS vol.drop is
10% of that in LVDS)
c)Reduction in possibilities for theft of energy by direct hooking from
LT linesas the LV lines are virtually eliminated and even the short LV
lines required are of AB cable..
d) Reduction in transformer failures as there will be no over loading andminimum or no LT line defects.
. Lesser interruptions, lesser delays in replacement of failed transformers
and lesser damage to standing crops .Better consumer satisfaction
-
8/10/2019 HVDS basic
22/67
Advantages under HVDS
e)Increase in end use efficiency causing better delivery of water,drawing lesser current.
g)Sense of ownership of the transformer develops among theconsumers as the transformer caters to only two to three consumers)
Possibilities for fluctuations get reduced due to fewer consumers.
i) 11KV lines are controlled by breakers and LT lines are of ABcables. Chances for accidents due to snapping of conductors get
reduced.
J) With increase in the reliability of supply and better end use
efficiency resulting in higher delivery of water, 2 crops are beingraised increasing productivity.
k) Improvement in voltage profile, brings down cases of consumersmotor burning out drastically.
-
8/10/2019 HVDS basic
23/67
Advantages under HVDS
l) Better socio economic development in rural areas. m) In case of any failure of a transformer only 2to3 consumers
will be affected.
n) In view of reduction in losses, additional loads can be fed
with the same generation , without adding any new capacity. o) schemes covering conversion of LVDS to HVDS are eligible forSale carbon emission reductions (CMRs) under Clean Development
Mechanism (CDM) . This additional benefit to the utilities will bring
down the Pay back period to a considerably lesser time frame
p) LT line maintenance is almost absent No tree cutting is requiredfor LT lines
-
8/10/2019 HVDS basic
24/67
Advantages of HVDS compared to LVDS
System is more reliable because:
The LV lines are short and insulated, avoiding all LV faults. The faults on HT line comes to the notice of the operator immediately
due to the tripping of substation breaker.
The failure of transformer affects only a very small number of
consumers served by it. Voltage fluctuations: The voltage drop on the LV line is negligible.
The additional drop due to extension of HV line up to consumer
premises is also negligible. Thus the voltage profile is very stable and
there is no need to use voltage stabilizer.
With least or No possibilities for theft of energy , load management iscomparatively easier
Ad t f S h HVDS d
-
8/10/2019 HVDS basic
25/67
Advantages of S ph. HVDS compared
to LVDS
The important drawbacks of LVDS and the way in which these areautomatically solved by adopting popular PhaseNeutral HVDS are:
Line Losses:The loss in Sph.HVD system for the distribution of the
same amount of power is less than 1% as compared to that of LV line.
In fact it is lesser than the losses under 3 ph. HVD system
Voltage Drop: The voltage drop for distribution of same quantum of
power is less than 1% as against that in LVDS and this ensures proper
voltage profile at all customer points.
System Power Factor : The single phase motors can be used for all
Agricultural services. The single phase motors have built in capacitorsessentially required for starting the motors.
Thus system power factor is always maintained high with good
capacitive compensation at theload end
-
8/10/2019 HVDS basic
26/67
Advantages of S ph.HVDS Capital cost is less as Transformer, surge arrestor requiring 1 No.
Instead of 3, protection system cost less in sph.HVDS
compared to 3 ph. system
Protection requirements are simpler
For cost effectiveness new villages with lesser load demand can beelectrified through S ph. HVDS, which can be converted in to 3
ph. HVDS once the load picks up
Thus if Existing LVD systems are converted in to HVD systemstaking due care of the System improvement aspects in respect of
33 and 11kV Systems, HVDS will prove to be a boon forotherwise tottering Distribution networks.
-
8/10/2019 HVDS basic
27/67
CAPITAL COST
HIGHER INVESTMENT ON TRANSFORMATION EQUIPMENT
LARGER CAPACITY DUE TO LOW DICERSITY
HIGH COST/KVA DUE TO SMALL CAPACITY OF TR
LOWER INVESTMENT ON LINES
SMALL SIZE CONDUCTORS ARE ADEQUATE DUE TO
LOW CURRENTS
LESS NUMBER OF CONDUCTORS
OPERATING COST.
HIGHER TRANSFORMATION LOSSES DUE TO HIGHER NO.OF. DTrs
NO LOAD LOSSES PER KVA CAPACITY
LOWER LINE LOSSES DUE TO LOW CURRENTS HANDLED
QUALITY OF SUPPLY
BETTER VOLTAGE PROFILE
LOWER SYSTEM LOSSES
BETTER RELIABILITYPREVENTS DIRECT TAPPING OF LINES
LOAD MANAGEMENT IS EASIER
-
8/10/2019 HVDS basic
28/67
PROBLEMS AND SOLUTIONS fOR
PROBLEM SOLUTION1 Voltage bandwidth limited
to 10 %
Bandwidth can be
extended up to 20%
with a AVB online
2 Maintenance of large
number of Transformers .
ADOPT cast resin dry
technology for maintenancefree operation and reliability
These units are 25% costlier
than oil filled units.
3 Reconfiguration of
network
HVDS requires running of
continuous neutral wire from
substation.Line strengthened with
intermediate supports and stays
-
8/10/2019 HVDS basic
29/67
. Capacitive compensation Provide online switchedcapacitor banks with automatic
SF6/VACCUM switches for
maintenance free operation and
switching on and off capacitorwith load.
Sectionalisation of primary
distribution feeder .
Provide automatic
VACCUM/SF6 line
sectionalisation on the SPUR
lines which sense the voltage on
and off sequence generated bycircuit breaker at the substation
and isolate the faulty section
automatically.
-
8/10/2019 HVDS basic
30/67
Sphase motors Indigenous manufacturing
capacity for high efficiency
and high power factor motors
developed.
High transformation losses No load losses constitute50% of total system losses
Use of metal AMORPHOUS
ALLOYS for TR core which
reduces losses by 80% is very
attractive in the long run as
cost of AMORPHOUS metalis expected to come down
with increased production
immediately load
management of pump sets
can be adopted by
S f i l i
-
8/10/2019 HVDS basic
31/67
Strategy for implementation
The strategy for implementation of high voltage distribution system can
be broadly divided into two parts.First part relates to extension of HVDS to meet new loads. This
ensures that the new distribution system built is energy efficient.
Second part relates to conversion of existing LV distribution system
to HVDS.
The two parts are inter dependent and can be executed simultaneously.
-
8/10/2019 HVDS basic
32/67
Part-I of Strategy
The important problems likely to be encountered under this part are
investigated and appropriate solutions are presented.
Manufacture of small capacity single phase transformers which arerobust and fail proof.
Integration of new HVDS with existing LVDS.
Running of continuous neutral wire.
-
8/10/2019 HVDS basic
33/67
Part -II of Strategy
Part II relates to making the existing distribution system energy efficient
by conversion to HVDS.
The work involved in this phase is :
Conversion of existing low voltage lines to single-phase 2-wire HVline.
Replacement of existing three-phase distribution transformers ofconsiderable capacity with small capacity single-phase transformers
Replacing all LT Guy insulators of Stay sets by HT Guy insulators
-
8/10/2019 HVDS basic
34/67
Discussion
HVDS is technically superior and provides ready solution to theproblems of distribution system.
Capital investment required for building new HVDS is 16.5% lowerthan that of LVDS. The Peak Power loss and energy losses of HVDSare 33% and 18% lower than that of LVDS respectively.
Capital investment required to restructure the existing network asHVDS is marginally cheaper than restructuring the network as LVDS. The peak power loss and energy losses of restructuring HVDS are
lower by 25% and 27% respectively compared to that of LVDS.
The peak power losses and energy losses reduction by restructuring as
HVDS are 80% and 66 % respectively. Restructuring of existing distribution network as HVDS is highly
viable as the pay back period is about 18 months.
-
8/10/2019 HVDS basic
35/67
Conclusions
Phase neutral HVDS is identified as the best system among thedifferent HVDS schemes.
HVDS effectively tackles the problems faced by the utilities in theexisting LVDS.
The strategy proposed for implementation of HVDS and itsintegration with the existing network is found to be technicallyfeasible and financially viable.
The cluster based algorithm proposed for restructuring the existingLVDS as HVDS is an effective tool for large scale restructuring of the
existing network. The restructuring of existing LVDS as HVDS is practically feasible
and financially viable.
-
8/10/2019 HVDS basic
36/67
Summing up, the recommendation is that the utilities should adopt
HVDS in place of the prevailing LVDS; extend it to all newextensions; also restructure the existing network as HVDS
simultaneously. This is the only technically feasible and least cost
solution approach for reduction of losses in Low Voltage network.
-
8/10/2019 HVDS basic
37/67
CASE STUDY
-
8/10/2019 HVDS basic
38/67
Case Study 1-HVDS 1 Ph
In order to propogate the concept and as a technology demonstration the
following Two schemes are formulated.
-
8/10/2019 HVDS basic
39/67
g
H V D S SCHEMES
WARANGAL NALAGONDA
1.Noofpumpsets 7000 3200
2. Year of sanction 1993-94 1997-98
3. Cost of the projects Rs 8.0 cr Rs 8.4 cr
4. Pay back period 3 years 3 years
5. Achivements 2500 nos 1100 nos
6. Financed by OECF(Japan) DFID( U K )
-
8/10/2019 HVDS basic
40/67
REASONS FOR POOR PROGRESS
1. Conversion of 3 ph motors to 1 ph motors.
2. Unauthorized pump sets
3. Higher H P
4. Industrial services above 10 HP
5. Local mechanics
EVALUATION REPORT
M/S EEEC BANGLORE
OBSERVATION AND FINDING
1. Over all losses reduced from 20% to 4%.
2. Voltage level has improved substantially
3. P.F increased to 0.91 from 0.7
4. No of pump sets increased to 36% from 25%5. Possibility of theft of energy reduced
6. Pay back periods are in line with anticipated results.
-
8/10/2019 HVDS basic
41/67
SUGGESTIONS
To go for 3 HVDS by providing small capacity DTR ie 10 / 15 / 16 KVA
ADVANTAGE1.Loss reduction is same in both cases
2.Pay back period is faster
3.Consumer involve is avoided
4.All benefits relating to s HVDS conversion ie
Better VoltageReduction in interruptions and Break do wnsTheft of energy controlledReduction in DTR failuresLoss reduction etc
SI No. Item LVDS HVDS
-
8/10/2019 HVDS basic
42/67
1. Distribution Transformer 1. No 100 KVA11kv/415V
11 NOS 15 kVA
11kV/415 V
distribution Trs
2. Line LT 3 phase 4 wire line(3phase one 1 neutral)
11KV line (3wires)LT
line with AB cable
having 4 core cable
3. Length of the line LT-3.6mm HT(11kv)-2.6km & LTAB cable-1km
( both are cases of
conversion from LTLine)
4. NO. of agriculture loads
(Pumpsets)
39Nos. 39Nos.
5. Connected Load 179.5 HP 179.5 HP
6. Crop pattern Rice and Sugarcane Rice and Sugarcane but
2 crops
-
8/10/2019 HVDS basic
43/67
(a) No. of days of study 13 days 15 days
(b) Input 4290 Units 5310 Units
(c) Output 3490.4 Units 5019.8 Units
(d) Loss of units 799.06 Units 290.8 Units
(e) %Line losses 18.63% 5.47%
(f) Voltage at tail end 350V 420V
-
8/10/2019 HVDS basic
44/67
Table C: Cost benefit Analysis
Line losses before conversion :18.63%Line losses before conversion :5.47%
Connected load :179.5HPNo. of units fed into LT network per annum
(approximately 900 units/H.P) :161550
5) (a) Line losses under LVD System (units) :30097
( b)Line losses HVD System (units) :8837
6) a) Savings in losses (units) by conversion to
HVDS (units) 21260
b) Hence with the same input energy, additional units
available for sale after meeting the load demand
of 179.5HPagl.loads :21260
HVDS t ti P ti
-
8/10/2019 HVDS basic
45/67
HVDS construction Practices
HVDS conversion can be in two ways
A)Erecting a new HVDS network altogether, transferring theloads to the new system and dismantling the old system, as is
being adopted in Rajasthan where a large portion of LVDS is
already converted in to HVDS .
Push-fit covers for meters and armoured cabels for service wiresare used to curb thefts.
Where only 1 or 2 services are to be fed, Meters and capacitorsare located in a separate compartment on the backside of the
transformer.
This method permits free flow of work and reduces interruptionsto the consumer during conversion.
But it is costly and suffers from right of way problems.
-
8/10/2019 HVDS basic
46/67
B) By converting LT 3ph. 4wire into 11kV line to the extentrequired.
No new lines are needed to be laid to execute this new concept.
Re- configuration and modification of the existing lines is done,using the materials that are already in use except for a few items.
ie converting existing LT lines in to 11kV (HT) lines by replacingonly insulators, suspension and tension hardware and x arms,
introducing new stay sets where required etc.
Existing poles are continued except for introducing 9.01 mt polesin the new transformer locations, for obtaining standard
clearances.
If the existing conductors are of adequate size, 3 out of 4 areused dismantling the fourth n is carriedout during the hours when
there is no su l in a ricultural feeders. .
-
8/10/2019 HVDS basic
47/67
Using polymer insulators for 11kV line extension, for easyinstallation and puncture proof life
This method is less costlier and involves no right of wayproblems. As adopted in APSPDCL, Constructio
Specific steps needed to derive benefits in full
-
8/10/2019 HVDS basic
48/67
Specific steps needed to derive benefits in full
The new system also requires certain steps to be taken to make itwork successfully.
With increased transformers their maintenance requiresadditional attention, particularly in remote areas. Better to use
Fail proof / Cast Resin transformers.
Perfect Earthing of transformers is essential to lessentransformer failures and accidents, as these locations cannot be
revisited frequently.
HT line shall be maintained systematically, particularly in case oftree trimming, as even a momentary fault will trip the feeder.
-
8/10/2019 HVDS basic
49/67
Each transformer shall be provided with drop out switches tolocalize the unavoidable interruption.
Measures to prevent theft of oil or winding from transformers ortransformer itself, shall be adopted.
It is equally important to upgrade and strengthen the up stream
systems ie., 11kV and 33 kV systems adequately, to reap thebenefits of change in full.
In either case, survey of existing 3 phase or single phase motorloads has to be carried out ( using tongtester and measuring load
current of each motor
This is required to ensure that small capacity transformers beinginstalled under HVDS do not get over loaded and fail
Erecting New Line
-
8/10/2019 HVDS basic
50/67
Erecting New Line
Route survey to be conducted ( Preliminary walk over fallowed bydetailed survey)Route shall be as close to the loads it has to feed as
Possible, as short as possible ,avoiding difficult country side,naturalhazards, higher transportation costs etc
Transportation of RCC/PCCpoles:
a) Generally heavier and stronger on the longer axis than shorter axis.This shall be considered
b)Un loading from trucks and trailers shall be by using suitable skid
boards(Not to be dropped).Preferable to use chain pulley block and a
beam arrangement.c) Shall not be dragged on rough surfaces.Use Small carts
Pole locations
-
8/10/2019 HVDS basic
51/67
Pole locations
A) spans shall be limited by the tensile strength of the conductor,wind pressure .
In a given length span shall be uniform with horizontal grade to theextent possible
Not to be located along the edges or cuts
Cut points for a section, geneally not longer than 1,6 km (10 poles/km for HT and 15 poles/ km for LT)
Right of way shall be identified and tree and vegetation clearanceshall be carried out
HTLine Erection
-
8/10/2019 HVDS basic
52/67
HTLine Erection
Pit marking and digging
Erection of poles and concreating
Providing of Stays with guy insulators
Mounting x arms, insulators
Paying out and Stringing the conductor
Sagging and tensioning the conductor
Providing earthing and gaurdings
Testing and commissioning
Pit- 1.2mtx o.6mt
poles to be erected with its longer axis in the direction of the line.
Planting depth for pole 1/6 th of the pole length
-
8/10/2019 HVDS basic
53/67
Each pole shall be raised on a base plate or RCC padding for betterload distribution on the ground below
For smooth sliding an inclined trench of a length of 15.2cmWx10.2cm L is made adjacent to the pit and a piece of MS channel
is placed on the other side in an inclined position so that pole can
smoothly slipped in to the pit Using a Bipod and 3 ropes pole is erected and kept in vertical position
using manila ropes. Verticality checked with spirit level, earth filling
in the balance pit and ramming is done. In Swamp locations poles are
concreted up to pit level
Stay sets with 7/3.15 mm stay wire and turn buckle rod of 16mm diaae erected to prevent tilting of poles. Most commonly used is anchor
guy
-
8/10/2019 HVDS basic
54/67
.
Guy is used at angle locations, Dead ends, Tee offs, steep geadientsand where wind pressure is more than 50 kg/Sq.m Guy insulator kept
at a level of 3.5mts .Stay rod shall project 2mts. above ground level
(A type for LT line and C type for 11kV line)
At 35 to 40 inclined. After concreting and backfilling the balance 7
days are allowed for settling X-arms and insulators are fixed
Conductor drum or conductor shall not get damaged while transport,paying out.
Conductor is passed through Wooden or Aluminium rollers or snatchblock
Mid point joint through compression crimping o if helical fittings areused manually
-
8/10/2019 HVDS basic
55/67
Conductor is pulled using come along clamp, tensioned and passed onto the insulator after Sag tensioning as per the Chart
Sag d= WI/2T
I= half the Span, T= tension in the conductor
W= w+ww., w= wt. of the unit length of conductor acting
vertically
Ww= Wind pressure on the conductor
Up to 33kV sag is checked by sighting
Pin binding with tie wire
Soft annealed Aluminium wire so that may not be brittle and injurethe conductor
Length of wire 1mt to 3 mt(33kV) required for a complete
Constuction Practices
-
8/10/2019 HVDS basic
56/67
Constuction Practices
Metal supports Facto
Lattice type& compound type- not less than 1.5
Mechanically processed concrete pole- 2.0
Hand moulded concrete pole --------------- 2.5
Lattice & compound type -- not less than 1.5( under broken wire condition)
Minimum factor of safety for Guard wire,
stay wireand bearer shall not be less than 2.5, based on
Ultimate strength of the wire
Minimum FS for a conductor shall be 2 based on its Ultimate
strength
-
8/10/2019 HVDS basic
57/67
For calculating F.S.:
Max. wind pressure as specified by the State govt.
For cylindrical bodies, the effective area shall be taken as 2/3 of theprojected area exposed to wind pressure
For lattice or compound structures the wind pr. On the lee side shall
be taken as one half of the wind pressure on the windward side
Factor safety shall be calculated on the the crippling loads for thesupports used as struts and up on the Elastic limit of the tension
members
Max. and Minimum temperatures as specified by the State govt. Not withstanding any thing stated above, in locations susceptible forice accumulation loadings to be stated by govt.
-
8/10/2019 HVDS basic
58/67
Conductor tension at 32degC without external load shall not exceedthe following % of the ultimate tensile strength of the conductor
Initial unloaded tension- 35%
Final unloaded condition 25%
Conductors having a cross section of a triangular shape like
conductors composed of 3 wires, final unloaded tension at 32C shallnot exceed 30% of the ultimate tensile strength of the conductor
-
8/10/2019 HVDS basic
59/67
Rule 82: When conductors forming part of circuits of differentvoltages are to be erected on the same support, proper clearance
between circiuits of different voltages shall be ensured.
Once a line is commissioned , if any building / structure is to beerected/ extended fouling the clearances, corrective action shall be at
the cost of building / structure owner. Cost shall include a) cost of the material giving credit for depreciated
cost b) cost of retrieved material giving credit C) Cost of labour d)
supervision charges@ 15% of wages and e) any other charges
involved
-
8/10/2019 HVDS basic
60/67
TYPE Voltage level Ground clearance in mts
Across the street Low and medium voltage lines 5.8
High voltage lines 6.1 mts
Along the street Low and medium voltage lines 5.5
High voltage lines 5.8.mts
Else WhereLow and medium voltage and highvoltage lines up to 11kV bare 4.6
Low and medium voltage and high
voltage lines up to 11kV(Insulated) 4.0
High voltage lines above 11kV 5.2
Extra high voltage linesProvided minimum clearance across or
along
5.2 + 0.3 mt for every 33 kV6.1
Min. CLEARANCES in mts AT LINE
CROSSINGS
-
8/10/2019 HVDS basic
61/67
CROSSINGS
Line
volt.
22kV 33kV 66kV 110kV 132kV 220kV
250V 2.44 2.44 2.44 2.75 3.05 4.58
11kV 2.44 2.44 2.44 2.75 3.05 4.58
22kV 2.44 2.44 2.44 2.75 3.05 4.58
33kV 2.44 2.44 2.44 2.75 3.05 4.58
66kV 2.44 2.44 2.44 2.75 3.05 4.58
110kV 2.75 2.75 2.75 2.75 3.05 4.58
132kV 3.05 3.05 3.05 3.05 3.05 4.58
220kV 4.58 4.58 4.58 4.58 4.58 4.58
-
8/10/2019 HVDS basic
62/67
Rule 87: When two lines cross
It shall be as nearly at right angle as possible
As near to the support as possible
Support in the lower line shall not be erected below the upper line
Rule 88:Guarding at crossings :
Every guard wire is to be connected with earth at each point at whichits electrical continuity is broken.
Every guard wire shall have an actual breaking strength of not lessthan 635.02 kgs and if made of Iron or steel it shall be galvanized
Every guard wire or cross connected system of guard wire shall haveenough current carrying capacity so that they shall not melt or fuse
before the live line wire is rendered dead or removed
CLEARANCES of OH LINE &
S i Wi AS PER RULE 77
-
8/10/2019 HVDS basic
63/67
Service Wire AS PER RULE 77 Rule 89:No service line or tapping shall be taken of from any over
headline except from the point of support
Rule 90: Earthing
All metal supports and metallic fittings attached there to shall bepermanently & efficiently earthed.
A continuous earth wire shall be secured fastened to each pole andconnected to the earth at 4 points per every 1.609 km
Each stay wire shall be earthed efficiently or a guy insulator shall beprovided in it at a height not less than 3 mts from the ground
Spacing between the 4 points shall be equal to the extent possible Alternatively each pole and metallic fittings attached there to shall beefficiently earthed.
-
8/10/2019 HVDS basic
64/67
Metallic bearer wires supporting insulated low/ medium voltageservice lines shall be efficiently earthed/ insulated
Each stay wire shall be earthed unless guy insulator is placed at aheight not less than 10 from the ground
Rule 91 Safety devices
Every over head line laid along/ across the street shall have aprotective device to render it harmless when it brakes,
Every over head line Shall be fitted with an anti- climbing device toprevent unauthorized persons climbing the poles/towers
Rule92: Every over head line Shall be fitted with a device toprotect the line from lightning by diverting the surge to the earth
connected to earth mat
-
8/10/2019 HVDS basic
65/67
The earthing lead from a LA shall not pass through any metallic pipebut taken directly to an earth electrode in a separate earth pit
Guard wire shall be earthed at each point where its electricalcontinuity is broken
Guard wire minimum breaking strength-635 kgs
To be galvanized if made of iron or steel Guard shall have sufficient capacity not to melt or fuse till the live
wire in contact is removed
-
8/10/2019 HVDS basic
66/67
1/6th of the pole height be buried in the pit.
Base plate shall be provided underneath the pole for uniformdistribution of load on a larger area.
Pole shall be earthed through earths and combined earth resistanceshall not be more than 5 ohms