How can we reduce the “no beam„ time? Walter Venturini Delsolaro D. Arnoult, S. Claudet, G....
-
Upload
merry-barton -
Category
Documents
-
view
221 -
download
0
Transcript of How can we reduce the “no beam„ time? Walter Venturini Delsolaro D. Arnoult, S. Claudet, G....
How can we reduce the “no beam„ time?
Walter Venturini Delsolaro
D. Arnoult, S. Claudet, G. Cumer, K. Dahlerup Petersen, R. Denz, F. Duval, V.
Montabonnet, D. Nisbet, H. Thiesen
LHC Performance Workshop – Chamonix 2011
Outline
• Beam statistics for the 2010 run, H factor• How to reduce the no beam time:
– Faults statistics of top 4 systems (mitigation actions)
– Review of technical stops – Possible gains in setup time without
beam
Machine statistics 2010
Stable beams16%
Fault25%
beam setup40%
Technical stop/ HC10%
setup no beam9%
Machine statistics along the run
1 3 5 7 9 110.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
Availability
Month
% o
f to
tal ti
me
1 3 5 7 9 110.00
10.00
20.00
30.00
40.00
50.00
60.00Beam setup Setup no beam
Month
% o
f to
tal ti
me
1 3 5 7 9 110.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00Technical stop
Faults
Month
% o
f to
tal ti
me
1 3 5 7 9 110.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
Stable b...
Month
% o
f to
tal ti
me
physics oriented operation0.2 < H < 0.3
August
beam setup32%
setup no beam6%
Technical stop/ HC
7%
Fault26%
Stable beams29%
0 1 2 3 4 5 6
QPSCryogenics
PCEL+UPS
InjectorsAccess system
LBDSCol l imators
ControlsRFOP
BLMCV
Q, Qp FeedbacksExperiments
NOFMKI
VacuumBICPIC
Alarm-fi re IT
IQCsetti ngs
BPMTiming
SoftQuench
Faults downtime distribution
% of total time
70% of all faults downtime
Covered in Verena’s talk
QPS detailed statistics and mitigation actions
R .Denz
Equipment type Faults
Qty. Availability [%]
MTBF [hours]
Quench heater power supplies
26 6076 99.998 1145760
Quench detection systems 19 10438 99.999 3362135
DAQ caused by radiation (SEU)
12 1624 99.997 828240
DAQ other causes than radiation
8 2532 99.999 1936980
DAQ all faults combined 20 2532 99.997 774792
Equipment type
Mitigation
Quench heater power supplies
Replacement of faulty switches (1000), additional software interlocks allowing to continue to run MB systems with 3 out of 4 quench heater power supplies and postpone intervention to a convenient time e.g. technical stop
Quench detection systems
Removal of obsolete systems (global bus-bar detector), increase EMC immunity for Q9 and Q10, try to improve noise immunity of RU.L4 (re-cabling of current sensor)
DAQ caused by radiation (SEU)
Firmware upgrade in hot spots, i.e. point 3, point 7, L2, R8
Cryogenics downtime and perspectives (S. Claudet)
Major causes in 2010 Forecasts 2011
Cold Compressors (bearings, drives)Consolidation done at Xmas, and new diagnostics
Less failures (1 or 2)
Sub-atm filter clogging:Last leaks (P4) identified at Xmas and treated
No perturbations (possible surprise at Beg. of the run)
Valves for flow control of current leads:50% of valves changed with new type (flex bearings)
Almost no failure, existing mitigation program continued
Instrumentation:Fuses, old FPGA cards, non-conformity treated at Xmas
Less failures (max. 10?)
24V power supply units:Checks done all sites, long term repair under investigation
Few failures (1 or 2)
+ 2-5 failures due to minimal preventive maintenance
Detailed analysis fault statistics of power supplies in EDMS 1109277
PC detailed statistics and mitigation actions
Target MTBF 80000 hours
0
10
20
30
40
50
60
70
80
QD-QF IPD-IPQ Main IT 600A-10V
WarmMagnetsPoint 3 &
7
COD 120A-10V
RB WarmMagnetsexcept
Point 3 &7
Faul
ts n
umbe
r
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
Faul
ts/c
onve
rter
Faults
Faults/ converter
Check of connector contacts during winter
technical stop,ADC-DCCT Calibration
Spurious fault? Change of internal logic, being
tested
Most faults in RBA78, solved
Redesign of the earth current monitoring card in 2011-2012
In general, sensitive to Electrical perturbations
ALICE dipole: Expertise on going on the transformer, U CAPA OVER RIPPLE fault
threshold revisited
SPA reference to be revisited during 2011
HWC campaign
Spurious faults due to bad contact during the first part of 2010
3x ERD fuse blown without any problem observed on the converters (no
explanation YET)
AUG18 kV prot
UPS
Ext non RTE
RTE
EL-UPS (LHC downtime)
Electrical network perturbations
-45%
-40%
-35%
-30%
-25%
-20%
-15%
-10%
-5%
0%
0 20 40 60 80 100 120 140 160
time (ms)
Vari
ation
LHC stop
EN-EL
Zone defined in EDMS 113154
Technical Stops• In 2010 we had 6, as scheduled, starting on March 15• Pattern: 4-36-3-31-4-45-5-37-4-45-4-40+• After TS, an increment in faults was observed. Effect is
decreasing along the run
-15
-10
-5
0
5
10
15
20
25
30
1 2 3 4 5 6
TS progressive number
Faul
ts (a
fter
- be
fore
) [%
of t
otal
tim
e]
Expressed needs for TS in 2011
• Cryo: “3 TS equally spaced, 4 days each”• QPS: “at least two, first one not too late. 4
days too short”• EPC: “none, see how it goes with 60A”• EL: “frequency is not important, but 4 days too
short. Can reduce during the run but must recuperate during the Xmas break”
• CV: same as EL• Experiments?• …
0
5
10
15
20
25
30
35
40
0.0E+00 1.0E-04 2.0E-04 3.0E-04 4.0E-04 5.0E-04 6.0E-04 7.0E-04
Resistance [Ohm]
Tim
e to
ram
p do
wn
[min
utes
]
148 mH74 mHTexp 148 mHTexp 74 mH
Setup without beam: Q4 ramp down time is the bottleneck,
due to converter topology and warm cables resistances
How to ramp down faster1) Ramp down “open loop” (less precision on current with no beam)
IT becomes the bottleneck IT min time from 3.5 TeV to I min op ~ 25 minutes (H. Thiesen)
2) Add an extra cable on the mid lead:allows faster ramp down with beam (squeeze) (already studied for TOTEM high β* optics)
Would bring advantages in controllability, optics flexibility (and gain time when squeezing to low β*)
IT warm cables section “over sized”, reducing it could gain ~30% in time constant while keeping reasonable margin
Hardware changes not possible before next long shutdown
D. Nisbet at LMC 10
Access recovery
• Normal Ramp down/pre cycle
• Proposed Ramp down for short access (EDMS 1076139)
5890 A
350 A 500 A760 A
5890 A
100 A (access here)760 A
Today: need to pre cycle after access, as the main magnets are put off. A new procedure (under approval) proposes to leave them at 100 A
Magnetically almost equivalent, small effect on static b3 (Q’)
-30
-10
10
30
50
70
90
110
0 500 1000 1500 2000
Current (A)
b 3 (u
nits
)
Standby current (100 A)
End of ramp down current (350 A)
Between 350 A and 760 A:
ΔB in the bore ~ 280 mT
Penetration field is ~ 150 mT
But b3 comes from detailed distribution of magnetic moments in the cross section
Easy to solve!
Injection current
Conclusions: how can we reduce....
• Reduce fault numbers: mitigation QPS, Cryo, PC
• Review frequency and duration of TS • Faster turnaround:
– IPQs, IT: gain 10 mins with no hardware changes
– Hw changes (with gains for squeeze duration and optics flexibility) possible during long shutdown
• No pre cycle after short access (needs approval of new prodedure)
Backup slides
0
10
20
30
40
50
60
70
80
90
100
25 01 22 02 22 03 19 04 17 05 14 06 12 07 09 08 06 09 04 10 01 11 29 11
Ava
ila
bil
ity
Daily "Global LHC Cryo" weekly AVG Monthly AVG Scheduled Stops
LHC Cryo global availability
Powering tests
Perturbations: clogging sub-atm circuits-CV891-instrumentation-Shaft seals-VFD/MB-24V
Learning spring Fantastic since summer !
Results for 2010 above expectations, thanks as well to periodic technical stops
S. Claudet
Availability
90.0
91.0
92.0
93.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
12 23 34 45 56 67 78 81 Average
%
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
%
12 23 34 45 56 67 78 81 Average
Supply
Cryo
Users
ScheduledStops
Availability, as percent of the time since 1st beams
Unavailability, per origin
3.47
0.12
0.940.48
95.0
No visible impact of “1 Ref. for 2 sectors”
RF emptied during technical stops
Cryogenics detailed statistics
S. Claudet
Measurement in MBP2O1 - Aperture 1
-30
-20
-10
0
10
20
30
0 500 1000 1500current (A)
b3
(u
nits
@ 1
7 m
m)
injection -10
-8
-6
-4
-2
0
0 200 400 600 800
minimum current (A)
b3 (
units
@ 1
7 m
m)
0.2
0.4
0.6
0.8
1
1.2
b5 (
units
@ 1
7 m
m)
L. Bottura