NORTH WARWICKSHIRE BOROUGH COUNCIL
HOUSING DIVISION
ASSET MANAGEMENT PLAN
2008 - 2009
Housing Division Asset Management Plan – 2008-2009Version 5
Page 1 of 37
Contents
Executive Summary
1 Introduction and Context
1.1 Context
1.2 Scope of the Asset Management Plan
1.3 Definition and Purpose
1.4 Corporate Goals and Objectives
1.5 Lifespan and review process
1.6 Data Sources
2 Current Position
2.1 Stock Profile and Condition
2.2 Customer Profile – Meeting Housing Needs
2.3 Modern and Efficient Homes
2.4 Safe and Accessible Homes
2.5 Sustainable Neighbourhoods
3 Use of Resources
4 Review of Asset Management
4.1 Customer Profile
4.2 Engaging with Tenants
4.3 Meeting Housing Needs
4.4 Garage Sites
4.5 Stock Condition
4.6 Housing Direct Works Team
4.7 Standards
4.8 Estate and Tenancy Management
4.9 Leaseholders
4.10 Other Stakeholders
Housing Division Asset Management Plan – 2008-2009Version 5
Page 2 of 37
Executive Summary
1 Introduction and Context
1.1 Context
The Asset Management Plan for the Housing Division has developed to provide detail necessary to provide a clear direction for the management of the assets that the Housing Division manages. The Plan has been developed in a way that enables Tenants to understand the current position of the Housing Division with regard to Asset Management and future direction. The Borough Wide Tenants Forum has been fully involved in all of the decisions which have been necessary to establish the foundations set out in the Plan. This Asset Management Plan identifies the investment and maintenance needed to contribute to the Council’s strategies. The Asset Management Plan supports and is informed by the Council’s Corporate and Housing strategies.
The Asset Management Plan reflects the priorities set out in the Housing Revenue Account Business Plan. It also updates the information set out in the Business Plan which is currently under review and therefore will be used to inform the revised Business Plan.
1.2 Scope
The Housing Division Asset Management Plan covers all of the housing stock owned and managed by North Warwickshire Borough Council and includes garages and sheltered scheme communal rooms.
1.3 Definition and Purpose
This Asset Management Plan provides a framework to enable us to manage the stock proactively and support the Business Plan objectives. It helps to ensure that resources for maintaining the assets in good condition and investments made are clearly focussed.
1.4 Corporate Goals and Objectives
The objectives for the Asset Management Plan support the strategic objectives set out for the housing service in the Corporate Plan. These include achieving the Council’s Bronze Standard, the efficient and effective management of the Authority’s stock and ensuring equal opportunities in service delivery and provision.
1.5 Lifespan and review process
This plan reflects the changes and improvements made to the services the Housing Division provides during 2007 and provides a position statement for 2008/2009. It also looks to the future when a more comprehensive Asset Management Plan will be built out of the work carried out in 2008 to improve our information base across all areas of work, engage further with Tenants to continue to explore what their aspirations for their homes are and to develop plans further to improve capacity to deliver services.
1.6 Data Sources
The Asset Management Plan links strategic and operational drivers for the Housing Division’s services. In order to achieve this link this plan considers:
the profile of the stock and its condition the profile of current and future customers services required to provide sustainable neighbourhoods
Housing Division Asset Management Plan – 2008-2009Version 5
Page 3 of 37
2 Current Position
This section outlines the Council’s current position with regard to its stock and its customer profile.
The housing stock totals 2,773 as at 1 January 2008. The stock condition survey undertaken in 2004 has been updated during 2007 with the information transferred onto the Division’s housing management system. A new stock condition survey will be carried out during 2008. Section 2.1 provides information on the Council’s stock of properties, garages and sheltered scheme communal rooms. Section 2.2 gives an outline of the Housing Division’s current Tenants and potential Tenants of the future. Work will be undertaken to update these profiles during 2008 and the information used to inform service development. Section 2.3 provides information on work which has been carried out to ensure that the Council’s properties meet modern standards and are energy efficient. It also gives an indication of future programmes of work which will build on work already undertaken. This includes work to be carried out at the ex- coal board estates at Hill Top, Arley, and Piccadily, near Kingsbury. Section 2.4 sets out the work undertaken by the Housing Division to ensure Tenants’ homes are safe and accessible. It covers adaptations, gas servicing and asbestos surveys. Section 2.5 gives a broad view of how the Housing Division is working to ensure its neighbourhoods are well managed and are areas where people want to continue to live and will choose to live in the future.
3 Use of Resources
The Council has made a firm commitment as part of its Capital Programme to ensuring that the ‘Bronze Standard’ is achieved for its own stock by 2010. The commitment in financial terms is £16,945,500 until 2011. In addition, the Housing Revenue Account continues to be in a healthy position, even in the face of the demise of the Rental Constraint Allowance, and we can ensure that services required to address the Council’s landlord commitments are available. This section outlines our approach to Value for Money and procurement, as well as setting out changes to our staffing resources to improve our capacity to deliver services well.
The capital spend for the years after 2010 have been estimated on the current stock condition survey information. This equates to £2.1 million for 2011/12 to 2013/14 and £2.7 million for 2014/15 to 2017/18. However, this will be reviewed when the stock condition survey is undertaken during 2008.
4 Review of Asset Management
This Asset Management Plan sets out the Council’s current position with regard to the management of its stock. The Plan also looks forward to the development of a 10 year Plan which will be in place from April 2009. There are a number of steps which need to be undertaken to ensure the sound development of that 10 year plan. A broad outline of the work required to progress our Asset Management Plan is set out in the Plan and this includes work to be undertaken to
Improve our customer profile information Engage with Tenants Address housing needs Carry out options appraisals on our garage sites Update our stock condition information Improve the productivity and efficiency of our Housing Direct Works Team Review and set out clear service standards Improve our estate and tenancy management services Work with leaseholders Engage with other stakeholders to set out a 10 year Asset Management Plan
Housing Division Asset Management Plan – 2008-2009Version 5
Page 4 of 37
1. Introduction and Context
1.1 Context
1.1.1 North Warwickshire is a rural Borough with the largest centres of population in the market
towns of Atherstone, Coleshill and Polesworth. Atherstone is the area with the largest
numbers of Council properties. The Borough has a mining legacy and still has a working pit
in the area. The mining legacy is reflected in some of the issues the Council is dealing with
in respect of its stock – including issues such as re-generating ex coal board housing
estates and dealing with a stock which for many years housed Tenants who predominantly
preferred solid fuel heating systems.
1.1.2 This plan accords with the principles set out in the Council’s Corporate Property Strategy,
Capital Strategy and Asset Management Plan which are currently being reviewed. The
Housing Division has developed an Asset Management Plan as a separate strategy
because of the detail necessary to provide a clear direction for the management of the
assets that the Housing Division manages. The Plan has been developed in a way that
enables Tenants to understand the current position of the Housing Division with regard to
Asset Management and future direction. The Borough Wide Tenants Forum have been fully
involved in all of the decisions which have been necessary to establish the foundations set
out in the Plan.
This Asset Management Plan identifies the investment and maintenance needed to
contribute to the Council’s strategies. The Asset Management Plan supports and is
informed by the Council’s Corporate and Housing strategies.
1.1.3 The Asset Management Plan reflects the priorities set out in the Housing Revenue Account
Business Plan. It also updates the information set out in the Business Plan which is
currently under review and therefore will be used to inform the revised Business Plan. In
2004/2005 the Council undertook an Options Appraisal for its stock. The Government
Office for the West Midlands signed off the Council’s Appraisal in July 2005. The outcomes
of the Options Appraisal are reflected in the Business Plan with the Council committed to
achieving the ‘Bronze Standard’ [Appendix 1] favoured by Tenants during the Appraisal
process.
Housing Division Asset Management Plan – 2008-2009Version 5
Page 5 of 37
Corporately the Council has committed 86% of its capital programme budget to ensure that
the Council’s Bronze Standard is achieved in all of its properties by 2010. This commitment
was required in order to accord with Tenants’ favoured option which was for the housing
stock to continue to be managed by the Council. In order to ensure that its commitment to
meeting the Bronze Standard by 2010 in a way that has customers at the heart of the
process the Council has undertaken a fundamental review of how it procures its
improvement programmes with a view to ensuring value for money into the future.
1.1.4 A commitment to stock retention is also a commitment to providing homes in sustainable
communities into the future. The Housing Revenue Account Business Plan sets out the
services the Housing Division provides to achieve this and again those commitments are
reflected and updated here.
1.2 Scope of the Asset Management Plan
1.2.1 The Housing Division Asset Management Plan covers all of the housing stock owned and
managed by North Warwickshire Borough Council and includes garages and sheltered
scheme communal rooms.
1.2.2 North Warwickshire Borough Council is responsible for the management of 2773 properties
(at 1st January 2008). Appendix 2 provides the breakdown of the Council stock by location
at 1 January 2008. The Council also has of stock of 1212 garages and 22 sheltered
scheme communal rooms. It manages 105 blocks of medium rise flats.
1.2.3 The Housing Division’s vision is:
“To provide customer focussed services by well trained knowledgeable staff with
tenants fully involved at a level suitable for them at both strategic and operational
levels.”
The focus of the whole Housing Division is to manage a very important asset for the
Council corporately and most importantly for the residents who live in the Council’s
properties and on estates that the Housing Division manages. Both the Management
and Maintenance Sections work together to provide services which are aimed at
maintaining and improving the Council’s asset to ensure we provide homes and estates
where people choose to and want to continue living. This is the case whether we are
carrying out day to day repairs, bringing homes up to modern standards, managing
tenancies so that they remain in good condition or providing neighbourhood services to
keep estates to a high standard and free from anti social behaviour. Housing Division Asset Management Plan – 2008-2009Version 5
Page 6 of 37
1.3 Definition and Purpose of the Asset Management Plan
1.3.1 This Asset Management Plan provides a framework to enable us to manage the stock
proactively and support the Business Plan objectives. It helps to ensure that resources for
maintaining the assets in good condition and investments made are clearly focussed on
meeting current and future customers’ housing needs in terms of type of properties
available, location, facilities and standards.
1.4 Objectives for the Asset Management Plan
1.4.1 The objectives for the Asset Management Plan support the strategic objectives set out for
the housing service in the Corporate Plan:
To achieve the Council’s Bronze Standard by 2010 To ensure the efficient and effective management of the Authority’s stock To provide a high standard maintenance and improvement service to the
Authority’s housing stock To ensure that the Authority takes a strategic and proactive role in meeting the
housing needs and associated issues across all tenures and that housing plays a fully integrated role in corporate initiatives
To ensure equal opportunities in service provision and delivery
The plan therefore aims to:
Set out the role of the Council’s stock in meeting housing need Set out the investment committed to bring properties up to the Bronze Standard
by 2010 and start to identify investment required to keep assets in good condition beyond 2010
Start to link the maintenance and investment in the stock to current and future customer needs
Set out how we will ensure neighbourhoods are sustainable into the future Achieve value for money in the delivery of the maintenance and investment needs
in the stock
1.5 Lifespan and Review Process
1.5.1 This Asset Management Plan is a working document that drives decision-making in the
management of the Council’s housing stock of dwellings and garages and sheltered
scheme communal rooms.
1.5.2 A considerable amount of work has been carried out during 2007 to review and improve
services provided by the Housing Division to manage the Council’s assets. Firm
foundations for Asset Management into the future have been laid and provide a clear
direction. We now need to work to mature the service and work with Councillors, Tenants
Housing Division Asset Management Plan – 2008-2009Version 5
Page 7 of 37
and other stakeholders to make decisions that take us beyond 2010. This plan reflects the
changes made and provides a position statement for 2008/2009. It also looks to the future
when a more comprehensive Asset Management Plan will be built out of the work carried
out in 2008 to improve our information base across all areas of work, engage further with
Tenants to continue to explore what their aspirations for their homes are and to develop
plans further to improve capacity to deliver services.
1.5.3 This Plan will be fully reviewed and enhanced during 2008 to provide a ten-year plan from
April 2009.
1.6 Data Sources
1.6.1 The Asset Management Plan links strategic and operational drivers for the Housing
Division’s services. In order to achieve this link this plan considers:
the profile of the stock and it’s condition, and the profile of current and future customers services required to provide sustainable neighbourhoods
This information is then used to inform:
the programmes of work, the budget profile, and the methods of delivery future arrangements for tenancy and neighbourhood management services
The data used in the preparation of this plan are from:
Housing Strategy 2006 Housing Revenue Account Business Plan 2006 NWBC Asset Management Plan 2007 Housing Division Procurement Strategy Statement 2007 Housing Revenue Account Business Plan 2006 NWBC Asset Management Plan 2007 Housing Division Procurement Strategy Statement 2007 Procurement Strategy for Housing Maintenance 2007 Affordable Warmth Strategy 2007-2010 Current information about responsive repairs and stock condition data as
held on the IBS housing management system Customer Profile Information held on IBS housing management system
Housing Division Asset Management Plan – 2008-2009Version 5
Page 8 of 37
2 Current Position
2.1 Stock Profile and Condition
2.1.1 The housing stock totals 2,773 as at 1st January 2008. In summary the stock comprises:
Property Size NumberBedsit 23Flat 1 Bed 471
2 Bed 1293 Bed 10
Maisonette 1 and 2 Bed 37Houses 2 Bed 460
3 Bed 10094 Bed 55
Bungalows 1 Bed 3092 Bed 270
Total 2773
The stock can be stratified into the following archetypes which reflects the Department for
Communities and Local Government criteria and reported as part of the Business Plan
Annual Monitoring submission.
Archetype Count Pre 1945 small terrace houses 212Pre 1945 semi detached houses 304All other pre-1945 houses 21945–64 houses 6591965 –74 houses 254Post 1974 houses 158Non Traditional Dwellings 0Pre 1945 low rise flats 0Post 1945 low rise flats 185Medium rise flats 419High rise flats 0Bungalows 580Total 2773
2.1.2 A 25% stock condition survey based on a banded sample of property archetypes was
completed by FPD Savills in 2004. Since that survey was carried out further work has been
carried out to ensure the information was accurate and up to date. The information has also
been moved to the Housing Division’s housing management system so that it can be
readily used and reports can be drawn from it to inform programmes of work.
As part of the efficiencies gained because of new ways of working capacity has been
increased to be able to carry out a comprehensive stock condition survey during 2008. The
Housing Division Asset Management Plan – 2008-2009Version 5
Page 9 of 37
sample completed will be the remaining 75% of the stock not surveyed by Savills. Once this
work is complete there will be a continuous cycle of surveys every three years.
The investment planned to ensure the Council’s stock of properties is kept in good
condition is set out at Appendix 3. The Council’s housing stock is in demand with most of
the stock in good condition and has benefited from considerable investment for the last 7
years. These include programmes to upgrade kitchens and bathrooms, replace windows,
renew roofing, install external installation, installing gas central heating boilers and carrying
out electrical upgrades. Three estates of older ex coal board properties – at Ansley
Common, Hill Top Arley and Piccadilly near Kingsbury – have been highlighted as needing
considerable remedial works. These are the last of the coal board legacy properties which
require major capital work schemes to be undertaken to ensure they are sustainable in
future years. Decisions have been made to take action to improve each of the estates and
these are now being addressed and the work undertaken is set out below.
A survey of the Council’s garages was undertaken during 2007. The Council’s stock of
garages is generally in good condition although some will benefit from future painting
programmes of work and disrepair to tarmac areas is being addressed where required.
Some garage sites are in good demand from Tenants and applicants but others are not.
There are currently 160 vacant Council garages across the Borough.
The Housing Division manages 22 communal rooms as part of its sheltered schemes.
These were subject to an audit with regard to their compliance to the Disability
Discrimination Act during 2004 and work is now being undertaken to ensure all of the
rooms are accessible and user friendly. Current finances only allow for one communal room
per year to have a substantial refurbishment but work is underway to review the work
undertaken so far and where possible to carry out small-scale improvements to some
rooms until they are time tabled for major work.
2.2 Customer Profile – Meeting Housing Needs
2.2.1 The information collected on the profiles of our current customers informs what services we
deliver for our customers and how. We collect information from our current Tenants and
housing applicants. The information is based on information which has been provide by our
customers either in conversation or by way of questionnaire. We hold it in our housing
management system. It is kept up to date by way of a number of methods – routine contact,
annual visits to Tenants, at point of tenancy sign up and periodic telephone surveys.
Housing Division Asset Management Plan – 2008-2009Version 5
Page 10 of 37
96% of our Tenants identify their ethnicity as ‘British/European White’. Of the remaining
respondents ‘Irish White’ was identified as the highest ethnicity description at 3%. 96% of
our housing applicants identify their ethnicity as ‘British/European White’. Of the remaining
respondents ‘Irish White’ was identified as the highest ethnicity description at 1.9%.
Indications from our current customer profiling are that we have an older population in our
properties with only around 7.4 % of our Tenants between 18 and 25 years. This age profile
suggests that there is an ageing population in the Council’s stock but further work needs to
be done to increase the information base to ensure the information is valid and usable. The
age profile of housing applicants shows that 0.8% are under 18, 35% are between 18 and
35 and 35% are over 55 years old.
We have started to collect information from our customers about needs they might have
because of a disability. Further work needs to be done to improve the information available
and make it more comprehensive. However current indications are that around 1493 of our
Tenants has a disability of some sort that 110 of our Tenants are wheelchair users. Of
those occupiers who responded, 35.3% describe themselves as having a ‘hidden
impairment’ and 19.9% as having ‘mobility problems’. The information provides an indicator
of likely demand for future programmes and spend, for example, the refurbishment of stock
to meet disability needs and/or the adaptation of properties in response to individual
requirements.
We are carrying out further customer profile work to identify specific issues and how we can
assist Tenants – for example by collecting information on mobility (with dexterity in use of
hands as well as with walking difficulties) and whether they would benefit from adaptations
to their homes. The questionnaire and process we are using for this is attached at Appendix
6. Discovering information about customers will assist us to identify the level of service to
match individual needs both in the delivery of planned and responsive maintenance and
with regard to providing support for Tenants to enable them to retain their independence in
a positive way.
Further work is required to carry out the same profiling of future tenants. The information is
currently gathered from customers and we are awaiting the development of our housing
management software to enable us to collate and assess this information to inform service
delivery.
Housing Division Asset Management Plan – 2008-2009Version 5
Page 11 of 37
2.2.2 The Council’s annual stock turnover is low – at around 6%. The type of properties which
becomes vacant does change however profiling indicates that around 40% of vacancies are
houses 20% bungalows and 40% flats. This means that as well as ensuring focussed
services for our older Tenants we also need to consider services for younger Tenants who
may be moving into their first home to live independently and as well as support to settle in
and deal with financial issues or life skills may also require assistance to ensure that they
are able to manage their obligations with regard to maintaining their home in good condition
and repairing responsibilities.
2.2.3 The Council’s recent Housing Market Assessment (2007) has provided some useful
indicators with regard to the role of the Council’s own stock in meeting housing needs. The
research set out in the Assessment shows that there continues to be an affordability gap in
the Borough estimated at around 300 properties a year. The Council’s own stock turnover
is relatively low and therefore our work in partnership with the Housing Corporation and
Housing Associations to develop more affordable homes in the Borough remains a
corporate priority. Nonetheless our contribution is important as the largest stockholder of
affordable rent homes in the Borough so we also recognise that for the Council to continue
to provide properties where people choose to live our Asset Management must provide
properties which meet modern standards and are part of estates which are in good
condition and free from anti social behaviour. Currently we have a refusal rate of around
5% and we intend to work to sustain that.
The Housing Division is realistic with regard to the extent that its own properties can help to
meet housing need. There are 1700 applicants on the Housing Register and the Council
lets around 170 to 180 properties a year. A reasonable % of these are accommodation for
older people. The Council has for many years worked to ensure support services are
available to help older people live independently longer in their own homes. However in
recognition of the growing affordability gap and the information we have on stock turnover
will also be using our customer profiling work to discover how many properties are under
occupied and whether the Council should consider developing support and incentive
schemes to assist people to move to smaller homes in order to make better use of the
stock.
The Housing Market Assessment also mirrors our own customer profiling with regard to an
ageing population. North Warwickshire has a particularly high proportion of the younger
generation of older people (aged 60-79) compared with neighbouring districts. According to
the research 14.5% of these older people are owner-occupiers and this is lower than our
neighbouring districts. 5.4% are in social rented accommodation in North Warwickshire and Housing Division Asset Management Plan – 2008-2009Version 5
Page 12 of 37
this is higher than our neighbouring districts. The Housing Market Assessment also
indicates that expectations around space have changed and the types of housing related
support differ from the past because of expectations for continuing independence and
choice. This has implications for future decisions around the quality and sustainability of
older types of local authority bungalow accommodation (which tends to be small, one
bedroom and limited kitchen space) in terms of space standards, mobility and access
requirements as well as the balance between low level support needs (Category 1),
medium support needs, (Category 2) and higher level support needs. (Extra care services.)
This information reflects the experience of the Housing Division over recent years with older
people being less likely to accept flat type accommodation or our smaller bungalows. This
has resulted in re-designating some flats in the past and this is an area of work we will
revisit as part of this Plan.
2.3 Modern and Energy Efficient Homes
2.3.1 The Council has prioritised providing modern and energy efficient homes to meet the
expectations of both current and future Tenants. It is currently undertaking a wide range of
modernisation schemes that reflect the priorities of current Tenants. These include:
Modernising kitchens and bathrooms Installing new external doors to modern standards Ensuring all homes have double glazed windows Installing gas mains where none exist to improve choices about heating External installation
These works are carried out to high levels of customer satisfaction. They not only look to
meeting the Decent Homes Standard but to take the opportunity to work with Tenants to
ensure their homes are brought up to standards for modern living – including where
requested and possible re-designing kitchens and utilising space better. All of this work will
assist to ensure our properties meet customers expectations in the future.
The Council has set out its programme to deliver the ‘Bronze Standard’ agreed with
Tenants in the Stock Options Appraisal by 2010. The programme for achieving the Decent
Homes and Bronze Standard is progressing in accordance with the stock condition survey
information. Good progress is being made and we are on target to meet the Decent Homes
Standard for all of our stock by December 2010.
Tenants have been fully involved in setting out the programme of works for major
investments from 2008 to 2010. A table of involvement is attached at Appendix 4. A
summary of this programme has been is provided at Appendix 3. The contractor who will
Housing Division Asset Management Plan – 2008-2009Version 5
Page 13 of 37
deliver this programme will be appointed in January 2008 and will start on the programme
by April 2008. As part of the contract arrangements they will delivery of this work
collaboratively with the Council to identify any efficiency gains that can be achieved by
adjusting the programme.
2.3.2 The Council manages three estates in the Borough that require regeneration and work
above that set out in the Decent Homes Standard. These are estates at Ansley Common
(35 properties) Hill Top Arley (34 properties) and Piccadilly (36 properties). Each of these
estates has suffered from being less attractive to new Tenants than other Council
properties in the past. This is because as well as not being seen as an acceptable modern
standard internally they also have problems externally – with service roads separating
properties from gardens and large unmanageable gardens. The Council inherited a number
of properties from the coal board and spent 10 years in partnership with Housing
Associations resolving issues presented by the PRC constructed properties. Following on
from that major partnership project the Council has been keen to find the right solution for
all three of the estates – with wider objectives than refurbishment and ensuring that they
are regenerated and modernised to good standards and are attractive to current and future
Tenants.
The estate at Ansley Common is being regenerated in partnership with the Housing
Corporation and Waterloo Housing Association. Phase one of the regeneration is complete
and phase two is well underway. Phase three will begin late in 2008. The development
scheme has involved the refurbishment of some properties and has also produced some
new homes as part of the scheme all to a high specification.
Properties at Piccadilly will be improved as part of the Council’s capital programme. There
are land ownership issues here which limit the scope for external major improvements but
where possible work will be undertaken to change external areas as well as internal. Once
partnering arrangements are in place work will begin with Tenants in the spring of 2008
prepare for the refurbishment of their homes. The estate at Hill Top Arley requires
regeneration and the Council is committed to attracting funding which will facilitate both
improvement to individual properties and external areas in order to provide sustainable
homes for the future.
2.3.3 The forward Capital Programme agreed for 10 years following the completion of the major
investment programme, allows for maintaining the Decent Homes and Bronze Standard.
This has been driven by the stock condition survey and the life cycle of elements. The
capital programme is detailed in Appendix 3.Housing Division Asset Management Plan – 2008-2009Version 5
Page 14 of 37
2.3.4 The initial programme of work has been developed for 3 years. This programme will be
refreshed following the selection of a contractor partner to determine any efficiency gains in
reprogramming the work. The possibility of completing all works within a two year period
will be explored. Any revisions to the programme will be subject to consultation with Tenant
representatives.
2.3.5 As well as modernisation schemes the Council has programmes for cyclical repairs and
minor planned works. The allowance and type of work completed on the cyclical
programme is likely to reduce given the installation of low maintenance products such as
PVCu windows. However, requirements for servicing of new products introduced as part of
the major investment programme may neutralise any potential savings. This is an area of
work that we are currently assessing in order to plan services and work in the future. The
cyclical and minor planned work budget will be subject to an ongoing review in light of the
work completed as part of the major investment programme.
2.3.6 Fuel poverty is an issue for Council Tenants – especially those who live in older ex-coal
board properties that require better insulation and an alternative heating system to solid
fuel. The Council’s Affordable Warmth Strategy, 2007, aims to co-ordinate the improvement
to energy efficiency across all tenures. The priority areas for the strategy are:
Vulnerable groups; people living in areas of deprivation; older householders; families
with children; householders who are disabled or suffering from a long term illness.
Properties of all ages in all tenures.
In comparison to neighbouring authorities the annual domestic consumption of electric and
gas is higher than similar areas as demonstrated by the graphs below:
Housing Division Asset Management Plan – 2008-2009Version 5
Page 15 of 37
The SAP (Standard Assessment Procedure) rating is the Government’s
recommended measurement for the energy efficiency of dwellings. The average SAP
rating for the Council’s stock is above the national average. The Council’s housing
stock achieves an average rating of 53.06, compared to the national average of 45.
However, the local authorities in the upper quartile are achieving an average SAP
rating of 63. We are below upper quartile because of the number of properties in our
stock which still have solid fuel heating – a legacy of a predominantly mining area
with regard to the stock around Atherstone, Arley and Baddesley. The Council’s
investment programme for its own stock includes work to address energy efficiency.
The work programmed includes work to improve the insulation of dwellings through:
External insulation
Re-roofing (including increasing insulation)
Replacement of windows and doors
In addition, energy efficiency will be improved through our pro-active schemes to
replace of boilers and provide gas mains supplies in areas where there is currently no
gas and therefore increase our ability to change heating systems which are currently
heated by solid fuel systems. It is expected that the improvements will bring the
average property SAP rating up to a level in line with the upper quartile performing
authorities. In future years, in response to Tenants feedback, we will also consider
the effectiveness of storage heaters with regard to energy efficiency and running
costs for Tenants.
In addition to these schemes of work the Council is keen to maximise the opportunity
to benefit from the government’s ‘Enhanced Capital Allowance’ scheme for the
investment in equipment that meets published energy-saving criteria. NWBC will be
working with their Construction Partner and supply chain who will be involved in the
long term programme for the delivery of major investment, to identify potential new
technologies to maximise energy efficiency and cost savings.
2.3.7 As part of our most recent Tenant Satisfaction Survey we asked Tenants to prioritise
the services we provide in order of importance. 83% of those replying said repairs
and maintenance was the most important and 64% said the overall quality of their
home was the most important. The Council recognises that how we deliver our
response repairs service is an important aspect of keeping properties in good
condition. We want a comprehensive, prompt, efficient and customer friendly service
for our Tenants. Tenants have consistently told us that they prefer the services to be
delivered by the in-house team – with 93% of them judging the workforce has having
a positive attitude to customers. In view of this we have restructured our in-house
Housing Direct Works Team to extend the service they deliver and to provide a more
efficient and flexible service. The Housing Direct Works Business Plan is attached at
Appendix 7. Appendix 5 gives an indication of the costs of providing the gas servicing
work and electrical work in house. The work that the Housing Direct Works Team
carries out dovetails importantly with the improvement work being carried out by the
Housing Division and ensures properties remain in good condition once the work has
been completed. As the Housing Direct Works Team develops over the next few
years we would expect that it will carry out some improvement works itself in the
future.
2.4 Safe and Accessible Homes
2.4.1 The Housing Division carries out around 90 adaptations every year – a mix of minor
(40) and more substantial (50) adaptations. Whatever the adaptation a speedy
response to the need for adaptations makes a significant difference to Tenants. The
Housing Division is currently involved in fundamental countywide review of the
adaptations procedures in order to improve services for customers. The action plan
being used to drive the review is attached at Appendix 8.
In the interim the Housing Division is implementing new systems of working to ensure
adaptation requests are dealt with promptly and sensitively as part of our re-
structured Housing Direct Works Team. This team will deal with all requests for
adaptations – acting promptly to address minor adaptations that do not need an
Occupational Therapist referral and either doing the work to carry out larger
adaptations as part of their day-to-day work or employing specialist contractors when
necessary. Turn around performance has already improved in this area and further
improvement is expected as new systems of work bed in.
2.4.2 The Housing Division has a clear and robust stance to asbestos management. A
Type 1 survey has been carried out to develop an initial asbestos register that is
maintained electronically and forms an integral part of the housing management
system to:
identify potential asbestos for responsive repair operatives and planned work
contractors, and
inform the investment programme costs for the removal of asbestos.
A visual survey is the minimum standard for compliance with the Control of Asbestos
at Work Act 2006. However, these surveys often over-exaggerate the extent of
asbestos materials as, where there is a potential for a material to contain asbestos, it
is assumed that it does. Each material identified requires to be monitored as part of
the overall asbestos management plan. This means that we could be spending more
time and effort managing materials that in fact may not contain asbestos. In view of
this in future we will be undertaking two phases of sampling, the first of which is to
communal areas of our housing premises. These areas are currently covered by the
Control of Asbestos at Work Regulations 2006, as they are deemed as “non
domestic” properties. These surveys will be carried out within the financial year. For
the remainder of the stock properties we will be undertaking an archetyping exercise
to identify properties of similar type and age. A type 2 asbestos survey (visual with
samples) will then be undertaken of these properties. Initial investigations show that
there are approximately 420 different archetypes, which will require survey.
The information will be continually developed and updated given that:
type 2 surveys are being carried out in 2008, and
the construction partner delivering the investment programme is required to
organise a type 2 survey where potential risk is identified.
We currently provide Tenants with information about asbestos safety however more
comprehensive information will be developed when the additional survey work is
complete.
2.4.3 Ensuring gas servicing of appliances is an important area for customer safety. We
currently service 2809 appliances. This will increase in future years as we continue
our programmes to change heating systems to gas in line with customer demand
and we provide gas mains supplies to our estates which do not currently have gas
supplies. Over the last twelve months the Housing Division has improved its
performance to ensure that properties receive a gas service at the scheduled time. It
is now working to improve value for money in this area of work and to ensure that it
is a customer focussed service.
From February 2008 the Council will be carrying out the gas servicing work within its
enhanced Housing Direct Works Team. The objective here is to have a service which
is better value for money than the current contracted out service and one which is
both more sensitive and more robust in addressing issues with customers. The
capacity within the team is sufficient to anticipate the need to service more gas
appliances in the future as we convert properties to gas heating.
We have already undertaken to publicise the importance of customers allowing the
gas safety checks to be undertaken in a timely manner. It is something we stress to
new Tenants as part of the new Tenant sign up procedure. Over the next year we will
be doing more work to raise the profile of the annual service to their appliances with
Tenants.
2.5 Sustainable Communities
2.5.1 An important part of our Asset Management is concerned with ensuring that we are
delivering the right services in the right way to our customers. Part of this work is
driven by the information we have and are able to use to profile our customer base.
Another good source of information is what customers tell us about our service. We
have noted recently that there is a disparity between the feedback we receive from
older Tenants compared to younger Tenants.
An example of this is reflected in our most recent Tenant Satisfaction Survey (2006).
This indicated that in total 69% of Tenants who have had their tenancy for eleven
years and over were satisfied with the final outcome of an enquiry that they made to
the Council while this figure drops to 60% among those Tenants of under two years.
Levels of satisfaction with the final outcome also drop, for example to 45% of the 16
to 34 age group and 53% of Tenants with children.
We are doing a follow up survey to try to discover why there is this disparity but it is
clear that we must build on the positive work we already undertake to support tenants
in their homes – by using Supporting People services and settling in visits as well a
named Tenancy Services Officer contact to resolve issues and annual visits to all
Tenants. An in-house response repairs Team also allows us the flexibility to respond
to Tenants needs and to develop our service based on local knowledge and personal
service.
2.5.2 We want to provide customers with homes that they choose when the need to move
home and choose to live in for many years after that. Customers on our housing
register (including homeless applicants) have choice as part of the allocations
process. They advise which area they want to live in and there is no penalty if they
refuse an offer made to them. Our refusal rate is around 5% of offers made. However
we want to improve on how customers can choose where they want to live and are in
the process of working in partnership to develop a sub regional choice based lettings
system of marketing properties and as a consequence being able to share with
customers a lot more information about lettings in the area than we can easily do
currently. The sub regional partnership includes our Housing Association partners
who have stock in this area, is intended to include private landlords in the future and
the sub regional structure will enhance the possibility of mobility for customers.
2.5.3 We perform well in vacant property management. Our average turn around time is
currently 19 days in 2007/2008. We ensure that properties are not routinely left empty
for long periods of time causing blight to estates and compromising rent income
levels. Our allocations policy ensures applicants choose the area in which they want
to live however it doesn’t end there. We also work to ensure that new Tenants have
good information about our service and the property and area they are moving to as
well as access to support if appropriate. Before letting properties are brought up to an
agreed and publicised void property standard. Action is also taken to ensure that the
opportunity is taken to bring new lettings up to the ‘Bronze Standard’ where required.
Random checks are undertaken by members of our Borough Wide Tenants Forum to
give additional feedback on letting standards.
2.5.4 Sustainable neighbourhoods are about estates and communities as well as properties
which are in good condition and have modern standards. In general the Housing
Division has very little serious anti social behaviour on its estates – with on average
no more than 1 or 2 cases a year where a Notice of Seeking Possession or other
legal enforcement action has to be taken. When it does occur we work with partner
agencies to address issues promptly. In 2007 we asked Tenants to give us feedback
about serious problems that they experience on their estates. Their feedback is set
out below:
Litter & rubbish in the street 12%Vandalism 12%Dogs 12%Drugs dealing 9%Graffiti 7%Other crime 7%Noise from people 7%Noise from traffic 6%Problems with neighbours 5%People causing damage to your home 2%Racial harassment 1%
We are addressing these issues as part of the objectives set out for our recently
formed Post Tenancy Team. This Team has two separate but interlinked aspects –
Tenancy Services which works with individual Tenants to resolve issues and
Neighbourhood Services which ensures that communal areas of estates are in good
condition. Both Teams are pro-active – with annual visits to Tenants and publicised
estate walkabouts at the heart of the work that they do.
The Post Tenancy Team aims to respond to the needs of the area. It does have a
Tenancy Enforcement Officer to deal with tenancies with persistent and serious
nuisance issues but the general thrust is to work with Tenants and other occupiers to
individual properties and the surrounding neighbourhood are kept in good condition.
The new Neighbourhood Services Team is already making a visible impact on
estates and we now need to build on this. The Council has not yet signed up to the
Respect Standard for Housing Management but has already built the foundations
necessary to take that step.
2.5.5 A large part of the work of the Tenancy Services and Neighbourhood Services Teams
is to engage with Tenants. They do this as part of their mainstream work as well as
our specific Tenant Led Community Panels. The Panels are relatively new. We have
five Panels set up in the Borough and are working to establish more. As part of their
objectives the Panels agree to:
Find our what the important issues are in their local area and represent those
views
Promote awareness of the Community Panel in their area
Get involved with visits and events taking place in their local area and beyond
To ensure the Panels can pro-actively take remedial action on estate issues within
their area Constituted Tenant Led Community Panels can bid for monies from the
Housing Revenue Account to cover small scale environmental improvement issues
such as installing gates, erecting additional fencing, installing security lighting,
providing additional gardening services, removing or pruning bushes, erecting
signage. It is envisaged that these environmental improvements are not currently
covered by spending priorities but are important to the local Tenant community. A
sum of £20,000 has currently been set aside for the work the Panels request.
2.5.6 Listening to what Tenants tell us and acting on their feedback is at the heart of our
asset management. We understand that most of our customers cannot readily take
their ‘custom’ elsewhere and therefore we must have easily accessible ways for them
to be able to voice their opinions about our services. We want to encourage
communities to work with us. Tenant participation has grown in the Borough and we
have a well established, very strong and experienced Borough Wide Tenants Forum
who give us clear and honest feedback on our services. Over the last year they have
been involved in giving direction to all of the changes which are set out in this Plan.
We have also worked closely with Community Panels and other local groups.
However we know that we need to build on that work and involve a wider range of
Tenants in service development in the future. Our fully revised Tenant Partnership
Agreement 2007 sets out how we intend to do that.
3 Use of Resources
3.1 The Council has made a firm commitment as part of its Capital Programme to
ensuring that the ‘Bronze Standard’ is achieved for its own stock by 2010. The
commitment in financial terms is £16,945,500 until 2011. In addition the Housing
Revenue Account continues to be in a healthy position, even in the face of the
demise of the Rental Constraint Allowance, and we can ensure that services required
to address the Council’s landlord commitments are available.
3.2 Value for Money is central to our asset management. Our position is set out in the
Housing Division’s Value for Money Strategy. Specific issues pertinent to the
Division’s Asset Management Plan include:
Our approach to procuring the next stage of works to deliver improvement programmes
Improved efficiency to deliver gas servicing Improved effectiveness and better customer service in delivering adaptations Developing a more efficient and effective Housing Direct Workforce Working in partnership to regenerate older ex coal board stock
More efficient and effective cleaning and caretaking services
3.3 Procurement is a key area of business in managing our assets well. How we procure
services to manage the assets is set out in the Housing Division’s Procurement
Strategy Statement. Again the objectives set out in the Procurement Strategy
Statement are pertinent to this Plan. These include:
Achieve the ‘Bronze Standard’ target by December 2010 within or less than the budget allocation
Ensure the Response Repairs service offers good value for Tenants Have a clear customer focus in all procurement decisions Ensure that all other housing objectives are achieved within or less than the
revenue budgets Be able to prove value for money in all significant spending areas within the
housing division Maximise the use of partnership working or consortia agreements. Have arrangements in place to monitor the effectiveness of contracts and use
the information improvements in future procurement Have consideration for sustainability and equality issues in procurement
To assist us to monitor our use of resources we are working within the Housemark
benchmarking club and have also become a member of Checkmate to enable us to
carry out some specific benchmarking with regard to the work of the Housing Direct
Works team.
3.4 Over the last 12 months we have carried out a root and branch review of staffing
resources needed to undertake the services we provide. Both the Management and
the Maintenance Sections have been re-structured to both increase capacity and a
better focus on the priority service areas. Structure charts for the Management and
Maintenance Sections are attached at Appendix 9a and 9b.
3.5 The objectives set out in the Value For Money Strategy and Procurement Strategy
Statement have driven the Housing Divison’s procurement process for the selection
of a construction partner to a long term partnering arrangement for the delivery of the
major investment programme. The Council, is embracing the recommendations of
the Egan Report “Rethinking Construction – Accelerating Change”, and adopting a
partnering approach for the delivery of their planned housing investment services.
The Council recognises that by working closer with contractors and suppliers under
the umbrella of partnering, tangible improvements in terms of time, cost and quality
can be achieved. The contract awarded in January 2008 will run for 3 years plus a
further 2 years dependent on performance.
3.6 The Council’s spend on response and planned maintenance is a significant financial
commitment at around £1.7 million per year. Following its fundamental review of how
its delivers its response repairs service the Council has committed itself to developing
a modernised and effective in-house Team as key resource in how it manages its
resources in the future. As part of the review it was recognised that the structure of
the Housing Direct Works Team at that time meant that it could not perform in terms
of productive income in way that was efficient compared to other in-house teams. The
re-structure of the Team, including an expanded workforce able to tackle additional
work streams, will provide a more efficient workforce into the future while retaining the
customer focus that Tenants recommend to us about the in-house Team. Additional
work streams include the delivery of cyclical maintenance so that the optimum size of
the business is reached to ensure that the service within each area can be sustained.
Working across planned and responsive work streams will mean that overhead costs
are better value and staffing resources can be management across work streams to
maximise productive time.
The annual spend profile for cyclical works is around £320,000 per year. The cyclical
and minor planned work budget will also be subject to an ongoing review in light of
the work completed as part of the major investment programme. For example, where
major investment is being carried out to bathrooms, any adaptations required for level
access showers will be installed. The spend profile and type of work completed for
cyclical works will be reviewed to determine changes to the profile of the budget in
light of the impact of the major investment programme.
3.7 The level and type of repair spend will be monitored as the housing investment
programme is delivered, with the aim of decreasing responsive and void spend as
the level of capital spend increases. The key spend target for responsive and
cyclical and minor planned work is responsive at 30% of the total cost and planned
work at 70%.
3.8 The capital spend for the years after 2010 have been estimated on the current stock
condition survey information. This equates to £2.1 million for 2011/12 to 2013/14 and
£2.7 million for 2014/15 to 2017/18. However this will be reviewed in when as the
stock condition survey is undertaken during 2008.
4 Review of Asset Management
4.1 This Asset Management Plan sets out the Council’s current position with regard to
the management of its stock. The Plan also looks forward to the development of a 10
year Plan which will be in place from April 2009. There are a number of steps which
need to be undertaken to ensure the sound development of that 10 year plan. A
broad outline of the work required to progress our Asset Management Plan is set out
below and more specifically in the action plan that is appended to this report.
4.2 Customer Profiling
4.2.1 It is crucial to the soundness of the Asset Management Plan that our profile of our
customers is comprehensive and accurate. We have made progress to develop our
customer profile – both for Tenants and Housing Register Applicants but recognise
that much more needs to be done. We have refreshed our customer profile
questionnaire and our procedures for collecting information. We will be carrying out
some intensive work on this from February to May 2008 with the aim of having key
information on most of our customers that is sufficient to inform what services we
need to develop and change over the next 10 years.
4.2.2 It is likely that the impact of an aging population will figure significantly in future plans.
This will reflect information provided in our own customer profiling and that provided
by the Housing Market Assessment 2007. We are already exploring how we can work
closer with Warwickshire County Council and the Primary Care Trust to provide better
services for older people in partnership. We will also use this information and
combine it with feedback we receive from customers in the lettings process to
consider which of our properties are designated for older people in the future and
what facilities those properties require. In addition we will be carrying out a review of
the use and accessibility of our sheltered scheme communal rooms to ensure that
they are fully utilised and contribute to the ability of older people to remain
independent in the community.
4.2.3 The information on the needs of individual customers due to disability will be used to
inform repair and major investment services. Information is readily available to all
staff on our housing management systems and with the Tenant’s permission, the
information will be made available to external contractors procured for the delivery of
planned and major improvement works.
4.2.4 We will also be working in 2008 to better understand how we can meet the needs of
our younger tenants. The most recent Tenant Satisfaction survey indicated that the
older Tenants were happier with the Division’s services than younger people. We will
use our customer risk assessments to assess what services Tenants need from us.
This will enable us to help younger Tenants as well as older residents. Looking to
assist younger tenants, for example, who could need help to settle into their property.
This will include support from named Tenancy Services Officers, providing additional
support services if required and assistance from the Housing Direct Works Team to
understand basic maintenance. During 2008 we will be introducing a repairs
handbook for tenants with diagrams, pro-active offers to show them how to get the
most from their heating systems, clear indication of basics with regard to looking after
the property and assisting them to be able to act to meet their own repairing
responsibilities.
4.3 Engaging With Tenants
4.3.1 Ensuring our services are focussed will also depend on how we are able to engage
with Tenants in future years and to enable them to tell us what services they need.
We will be building on the work we currently do in a number of ways. As well as a
menu of different ways Tenants can participate in directing the services the Housing
Division provides set out in our Tenant Partnership Agreement we are developing
services in such a way that they are closer to Tenants who can then more readily tell
us about issues relevant to them – these include annual tenancy visits, developing
neighbourhood services and increasing the capacity of our in-house Housing Direct
Works team. During 2008 we will be working to mature current systems so that we
improve how we capture and use the information Tenants give us on an informal and
formal basis. This will include how we deal with and use complaints and compliments.
4.4 Meeting Housing Needs
4.4.1 We want to provide homes on estates where people choose to live. During 2008 we
will be developing a Choice Based Lettings system with our sub regional partners. As
part of this work we will monitor and analyse very closely in which areas and
properties customers are expressing an interest. We will analyse this by area and
property type and use it to inform our view on the demand for our stock.
4.4.2 The Council has always been keen to work with Housing Association partners to
bring additional funding into the Borough to refurbish properties and re-generate
properties where there is a clear benefit for Tenants. However, transferring stock to
Housing Associations in addition to stock lost through Right to Buy sales, does mean
a reduction in our assets and as we do our scheme by scheme option appraisals we
do have an eye to the continued viability of the size of our stock. We have noted with
interest the Government’s encouragement to Local Authorities to consider whether
they can develop homes themselves. The Council is not currently in a position to
develop new homes itself but to do so will be a consideration in future Asset
Management Plans. In the meantime we will continue, as part of our Housing
Strategy, to work closely with the Housing Corporation and Housing Associations to
develop additional affordable homes in the Borough to meet needs which compliment
what its own stock provides. In addition we will consider information available to us as
part of our household profiling to consider how we can ensure that we are able to
make the best use of our own stock by considering the possibility of using incentive
schemes – including support to move - to encourage single people who are currently
under occupying family homes to move to smaller properties. This will, of course, be
balanced against respecting a Tenants right to remain in their current home if that is
their wish.
4.5 Garage Sites
4.5.1 During 2007 we carried out a desk top review of garage sites. This revealed that the
Council’s stock of garages is in good condition but vacancies are an issue. During
2008 we will continue with the review of the garage sites with a significant number of
vacancies with a view to carrying out options appraisals to inform decisions on the
viability of the sites and whether they would be better utilised as land to develop small
schemes for affordable homes. Limited parking is an issue on many of our estates so,
as well as undertaking options appraisals to understand the viability of sites we will
also be considering our lettings policy for garages and also our marketing of the
availability of Council garages to rent to encourage car owners to park their vehicles
off the street.
4.6 Stock Condition
4.6.1 A further stock condition survey will be carried out during 2008 and the information on
the stock updated further. This will be used as the base line to determine the spend
profile of capital investment work over 10 years. This programme will be reviewed
and developed in light of service needs and customer profile as well as resources
available to carry out works to keep the stock in good condition.
4.6.2 There is a process of continual updating of the information contained on the asbestos
register. This will be assisted by the Type 2 survey that will be undertaken in 2008.
The results of this survey will be used to update our stock condition information and
will also influence the development of the Asset Management Plan in the future.
4.6.3 The Affordable Warmth Strategy is now coming to fruition with workshops undertaken
to ensure actions are addressed and a conference arranged for March 2008 to raise
the profile of this work. The outcomes from the workshops and conference will
influence the content of the Asset Management Plan from 2009. In addition the work
which is progressing to install gas mains to Council estates which do not currently
have them to enable different choices in heating systems will make a serious impact
on the Council’s ability to ensure its Tenants have warm and energy efficient homes
in the future. The capital investment programme also addresses the replacement of
elements to improve the thermal efficiency of the Council’s housing stock. The
benchmark information on consumption levels of gas and electricity and SAP ratings
will be used to monitor the effect of the investment programme
4.6.4 Progress against our plans to re-generate the Council’s estates at Piccadilly and Hill
Top will have a considerable impact on our Asset Management Plan because these
are the areas which currently require the most significant capital investment and work
with Tenants to improve them and ensure they are sustainable communities beyond
the requirement for Decent Homes Standard work. Tenant consultation in both areas
will continue through to April 2008 as improvement plans are developed and finalised.
It is hoped that the option to develop Hill Top in partnership with Waterloo Housing
Association and therefore include extensive environmental works and a different mix
of tenures on the estate will be progressed positively. The Council’s partnering
contractor will refurbish the properties at Piccadilly. Work is likely to begin in Hill Top
and Piccadilly from April 2008 and will certainly be complete by December 2010.
4.6.5 As part of the stock condition survey the Housing Division will also carry out options
appraisals on the Council’s stock of shops which it leases. The appraisal will consider
the condition of the buildings and funding commitments to keep them in good
condition, demand for the premises and whether, if they are part of a site that is being
developed for affordable housing, they should be re-built and kept in Council
ownership.
4.7 Housing Direct Works
4.7.1 The decision to keep an in-house work force is a key platform in the Council’s
strategy to manage it property assets not just in the short term but into the future.
Work is well underway to change how we deliver response repairs and planned
programmes of work through the enhanced Housing Direct Works team. The scope of
works that the Housing Direct Works will team will undertake will be broadened to
include all of the work included in the Housing Repairs Fund include planned revenue
and cyclical works and will allow the introduction of new trades into the business,
namely:
Pre paint repairs Disabled adaptations Gas servicing and central heating repairs Electrical testing and remedial works Concessionary decorations Solid fuel servicing Minor planned works
The success of this endeavour over the next 12 months will have a major influence
on how we work on a daily basis to keep the Council’s housing stock in good repair,
work with vulnerable Tenants and work to meet customers’ needs for adaptations.
4.7.2 We are in the process of analysing responsive repairs and voids. The analysis model
allows for the cost of responsive repairs by estate to be monitored against the
delivery of improvements by area. We will use this information to inform and identify
our work to reduce the proportion of responsive to planned work to 70% planned and
30% responsive. In addition the model will assist with monitoring sustainability with an
on-going review of housing management measures by estate outlined in a ‘Red,
Amber, Green’ model will provide the basis for review of the Asset Management Plan
to ensure investment is targeted at supporting the maintenance of a sustainable stock
4.7.3 There will be an impact on cyclical and planned maintenance because of the
installation of low maintenance elements replaced as part of the major investment
programme the level and type of work completed on the cyclical programme is likely
to reduce. However, requirements for servicing of new products introduced as part of
the major investment programme may neutralise any potential savings. The Asset
Management Plan therefore determines the need for the cyclical maintenance budget
to be held at the same level as before the major investment programme.
4.8 Standards
4.8.1 During 2007 we have worked extensively with Tenants to develop service standards.
During 2008 we will build on this and develop them further – for example to ensure
that cyclical and minor planned works will be subject to the same service and
consultation standards as major investment work. This will include:
Responding to ethnicity, age, disability Information Choice Code of conduct Satisfaction
4.8.2 We recognise that carrying out improvement works to their home is a significant event
for our Tenants. Tenants have been involved in the selection of the contractor partner
for the delivery of the major investment programme and will be involved in the
delivery structure for the major investment programme. However our work with
Tenants will not stop there. During 2008 Tenant representatives will be represented
on the Partnering Core Group and Task Teams and in addition representatives of
areas where the major investment programme is being delivered will be part of the
work package delivery team meetings.
4.9 Estates and Tenancy Management
4.9.1 Our Forward Work Plan makes a commitment to work towards signing up to the
Government’s Respect standard for Housing Management in 2008. We will use this
process as a vehicle to build on the positive work undertaken to improve the capacity
of the Post Tenancy Team and therefore their ability to be pro-actively engaging with
Tenants to ensure estates are in good condition, support services are available for
those who need them and nuisance behaviour is curtailed.
4.10 Leaseholders
The Council has 97 leaseholders. Their wish to participate in the Housing Services
has been limited in the past. However we do undertake an annual survey and during
2008 as well as being consulted about our major improvement programmes they
were also invited to participate in the process. We will use the feedback leaseholders
have given us to review and improve our consultation processes in the future.
4.11 Other Stakeholders
As we develop a more extensive Asset Management Plan we will involve other
stakeholders to help us shape its content. This will include external partners - our
contractors, Housing Associations, the County Council - as well as internal partners –
Streetscape, Community Development, Community Support.
Housing Division Asset Management Plan 2008-2009Relevant Actions from Forward Work Plan that will assist to progress the Asset Management Plan & Supplementary Objectives
Vision for the ServiceThe provision of a customer focussed service by well-trained knowledgeable staff with tenants fully involved at a level suitable for them at both strategic and operational levels.
Action Community Plan, Corporate,
Divisional Objective or Policy the task
relates to
Lead Officer Start Date
End Date
Priority Measurement of Success Resources – including Value for Money (VFM)
Implications
Improve Customer Profile information and keep up to date
Quality ServicesCustomer Access Strategy
Performance and Quality Officer
Feb 2008
April 2009
High Undertake a telephone questionnaire with Tenants to ascertain information to inform service provision by April 2008
Procedures in place to ensure information continues to be updated and collected
Clear evidence of use of information to change and improve services
Staff time to input and collate information.
Better information will ensure we can improve how we manage our information to Tenants
Progress action plan for older persons strategy
Community LifeHealth and Well Being
Housing Strategy & DevelopmentOfficer
May 2008
March 2009
High Progression of actions will include:
Work with County to
provide extra care scheme
in the Borough
Provide low level support schemes to assist with independent living
Improve adaptations processes
Staff Time
Working in partnership to pool resources
Progress Affordable Warmth Strategy Action Plan
Community LifeHealth and Well BeingCustomer Access
Housing Strategy & DevelopmentOfficer
March 2008
April 2010
High Progression of actions will include: Operate an affordable
warmth work group Hold a conference in
Staff Time. Information in the strategy will be used to better direct Council funds and to
Page 32 of 37
Action Community Plan, Corporate,
Divisional Objective or Policy the task
relates to
Lead Officer Start Date
End Date
Priority Measurement of Success Resources – including Value for Money (VFM)
Implications
Strategy March 2008 to raise awareness
Improve heating & insulation in Council stock
access external funding and partners to further the aims of the Strategy.
Progress Equalities Policy
Community LifeHealth and Well BeingSocial InclusionCustomer Access Strategy
Principal Housing Management Officer& Housing Policy and Strategy Officer
January 2008
March 2009
High Set up Divisional equalities group
Progress work to have comprehensive customer profile base
Improve monitoring on equalities
Ensure new staff have equalities training
Increase numbers of staff who have equalities impact assessment training
Staff time
Work with sub regional partnership to introduce Choice Based Lettings Scheme
Quality ServicesSocial InclusionCustomer Access Strategy
Principal Housing Management Officer
Feb 2007
June2008
High Progress against the project plan for the sub regional partnership
Progress against the project plan for the delivery of the scheme locally.
Events to raise the profile of the scheme with customers and partners.
Choice Based Lettings Scheme in place by June 2008.
Government grant for the partnership is £108,000. North Warwickshire’s contribution is around £10,000 and is included in the 07-08 budgets
Working in partnership has attracted Government grant and resources and expertise will be shared.
Progress work against Respect Standard for Housing Management
Community SafetyQuality Services
Principal Housing Management Officer
April 2008
March 2009
High Improved procedures for monitoring anti social behaviour
Improved engagement with residents about anti social
New staffing arrangements are in place which provide improved capacity
£20,000 is available to
Page 33 of 37
Action Community Plan, Corporate,
Divisional Objective or Policy the task
relates to
Lead Officer Start Date
End Date
Priority Measurement of Success Resources – including Value for Money (VFM)
Implications
behaviour in their area
Improved performance management arrangements with Tenants and Councillors
Community Panels to tackle estate issues
Continue to work with Supporting People to progress support service for older people.
Health and Well BeingQuality Services
Principal Housing Management Officer
March 2008
March 2009
High Achievement of level ‘B’ against the Supporting People Quality Assessment Framework
Consistent achieving contract numbers of 50 people being supported by the service
Funding of £44,000 from Supporting People is in place until April 2009.
To ensure that the Council’s stock condition data is accurate and up to date.
To achieve the Council’s Bronze Standard by 2010
ContractsManager
April 2008
March 2009
High Appoint member of staff to carry out stock condition survey
Update stock condition information held on housing management software.
Implement procedures in place to keep the data up to date.
Staff reduction through efficiencies are being re-invested to employ a member of staff for 12 months to carry out the survey.
Having accurate and current stock information will ensure the Council’s resources are well directed.
Review programme of works to improve sheltered scheme communal rooms
Quality Services Contracts Manager
May 2008
Feb2009
Medium Audit of rooms to ascertain accessibility & condition
Revised programme of works in place to address issues in the audit
Staff Time
Capital programme
To develop a comprehensive 10 year Asset Management Plan for the
To achieve the Council’s Bronze Standard by 2010
Maintenance Manager
April 2008
April 2009
High Implement action plan set out in the current Asset Management Plan
Present an up to date and
Staff Time
Capital programme
Housing Revenue Account
Page 34 of 37
Action Community Plan, Corporate,
Divisional Objective or Policy the task
relates to
Lead Officer Start Date
End Date
Priority Measurement of Success Resources – including Value for Money (VFM)
Implications
Council’s stock of dwellings and other related assets managed by the Housing Division
comprehensive Plan to Tenants and Members by February 2009 The Asset Man Plan sets
out agreed priorities and ensures resources are well directed.
Achieve the Council’s ‘Bronze Standard’ for its own stock by December 2010
To achieve the Decent Homes Standard by 2010
Maintenance Manager
Feb 2008
Dec2010
High Partnering contract in place to deliver improvement programmes.
Develop new procedures in to monitor the partnering contract
Clear processes to involve Tenants throughout the work programmes.
Resources for the programme of works has been agreed.
Improved procurement methods have VFM principles at their heart.
To act on the Council’s decisions to implement improvement programmes at Hill Top
To achieve the Council’s Bronze Standard by 2010
Principal Housing ManagementOfficer
April 2008
Dec2010
High Clear progress of scheme of works against project plan
Clear procedures in place for involving Tenants throughout the improvement scheme
Working in partnership to regenerate this estate will bring in additional funds to improve the scheme of works that can be carried out.
Provide gas mains supplies to Council estates which do not currently have gas mains supplies
To achieve the Council’s Bronze Standard by 2010
MaintenanceManager
Feb2008
Dec2010
High Complete consultancy work to set out how the work can be carried out and prepare tender specificationProcurement of contractor to undertake work to provide gas mains supplies in accordance with specification
Page 35 of 37
Action Community Plan, Corporate,
Divisional Objective or Policy the task
relates to
Lead Officer Start Date
End Date
Priority Measurement of Success Resources – including Value for Money (VFM)
Implications
To act on the Council’s Housing Direct Works Business Plan to develop an effective and efficient work force.
Quality Service DeliveryAccess to Services
Maintenance Manager
January 2008
April 2008
High Actions taken to fully implement the Business Plan will include:
Customer friendly appointments system
Provide a repairs handbook for Tenants
Improve performance to provide adaptations
Improved productivity of workforce
Undertake quality assessments
Undertake benchmarking of the service to assist in measuring performance
Improved procurement of supplies and services
Around £1.7 million is spent on the Council’s response repairs service for Council Tenants
Review Asbestos Management Plan in light of new arrangements for providing response repairs service
Quality Service Provision
Maintenance Manager
January2008
Oct2008
High Revised procedures in place for asbestos management
Implementation of a Type 2 asbestos survey.
Improved information produced for Tenants
Budgetary allowance is in place to carry out the Type 2 survey.
Carry out a review of Council owned garages
Quality Service Provision
Principal Housing Management Officer
May 2008
April 2009
Medium Produce information profile on all Council garage sites
Carry out options appraisal with regard to demand and development opportunities on relevant garage sitesReport to Resources Board on findings
Staff time
The information will be used to improve the management of garages – including income generation.
Page 36 of 37
Action Community Plan, Corporate,
Divisional Objective or Policy the task
relates to
Lead Officer Start Date
End Date
Priority Measurement of Success Resources – including Value for Money (VFM)
Implications
Carry out a review of Council owned shops
Quality Service Provision
Principal Housing Management Officer
May 2008
April 2009
Medium Produce information profile of Council owned shops
Carry out options appraisal with regard to demand and development opportunities
Report to Resources Board on findings
Page 37 of 37