July 15, 2019 Construction began on Monday July 8 th , 2019 by removing the existing roadway where the tunnel will be constructed and installed. Last week the contractor wasted no time by quickly starting to excavate for the east wing wall footing as well as setting forms and tying rebar. Concrete was poured this morning for the footings. Moving forward this week and into the next, the contractor plans to continue work on the wing walls and excavate for the installation of the precast box culvert that will be installed next week. They also plan to relocate the Serpent Lake Sanitary Sewer District’s forcemain. Below are a few photos from the first week of construction. /home/website/convert/temp/convert_html/5f35fe8bdd03fa518a69972b/document.docx Excavation of the East Wing Wall

Transcript of Home Page - Bolton & Menk · Web viewConcrete was poured this morning for the footings. Moving...

Page 1: Home Page - Bolton & Menk · Web viewConcrete was poured this morning for the footings. Moving forward this week and into the next, the contractor plans to continue work on the wing

East Wing Wall Foundation Forms Set

Preparation of the East Wing Wall Foundation

July 15, 2019

Construction began on Monday July 8th, 2019 by removing the existing roadway where the tunnel will be constructed and installed. Last week the contractor wasted no time by quickly starting to excavate for the east wing wall footing as well as setting forms and tying rebar. Concrete was poured this morning for the footings. Moving forward this week and into the next, the contractor plans to continue work on the wing walls and excavate for the installation of the precast box culvert that will be installed next week. They also plan to relocate the Serpent Lake Sanitary Sewer District’s forcemain. Below are a few photos from the first week of construction.

/tt/file_convert/5f35fe8bdd03fa518a69972b/document.docx

Excavation of the East Wing Wall (Tunnel Entrance)

Page 2: Home Page - Bolton & Menk · Web viewConcrete was poured this morning for the footings. Moving forward this week and into the next, the contractor plans to continue work on the wing

East Wing Wall Foundation Iron Rebar Placement

Concrete Pour for the FoundationF

TH 6 Multi-Use Trail Tunnel Project Construction UpdateJuly 15th, 2019

/tt/file_convert/5f35fe8bdd03fa518a69972b/document.docx