Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy –...

62
Harris Nuclear Plant Nuclear Regulatory Commission - Region II Presentation September 23, 2003

Transcript of Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy –...

Page 1: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Harris Nuclear PlantNuclear Regulatory

Commission - Region II Presentation

September 23, 2003

Page 2: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Introductory Comments

Jim Scarola

Page 3: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Agenda

Plant Overview – Bob DuncanReliability Improvement Initiative – John DillsEquipment Related Improvements – Garry MillerPerformance/People and Risk-Related Improvements – Ed WillsSelf Evaluation Program – Terry MortonLooking Ahead

Page 4: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Harris Organization

J. Scarola Vice President

Harris Plant

R.J. Duncan, IIDirector

Site Operations

J.W. GurganiousManager

Nuclear Assurance

T.C. MortonManager

Support Services

(Vacant)Manager

Engineering

E.A. McCartneyManagerTraining

B.C. WaldrepGeneral Manager

Harris Plant

G.D. MillerManager

Maintenance

D.G. SimmonsSuperintendent

Radiation Control

E.L. Wills, Jr.Manager

Operations

J.F. BriggsSuperintendentEnv & Chemical

T.J. NataleManager

Outage & Scheduling

Page 5: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Harris Plant Overview

Bob Duncan

Page 6: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

1999 Improvement Program“Above the Rim”Aggressive Goals EstablishedFocus:

Human PerformanceEquipment ReliabilitySelf Evaluation

Harris

Page 7: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Harris Plant Self-Evaluation

Program Components:Self-AssessmentCorrective ActionOperating ExperienceBenchmarking

Integrated Via Corrective Action ProgramFoundation For Continuous ImprovementLed by Line Organizations

Page 8: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Commitments RealizedImprove Nuclear SafetyIndustrial SafetyHuman Performance Plant Material ConditionZTEF ProgramALARAChemistrySecuritySpent Fuel ShippingOutage Planning/Execution

Page 9: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Commitments Realized

Operational FocusOSI/PIEmployee DevelopmentOperator PipelineDiversity

Page 10: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Risk Reduction Programs

Secondary Chemistry ImprovementsZero Tolerance For Equipment FailureFire ProtectionALARAEmergency PlanningReactor Head Inspection Self Evaluation

Foreign Material DiscoveryPlant Security

Page 11: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Harris Plant Security

NRC “Interim Compensatory Measures Order” (February 25, 2002)Facility ModificationsPlant Equipment UpgradeProcess/Procedure ChangesSecurity Staffing & TrainingPlant Access ControlsCoordination & Liaison With Federal, State & Local AgenciesOctober 21-25, 2002, Tabletop Drills

Page 12: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Fire Protection

Safe Shutdown Analysis ReconstitutionPlant Modifications in DevelopmentHarris Team Communicating With Region II InspectorsIn Touch With Industry Actions for Associated Circuits

Page 13: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Harris Nuclear PlantPerformance Summary

2Q03Reactor Safety

Radiation Safety Safeguards

Initiating Events

Mitigating Systems

Barrier Integrity

Emergency Preparedness

Occupational Radiation Safety

Public Radiation Safety

Physical Protection

Performance Indicators

Occupational Exposure Control

Effectiveness

RETS/ODCM Radiological

Effluents

Protected Area Equipment

Personnel Screening Program

FFD / Personnel Reliability Program

Drill / Exercise Performance

ERO Drill Participation

Alert and Notification

System

Reactor Coolant System Specific

Activity

Emergency AC Power System Unavailability

UnplannedScrams

Reactor Coolant System Leakage

High Pressure Injection System

Unavailability

Emergency System

Unavailability

Residual Heat Removal System

Unavailability

Safety System Functional

Failure

Scrams With Loss of Normal Heat Removal

Unplanned Power

Changes

Significant Inspection Findings

Air Monitors Inst. Calibration

No Findings this Quarter

Strategic Performance Areas

Cornerstones

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

Fire Protection 9 URIs

4Q/2002

No Findings this Quarter

3Q/2002

No Findings this Quarter

FFD – Failure to withhold access

No Findings this Quarter

No Findings this Quarter

1Q/2003

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

LTA 50.59

No Findings this Quarter

RWST L/T Flooding

No Findings this Quarter

No Findings this Quarter

No Findings this Quarter

2Q/2003Loss of CCWLTA Procedure

AFW Actuation

No Findings this Quarter

Page 14: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

HNP NRC CommitmentsInspections With No Findings2002:

SSDIEPModifications/50.59Maintenance RuleOperator Training

2003:PI&RHeat SinkSecurity – ICM ImplementationOutage – RPOutage - ISIOutage – Vessel Head / Boric Acid ControlSimulator

Page 15: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Key Performance IndicatorsINPO Index

60

70

80

90

100

1997 1998 1999 2000 2001 2002 2003YTD

Inde

xIn

dex

99.099.0Top Quartile Threshold

82.5

93.7

89.3

78.3

89.1 96

.6

99.0

Page 16: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Key Performance IndicatorsRadiation Exposure (Person-Rem)

300

1997 1998 1999 2000 2001 2002 2003Aug YTD

133

16 101 77

149

0

50

100

150

200

250HNP Annualized HNP Annualized

ExposureExposurePer Fuel CyclePer Fuel Cycle

Top Quarter Threshold

(Fuel Cycle)

67.467.4Pers

onPe

rson

-- RemRem

252

18 Month Actual is Currently 46.1 Rem 18 Month Actual is Currently 46.1 Rem

62.4

Page 17: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Key Performance IndicatorsChemistry Index (Fuel Cycle)

Che

mis

try

Inde

xC

hem

istr

y In

dex

1.001.00

1.04

1.0

1.2

1.4

1.6

1997 1998 1999 2000 2001 2002 2003YTD

Top QuartileThreshold1.2

7 1.34

1.36

1.24

1.15

1.08

2003 YTD Actual is Currently 1.00 2003 YTD Actual is Currently 1.00

Page 18: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Key Performance Indicators Capability Factor (Fuel Cycle - 18 Mo. Avg.)

Top Quartile Threshold

83.3

92.3 93.3

81.5 80.6

93.789.2

60

70

80

90

100

1997 1998 1999 2000 2001 2002 2003Aug YTD

%%

93.393.392.6

Page 19: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Key Performance Indicators Refueling Duration (Days)

77.0 73.367.5

80.5

54.5

40.9

65

36.027.4

103.4

22.6

0

20

40

60

80

100

RFO1

RFO2

RFO3

RFO4

RFO5

RFO6

RFO7

RFO8

RFO9

RFO1

0RF

O11

Day

s

Page 20: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Key Performance Indicators Forced Outage Hours (Full & Partial)

Equi

vale

nt H

ours

Equi

vale

nt H

ours

Current HNP 3-Year Forced Loss Rate is 1.3%

486545

374398

7724

142193

200

367

468

324276

177 166

0

100

200

300

400

500

600

1995 1996 1997 1998 1999 2000 2001 2002

HNP HNP 3 Year Average3 Year Average

Top Quartile Threshold 3 Year Average

7979

2003Aug YTD

55133

81

Page 21: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

HNP Improvement Plan Status

Trip Reduction Initiative

John Dills

Page 22: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Strategy – The Three “R’s” Reliability

PMsMonitoring

RedundancyEliminate Single-Point VulnerabilityECRs

ResiliencySurvive Ability

HNP Improvement Plan StatusTrip Reduction Initiative

Page 23: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Equipment Related Improvements

Garry Miller

Page 24: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

ZTEF Zero Tolerance for Equipment FailuresCulture of Intolerance for Unplanned Equipment FailuresFocused on Critical Components3-Phase Implementation

Instill ZTEF Culture and VisionIdentify Critical ComponentsDevelop Integrated Management Strategy

Page 25: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

ZTEF Phase 3 Current Status

Pilot on 5 Systems CompletedMaint and failure historyOE, EPIX, EPRI PM Basis Documents

Lesson Learned to Remaining SystemsPhase 3 Complete by End of 2004

Page 26: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

0

20

40

60

80

100

120

140

2001 2002 2003

Unplanned LCOs

ZTEF Unplanned Action Statement Entries

YTD as of 8/30/03

Page 27: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

0

50

100

150

200

250

2001 2002 2003

On-Line Backlog

ZTEFOn-Line Corrective Maintenance Backlog

Actual as of 8/30/03

Page 28: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

R-11 Outage - 1A Bus Repairs

UAT feed to 1A Non-safety BusBus Bar Insulation Deficiencies Identified during Planned InspectionsRepair Options InvestigatedPermanent Repair Completed

Page 29: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

R-11 Outage - 1A Bus Repairs

Page 30: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 - ECCS Vent Modification

SOER 97-01PM established for NDERouted CSIP Recirculation Flow to VCT topInstalled 14 additional vents in 9 locations

Page 31: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 - ECCS Vent Modification

Page 32: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – ESW Inspections

2700’ of Large Bore Piping Inspected and Cleaned

No Significant findings~100’ Small Bore Piping ReplacedHeat Exchangers in Good Overall Condition

Fouling Significantly Less than RFO-10Few Tubes Required Plugging

Page 33: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – Reactor Head InspectionsSpare Reactor Vessel Head Used for Mock-up TestingComprehensive Inspection

Established Acceptance CriteriaNo Evidence of LeakageVideo Record

Page 34: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – Reactor Head Inspections

Page 35: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – Bottom Vessel InspectionProactive Response To STP Finding

2 Weeks After STP100% Bare Metal Visual Exam (VT-2)Video Record

Used Same Acceptance Criteria As Developed For RPV Head Exam

Page 36: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – Bottom Vessel InspectionNo Evidence Of Leakage From Bottom Mounted Instrumentation (BMI) NozzlesSome Streaking From Removable Cavity Seal Ring Leaks (Replaced In 1994):

Thin, Transparent Film; No MaskingMet Acceptance CriteriaLocal Cleaning Performed To Aid In Evaluation

Page 37: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – Bottom Vessel Inspection

Page 38: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – CETNA Modification

RFO-10 Experience CETNA Design – Old versus New

Why Modify…Advantages of New CETNA Design

Page 39: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

RFO-11 – CETNA Modification

Control Rod Drives

Vessel Head

Insulation Thermocouple Nozzles

Page 40: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Operations

Ed Wills

Page 41: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Operations Performance

RFO-11Trips Post-RFO-11Forced Downpowers

Page 42: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Risk Improvements

Raised 1CC-294 SetpointDEH Changes

FirmwareProcedure Changes

Surge Protection A Condensate Pump MotorMinimize ESW Operation (GL 89-13)Procedure Changes to Support AFW Outage

Page 43: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Operator Career Path

Operations PipelineTen NLO New HiresEleven Operators Currently in ClassNext License Class

Overtime ChallengeMoving to Other Organizations

EngineeringNuclear AssessmentTraining

Page 44: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Self Evaluation

Terry Morton

Page 45: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Overview

Self Evaluation Continuous ImprovementExamples of Results

CAPSelf AssessmentOperating ExperienceBenchmarking

Page 46: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Continuous Improvement

Page 47: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Condensate Pump Root Cause Investigation

1999 FailureAugust 17, 2003 FailureAugust 27, 2003 Failure96 Possible Failure Modes Analyzed

CAP Results

Page 48: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

CAP Results

ActionsRefurbishment & TestingModification to Prevent Surge Damage on “A” Bus

Page 49: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Surge Suppression and Lightning Arrestor

Page 50: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Surge Suppression and Lightning Arrestor

Page 51: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

CAP Results

Component Cooling Water Event Root Cause

18 Failure Modes AnalyzedRelief Valve Set Point too Close to System Transient PressureReseat Error Caused by Incorrect Settings

Page 52: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Counting notches

Page 53: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Relief Valve Secured for

Testing

Page 54: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

CAP Results

ActionsRevised Set Point Revised Maintenance Procedure – In Shop SettingsImplemented Concurrent Verification of SettingsRetrain TechniciansShared OE with the Industry

Page 55: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Operating Experience Results

Reactor Vessel Head InspectionsSouth Texas Project Bottom Mounted Instrument LeaksAction Prior to SEN 238Proactive 100% Bare Metal InspectionBaseline for Future InspectionsNo Evidence of Leakage

Page 56: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Operating Experience Results

Davis-Besse EventMajor contributor to this event was a shift in the focus at all levels of the organization from implementing high standards to justifying minimum standards. Senior Management InvolvementConducted an Independent Fleet Evaluation

Page 57: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Self Assessment ResultsDavis-Besse Self Assessment

Focused Assessment to Determine Degree of Respect for Nuclear Safety Emphasis on LeadershipFive Key Attributes

Page 58: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Self Assessment Results

HNP has Healthy Respect for Nuclear SafetyAll Five Attributes Satisfactorily MetActions

Improve Lower Threshold Problem ReportingEnhance Approval and Funding Process for Equipment Repairs

Page 59: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Self Assessment ResultsElectrical Safety

Fleet Round Robin Self AssessmentStrengths

Zero Energy Checks Prior to Work StartPre-job Briefs with Non-Station Personnel

ActionsImprove Use of pre-job Inspection ChecklistAcquire Additional Insulated Tools for OperationsImproved Verification During Electrical Tag Outs

Page 60: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Benchmarking Results

Rigging ProgramBenchmarked Program to Industry StandardsProgram In Compliance with RegulationsFocus Included

Inspections and RecordsSafety RecordTraining and QualificationProgram Ownership

ActionsDevelop Fleet Procedure

Page 61: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Benchmarking Results

Service Water ProgramIndustry Contact Through EPRI MeetingSuccesses and Opportunities Discussed with a Focus on Piping IssuesActionsImplement Improved Motor Oil Cooler Cleaning TechniquesUse of MIC Indices

Page 62: Harris Nuclear Plant - NRC - Region II Presentation - September … · 2012-11-18 · Strategy – The Three “R’s” OReliability ZPMs ZMonitoring ... OSurge Protection A Condensate

Continuous Improvement