    HARDWARE INSTALLATION STANDARD FOR INDOOR BTS3900(NEW/SWAP)

    (Introduction of 3G Technology and Expansion of 2.5G Network)

    Version : 1.1

    Quality Assurance Department.

    Huawei Technologies BD Lit.

    Prepared on : 29 January, 2013

    Prepared By : Md. Jahangir Alom

    Quality Assurance Department of Huawei Technologies Limited

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    2/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    3/53

    Huawei Technologies BD Ltd.

    Swap Scope of work (SOW) 

     Swap Scope of work (SOW) 

    BTS3900 :

    1. Cabinet installation

    2. RF connector installation for the jumper cable

    3. All Alarm Sensor installation

    4. EMU Box installation, connection and check5. DDF Box installation and connection

    6. All Cable Labeling as per standard

    7. Attend PAT Activity

    8. Site installation Quality check

    Node-B :

    1. Node-B Equipment installation

    2. FE, power and grounding cable installation

    3. RRU and Antenna installation

    4. RF connector installation5. CPRI and power cable installation and latching

    6. RRU grounding cable installation

    7. Attend PAT Activity (if required)

    8. Site installation Quality check

    Common Activity:1. As per site swap plan need to arrange site access key from regional Teletalk office.

    2. Dismantle the BTS Cabinet (if required )

    3. Packaging the BTS Cabinet (if required)

    4. Fall Back (if required)

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    4/53

    Huawei Technologies BD Ltd.

    Safety Requirement for site installation

    Safety Helmet

    Safety shoes/boots

    Eye protection

    Safety harness (when working at height)

    Hand gloves

    First aid box

    Huawei QC PASS ID

    Safety Belt

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    5/53

    Huawei Technologies BD Ltd.

    1. Work Permit and Site Access Letter (if required)

    2. Site Survey checklist (Approved)

    3. Site Quality Audit Checklist (EIR)

    4. Toolbox Talk Report

    5. GSM Planning Doc.

    6. Quality Standard Document for the BTS V1.1

    7. Labeling convention document v1.1

    8. Site Diary9. EHS Handbook v1.0

    10.PAT Checklist

    Site Documents to be left at Site:

    1. As Built & As Plan Drawings

    2. Equipment Wiring Diagram & Layout

    3. Site Inventory

    4. Factory test report

    Reference Documents:

    1. Site Acceptance Process (if required)

    2. Quick Installation Guide for BTS and Node-B3. Quick Installation Guide-Antenna & RRU System

    4. Quality Standard Document for this project.

    5. Equipment Installation Ready (EIR)

    Site Pack Documents Before and During Working at Site:

    Document Requirement at Site

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    6/53

    Huawei Technologies BD Ltd.

    Additional Installation Materials Requirement

    For Indoor:

    1. flexible PVC pipe and PVC channel as required

    2. Silicone gel (if required )3. Cable lug for Ø 16mm (if required )4. Full set of M12 Bolt spring washer, flat washer, insulation

    washer (if required )

    For Outdoor:

    1. Black Cable Ties 6 Inch (if required )

    2. Black cable ties L300 x 4.8mm (if required )

    3. Insulated black tape (Brand 3M) (if required )Common:

    1. Tape for labeling tape write.

    2. Marking pipe as required3. T-ties (if required )

    4. Yellow later marking

    Tape writer Marking tape Cable lug

    cable ties (white )

    cable ties (Black )

    flexible PVC pipe

    Yellow later marking 

    PVC Channel 

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    7/53Huawei Technologies BD Ltd.

    Tool and Test Equipment Requirement

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    8/53Huawei Technologies BD Ltd.

    Tool and Test Equipment Requirement

    Sl No Name of the Tools Quantity need per team

    1 Laptop 1

    2 Test Phone 2G & 3G 1+1

    3 Test SIM for PAT & Test (Subcon need to Buy ) 1+1

    4 Sharp Knife 2

    5 75Ω connector maker(BNC puncher) 1

    6 Sitemaster 1

    7 Screw Driver Large set 1

    8 L end Key set 1

    9 Fixed wrench dully set 1

    10 Adjustable wrench 12" 2

    11 Munkey wrench 1

    12 Cable cutter 10" (round) 2

    13 Tie cutter small 6" 1

    14 Tie cutter small 4" 2

    15 Nose plair 6" 1

    16 Combination plair 6" 1

    17 Power connector pin crimping tools 1

    18 Soldering iron 60 watt 1

    19 Drill machine (Heavy) 1

    20 Iron drill bit set 1

    21 Hydrolic crimping tools 1

    22 Hack saw with frame big 1

    23 Hack saw with frame small 1

    24 Hot Air Gun 1

    25 Rough file 1

    26 File set (Jewelry) 1

    27 Measuring tape 50m 1

    28 Measuring tape Small 5m 1

    29 Verniar scale 1

    30 Scissor 1

    31 1/2" cutter for making Flex connector 1

    32 Super Flex connector maker 1

    33 7/8" cutter for making feeder connector 1

    34 1 5/8" cutter for making feeder connector 1

    35 Hammer medium 1

    36 T Screw driver set 1

    37 41Pcs Reset socket wrench & bit set 1

    38 Solder sucker 1

    39 Level meter 1

    40 Digital multimeter Fluke 2

    41 Compass with mirror 1

    42 Digital Tilting Meter 1

    43 Insertion tools 1

    44 Insertion tools 1

    45 DDF loop cable 3

    46 Safety belt 4

    47 Helmets 4

    48 Rope cotton 130m

    49 Back hook for Harness 4

    50 Pulley 1

    51 Hand gloves (Indoor power works) 2 pair

    52 Hand gloves (Outdoor works) 2 pair

    53 Safety goggles 2

    54 Safety shoe 4 pair

    55 Torque wrench with spanner set 1

    56 Copper Brush 1

    57 Hand Brush 1

    58 Charger Light (Small & Big) 2

    59 Label writer machine 1

    60 Gullu 1

    61 LED 2

    62 First Aid Box 1

    63 Spanner 56" 1

    64 Spanner 46" 1

    65 Hook 1

    66 Digital Camera 1

    67 Vacuum cleaner 1

    Sl No Name of the Tools Quantity need per team

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    9/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    10/53

     The BTS cabinet Keep on the

    base very carefully.

     Located the cabinet with the

    back protected properly.

     Tighten the bolt's front of BTS

    base with the torque wrench at

    45NM.

    The lock back side of

    BTS base

    Huawei Technologies BD Ltd.

    Cabinet Installation on the base.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    11/53

    This section describes the procedures & precautions for

    installing single cabinet on a base. 

    Step 1: Remove the cabinet door.

    Step 2: Lift the cabinet onto the Base.

    Step 3: Slide the cabinet along the base to ensure that back

    of the cabinet is aligned with the back of the base. Use a

    torque wrench to tightens the two bolts in the front

    of the cabinet until the fastening torque reaches 45Nm.

    Step of Installed to the cabinet. 

    Huawei Technologies BD Ltd.

    Following details is for “Installing cabinet”

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    12/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    13/53

    Route the PGND cable along the leftinterior of the cabinet. Route the Six

     jumpers on the left along the left interior of

    the cabinet. Route the external input power

    cable along the left interior of the cabinet.

    Route the transmission cables along the

    right Route the transmission cables alongthe right interior of the cabinet. Route the

    monitoring signal cables close the CPRI

    cables.

     Note: The cables in the BTS3900 cabinet

    must be routed according to the cabling

    requirements androuted according to the cabling

    requirements and must be bound by using

    cable ties.

    Huawei Technologies BD Ltd.

    Route the cables in a cabinet

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    14/53

     Do the cable lay from GRFU port

    to feeder connector left and rightinterior position of the cabinet.

    The RF cable bending is accepted

    not less than 90 degree.

    The cable lay from GRFU port to feeder

    connector left and right

    Huawei Technologies BD Ltd.

    Route the cables in a cabinet

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    15/53

    RF cable latching top of the cabinet

    Huawei Technologies BD Ltd.

    RF Cable Latching on Top of The Cabinet.

    RF cable latching on the ladder

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    16/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    17/53

    With bus bar.

    Indoor main grounding bar

    Huawei Technologies BD Ltd.

    For cabinet grounding

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    18/53

    Indoor maingrounding

    bus bar for

    all indoor

    equipment

    grounding.

    Huawei Technologies BD Ltd.

    For cabinet grounding

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    19/53

    Grounding cables arrangement must be in straight running and firm bundling. Cable

    length must be somewhat longer than necessary at bending point. The EMU grounding

    cable will be 6mm & connected directly with BTS left site to the equipotential grounding port through cable ladder.

    EMU PGND port at BTSEMU PGND port at EMU

    Huawei Technologies BD Ltd.

    EMU Grounding.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    20/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    21/53

     Measure the distance between the DCDU-01 and the external power

    equipment according to the actual cable route, and then prepare power cables of

    a proper length. (reserve and extra length of 300mm when preparing the input

    power cables.).

     Make an OT terminal at each end of the power cable.

     Remove the protecting hood from the terminal block of the DCDU -01.

    Connect the blue cable to the wiring terminal labeled NEG(-) and blackcable to the wiring terminal labeled RTN(+).

     Use a screwdriver to tighten the screws to the wiring terminals.

     Install the protecting hood, and then use a screwdriver to tighten the screws .

     The redundant part of power cable cannot be coiled. Should be cut.

     The Lug used at both end of power terminal should crimped firmly. 

    Huawei Technologies BD Ltd.

    Installing power cable

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    22/53

    metal wires, as shown in below figure red cross marked. Confirm whether the rated

    Circuit breaker (63 amps) is available or not at non critical load. Ensure the properconnection done to the defined CKB. 

    Connect to

    non critical

    load CKB

    of rectifier

    inside

    Connect to

    BTS end

     blue & black

     power cable

    metal wire 

    Huawei Technologies BD Ltd.

    Installing power cable

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    23/53

    The input power cable for the -48, cabinet connects the wiring terminal for the

    input power cable on the DCDU-01 to the rectifier equipment.

    Latching in the BTS inside Rectifier inside latching Latching on the ladder

    Huawei Technologies BD Ltd.

    Installing power cable

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    24/53

     Route the power cable

    along the left interior and laid

    top surface of the BTS

    cabinet to exist Rectifier.

    Cable are bundled together

    by tie uniformly & there no

    need to fix the cable at the

    top surface of the cabinet.

    Huawei Technologies BD Ltd.

    power cable latching

    The cable laid through the wall tiles using

    PVC channel

    Power Cable Latching Inside The BTS Cabinet &

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    25/53

    Power cable latching Inside of

    BTS cabinet. Power cable latching Outside of

    Rectifier. 

    Huawei Technologies BD Ltd.

    Power Cable Latching Inside The BTS Cabinet &

    Rectifier Outside.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    26/53

     Alarm & E1 Cable Latching on the

    BTS top to ladder

    EMU Power Cable latching top on the

    Emu box to laid through the wall using

    plastic channel

    Huawei Technologies BD Ltd.

    EMU Power, Alarm & E1 Cable Latching

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    27/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    28/53

    Follow the measurement during connector

    installation outer cupper 21mm & inner pin 7mm 

    Must use connector

    maker & feeder cutter 

    Huawei Technologies BD Ltd.

    ½” Connector installation 

    ½"J bl t I t ll ti d

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    29/53

    Jumper cable Cutting by the

    connector maker

    Measuring inner pin by the Venire

    scale

    Huawei Technologies BD Ltd.

    ½"Jumper cable connector Installation procedure

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    30/53

    Dust cline by the Cupper brush

    before the connector setting

    Cable inner pin feline for smooth &

    leveling after the cable cited by the

    connector maker

    Huawei Technologies BD Ltd.

    ½"Jumper cable connector Installation procedure

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    31/53

    Finale measure outer cupper & inner pin

    by the Venire scale after the connector

    making.

    Tightening the connector finale using

    torque wrench at 20nm to 25nm

    Inner pin should be 7mmOuter cupper should be 21mm

    Huawei Technologies BD Ltd.

    ½"Jumper cable connector Installation procedure

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    32/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    33/53

     The monitoring signal cable for the EMU transmits monitoring signals from the EMU to the BBU3900.

    The Communication cable from BTS 3900 and Alarm cable to the external sensor should be laid through PVC

    channel.Insert the alarm cable to required port of EMU and tighten the screw as need. extra cable keep in good

    bundling inside PVC channel.

    Monitoring signal cable & Sensor signal

    cable latching of the EMU End.

    Huawei Technologies BD Ltd.

    Installing the Monitoring Signal Cable for the EMU.

    Monitoring signal cable latching of the EMU

    End.

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    34/53

     Alarm & E1 extra length cable Latching to

    the BTS bottom under DCDU

     Alarm & E1 Cable Latching top of the BTS

    outside .

     Do fine coil and keep the extra length of the both cable at the BTS bottom under DCDU

    rack.

    Huawei Technologies BD Ltd.

    Alarm & E1 Cable Latching BTS inside & outside.

    I lli h M i i Si l C bl f h EMU

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    35/53

    The monitoring signal cable for the EMU transmits monitoring signals from the EMU to the BBU3900.

    Insert RJ-45 Connector at one of the monitoring signal cable for the External Alarm Sensor into the port

    labeled MON1 on the UPEU in the BBU3900. The link DB9 male connector at the other end of the monitoring signal cable for the EMU to the port

    labeled RS485 on the EMU.

    Installed the alarm cable from the BTS mon1 port to EMU RS485 port

    Huawei Technologies BD Ltd.

    Installing the Monitoring Signal Cable for the EMU

    Al & E1 C bl L t hi BTS i id & t id

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    36/53

     E1 cable should be through the PVC channel and do fine Latching and keep the extra

    length of the both cable in the DDF box.

    Huawei Technologies BD Ltd.

    Alarm & E1 Cable Latching BTS inside & outside.

    E1 cable through the PVC

    channel

    E1 cable latching in the DDF

    box

    C S

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    37/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

    I t ll ti f N d B

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    38/53

    TX rack over view

    Huawei Technologies BD Ltd.

    Installation of Node-B

    This position of SLPU

    This position of Node-B BBU

    5mm gap

    This position of DCDU

    Node-B Equipment

    installation procedure

     The Node-B Components Installation to the Tx rack, as shown in

    the following picture.

    N d B ti

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    39/53

    Huawei Technologies BD Ltd.

    Node-B power connection

    Power and CPRI cable

    installed at the Node-B end

    Power cable installed at the

    Rectifier end

     Check and ensure the secure connections of the Inter-Node-B power cables

    which are installed inside the Node-B DCDU and Rectifier.

     All Node-B

    Equipment

    should be

    grounded withthe Tx rack

    and Tx rack

    should be

    grounded with

    the indoor

    main bus bar

    C t t S

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    40/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

    RRU I t ll ti

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    41/53

    Huawei Technologies BD Ltd.

     Lifting the RRU and Installation Components to the Tower, as shown in

    the following figures.

    1. Installers A climb onto the tower. Then,

    installer A fixes the pulley to the support of the

    tower platform and leads the lifting rope

    through the pulley.

    2. Installer C uses a lifting rope to bind the

    RRU and installation components as shown inthe preceding figure and then tie a knot in the

    steering rope at the handle of the RRU.

    3. Installer B pulls the lifting rope, and at the

    same time, installer C pulls the steering rope

    away from the tower to prevent the RRU and

    installation components from colliding with thetower.

    4. Installers A hold the RRU and installation

    components and untie the ropes.

    RRU Installation

    RRU Fi ti t t

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    42/53

    Huawei Technologies BD Ltd.

    RRU Fixation at tower

    The RRU will be installed at the approved

    height of site design. It may be installed by

    installing additional pole on tower angle or

    behind the GSM antenna. Feeder length

    from GSM antenna to RRU will be as

    close as possible. And the length of RRU

    pole (if used) will be 1.5 m. The groundingof RRU will be 35 rm Al or 25 rm Cu. In

    case of RRU installation at more than 35

    m of tower, RRU will be installed inside or

    outside of tower angle. It will be subjected

    to the field condition whether there is free

    space available on tower or not. Adequate

    mounting kit will have to be used during

    RRU installation.

    3G-GSM Antenna

    3G-RRU

    RRU Fi ti t t

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    43/53

    Huawei Technologies BD Ltd.

     If proposed tower leg have any other antenna

    or obstacle than RRU will be below or upper height

    between the other antenna or obstacle (beforeinstallation discus with responsible person )

    RRU Fixation at tower

    Caution : When installing the main

    fixture, ensure that the arrow on the mainfixture is upward. When installing the

    main fixture, ensure that the contact

    piece on the fixture is fixed.

    Antenna fi ation at to er

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    44/53

    Huawei Technologies BD Ltd.

    Antenna fixation at tower

    • Preparing for the Installation

    Caution : When installing the main

    fixture, ensure that the arrow on the

    main fixture is upward. When

    installing the main fixture, ensure that

    the contact piece on the fixture is

    fixed.

    Content Summary

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    45/53

    Content Summary

    1 General information

    2 Cabinet Installation

    3 Cable routing principles

    4 Grounding installation

    5 Power connection

    6 RF cable & connector installation

    7 Installing Alarm and E1 cable

    8 Installation of Node-B

    9 Installation GSM Antenna and RRU

    10 Installation CPRI and Power cable

    Huawei Technologies BD Ltd.

    Installation of RRU power cable

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    46/53

    Huawei Technologies BD Ltd.

     Making OT Terminals at the Input End of the Power Cable by Using a Knife.

    Lead the wires made of the

    shielding layers through

    heat-shrinkable tubes.

    Wrap the PVC

    insulating tape at

    the joint where the

    three wires meet.

    OT terminal on

    the shielding layerCaution : Do not damage the shielding layer

    of the power cable when cutting around the

     jacket.

    Installation of RRU power cable

    RRU Cable Connections of a Single RRU

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    47/53

    Huawei Technologies BD Ltd.

     Cable Connections of a Single RRUInstall the PGND cable

    Install the RF jumper

    (interconnect jumper is optional)

    Install the RRU power cable

    Install the CPRI optical cable

    Install the alarm cable(optional)

    Install the AISG multi-wire cable between the RRU

    and the RCU (optional)

    Install the AISG multi-wire cable and extensioncable(optional)

    CAUTION: When a dual-polarized antenna is shared by two RRUs in the same sector, the two RRUs are connected through

    an inter-RRU jumper. The connections of three RRUs in the same sector are not supported.

    RRU Cable Connections of a Single RRU

    RRU Cable Connections of a Single RRU

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    48/53

    Huawei Technologies BD Ltd.

     Cable Connections of RRUCAUTION:

    1. Press the strap on the exposed shielding layer of the power

    cable tightly. Ensure that the lower edge of the exposed shield

    layer does not exceed the position shown in the figure.2. The shielding layer of the other end of the power

    cable should be grounded.

    3. When the alarm cable is connected, ensure that the

    shielding layer of the alarm cable on the RRU side is

    exposed and that the shielding layer is tightly pressed

    by the strap.4. The alarm cable is preferably led out of the RRU

    from the narrower cable trough in the middle of the

    cabling cavity. If the cable trough is used by the CPRI

    optical cable, the alarm cable is led from the wider

    cable trough near the middle one. In this case, the

    alarm cable must be wrapped with 10 to 17 layers of

    waterproof tape so that the diameter of the cablereaches 10 mm to 12 mm.

    5. To avoid sharp bending, the optical cable must be

    pressed by the strap next to the power cable during

    the optical cable installation.

    RRU Cable Connections of a Single RRU

    The connection of RRU power cable- RRU End

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    49/53

    Huawei Technologies BD Ltd.

    The connection of RRU power cable- RRU End

    RRU Power

    Cable

    Grounding

    During installation of RRU powercable we should follow the belowrules:

    i. Negative portion of the RRU powercable must be connect with negativeport of RRU.

    ii. Positive portion of the RRU powercable must be connect with positiveport of RRU.

    iii. Shielding layer of DC RRU power

    cable should be installed as per sidepicture in RRU end.

    CPRI bl ti f RRU

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    50/53

    Huawei Technologies BD Ltd.

    CPRI port RRU End

    CPRI port GTMU end

    CPRI cable connection for RRU

     In HW RRU have 2 CPRI cable

    connection port 1st is CPRI 0 another

    is CPRI 1.We must be connect CPRI

    cable short end(1A & 1B) with CPRI 0port in RRU . On the other hand, long

    end (2A & 2B) of the CPRI cable we

    must be connect with CPRI 0 port of

    GTMU card in BBU board.

    Jumper Cable Connection(Antenna & RRU)

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    51/53

    Huawei Technologies BD Ltd.

    Jumper Cable Connection(Antenna & RRU)

    During installation the short jumpercable between GSM antenna & RRU,we must follow the below instruction:

    i. Cable must be Super flex.

    ii. GSM 900 antenna left/Tx/+45 portwill be connect with RRU

     ANT_TX/RXA port by super flex short jumper cable.

    iii. GSM 900 antenna right/Rx/- 45port will be connect with RRU

     ANT_TX/RXB port by super flex short jumper cable.

    RRU CPRI and power cable Latching

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    52/53

    Huawei Technologies BD Ltd.

    RRU CPRI and power cable Latching

    The RRU’s CPRI & Power cables must be straight after laid. 

    Distance between the clamps should not be less or more than 1 meter.

    Sequentially clamping the power & CPRI cables of RRU. Example: Picture 02

    Picture-01 Picture-02 Picture-03

  • 8/18/2019 Hardware Installation Standard for Indoor BTS3900 _new and Swap

    53/53