Great Lakes Tunnel Project

51
Great Lakes Tunnel Project Lansing, Michigan Design, Construction, and Operations Information Session September 20, 2021

Transcript of Great Lakes Tunnel Project

Page 1: Great Lakes Tunnel Project

Great Lakes Tunnel Project

Lansing, Michigan

Design, Construction, and Operations Information Session

September 20, 2021

Page 2: Great Lakes Tunnel Project

Safety MomentLifesaving Rule #1: Hazard Management

Page 3: Great Lakes Tunnel Project

Enbridge Lifesaving Rules

• Each Lifesaving Rule

focuses on an area of

high risk and

consequence

• The rules are intended

to heighten awareness

Page 4: Great Lakes Tunnel Project

Life Saving Rule #1: Hazard Management

I will complete a hazard assessment prior to starting work and

reassess if conditions change and new hazards are introduced.

• The assessment is meant to identify, assess and control the field-based hazards of

the work being performed

• Examples of questions to be addressed:

• Have we identified hazards today? Is it documented?

• Did everyone on the crew have an opportunity to provide input?

• Have results from the assessments been communicated to all workers?

• Do we have effective controls in place and are they in compliance to the

Enbridge Safety Manual, local legislation and the Contractors Program?

Page 5: Great Lakes Tunnel Project

Line 5 Update

(1) Michigan Department of Environment, Great Lakes and Energy (2) Michigan Public Service Commission (3) U.S. Army Corps of Engineers

Committed to ensuring the safe and reliable delivery of essential energy supply

• Delivers on average 540 kbpd of crude and NGLs to 10 refineries in Michigan, Ohio, Pennsylvania, Ontario and Quebec

State Permitting:• EGLE1 Permits Awarded

• MPSC2 Approval (In Progress)

Federal Permitting: • USACE3 permit (In Progress)

Contracting:• Engineering & Design Phase

• Preparation for Construction Phase (Commencing)

Critical Infrastructure

WI

MI

ON

MNLine 5

QC

PA

OH

Superior

Sarnia

Great Lakes Tunnel Project

Tunnel Design

Additional Uses (e.g. Fiber Optics)

Pipeline

Page 6: Great Lakes Tunnel Project

Meet the Speakers

Liza DwyreWSP Owner’s

Engineer

Aaron DennisTunnel Project Lead Engineer

Jon HurtSubsurface Design

Lead

Page 7: Great Lakes Tunnel Project

Tunnel Animation

7

Page 8: Great Lakes Tunnel Project

Ground Conditions

Page 9: Great Lakes Tunnel Project

Regional Geologic Setting Ground Conditions

Page 10: Great Lakes Tunnel Project

Historical Data: Mackinac BridgeGround Conditions

Page 11: Great Lakes Tunnel Project

Marine Seismic Reflection/Refraction Survey (2018)Ground Conditions

• Data is interpreted to characterize the subsurface geologic conditions and geologic structure

Page 12: Great Lakes Tunnel Project

Boring LocationsGround Conditions

Page 13: Great Lakes Tunnel Project

Onshore, Nearshore, and Deepwater Borings

13

Ground Conditions

Dynamically-positioned Drill ShipSouth Shore Jack-up Barge

Page 14: Great Lakes Tunnel Project

Hydraulic Conductivity (permeability)

• Water is pumped out of the rock mass, from a pumping well

• Drawdown is measured in surrounding observation wells

Pump TestPacker Test

Ground Conditions

• Water is pushed into the rock formation under pressure

• Tests local zones, isolated between inflatable packers

Page 15: Great Lakes Tunnel Project

Borehole GeophysicsGround Conditions

Optical TeleviewerAcoustic Televiewer

Page 16: Great Lakes Tunnel Project

Laboratory Tests of Rock PropertiesGround Conditions

Page 17: Great Lakes Tunnel Project

Generalized Subsurface ProfileGround Conditions

PROFILE (TRUE SCALE)

PROFILE (10X VERTICAL EXAGGERATION)

Page 18: Great Lakes Tunnel Project

Mackinac BrecciaGround Conditions

St. Anthony's Rock

Located in St. Ignace, MI

Page 19: Great Lakes Tunnel Project

Generalized Subsurface ProfileGround Conditions

PROFILE (TRUE SCALE)

PROFILE (10X VERTICAL EXAGGERATION)

Page 20: Great Lakes Tunnel Project

Rock Core Examples from Each FormationGround Conditions

St IgnaceBois Blanc Pointe Aux Chenes

Page 21: Great Lakes Tunnel Project

• Deeper-than-expected buried valley

• Open voids (karst)

• Toxic/combustible gases

• Variable ground conditions

• Some fractured, more permeable zones

• Claystones in Point Aux Chenes - weak rock, slaking

• Borings most closely spaced in deep channel

– Increased confidence in top of rock elevation

Geotechnical EvaluationLow Likelihood Conditions Known Rock Conditions Sufficient Geotechnical Data

Not anticipated – but if they occur

can be managed with some

adaptations during tunneling

Rock parameters influence

cutting tool wear and tunneling

progress rates.

Managed with the specified TBM and construction methods

Geologic understanding and

subsurface data provides a

sufficient basis for tunnel design

and state-of-the-practice

TBM specifications

Understanding of the geotechnical conditions shaped the design approach

Ground Conditions

Page 22: Great Lakes Tunnel Project

Overall Design

Page 23: Great Lakes Tunnel Project

Tunnel Boring Machine (TBM)Overall Design

Image courtesy of Chesapeake Bay Bridge Tunnel Project

~500 ft

Hydraulic rams push against newly-placed

concrete segments to drive machine forwards

Rotating

cutter headThe machine is operated from the control room

Pre-cast concrete segments

delivered to rotating arm

Excavated material removed

through slurry pipes

Rotating arm adds pre-cast concrete

tunnel segments to form a ring

Pressure is maintained

in the cutting chamber

Page 24: Great Lakes Tunnel Project

TBM InterventionsOverall Design

Page 25: Great Lakes Tunnel Project

Vertical AlignmentOverall Design

PROFILE (TRUE SCALE)

PROFILE (10X VERTICAL EXAGGERATION)

Page 26: Great Lakes Tunnel Project

Horizontal AlignmentOverall Design

Page 27: Great Lakes Tunnel Project

Tunnel DiameterOverall Design

SPACE FOR THIRD-PARTY UTILITIES

Page 28: Great Lakes Tunnel Project

Mackinaw Station PortalOverall Design

Page 29: Great Lakes Tunnel Project

North Straits ShaftOverall Design

Page 30: Great Lakes Tunnel Project

Tunnel Lining

Page 31: Great Lakes Tunnel Project

Precast Concrete Tunnel Lining (PCTL)Tunnel Lining

Page 32: Great Lakes Tunnel Project

Precast Concrete Tunnel LiningTunnel Lining

Ring length – 6ft

Tunnel Direction

Lining thickness – 15”

Typical Rebar

Page 33: Great Lakes Tunnel Project

GasketsTunnel Lining

Page 34: Great Lakes Tunnel Project

Break – 10mins

Page 35: Great Lakes Tunnel Project

Tunnel Construction

Page 36: Great Lakes Tunnel Project

The shield of the TBM prevents water, soil and rock

from entering the tunnel during construction

The concrete segments are assembled into a water-

tight lining inside the shield; under the protection of

the shield. No water, soil or rock enters the tunnel

during construction

As the shield advances during tunneling three seals

prevent water from leaking inside the TBM

TBM Tunneling Tunnel Construction

Page 37: Great Lakes Tunnel Project

Tunnel Grouting

• As the TBM advances, it pushes forward off the lining and simultaneously fills the void behind the lining with grout

Tunnel Construction

Page 38: Great Lakes Tunnel Project

TBM Face Pressure

Earth pressure

Water pressure

Tunnel Construction

Bentonite slurry in

the excavation

chamber is

pressurized to

counterbalance the water and earth

pressures that may

act on the TBM face

The TBM has been designed to prevent any impact to the water in the Straits

Page 39: Great Lakes Tunnel Project

Separation Plant Tunnel Construction

2nd Separation

Plant

1st Separation

Plant

Water Treatment

Plant

Discharge

Filtered water

Tank Surplus

slurry tank Driving tank

Primary Solids SeparationPrimary Solids

Separation

Secondary

SeparationWater Treatment

2nd separation sludge

1st separation sludge

Dosage of Flocculant

& Coagulant

Return Slurry

Water refiling

Feed Slurry

Spoil slurry

Tank

1st stage separation solid materials

2nd stage separation solid materials

Page 40: Great Lakes Tunnel Project

Other Construction Activities

• Interventions

• Water Treatment

• Hazardous Gases

• Inspections

• Schedule

• Disposal of Excavated Material

Tunnel Construction

Page 41: Great Lakes Tunnel Project

Operations

Page 42: Great Lakes Tunnel Project

Mackinaw StationOperations

Existing security

fence

Page 43: Great Lakes Tunnel Project

Mackinaw Station Section ViewOperations

Ground level

Page 44: Great Lakes Tunnel Project

North StraitsOperations

Page 45: Great Lakes Tunnel Project

North Straits Shaft Section View

45

Operations

Ground level

Page 46: Great Lakes Tunnel Project

Space Proofing & Maintenance

• Pipeline

• Tunnel Systems & Third-Party Utilities

• Third Party Utilities

• Maintenance Area – accessed using Tunnel Service Vehicle (TSV)

SPACE FOR THIRD-PARTY UTILITIES

SPACE FOR THIRD-PARTY UTILITIES

Operations

Page 47: Great Lakes Tunnel Project

Tunnel Systems Operations – Minimize Entry

KEY: North Strait Shaft (Push-only Mode)Mackinaw Station Portal (Push-only Mode)

Mackinaw Station Fan Plant

Straits TunnelMS ShaftNS Shaft

Tunnel Ventilation

Operations

Page 48: Great Lakes Tunnel Project

Operations - Other Tunnel Systems Operations

Tunnel Systems

• Gas & leak detection

• Electrical & Communications

• Mine Phone

• Low point sump

Page 49: Great Lakes Tunnel Project

Normal Operations and Maintenance ActivitiesOperations

Page 50: Great Lakes Tunnel Project

RFP Process

Page 51: Great Lakes Tunnel Project

• In Jan 2019, Awarded Engineering and Pre-Construction Services contracts

• Constructability input received and incorporated into the design

• Delivery model provides for an opportunity to contract with the Pre-Construction services phase contractor or go to market

• Earlier this year expression of interest issued and submittals reviewed

• RFP is organized into two sections:

1. Commercial

2. Technical

• Key documents included in contractors RFP:

✓ Instructions

✓ Project scope description

✓ Permit conditions

✓ Specifications

✓ Construction drawings

✓ Geotechnical Reports

✓ Other reference documents

Request For Proposal (RFP) Process

The Process to Date The RFP Package The Next Step

• Obtain MSCA concurrence