Graduation Project
-
Upload
mahmoud-moustafa-elnegihi -
Category
Documents
-
view
30 -
download
0
description
Transcript of Graduation Project
-
7/13/2019 Graduation Project
1/144
Mu`tah University
Faculty of Engineering
Civil Engineering Department
Adaptive Reuse of Traditional Masonry
Buildings
Hmoud Tourist Village)
Supervisor : Dr.Majdi Al-Khresheh .
Prepared by:
Lana Al-Halaseh . Mazen Al-Kheetan .
Ekaterina Al-Bakain . Yazeed Jweihan.
Mariana Al- Zyadeen .
Second semester
2010/2011
-
7/13/2019 Graduation Project
2/144
Contents
Preface
Acknowledgement
Chapter (1): Introduction
1.1 Country Background
1.2 Original Methods of Construction
1.3 Buildings' Rehabilitation
1.4 Proposed Future Village
Chapter (2): Common Masonry Problems2.1 Cracking
2.2 Faulty Flashing
2.3 Efflorescence
2.4 Plaster Pealing
2.5 Mortar Deterioration
2.6 Cleaning Treatments
Chapter (3): Rehabilitation Techniques
3.1 Arches
3.3.1 Theoretical Aspects of Masonry
Arches
3.1.2 Construction Phase of Arches
3.1.3 Minor Arches Design
3.1.4 Graphical Analysis
3.1.5 Cracks in Arches3.1.6 Repair of Cracks
3.2 Classification of the Village's Buildings
3.3 Masonry construction
3.3.1 Factors Affecting the Design of
Masonry Buildings
3.3.2 Design and Construction Standards3.3.3 Basic Construction and Terminology
i
-
7/13/2019 Graduation Project
3/144
3.3.4 Demolition and Reuse of Masonry
3.3.5 Framing Windows and Doors
Chapter (4): Design and Analysis
4.1 Structural Analysis
4.1.1 Introduction4.1.2 Two-Way Solid Slab
4.1.3 One-Way Ribbed Slab
4.1.4 Two-Way Ribbed Slab
4.1.5 Conclusion
4.1.6 Will the Old Walls Bear?
4.1.7 Design of a Continuous Slab
4.1.8 Design of a Space Frame
4.2 Hydraulic Design
4.2.1 Design of Sanitary Sewer System
4.2.2 Conclusion
4.2.3 Design of square Concrete Tank
4.3 Pavement Design
4.3.1 Introduction
4.3.2 Flexible Brick Paving4.3.3 Method of Construction
Chapter (5): Conclusion
Referances
Appendixes
ii
-
7/13/2019 Graduation Project
4/144
Preface
Jordan is well known for its historic and traditional places spreading
widely all over the kingdom. Hmoud village is one of these places; it is atraditional village still inhabited until now.
In this project we are proposing a number of treatments to rehabilitate
the buildings, these treatments are: firstly, preservation of walls by means
of cleaning, pointing and treatment of plaster pealing.Secondly, reconstruction of slabs by introducing new reinforced concrete
solid and ribbed slab. Thirdly, removal and addition of walls to meet the
adaptive uses.
Our purpose is to convert the village to a unique tourist village, and thework plan is discussed in this paper.
iii
-
7/13/2019 Graduation Project
5/144
Acknowledgements
We would like to express our thanks and deep appreciation to
our instructor:
Dr. Majdi Al-Khresheh
For his guidance and encouragement.
We also give our thanks to those who helped in accomplishing
this work, namely.
Prof. Abbas Z. Ijam (Mu'tah University).
Dr. Omar Al-Maitah (Mu'tah University).
Dr. Jawdat Goussous (The University of Jordan).
Eng. Leen Fakhoury (The University of Jordan).
Eng. Ihab Amarin.
All the academic staff of the civil engineering department-
Mu'tah University.
Lana Halaseh
Mazen Kheetan
Ekaterina Bakain
Yazeed Jweihan
Mariana Zayadeen
iv
-
7/13/2019 Graduation Project
6/144
1
-
7/13/2019 Graduation Project
7/144
2
Hmoud is one of Al-Karak's governorate villages. It was established in
its current form in the late nineteenth century, about 1885, to be an
agricultural place for Al-Karak's citizens. It was known as a pastoral
agricultural civilization.
The total area of Hmoud is about 25259 acres (102.22 2km ).
1.1 Country Background
Properties
We have chosen this village for our project because of the following
factors:
1) All the buildings in the village have an archaeological nature and are not
totally destroyed, so the restoration can be easily done.
2) These buildings are close to each other which will make the proposed
future village function as one block.
3) The local site of Hmoud; it is located in the northern part of Al-Karak
governorate, so it is considered as a link between the regions around it,
especially the historic ones, so the visiting of the archaeological places
will be easier. Also this village could be considered as a rest station.
1. 2 Original Methods of Construction
1TActually these methods depend mainly on soil and water or the result of this
combination " Mud " , also stones , rocks and secondary materials , such as :
wood, bamboo, wheat strew (oqdeh) and ballan (a type of trees which were
common in that period) .
1T The amount of water used was estimated by observation, i.e.: when the mix
forms a paste, the addition of water is stopped. After that straw is added to makethe paste more cohesive and to strengthen the mixture, then all these materials
and additives are compacted to a certain degree by animals, this leads to
strengthening the mixture more and more, decreasing air voids, and decreasingthe solubility of mud in rainwater during winter.
1TDifferent sizes and shapes of stone were used in the front facade of the buildings.These irregular sizes and shapes of stone are called (Rubble stones). Rubble
stones are a result of crushing and destroying big stones by hammers and chisels,some of the stones were used without crushing because the weathering and
erosion processes played a significant role in shaping and forming those stones.
-
7/13/2019 Graduation Project
8/144
3
1TBleaching is very important in the building process; it was done by bleaching clay
and mounts it by hands.
Figure 1.1: Dense urban setting of building
-
7/13/2019 Graduation Project
9/144
4
Figure 1.2: some of Hmoud's buildings
-
7/13/2019 Graduation Project
10/144
5
Rehabilitation'Buildings1.3
A historic building is one that gives us a sense of wonder and makes
us want to know more about the people and culture that produced it, so
the rehabilitation and reviving of these buildings is very important.
To revive any old building many steps are needed which begin by theconservation.
Conservation
Conservation or preservation is the action taken to prevent decay and
change dynamically. It embraces all acts that prolong the life of our
cultural and natural heritage. Conservation must preserve and if possible
enhance the message and values of cultural property these values help
systematically to set overall priorities in deciding proposed interventionsas well as to establish the extent and nature of the individual treatments.So one can say it is heritage conservation.
The philosophy of conservative repairs to structures can be considered
as a sliding scale of desirability:
(1) Do nothing.(2) Add extra members in similar material.
(3) Add extra members in foreign materials.
(4) Carry out traditional repairs.(5) Insert new materials into the existing materials.
(6) Replace isolated members.
(7) Replace whole elements of the structure.
(8) Replace the entire fabric behind the facade (facadism).
(9) Rebuild in facsimile (copy of the buildings).
Adaptive Reuse
It is considered one of the most important methods to preserve theheritage, and it is focus on an economic aspect so it is considered
appropriate and necessary especially in developing countries.
The main ideas of this level is the rehabilitation and reuse of the
building for a new function which commensurate with the location, age
and environment and also keeping the external shape and the main
elements of a building, so as a result of this the building will keep the
technical and historical values.
-
7/13/2019 Graduation Project
11/144
6
Advantages of adaptive reuse:
1) Deliver a cultural, humanitarian and artistic message contained in
the building to the new generations.
2) Combine the past, present and the future of the village in a unique
unit gives a distinct sense of cultural continuity and gives the visitor asense of distinctiveness and uniqueness of this village.
3) Save the cost of establishing a new building and use the old one but
in a conterporary function.
1.4 Proposed Future Village
After doing all the rehabilitation steps and treating all the buildings'problems, we hope that Hmoud will be a unique tourist village.
In this paper we'll introduce some pictures of the proposed future village.
-
7/13/2019 Graduation Project
12/144
7
Figure 1.3: Buildings after rehabilitation
-
7/13/2019 Graduation Project
13/144
8
-
7/13/2019 Graduation Project
14/144
Each and every building, however humble or small, possesses a history, and
buildings from a different periods and regions are unique and interesting; their
importance is not a question since historic and traditional places attract millions of
visitors every year. Their appeal lies not only in there sense of history but also in
their rich variety of texture, color, form, materials and hand-made components.However, old buildings do not look after themselves, no matter how well
constructed ,and being subjected to loads, erosion, moisture and many other
destructive factors along with poor maintenance, over a long span of time the
building becomes deteriorated and in need for professional interference to control the
damages, and here comes the role of science and engineering to address the problem
properly and assign the appropriate remedy to revive the building again into a
functional state.
In this chapter we address the most common problems encountered when dealing
with traditional masonry buildings and proposing repair techniques which will help
adapt the village into an economically feasible proposal.
The term "masonry" refers to building with stone , this method provides numerous
advantages like being a cheap and available mean of construction providing good
thermal insulation and having a high bearing capacity and fire resistance at the same
time having the ability to deform elastically over a long period of time
accommodating small movements . As good as this sounds , masonry buildings , like
any other building face many problems on the long run , here are the most common
problems we found during our research and their proposed solutions .
Cracking.12
Left unrepaired, cracks provide an opening for water, insects, wind, plant life,
and dust penetration. Each of these has the potential for causing further damage.
Plus , cracks lead to load redistribution causing the crack to travel further or even get
wider.
A properly repaired crack will aesthetically look much better and may not even be
noticeable.
If the crack is not properly repaired but simply filled with mortar, the crack will
appear very obvious and the mortar-filled crack will likely reopen in the
future. Mortar cannot succeed as "glue" in holding cracked masonry together .
So repairing cracks is an essential step in any maintenance job , but before trying
to repair a crack in a masonry wall its important to determine what caused it ;
cracking occurs in different ways and patterns , by examining these patterns we can
often figure out the cause , one thing is for sure , any crack in a masonry wall is
caused by movement either due to
settlement or expansion .
9
-
7/13/2019 Graduation Project
15/144
*Settlement cracks :
Usually settlement cracks show as relatively vertical shears or lines . They occur
when part of the foundation settles unevenly in relation to another part of the
structure . Settlement cracks are usually larger at the top and get smaller at the bottom
(fig.2.1)* Expansion cracks :
Expansion cracks usually appear in a stair-step pattern that can be vertical orhorizontal . The most frequent locations of such cracks are near windows or doors.
They are usually caused by expansion and contraction due to temperature changes in
the surrounding environment. In many cases a crack that opens in one time of theyear will close up at the opposite time of the year .the crack is still there but it's very
small to be seen.
(fig2.2)
10
-
7/13/2019 Graduation Project
16/144
How to treat cracking ?
Grouting ( the injection of grout into cracks and holes ) is a very good option to
seal cracks , and provides the advantage of improving the fixity of individual units in
order to reduce the risk of them becoming loose and falling when subjected to
loading . Since old masonry was laid up with lime base mortar which tends to be relatively
week , the individual units where thus not highly bonded originally and so have
become further loosened due to age , settlement..etc. which is evident in almost all
the buildings under study , in such cases , these buildings can be reintegrated with
grouting .
What grouting material should we use ?
Grout is a type of mortar used to fill joints , cracks and cavities in masonry and
tiles .
It typically consists of water, cement, and sand. Used in semi-liquid form, it may be
pumped, spread, or poured into cavities and allowed to harden, creating a tight,
water-resistant seal.
There are three main types of grout :
1) Epoxy .
2) Portland cement based .
3) Furan resin .
The epoxy type is strong and water resisting and very effective. The furan resin is
considered extremely resistant to chemicals and used when working with strong acids
and generally more difficult to handle than other types of grout .Portland cement-based grout is available in many forms . Portland cement-based
grout is weaker than the epoxy type, and since we are working with traditional
masonry , it is not advisable to use it for the following reasons :
1) Masonry which is traditionally constructed is bedded in soft lime mortar and is
relatively flexible: injecting it with a hard cement restricts its movement, causing
stress in the surface of the wall where it is bound by the cement, and the face of soft
stone and brick will fail as a result.
2) Cement mortars are also impermeable - that is to say that they do not allow the
structure behind to 'breathe': moisture is forced to evaporate through the stone orbrick, and in extreme cases may cause these materials to deteriorate.
3) Cement mortars may also be visibly different, both in color and detail: being hard
they can be made to project forward from the face of the wall, or may be smearedacross the edges of stones, changing the appearance of the wall as a whole.
Not to mention that it will add additional weight for the structure to support.
Based on this , using an epoxy grout will be the best choice to seal the cracks in ourbuildings.
11
-
7/13/2019 Graduation Project
17/144
*How to grout ?
Grout injection has gained popularity in recent years as an effective method for
repairing or strengthening masonry walls. This well-researched technique involves
low-pressure injection of grout into cracks, voids, joints, or cavities within masonry
by following these steps :1) Cleaning a crack for patching and sealing :
The crack or expansion joint must be cleaned of all debris; power washing and
vacuuming may work but inspect the crack or joint to be sure it is clean along its
entire length otherwise the sealant may fail to adhere and the crack will leak.
2) Secure grouting ports :
There are several types of ports manufactured specially for epoxy injection available ,
they are secured over the crack in desired locations with the help of a glue gun , once
in place , sealing material is applied to the remaining crack intervals , the sealer is
also built up around the ports to provide additional fixity and prevent leakage .
3) Injecting grout:
To prevent damage while strengthening already fragile masonry, it's advisable to
use a grout pump capable of limiting the pressure to about 8 to 10 psi. Begin grouting
holes at the base of the wall and proceed to the top . Plug holes after grout has flowed
from them.
During injection, any grout spills should be cleaned from the masonry surface
immediately using a water hose. After completing the injection process, use water
and a stiff nonmetallic
brush to remove any remaining surface stains.Grout injection produces substantialrepairs that can turn back the clock on old buildings and help regain some of the lost
bearing capacity that can reach 10 15 %.
aulty flashingF.22
Flashing refer to thin continuous pieces of sheet metal or other impervious
material installed to prevent the passage of water into a structure. Since none of the
buildings in Hmoud village has a proper flashing system it's a necessity to install onebecause the walls don't drain ,water trapped inside causes wall movement and
corrosion. If it condenses on the inside wall it can peel paint or cause fungus growthneeding frequent maintenance and repair.
Flashing inside a masonry wall acts as a gutter. Placed completely through the
wall in horizontal mortar joints, it collects moisture that penetrates the wall anddiverts it out of the wall. The flashing is placed on a thin bed of mortar with another
thin mortar layer placed on top . Here is a comparison between different types of
materials used in flashing :
12
-
7/13/2019 Graduation Project
18/144
DisadvantagesAdvantagesMaterial
* Relatively costly
material
*Leads to staining in
adjacent materials.
*Durable.
*Relatively easy toform and install.
Copper
*Corrodes when installed
adjacent to mortar due toalkalinity thus requiring
high skill and experiment
in installation
Reasonable cost .*
*Soft, workable andframes easily .
Aluminum
*Brittleness or fracturing
at cold temperatures.
Low initial cost .*
*High flexibility which
makes them easy to
install .
Plastic
fflorescenceE3.2
When water containing dissolved salts evaporates from a masonry structure it
leaves a salt deposit. The stain is called efflorescence. Salts may be present in all
types of masonry materials: mortar, brick, concrete block, plaster and water.Besides being unsightly, efflorescence may lead to more serious problems such as
cracking. Salt crystals deposited in pores sometime generate enough pressure to crack
the masonry.To prevent efflorescence, we propose to prevent water from entering the wall and
provide drainage for water that does ;design properly and install flashing, weep holes,
and drips.
(Fig.2.3)
13
-
7/13/2019 Graduation Project
19/144
ealingPPlaster4.2
Plaster used in Hmoud village is composed of clay , sand and chopped
straw mixed together in the proper proportions to give a hard , durable and
beautiful covering that will help prevent cracking . Nevertheless plaster can
peal off due to the following :
1) loading stresses on the building .
2) Settlement and vibration.
3) Lath movement
4) Poor workmanship.
5) Moisture penetration.
All these factors will cause the plaster to crack and eventually detach
from the wall leaving the stone underneath exposed and unprotected and
giving an unpleasant view to the wall itself.
(fig.2.4) (fig.2.5)
How to repair plaster peel ?
ne is highly dependent on the extent to which
he best
ine the type of plaster to be used , either ready or after obtaining
laster. Reattach remaining loose
to prevent the dry plaster from drawing
s are small , plaster can be
applied immediately leveling it with the surrounding surface .
The amount of work to be do
the plaster is deteriorated and damaged . If the plaster Is a very badcondition and barely covering the wall , replacing the entire coat is t
option , otherwise a number of steps can be preformed to restore the plaster
coating :1) determ
the composition of the original coat by laboratory tests a compoundmatching the original can be prepared .
2) Remove any small, loose chunks of p
plaster with plaster washes ( plaster buttons ) spaced 25 mm away fromthe crack and from each other .
3) Mist the area with water first
moisture out of the compound too quickly .4) if the cracks are not too deep and the hole
14
-
7/13/2019 Graduation Project
20/144
5) If cracks go deep into the wall and holes are too large , sealing them w
grout mix or mortar is a good idea . Apply the sealing in layer
ith
s , scratching the
d
e
erioration
surface of the previous layer before applying the next one provides a good
frictional surface bonding the layers even better . The last layer is smoothened
and a patch of reinforced fiberglass is fastened with screws and then coverewith two or three coats of compound, allowing complete drying between coats
and feathering each coat over a wider area than the preceding one. Drying tim
varies according to the type of compound as well as with the humidity and the
amount of ventilation.
Mortar det.52
a masonry structure , with time these forces
will cause the mortar to weaken , crumble , dissemble and loose its strength and
A variety of forces are acting on
quality in a process called deterioration .
Fig.2.6)(
*What causes deterioration ?1) Thermal expansion and contraction.
soluble salts).
s to the masonry units.
nable to escape.
anship.
y.
ins to deteriorate, the rate of deterioration grows exponentially.
Repairing mortar as soon as possible costs much less in the long run and protects you
2)Efflorescence (expansion of
3)Expansion of rusting metal contiguou
4)Moisture trapped behind painted masonry u5)Effects of acid rain.
6)Poor detailing, design, installation , maintenance and workm7)Wind erosion.
8)Settling.
9)Seismic activit
Once mortar beg
from much greater damage and expense in the future. Deterioration can quickly lead
to more serious structural problems.
15
-
7/13/2019 Graduation Project
21/144
How to treat deterioration ?*
Repointing :
illing the outer parts of the joints in stone or brick walls
ing mortar has been deliberately left out or raked back, or where the
istake in repairing old stone work is to use Portland cement mortar. It's
readily available, strong and inexpensive, yes, But it's too strong ; It doesn't have the
d
vely soft.
ed
ural movement can be accommodated to
fact,
vent
ents of Mortar :
Sand
Repointing is the process of f
where the bedd
surface has weathered back from the face of the brick or stone. Re-pointing istherefore the re-filling of such joints. Here are the highlights of the re pointing
process :
* A big m
flexibility of the lime mortar that was used in stone construction. A major unwante
result of using Portland cement mortar, is that hairline cracks open almost
immediately between mortar and stone. These cracks allow moisture inside the wall,
where it becomes trapped. While Lime mortar is porous, flexible and relati
The porosity of the lime mortar enables the moisture within the wall to evaporate
through it, rather than through the masonry itself. This ensures that the potentially
damaging salts within the moisture, and those within the masonry itself, are expell
without affecting the face of the masonry.
The flexibility of the lime mortar ensures that small movements within the wall
caused by temperature change or by struct
some extent. It also has the ability to heal itself when hairline cracking occurs.
The softness of lime mortar is a characteristic of the constituent parts of the
mortar. This softness in no way indicates that the mortar is not doing its job. In
soft mortar is usually more flexible and more porous than hard mortar.Mortars for repointing should be softer or more permeable than the masonry
units and no harder or more impermeable than the historic mortar to pre
damage to the masonry units. It is a common error to assume that hardnessor high strength is a measure of appropriateness, particularly for lime-based
historic mortars. Stresses within a wall caused by expansion, contraction,
moisture migration, or settlement must be accommodated in some manner;in a masonry wall, these stresses should be relieved by the mortar rather
than by the masonry units. A mortar that is stronger in compressive strength
than the masonry units cause stresses to be relieved through the masonryunits--resulting in permanent damage to the masonry, such as cracking and
spalling,
* Compon
ortar and the material that gives mortar itsctive color, texture and cohesiveness. Sand must be free of impurities, such as
d
Sand is the largest component of mdistin
salts or clay. The three key characteristics of sand are: particle shape, gradation an
void ratios.
16
-
7/13/2019 Graduation Project
22/144
When viewed under a magnifying glass particles of sand generally have either
rounded edges, such as found in beach and river sand, or sharp, angular edges, found
d is
role in
tain
ns. A
rforms well fills all these small voids with binder (cement/lime
per
ld be
.
in crushed or manufactured sand. For repointing mortar, rounded or natural san
preferred for two reasons. It is usually similar to the sand in the historic mortar and
provides a better visual match. It also has better working qualities or plasticity andcan thus be forced into the joint more easily, forming a good contact with the
remaining historic mortar and the surface of the adjacent masonry units.
The gradation of the sand (particle size distribution) plays a very important
the durability and cohesive properties of a mortar. Mortar must have a cer
percentage of large to small particle sizes in order to deliver the optimum
performance.
A scoop of sand contains many small voids between the individual grai
mortar that pe
combination or mix) in a balanced manner. Well-graded sand generally has a 30
cent void ratio by volume. Thus, 30 per cent binder by volume generally shou
used,. This represents the 1:3 binder to sand ratios often seen in mortar specifications
.Lime
Traditional Mortar formulations use lime as a primary binding material. Lime is
d from heating limestone at high temperatures which burns off the carbon
ll
a sealed container. Lime (calcium
derive
dioxide, and turns the limestone into quicklime..
Lime when mixed with water into a paste is very plastic and creamy. It wi
remain workable and soft indefinitely, if stored in
hydroxide) hardens by carbonation absorbing carbon dioxide primarily from the air,converting itself to calcium carbonate. Once a lime and sand mortar is mixed and
placed in a wall, it begins the process of carbonation. If lime mortar is left to dry too
rapidly, carbonation of the mortar will be reduced, resulting in poor adhesion and
poor durability. In addition, lime mortar is slightly water soluble and thus is able to
re-seal any hairline cracks that may develop during the life of the mortar. Lime
mortar is soft, porous, and changes little in volume during temperature fluctuations
thus making it a good choice for historic buildings.
.Water Water should be potable--clean and free from acids, alkalis, or other dissolved
materials.
ents should be measured and mixed carefully to assure the
uniformity of visual and physical characteristics. Dry ingredients are measured by
should
r
organic
Mortar compon
volume and thoroughly mixed before the addition of any water. Half the waterbe added, followed by mixing for approximately 5 minutes. The remaining water
should then be added in small portions until a mortar of the desired consistency is
reached. The total volume of water necessary may vary from batch to batch,depending on weather conditions. It is important to keep the water to a minimum fo
17
-
7/13/2019 Graduation Project
23/144
two reasons: first, a drier mortar is cleaner to work with, and it can be compa
tightly into the joints; second, with no excess water to evaporate, the mortar cures
without shrinkage cracks. Mortar should be used within approximately 30 minutes
final mixing
*Filling th
cted
of
e Joint.
Where existing mortar has been removed to a depth of greater than 1 inch, these
e filled first, compacting the new mortar in several layers. The
sh
tooled to
match the historic joint. Proper timing of the tooling is important for uniform color
nd
deeper areas should b
back of the entire joint should be filled successively by applying approximately 1/4
inch of mortar, packing it well into the back corners.. As soon as the mortar has
reached thumb-print hardness, another 1/4 inch layer of mortar--approximately the
same thickness--may be applied. Several layers will be needed to fill the joint flu
with the outer surface of the masonry. It is important to allow each layer time to
harden before the next layer is applied; most of the mortar shrinkage occurs during
the hardening process and layering thus minimizes overall shrinkage.
When the final layer of mortar is thumb-print hard, the joint should be
and appearance. If tooled when too soft, the color will be lighter than expected, a
hairline cracks may occur; if tooled when too hard, there may be dark streaks called
"tool burning," and good closure of the mortar against the masonry units will not be
achieved.
After tooling, excess mortar can be removed from the edge of the joint by brushing
with a natural bristle or nylon brush. Metal bristle brushes should never be used on
dix ( A ) that provides a detailed listing of each one of the
building and the problems encountered in them .
historic masonry.
** Refer to appen
18
-
7/13/2019 Graduation Project
24/144
2.6 Assessing Cleaning and Water-Repellent Treatments
for Historic Masonry Buildings
Inappropriate cleaning and coating treatments are a major cause of
damage to historic masonry buildings. While either or both treatments may
be appropriate in some cases, they can be very destructive to historic
masonry if they are not selected carefully. Historic masonry, as considered
here, includes stone, brick, architectural terra cotta, cast stone concrete and
concrete block. It is frequently cleaned because cleaning is equated with
improvement. Cleaning may sometimes be followed by the application of a
water-repellent coating.
1. Preparing for a cleaning project:
Several major reasons for cleaning a historic masonry buildings:
improve the appearance of the building by removing unattractive dirt or
soiling materials, or non-historic paint from the masonry; related
deterioration by removing soiling materials that may be damaging the
masonry or provide a clean surface to accurately match re-pointing mortars
or patching compounds, or to conduct a condition survey of the masonry.Identified what is to be removed.
Consider the historic appearance of the building.
Consider the practicalities of cleaning or paint removal.Study the masonry.
2. Choose the appropriate cleaner:
The importance of testing cleaning methods and materials cannot
be over emphasized. Applying the wrong cleaning agents to historicmasonry can have disastrous results. Acidic cleaners can be extremely
damaging to acid sensitive stones, such as marble and limestone,
resulting in etching and dissolution of these stones. Others kinds ofmasonry can also be damaged by incompatible cleaning agents, or
even by cleaning agents that are usually compatible. There are also
numerous kinds of sandstone, each with a considerably differentgeological composition. While an acid-based cleaner may be safely
used on some sandstones, others are acid-sensitive and can be severely
etched or dissolved by an acid cleaner. Some sandstone contains
water-soluble minerals and can be eroded by water cleaning. And,
even if the stone type is correctly identified, stones, as well as some
bricks, may contain unexpected impurities, such as iron particles, that
may react negatively with a particular cleaning agent and result in
19
-
7/13/2019 Graduation Project
25/144
staining. Thorough understanding of the physical and chemical of the
properties of the masonry will help avoid the inadvertent selection of
damaging cleaning agents.
3. Cleaning methods and materials:
Masonry cleaning methods generally are divided into three major
groups: water, chemical, and abrasive. Water methods soften the dirt orsoiling materials and rinse the deposits from the masonry surface. Chemical
cleaners react with dirt, soiling material or paint to effect their removal, after
which the cleaning effluent is rinsed off the masonry surface with water.Abrasive methods include blasting with grit and the use of grinders and
sanding discs, all of which mechanically remove the dirt, soiling material or
paint (and, usually, some of the masonry surface). Abrasive cleaning is alsooften followed with a water rinse. Laser cleaning, although not discussed
here in detail, is another technique that is used sometimes by conservators to
clean small areas of historic masonry. It can be quite effective for cleaninglimited areas, but it is expensive and generally not practical for most historic
masonry cleaning projects.
Water cleaning:
Water cleaning methods are generally the gentlest means possible, and
they can be used safely to remove dirt from all types of historic masonry.
There are essentially four kinds of water-based methods: soaking; pressurewater washing; water washing supplemented with non-ionic detergent; and
steam, or hot-pressurized water cleaning. Once water cleaning has been
completed, it is often necessary to follow up with a water rinse to wash offthe loosened soiling material from the masonry.
Soaking. Prolonged spraying or misting with water is particularly
effective for cleaning limestone and marble. It is also a good method for
removing heavy accumulations of soot, sulfate crusts and gypsum crusts that
tend to form in protected areas of a building not regularly washed by rain.Soaking is a very slow method it may take several days or a week- but it is
a very gentle method to use on historic masonry.
Water Washing. Washing with low-pressure or medium-pressure
water is probably one of the most commonly used methods for removing dirt
or other pollution soiling from historic masonry buildings starting with a
very low pressure (100 psi or below), even using a garden hose, and
progressing as needed to slightly higher pressure generally no higher than
30-400 psi- is always the recommended way to begin.
20
-
7/13/2019 Graduation Project
26/144
Water Washing with Detergents. Non-ionic detergents which are
not the same as soaps- are synthetic organic compounds that are especially
effective in removing oil soil.
Steam/Hot-Pressurized Water Cleaning. Steam cleaning is actually
low-pressure hot water washing because the steam condenses almostimmediately upon leaving the hose. This is a gentle and effective method for
cleaning stone and particularly for acid-sensitive stones. Steam can be
especially useful in removing built-up soiling deposits it can also be an
efficient means of cleaning carved stone details and, because it doesn'tgenerate a lot of liquid and dried-up plant materials water, it can sometimes
be appropriate to use for cleaning historic masonry.
Potential hazards of water cleaning:
It s important to make sure that all mortar joints are sound and that thebuilding is watertight. Otherwise water can seep through the walls to the
interior, resulting in rusting metal anchors and stained and ruined plaster.
Some water supplies may contain traces of iron and cooper which may
cause masonry to discolor. Adding a chelating or complexing agent to the
water, such as EDTA (ethylene diamine tetra-acetic acid), which inactivates
other metallic ions, as well as softens minerals and water hardness, will help
prevent staining on light-colored masonry. Any cleaning method involving
water should never be done in cold weather or if there is any likelihood of
frost or freezing because water within the masonry can freeze, causing
spalling and cracking. Since a masonry wall may take over a week to dry
after cleaning, no water cleaning should be permitted for several days prior
to the first average frost date, or even earlier if local forecasts predict cold
weather.
Chemical Cleaning:
Acidic cleaners. Acid-based cleaning products may be used on non-
acid sensitive masonry, which generally includes: granite, most sandstones,
slate, unglazed brick and unglazed architectural terra cotta, cast stone and
concrete. Most commercial acidic cleaners are composed primarily ofhydrofluoric acid, and often include some phosphoric acid to prevent rust-
like stains from developing on the masonry after the cleaning. Acid cleanersare applied to the pre-wet masonry which should be kept wet while the acid
is allowed to "work', and then removed with a water wash.
Alkaline cleaners. Alkaline cleaners should be used on acid-sensitivemasonry, including: limestone, polished and unpolished marble, calcareous
sandstone, glazed brick and unglazed architectural terra cotta, and polished
granite. Alkaline cleaning products consist primarily of two ingredients: a
non-ionic detergent or surfactant; and an alkali, such as potassium hydroxide
21
-
7/13/2019 Graduation Project
27/144
or ammonium hydroxide. Like acidic cleaners, alkaline products are usually
applied to pre-wet masonry, allowed to dwell, and then rinsed off with water.
Chemical Cleaners to Remove Paint and Other Coatings, Stains and
Graffiti:Alkaline Paint Removers. There are usually of much the same
compositions as other alkaline cleaners, containing potassium or ammonium
hydroxide, or trisodium phosphate. They are used to remove oil, latex and
acrylic paints, and are effective for removing multiple layers of paint.
Organic Solvent Paint Removers. The formulation of organic
solvent paint removers varies and may include a combination of solvents,
including ethylene chloride, methanol, acetone, xylene and toluene.
Other Paint Removers and Cleaners. Other cleaning compounds
that can be used to remove paint and some painted graffiti from historicmasonry include paint removers based on N-methyle-2-pyrrolidone (NMP).
Or on petroleum-based compounds.
Potential hazards of chemical cleaning.
Since most chemical cleaning methods involve water, they have manyof the potential problems of lain water cleaning. Like water methods, they
should not be used in cold weather.
Abrasive and Mechanical cleaning:
Generally, abrasive cleaning methods are not appropriate for use on
historic masonry buildings. Abrasive cleaning methods are just that abrasive.Grit blasters, grinders, and sanding discs all operate by abrading the dirt or
paint off the surface of the masonry, rather than reacting with the dirt and the
masonry which is how water and chemical methods work. Since the abrasivedo not differentiate between the dirt and the masonry, they can also remove
the outer surface of the masonry at the same time, and resulting permanently
damaging the masonry. Abrasively-cleaned masonry is damaged
aesthetically as well as physically, and it has a rough surface which tends to
hold dirt and the roughness will make future cleaning more difficult.Abrasive cleaning processes can also increase the likelihood of subsurface
cracking of the masonry. Abrasion of carved details causes a rounding of
sharp corners and other loss of delicate features, while abrasion of polished
surfaces removes the polished finish of stone.
Mortar joints, especially those with lime mortar, also can be eroded by
abrasive or mechanical cleaning. In some cases, the damage may be visual,
such as loss of joint detail or increased joint shadows. As mortar joints
constitute a significant portion of the masonry surface (up to 20 percent in a
brick wall), this can result in the loss of a considerable amount of the historic
22
-
7/13/2019 Graduation Project
28/144
fabric. Erosion of the mortar joints may also permit increased water
penetration, which will likely necessitate repointing.
Poulticing to Remove Stains and Graffiti:
Graffiti and stains, which have penetrated in the masonry, often arebest removed by using a poultice. A poultice consists of an absorbent
material or clay powder (such as kaolin or fuller's earth, or even shredded
paper or paper towels), mixed with a liquid (solvent or other remover) to
form a paste which is applied to the stain. As it dries, the paste absorbs the
staining material so that it is not redeposited on the masonry surface.
Waterproof Coatings:
In theory, waterproof coatings usually do not cause problems as long
as they exclude all water from the masonry. If water does enter the wall from
the ground or from the inside of a building, the coating can intensify thedamage because the water will not be able to escape. During cold weather
this water in the wall can freeze causing serious mechanical disruption, such
as spalling. In most instances, waterproof coatings should not be applied tohistoric masonry. The possible exception to this might be the application of a
waterproof coating to below-grade exterior foundation walls as a last resort
to stop water infiltration on interior basement walls. Generally, however,waterproof coatings, which include elastomeric paints, should almost never
be applied above grade to historic masonry buildings.
23
-
7/13/2019 Graduation Project
29/144
-
7/13/2019 Graduation Project
30/144
3.1 Arches
Archesoffer architectural view and enhance aesthetic beauty of buildings.
They are used to cover openings of door and windows and transfer the
above loads to the side of walls. Various arches have been developedover centuries.
Brick Arches:
Brick arches are mainly classified into three groups according to their
construction and structure.
1. Rough Brick Arch
2. Fine Axed Brick Arch
3. Gauged Brick Arch
A growing interest in the preservation of historic structures has created a
need for methods for the analysis of load-bearing unreinforced masonry
structures, such as arches, vaults, and buttresses. Although the plasticity
methods, first applied to medieval structures in detail, provide a useful
and intuitive approach to the understanding of the behaviour of masonryarches and vaults, their usefulness in performing actual assessments of
such structures has limitations. The constitutive laws of the materials
used in masonry structures are not always amenable to accurate treatment
by the rigidplastic simplification, and the complexity of many vaulted
masonry structures makes the application of these methods difficult.
Moreover, empirical studies have shown that these structures may be
subject to three-dimensional effects that are not entirely addressed by the
application of plastic or elastic analysis in two dimensions. Progress has
been made recently in the development of constitutive laws for ancient
masonry structures and in the application of these to the analysis of
unreinforced masonry structural systems. Various formulations of three-
dimensional finite element analysis, including discrete element methods,
and plasticity methods have also proven useful .
24
-
7/13/2019 Graduation Project
31/144
3.1.1 THEORETICAL ASPECTS OF MASONRY
ARCHES:
Finding the ideal form of arches:
In nature, openings are covered by curved structures such as the ceilingof caves. The first man made spans in brick were corbelled arches. In
corbelled arches, bed joints are horizontal Drysdale (1994). For true
arches, bed joints are perpendicular to the thrust line, which ideally is in
the centre of well-designed arches. Students become aware of the fact that
structures should be shaped in a way that compression prevails, which
often leads to a curved structure that follows the thrust line. The effect ofweight on stability can easily be demonstrated by the overturning of a
wall. The theoretical failure load for an equally distributed loaded arch is
dominated by the compressive strength of the masonry as the full sectionis under almost equal compression. However, variable loads can cause a
shift of the thrust line, causing cracking of the arc.
The changes in the position of the thrust line due to life loads are used toestablish the thickness of the arch. In some cases the effects of back fill
and surrounding masonry should be considered too.
Form finding aspects under dead load:
Masonry only has a minor tensile strength in comparison with its
compression strength. Bending strength depends on the amount ofcompression. Elements that can take compression only do not exist.
When a compression load is applied, also some ability to take bending
moments develops. However, elements that can take tension only do
exist: a piece of wire or a chain. When strings are used to model
structures, bending moment are neglected. The ideal shape that an arch
would take under its weight can be visualized by showing a wire
suspended between two points. The wire takes up a catenary shape under
its own weight and is in pure tension. Imagine the shape turned upside
down, and tension would convert into compression, giving the thrust linefor this load situation. In a catenary shaped arch, the weight is distributed
evenly along the arch. It is easier to take the distribution of the weight (or
permanent load) evenly distributed horizontally along the span which
results in the chain taking the shape of a parabola. A circle segment also
can approximate the catenary.
A distributed load can be abstracted to a number of concentrated loads
and graphical solutions can be used to find the ideal shape of the arch.
When the loads are less evenly distributed it is much more complicated to
find the shape of the arch. Using the string model however gives the
perfect shape instantly.
25
-
7/13/2019 Graduation Project
32/144
Form finding aspects under variable loads:
In many if not all practical cases, the weight of a masonry arch
dominates. Fortunately, masonry material (essential clay) is available in
large quantities. Also sand is often used as a back filling. Other kinds of
loading can be incorporated in the cable model by adding equivalentweights. Consequently, more than one thrust line is possible and all lines
of thrust have to be contained within the arch. The lines of thrust for non-
symmetric loads like wind or axle deviate from the ideal line of thrust and
cause arch failure quite easily. The thrust line of a load in one point load
deviates most from the ideal thrust line. Arches do not fail because of
their insufficient material strength but on the fact the thrust line moved
too far. The differences in the position of the thrust lines give an
indication of the necessary width.
3.1.2 Construction phase of arches:Arches may be constructed in various forms , such as segmental,
elliptical, Tudor, Gothic, semicircular, andparabolic toflat orJack arches .The primary advantage of an arch is that under
uniform loading Conditions, the induced stress is principally
compression rather than tension.For this reason, an arch will frequently provide the most efficient
structural span. Since masonrys resistance to compression is
greater than to other stresses, it is an ideal material for the
construction of arches. Arches are divided structurally into two
categories. Minor arches are those whose spans do not exceed 6 ft
with a maximum rise/span ratio of 0.15, with equivalent uniform
loads of the order of 1000 lb/ft. These are most often used in
building walls over door and window openings. Major arches are
those whose spans or loadings exceed the maximum for minor
arches. With Larger spans and uniformly distributed loads, the
parabolic arch is often themost structurally efficient form.
26
-
7/13/2019 Graduation Project
33/144
Fig (3.1): Masonry arch forms.
Load distribution in masonry archesFig(3.2) :
27
-
7/13/2019 Graduation Project
34/144
3.1.3 Minor Arch Design:
In a fixed masonry arch, three conditions must be maintained to ensure
the integrity of the arch action: (1) the length of span must remainconstant; (2) the elevation of the ends must remain unchanged; and (3)
the inclination of the skewback must be fixed. If any of these conditions
is altered by sliding, settlement, or rotation of the abutments, critical
stresses can develop and may result in structural failure. Adequate
foundations and high-quality mortar and workmanship are essential to
proper arch construction. The compressive and bond strength of the
mortar must be high, and only Types M, S, and N are recommended. It is
also particularly important that mortar joints be completely filled to
assure maximum bond and even distribution of stresses.Arches are designed by assuming a shape and cross section based on
architectural considerations or empirical methods, and then analyzing the
shape to determine its adequacy to carry the superimposed loads.
Minor arch loading may consist of live and dead loads from floors, roofs,
walls, and other structural members. These may be applied as
concentrated loads or as uniform loads fully or partially distributed.
The dead load on an arch is the weight of the wall area contained within
a triangle immediately above the opening. The sides of the triangle are at
45 angles to the base, and its height is therefore one-half of the span.Such triangular loading is equivalent to a uniformly distributed load of
1.33 times the triangular load. Superimposed uniform loads above thistriangle are carried beyond the span of the opening by arching action of
the masonry wall itself when running bond patterns are used. Uniform
live and dead loads below the apex of the triangle are applied directly onthe arch for design purposes.
Minor concentrated loads bearing directly or nearly directly on the archmay safely be assumed as equivalent to a uniformly distributed load twice
magnitude of the concentrated load. Heavy concentrated loads should not
be allowed to bear directly on minor arches (especially jack arches).There are two basic theories for verification of the stability of an
assumed arch section. The elastic theory considers the arch as a curved
subject to moment and shear, whose stability depends on internal stresses.For arches subject to non-symmetrical loading that can cause tensile
stress development, the elastic theory provides the most accurate method
of analysis.
There are many methods of elastic analysis for arch design, but in most
instances their application is complicated and time consuming.
28
-
7/13/2019 Graduation Project
35/144
A second theory of analysis is the line-of-thrust method, which considers
the stability of the arch ring to be dependent on friction and the reactions
between the several arch sections or voussoirs. In general, the line-of-
thrust method is most applicable to symmetrical arches loaded uniformly
over the entire span or subject to symmetrically placed concentratedloads. For such arches, the line of resistance (which is the line connecting
the points of application of the resultant forces transmitted to each
voussoir) is required to fall within the middle third of the arch section,
so that neither the intrados nor extrados of the arch will be in tension .
3.1.4 Major Arch Design:
Major arches are those with spans greater than 6 ft or rise-to-span ratiosof more than 0.15 .The design of these elements is a much more
complicated structural problem than minor arches because of
increased loading and span conditions.
Leontovichs book, Frames and Arches, gives formulas for arches with
rise-to-span ratios (f/L) ranging from 0.0 to 0.6. These are straightforward
equations by which redundant moments and forces in arched members
may be determined.
The equations are based on a horizontal and vertical grid coordinate
system originating at the intersection of the arch axis and the left. Eachset of equations depends on the conditions of loading. Moments, shears,
and axial thrusts are determined at various increments of the span.No tensile stresses should be permitted in unreinforced masonry arches
under static loading conditions.
Arch Types :
1.
Flat ArchA flat arch is suitable only for small spans and light load. It is
constructed mainly on doors and windows in ordinary buildings.
The square shape of this arch is decorative and non load bearing.Generally it is used to cover reinforced lintel which bears the load
of wall from above.
2. Circular Arch
Circular archis suitable for long spans and can take heavy load.
In past these arches were constructed over bridges but nowadays
29
-
7/13/2019 Graduation Project
36/144
they are constructed in buildings where architectural appearance is
required. They add to the beauty of buildings.
3. Semi-circular Arch
Semi-circular archis very simple to construct or design as there is
no complex geometry or cutting of bricks. Its semicircular shape
with all the bricks facing towards the centre of the arch creates a
wonderful view. Two or three rows of bricks are layered to add
decorative touch to the beauty of the building.
Fig (3.3) : Arches
30
-
7/13/2019 Graduation Project
37/144
3.1.5 Cracks in arches:
Arched architecture can absorb thermal movements and excessive
loadings by forming local cracks in the arches which act as hinges. Three
such hinges are theoretically permissible, but it must be remembered thatwith pointed arches the apex may act as a hinge, so only one hinge crack
in each arc is safe.Thermal movements over long periods lead to drift or the lengthening
of the upper parts of walls caused by the sliding of the masonry in the
archs joints which tends to break up the mortar and weaken the
abutments and spandrels.
Approximately tangential diagonal cracks near the sides of the arch
springing, which spread up towards the apex of the arch, are generally
due to subsidence of an abutment, and, if extensive, may indicate adangerous state. Cracks in the spandrels near the quarter points of the
span indicate that the arch is acting as a hinged frame, but, other things
being considered, do not indicate a dangerous state. Sometimes even if no
settlement or cracking is visible the face of masonry in an arch or vault is
seen to be bulging outwards. This usually indicates poor internal
condition of the masonryit may originally have been badly built with
rubble, re-used 69*stone or poor mortar, or it may have deteriorated
owing to water penetration, etc. The soundness of the masonry can be
confirmed by listening to the tapping of a hammer on the opposite side ofthe wall. Masonry and brickwork which are consistently wet or where
damp often penetrates are likely to be weaker than similar dry areas.
3.1.6 Repair of arches
Repointing and grouting masonry in arches can, if applied to the
maximum depth possible, greatly strengthen an arch. The repair of all
types of arches may involve taking down the arch and rebuilding it, using
a traditional falsework of timber and shoring with close-centred needlesto carry the weights above the arch. On the other hand, if the arch is wide
and the voussoirs are not of the full width it may be possible to rebuild
half at a time or to take out defective stones or bricks and replace them
individually. This has the advantage of not affecting the walling above to
such an extent. Repair by rebuilding is rather drastic as it relieves
compressive stresses, raising questions of prestressing the arch to avoid
new deformations, which may require great ingenuity. Such prestressing
can well be carried out with hydraulic jacks. Occasionally an arch can be
freed by cutting out mortar joints and pushed back into position usinghydraulic jacks.
31
-
7/13/2019 Graduation Project
38/144
Figure (3.4) : Deformation in arches(a) Intact arch
(b) Arch cracked by spreading abutments
(c) Arch cracked by differential settlement of one abutment
32
-
7/13/2019 Graduation Project
39/144
After listing all the masonry problems and propose all the possibletreatment for these problems, in this chapter we will introduce the
mechanisms which will be used to form the future village as shown in
figure 3.5.
Figure (3.5)
33
-
7/13/2019 Graduation Project
40/144
s buildings'Classification of the village2.3
As mentioned previously the adaptive reuse is concerned with converting
buildings into other, more effective and more efficient uses. This means
that the adapted property serves the client's requirements better and givesthe building an extended useful life. An adaptation scheme would focus
on refurbishing the property internally as well as externally.
On the other hand, we should focus on the performance aspects of the
building. It means that its spatial and technical characteristics are
enhanced or are in keeping with the needs of the user. The layout of a
building, for instance, may require reconfiguration to make it suit new or
modified living or working practices.
Since our project focuses on converting Hmoud village to a tourist
village, we classify its buildings under categories depending on its use to:o
Motelo Restauranto Multi-Purpose Hallo
Shops
The following figures show the details of plan of the above parts
except the shops.
34
-
7/13/2019 Graduation Project
41/144
Fig. 3.6
35
-
7/13/2019 Graduation Project
42/144
Fig 3.7
Plan of the motel
36
-
7/13/2019 Graduation Project
43/144
Fig 3.8
Plan of the restaurant
Fig.3.9
Plan of the Multi-Propose Hall
37
-
7/13/2019 Graduation Project
44/144
Introducing these new functions resulted in some structural elements
are rid off such as arches and vaults, while the other are added or
constructed such as new walls, also some of the walls are partly
demolished or destroyed to open windows and doors openings.
The following figure illustrates these changes.
Fig. 3.10
Changes in motel building
This chapter discusses the mechanism of demolishing the existing walls
and constructs a new one also the mechanism of arches and vaults ismentioned in the following sections of this chapter.
38
-
7/13/2019 Graduation Project
45/144
Masonry Walls3.3
A masonry wall is a wall made from materials which have traditionally
been cemented together with the use of mortar. Masonry walls can be
used as structural walls in buildings, and they can also be utilized to
create barriers between property lines or different areas on a property.
People have been working with masonry in construction for thousands of
years, as ample examples of surviving masonry walls from all over the
world illustrate. Properly maintained, masonry can also last a very long
time; masonry walls from the medieval era, for example, are still in use in
parts of Europe, and the Great Wall of China is a particularly notable
example of a masonry wall
Stone Masonry:
Stone masonry is similar in many ways to unit masonry, but there are alsosome differences. Stone is a natural material, so its size and shape are not
uniform, and its also a very heavy material. Stone is dimensionally stable
and does not expand and contract with changes in temperature ormoisture content, so stone masonry construction does not require
expansion or control joints.
3.3.1 Factors Affecting The Design of Masonry
Buildings.
Before proceeding to the design of masonry walls as such, it will benecessary to give attention to a number of factors relating to the building
as whole.Thus it is necessary to consider the implications of the weight of the
masonry as it affects the supporting structure if the masonry is not load-
bearing. If the structure is load-bearing it is important to ensure that thelayout of walls is consistent with overall stability and is such as to avoid
susceptibility to failure in the event of accidental damage. It must also be
considered whether the area taken up by masonry walls is significant in
relation to the available floor area.
39
-
7/13/2019 Graduation Project
46/144
From the construction point of view, availability of the necessary skilled
labour, the construction time and its phasing with the overall building
schedule will also be relevant factors at the preliminary design stage.
Having resolved these questions, the masonry will be designed to meet
criteria relating to imposed loading, thermal, acoustic and fire conditionsand resistance to rain penetration. Consideration must also be given to
durability and movement, particularly in relation to contiguous elements
or materials. Appearance of external surfaces in terms of color and
texture is important and if applied facing or finishes are required,
compatibility with the masonry has to be assured.
.Design and Construction Standards.2.33
As with any building construction, direct control of both design and
construction practices is essentially in the hands of government agencies
with jurisdiction for the building site. This control is exercised by
enforcement of local buildings codes, zoning ordinances, and policies ofthe supervising agencies empowered to enforce the applicable ordinances.
For specific items , such as masonry construction, local codes may reflect
some local concerns and experiences , but they usually use data andcriteria from model building codes (such as the uniform building code or
the BOCA code) or from standards writing agencies. Despite regionaldifferences, most codes use the same basic references for standards, so
much of technical data, design requirements is similar in all codes.
However anyone doing actual design work is well advised to determinethe code of legal jurisdiction for the work and to study its requirements
carefully .
40
-
7/13/2019 Graduation Project
47/144
.Basic Construction and Terminolgy.3.33
Masonry takes some ordinary forms that retain classic elements and
terminology of ancient construction. Figure 4.7 shows some of the
common elements of masonry construction. The terminology and details
shown apply mostly to construction with bricks or concrete blocks.
Fig( 3.11)
Units are usually laid up in horizontal rows, called courses, and in vertical
planes, called wythes. Very thick walls may have several wythes, butmost often walls of bricks have two wythes and walls of concrete block
and natural stones are single wythe.
.solidthe construction is called,If wythes are connected directly
If a space is left between wythes, as shown in the illustration, the wall is
it is called a,If the cavity is filled with concrete.cavity wallcalled a
.grouted cavity wall
41
-
7/13/2019 Graduation Project
48/144
Figure (3.12)
.Demolition and Reuse of Masonry.4.33
With the increase in demolition on congested urban sites, the construction
industry has been obliged to develop more efficient techniques which arequieter and less intrusive.
This work deals with both the theoretical and practical aspects of the
demolition of masonry buildings and the recycling of demolishedmaterials.
The demolition of a masonry wall requires careful planning. Removing
part or most of the wall reduce the structural stability of the wall or
surrounding structural system. This can lead to collapse of the entirestructure if the wall is a load bearing.
42
-
7/13/2019 Graduation Project
49/144
Methods of demolition
Globally, there are several methods for isolating the portion to be
dismantled from the portion to be remained, and we conclude five
common methods used for this purpose, which they are:
1) Hand breaker
2) Cutter drum
3) Core-drill continuous drilling
4) Water jet
5) Flame jet
These methods were assessed globally from the viewpoint of
environmental problem, workability, influence upon the remainingbuilding, cutting performance as shown in table 3.1
43
-
7/13/2019 Graduation Project
50/144
Table 3.1: Assessing dismantling methods
Execution performanceWorkabilityEnvironment
al problems
Dismantling
principal
Methods
Globalevalua
tion
Working
ratio
Cutting
speed
Cutting
depth
Safety
Reaction
System
size
dust
vibration
Noise
D
C
C
C
D
C
C
D
D
D
1. Hand
breaker
Crushing by
shock using
oil hydraulic
force or
compressed
air.2. Cutter
drum
Cutting by
rotating
diamond bit.
C
D
D
B
B
B
C
A
AD
B
BD
D
A
B
C
C
A
A
Continuous
boring holes
using core
drill.
3. Core
drill
continuous
drilling
A
A: Excellent B: Good
C: less desirable D: Undesirable
C
BA
B
A
B
AAB
Cutting by
ejecting
under extra
high-pressure the
mixture of
water and
abrasive.
4. Water
jet
D
D
C
B
D
A
B
D
Fusion with
burning rod
of iron and
aluminum
alloy.
D A
5. Flame
jet
44
-
7/13/2019 Graduation Project
51/144
Framing window and door opening.53.3
Building partitions is one thing, but cutting an opening for a window or a
door in a wall is another thing altogether. To begin with, you will have tobuild a temporary support wall to carry the load from above when you are
working. Then you will have to cut a hole through the wall and exposethe interior of the house to outside weather. And once you have this hole
cut and properly framed, you will still have to modify the exterior siding
(and sometimes trim) to make a watertight seal around the window or
door.
Materials&Tools
1) Hammer
2) Circular saw, drill-driver, and 1/4 in. spade bit
3) Safety glasses
4) Measuring tape
In line with the requirements of the restoration of the
buildings to become apartments and restaurants we had demolished and
destroy many walls, on the other hand we built new ones.
This simplified sketch shows the mechanism which we used to introduce
an opening into the masonry wall.
Fig (3.13): open a window in solid wall.
45
-
7/13/2019 Graduation Project
52/144
46
-
7/13/2019 Graduation Project
53/144
4.1 Structural design
Slabs
4.1.1 Introduction:
One of the main problems in Hmoud village is the collapsed roofs; the
treatment of this problem is to replace the collapsed old roof with a new reinforced
concrete slab. Therefore, we prefer to use the most common types of slabs, either
solid slabs or ribbed slabs, so in order to identify which type is the best suited to use
in our work we designed each type separately and then compare them with each
other in terms of own weight, area of reinforcement steel per meter, and thickness.
We chose building number two, with the external dimensions 5x5.5m and
thickness of wall 50cm, as an example, to reach a decision, figure (4.1).
Figure (4.1)
4.1.2Two-way solid slab:
Reinforced concrete solid slabs are used in roofs when the length of the long side
is less than twice the length of short side, and the load is distributed in both
directions.
47
-
7/13/2019 Graduation Project
54/144
Solution:
(Dimensions are center to center).
wayTwoLx
Ly
-
7/13/2019 Graduation Project
55/144
y : Bending moment coefficient for longer span (table 13,Appendix B ) .
U: design load at ultimate 2mKg
Lx: length of shorter span .)(m
Ly: length of longer span ).(m
-Maximum moment at mid-span on a unit width of slab with span length Lx:
x=0.065
4.1285)5.4(6.976065.0 22 === LxUxMx mKg.
- Maximum moment at mid-span on a unit width of slab with span length Ly:
y=0.056
5.1107)5.4(6.976056.0 22 === LxUyMy mKg.
-Effective depth, d :
mfcb
Md 057.0
102501
4.12855.2
'
max5.2
4 =
=
=
Concrete cover = 3cm.
.936 cmdtcmd =+=
-Main Reinforcement in short span:
USEmcmdfy
MAs = ==/29.7
642007.0104.1285
7.02
2
712 (As=7.92 )2cm
-Main Reinforcement in long span:
49
-
7/13/2019 Graduation Project
56/144
USEmcmdfy
MAs =
=
= /85.7
)2.16(42007.0
105.1107
7.0
22
712 (As=7.92 )2cm
Check, As :
)60..(600
%.700
min. Grfordb
fy
dbAs
=
=
OKAscmdb
As ==
== 92.724100
61004.%4max. 2
-Torsionreinforcement at the free corners:
There is a special reinforcement that should be added to the slab to control
cracking and to resist moments due to torsion. This reinforcement will be as a mesh
with a length and a percentage equals to 75% of the main reinforcement in
the short span, and it will be placed in the top and bottom of each corner.
Lx2.0=
-Check for allowable shear stress:
To find shear force in two directions:
LxUVxX =
LxUVy y =
Where: :x Shear force coefficient for shorter span (table 14,Appendix B ).
:y Shear force coefficient for longer span (table 14,Appendix B ).
Shear force in short span, Vx:
36.0=x
kgLxUVx X 15825.46.97636.0 ===
50
-
7/13/2019 Graduation Project
57/144
Shear force in long span, Vy:
33.0=y
KgLxUVy y 3.14505.46.97633.0 ===
Maximum shear force, 1582max ==VxV Kg
Shear stress, 264.26100
1582maxcmKg
db
Vv =
=
=
Allowable shear stress of concrete, 'Vc :
4
3 '16'
d
fcVc
=
Where: Reinforcement ratio, %3
=db
As
ok>=
= 64.212.116
25032.116'
2
4
3
(No need to stirrups)
-Check for deflection: (just in short span)
( 1fPv = ) .must be greater thand
Lx
Where, : Slenderness coefficient (for simply support =20 )
: Factor modification1f
+
+=
9.0
.
82.155.0
2
1
db
Mf Where, M in (Mpa).
57.3)6(10010
102.1285
. 2
2
2 =
=
db
M
1f =0.957
51
-
7/13/2019 Graduation Project
58/144
14.19957.0201 === fPv
goodnotPvd
Lx=>>== )14.19(75
9
450
Try, t=17cm d=14cm.
66.0)14(10010
102.1285
. 2
2
2 =
=
db
M
1f =1.72
4.3472.1201 === fPv
OKPvd
Lx=
-
7/13/2019 Graduation Project
59/144
2Kg250' cmfc=
)60.(4200 2 GrcmKgfy=
-Calculation of loads:
(Weight = volume unit weight)
Self weight of ribs = 1082500118.02
14.01.02 =
+ 2mKg
Weight of upper section= (0.25-0.18)112500=175 2mKg
Plaster weight =0.02112200= 44
2
mKg
Hollow blocks = 10 15=1502
mKg
Dead load, DL= 108+175+44+150 = 477 2mKg
Live load, LL= 200 2mKg
Design load, U=1.4DL+1.6LL U=( 1.4477) +(1.6200)= 987.8 2mKg
Design load on each rib, u =2U =493.9 ribKg
-Design:
-Maximum bending moment in short span:
mKgLxu
M .2.12508
)5.4(9.493
8max
22
=
=
=
-Concrete cover = 3cm.
cmertd 22325cov ===
-Main Reinforcement:
USEribcmdfy
MAs =
=
= /69.1
2242008.0
102.1259
8.0
22
212 (As=2.26 )2cm
53
-
7/13/2019 Graduation Project
60/144
Check, As :
)60.(,sec.6003
4min. GrtionTfor
dbAs
=
OKcmAscmdb
As ==
== 22 26.26.10100
22124.%4max.
- Check for allowable shear stress:
The value of shear force calculated at a distance (d=22cm) from the supports is used
in design.
Reaction, .275.11112
5.49.493
2 Kg
lu
R =
=
=
Thickness of supports, T = 50cm.
Design shear force, ribKgT
duRV 142.879)25.022.0(9.493275.1111)2
( =+=+=
Shear stress, 233.32212
142.879cmKg
db
Vv =
=
=
Allowable shear stress of concrete, 'Vc :
4
3 '16'
d
fcVc
=
Where: Reinforcement ratio, %3
=db
As
ok>=
= 224
3
33.397.622
25086.016' (No need to stirrups)
-Check for deflection:
( 1fPv = ) .must be greater thand
Lx
54
-
7/13/2019 Graduation Project
61/144
+
+=
9.0.
82.155.0
2
1
db
Mf Where: M in (Mpa).
5166.0)22(5010
102.1250
. 2
2
2 =
=
db
M
1f =1.83
6.3683.1201 === fPv
OKPvd
Lx=
-
7/13/2019 Graduation Project
62/144
-Calculation of loads:
(Weight = volume unit weight)
Self weight of ribs = 1082500118.02
14.01.02 =
+ 2mKg
Self weight of ribs in other direction = 08.82250076.018.02
14.01.02 =
+ 2mKg
Weight of upper section= (0.25-0.18)112500=175 2mKg
Plaster weight =0.02112200= 44 2mKg
Hollow blocks = 8 15=120
2
mKg
Dead load, DL= 108+82.08+175+44+120 = 529.08 2mKg
Live load, LL= 200 2mKg
Design load, U=1.4DL+1.6LL U=( 1.4529.08) +(1.6200)= 1060.712 2mKg
Design load on each rib, u =2
U=530.36 ribKg
-Design:
- Maximum moment at mid-span on a unit width of slab with span length Lx:
x=0.065 ..(table 13,Appendix B )
698)5.4(36.530065.0 22 === LxUxMx mKg.
- Maximum moment at mid-span on a unit width of slab with span length Ly:
x=0.056 ..(table 13,Appendix B)
4.601)5.4(36.530056.0 22 === LxUyMy mKg.
-Concrete cover = 3cm.
cmertd 22325cov ===
56
-
7/13/2019 Graduation Project
63/144
-Main Reinforcement in short span:
USEribcmdfy
MAs =
=
= /944.0
2242008.0
10698
8.0
22
112 (As=1.13 )2cm
-Main Reinforcement in long span:
USEribcmdfy
MAs =
=
= /86.0
)2.122(42008.0
104.601
8.0
22
112 (As=1.13 )2cm
Check, As:
)60.(,sec.6003
4min. GrtionTfor
dbAs
=
OKcmAscmdb
As ==
== 22 13.16.10100
22124.%4max.
- Check for allowable shear stress:
Shear force in short span, Vx:
36.0=x .(table 14,Appendix B )
kgLxuVx X 18.8595.436.53036.0 ===
where, u =design load on each rib (kg/rib)
Shear force in long span, Vy:
33.0=y .. (table 14,Appendix B )
KgLxuVy y 58.7875.436.53033.0 ===
Maximum shear force, 18.859max ==VxV Kg
Shear stress, 225.32212
18.859maxcmKg
db
Vv =
=
=
57
-
7/13/2019 Graduation Project
64/144
Allowable shear stress of concrete, 'Vc :
4
3 '16'
d
fcVc
=
Where: Reinforcement ratio, %3
=
db
As
ok>=
= 224
3
25.352.522
250428.016' (No need to stirrups)
-Check for deflection: (just in short span)
( 1fPv = ) .must be greater thand
Lx
+
+=
9.0.
82.155.0
2
1
db
Mf Where: M in (Mpa).
29.0
)22(5010
10698
.2
2
2 =
=
db
M
1f =2.08
6.4108.2201 === fPv
OKPvd
Lx=
-
7/13/2019 Graduation Project
65/144
USEmcmAs == 205.11007100
15.028 (As=1.01) in two direction.
4.1.5 Conclusion:
The comparison between the slabs is made in terms of the own weight, area of
reinforcement steel per meter, and thickness.
ThicknessOwn weight2
mKg cm
Area of steel
in short span
mcm2
Area of steel
in long span
mcm2
Two-way solid
slab
469 17 (712)=7.92 (712)=7.92
One-way ribbed
slab
477 25 2(212)+ (28)
=5.53
(28)=1.01
Two-way ribbed
slab
529 25 2(112)+(28)
=5.53
2(112)+(28)
=5.53
Through the table shown above we notice that:
1 - The solid slab has the lowest value of weight.
2 - The solid slab has the lowest value of thickness.
3 - The largest amount of steel is used in the solid slab.
As a result, solid slab with the lowest thickness is preferred to be used,
although the amount of reinforcement for such slabs is more than the amount used
in ribbed slabs. In ribbed slabs there is an additional cost should be considered; the
cost of hollow blocks and the cost of transporting them to the site.
59
-
7/13/2019 Graduation Project
66/144
4.1.6 Will the old wall bear the weight of the new slab?
To answer this question we conducted a simple test on the walls of thebuildings; this test gives the compressive strength for the masonry stones and
the mortar between them by using the rebound hammer or Schmidt hammer.The Rebound hammer is an easy to use instrument, which provides a quickand simple non-destructive test for obtaining an immediate indication of
concrete or masonry strength in various parts of a structure.
The old mortar, which is a mixture of mud and straw, is the weakest link
in the walls of the buildings, so its strength is the most important element we
should consider here from the principle: "if the weak bears then the strongwill also bear".
Results:
Stone
(horizontal)
R
Compressive
strength
( )2/mmN
Mortar
R
Compressive
strength
( )2/mmN
Stone
(vertical)
R
Compressive
strength
( )2/mmN
63 90.7683 18 6.8658 50 62.45360 83.94 14 1.3286 56 75.11
58 79.4858 15 2.6835 52 66.5936
59 81.7031 14 1.3286 50 62.453
58 79.4858 15 2.6835 52 66.5936
60 83.94 14 1.3286 52 66.5936
65 95.4185 15 2.6835 50 62.453
59 81.7031 14 1.3286 58 79.4858
60 83.94 16 4.058 60 83.94
62 88.4726 14 1.3286 50 62.453
60 83.94 16 4.058 60 83.94
58 79.4858 16 4.058 62 88.4726
60 83.94 16 4.058 58 79.4858
52 66.5936 14 1.3286 60 83.94
54 70.8126 18 6.8658 60 83.94
48 58.3908 14 1.3286 52 66.593660 83.94 16 4.058 56 75.11
60 83.94 15 2.6835 52 66.5936
60 83.94 14 1.3286 60 83.94
57 77.2881 15 2.6835 60 83.94
55 72.9515 16 4.058 56 75.11
40 42.926 15 2.6835 56 75.11
65 95.4185 15 2.6835 60 83.94
48 58.3908 14 1.3286 60 83.94
45 52.4445 13 0 60 83.94
verage= 77.73 2.75 75.44
60
-
7/13/2019 Graduation Project
67/144
The previous results were obtained from an equation we've calculated by
curve-fitting,figure(4.2); the reason for doing that is because the hammer
gave us rebounds (R) more than 60 during the test (the max. number on the
hammer curve is 60).
y = 0.0098x2+ 1.0707x - 15.582
0
10
20
30
40
50
60
70
80
0 10 20 30 40 50 6
Rebound (R)
Compress
ivestrength(N/mm2)
0
Figure (4.2)
From the previous table:
Compressive strength for the stone (for vertical surfaces) = 75.44 2/mmN
Compressive strength for the stone (for horizontal surfaces) = 77.73 2/mmN
Compressive strength for the mortar = 2.75 2/mmN
Distribution of loads from the slab to the walls:
Here we will consider the two-way solid slab previously mentioned (for buildingnumber 2).
Design load = U = 976.6 2/mkg
61
-
7/13/2019 Graduation Project
68/144
aC : Factor for shear
)(2
1
1 L
L
C s
a =
sL = 4.5 m.
L= 5 m.
55.0)5
5.4(
2
11 ==aC
mkgUL
C sa /5.12082
5.46.97655.0
2=
=
Normal stress = 2/24175.0
5.1208mkg=
= 26 /02417.010102417 mmN=
62
-
7/13/2019 Graduation Project
69/144
0.02417 < 2.75 OK2/mmN 2/mmN
0.02417
-
7/13/2019 Graduation Project
70/144
4.1.7 Design of a continuous slab
From the previous comparison between the 3 types of slabs we've taken a
decision to use solid slabs as a primary solution to problems concerning the
roofs of the buildings.We'll choose building number 13-B (figure 4.3) as an example to a
continuous solid slab design. This building has external dimensions of
(1414) m.
Figure (4.3)
64
-
7/13/2019 Graduation Project
71/144
It consists of 4 spans resting on 3 arch-beams and the walls of the
building; three of them have the same dimensions of (3.514) m, and one
span has a dimension of (2.514) m.
Calculations:
wayOneLx
Ly>== 24
14
5.3
wayOneLx
Ly>== 26.5
5.2
14
y using PROKON software we have designed the following One-way solid
lab:
Tables
B
s
Input
(MPa) 25Fcu
Fy (MPa) 420
Fv (MPa) 280
Cover to center top steel (mm) 25
Cover to center bot. steel (mm) 25Dead Load Factor 1.4
Live Load Factor 1.6
Density of concrete (KN/m3) 0
Sec
No.
Bw
(mm)
D
(mm)
1 1000 120
65
-
7/13/2019 Graduation Project
72/144
Span NO. SectionLength (m)
1 2.5
2 3.5
3 3.5
4 3.5
Sup
No.
Support
Below,D (mm)
1 500
2 500
3 500
4 500
5 500
CaseD,L
spa leftN/m)
b(m)
n W(K
D 1 152
L 1 5 15
66
-
7/13/2019 Graduation Project
73/144
Deflection:
Max. Deflection = L/250 = 3500/250 = 14 mm OK
67
-
7/13/2019 Graduation Project
74/144
Shear and bending moment diagrams:
68
-
7/13/2019 Graduation Project
75/144
Reinforcement:
69
-
7/13/2019 Graduation Project
76/144
70
-
7/13/2019 Graduation Project
77/144
4.1.8 Design of space frame
Introduction:
One of the functions that we want to provide in Hmoud village is a multi-purpose hall; including services to the residents of the village.
For this reasons we selected a building with approximate dimensions of (20 15)
m which contains a lot of arch-beams that form an obstacle to the purpose of the
hall so we decided to remove them and also remove the old roof to get a large
hall.
Figure (4.4)
71
-
7/13/2019 Graduation Project
78/144
Here, we prefer to use a double layer grid (space frame) for the new hall, because
it is lighter than concrete.
Double-layer grids:
Double-layer grids, or flat surface space frames, consist of two planar
networks of members forming the top and bottom-layers parallel to each other
and interconnected by vertical and inclined web members.
Double-layer grids are characterized by hinged joints with no moment or
torsional resistance; therefore,all members can only resist tension or
compression. Even in the case of connection by comparatively rigid joints, the
influence of bending or torsional moment is insignificant.
Double-layer grids are usually composed of basic elements such as:
1. Planar latticed truss.
2. A pyramid with a square base that is essentially a part of an octahedron.
3. A pyramid with a triangular base (tetrahedron).
Figure (4.5)