Globul TP Installation FAQ_V2

8
ction plate for Outdoor TP adapting Flexible 1 2 3 4

description

Globul TP Installation

Transcript of Globul TP Installation FAQ_V2

Page 1: Globul TP Installation FAQ_V2

Connection plate for Outdoor TP adapting Flexible base 1 2

34

Page 2: Globul TP Installation FAQ_V2

TP Cabinets alarm configuration file upload

Important: After click “send”, the connection will be interrupted. Please Log on again and go truth an Alarm Configuration menu to check the alarm configuration is right.

For details, please check the “Quick TP Setup_Ver.3” file.

Page 3: Globul TP Installation FAQ_V2

Battery parameter setting Requirement-Basic monitor parameter setting for TP (Check and set on LCD after alarm configuration file upload)

Set the Bat number and capacity to:1*150Ah for 1 string of 150Ah, 1*300Ah for 2 strings of 150Ah, 1*450Ah for 3 strings of 150Ah, 1*600Ah for 4 strings of 150Ah

Page 4: Globul TP Installation FAQ_V2

If there is no spare AC breaker for new TP power on to do pre-commissioning, we can power on equipments using TP batteries.

Please follow the rules as below when power on new equipments for pre-commissioning by the battery.1. Install all new battery groups and make sure the battery cable connection is right.2. Measure the battery string voltage and make sure it's about 50V~53V.3. The pre-commissioning time should be less than one hour.4. The LLVD (Load Low Voltage Disconnect) voltage is 44V and low voltage alarm is 47V.

Please pay attention to the battery voltage reduction on LCD screen when you do pre-commissioning.

5. Turn back the battery manual switch from “BAT ON” to “NORMAL” status after you finish the pre-commissioning and the battery manual on alarm will disappear.

Battery Power on for pre-commissioning Requirement

TP48200B TP48200A

Page 5: Globul TP Installation FAQ_V2

TP48200A Fan fault handleFAN Group 1

(Internal cycle)

FAN Group 2(External

cycle)

Set the Fan Control Mode to Manual state and check which fan is not running when the door is open. At Manual state, the fans are running to default value of 50% speed ratio even the door is open.But after you finish the fan running test, please change the Fan Control Mode back to Auto. Settings->TCU Summary->Fan Ctrl Mode to “Manual”Check if something sticks in the fan or the fan power cable connector is loosen or not connected. If the fan is really broken, we have to replace it with a new one.

Page 6: Globul TP Installation FAQ_V2

TP Cabinet AC SPD failure handle If the AC SPD module window turns from green to red, it should be broken and can be replaced by spare one following the operation as below.

Page 7: Globul TP Installation FAQ_V2

Reusing of swapped PSS and BatteriesThe client is going to reuse the Guardian 10KW and Guardian 25KW power systemsMost of the batteries also will be reused

To avoid problems during re-installation of PSS equipment and batteries it is very important to keep whole installation set during de-installation. PS Cable terminals and battery front terminal adapters, straps, nuts, bolts, washers must be collected from the site and transferred to the warehouse together with the equipment.

Page 8: Globul TP Installation FAQ_V2