Getting Started with Advanced Network Operations
-
Upload
schneider-electric -
Category
Technology
-
view
651 -
download
2
description
Transcript of Getting Started with Advanced Network Operations
Getting Started with Advanced Network OperationsA fastrack DMS solution for distribution management
Make the most of your energySM
Summary
Executive Summary .................................................................................... p 1
Introduction ................................................................................................ p 2
Why a fastrack DMS? .................................................................................. p 4
Build ........................................................................................................... p 6
Learn .......................................................................................................... p 7
Plan ............................................................................................................ p 8
Execute ....................................................................................................... p 9
Move at the ‘speed of value’ ....................................................................... p 10
Conclusion .................................................................................................. p 11
Executive summary
Getting Started with Advanced Network Operations
White paper | 01
While many utilities look forward to the benefits of deploying smart grid
technology, they need help on where and how to start. A manageable distribution
management system (DMS) pilot implementation is a good kickoff toward the
smart grid goal, because it successfully demonstrates the possibilities while it
builds support from stakeholders across the enterprise. Schneider Electric helps
the utility implement the DMS pilot, using a phased Build — Learn — Plan —
Execute approach.
In such a DMS pilot project, the company works with a small team of utility
personnel knowledgeable of the organization’s network data stores and analytical
functions. They build a fully operational load flow model that represents a subset
of the network and reflects circuit data from the GIS database or other sources
and includes two HV/MV substations and four to eight feeders, ideally with the
switches and enough load profile data to support some switching and basic
optimization functionality.
In the Learn phase of the DMS pilot, team members evaluate functionality of the
model and completeness and accuracy of the data used. Tuning the model builds
team confidence in its understanding of the data needed and the accuracy of the
basic DMS algorithms.
In the Plan phase, the utility identifies current business plan and internal and
external drivers toward grid automation, considering throughout the political and
regulatory environments. A strategy is designed to remove obstacles and achieve
identified goals.
In the final Execute phase, the utility will contract for software and services; train
core team; develop system configuration and convert data; and finally deploy the
system with site acceptance testing and rollout.
This fastrack DMS implementation gets the utility started and moving at the ‘speed
of value’ as it builds confidence in DMS technology. It offers a proof-of-concept of
DMS benefits across the organization — more reliable service, reduction of peak
demand, utility cost savings and more.
Introduction
White paper | 02
Getting Started with Advanced Network Operations
Smart Grid technology offers a large and often confusing array of components
and solutions that promise potential benefits for stakeholders. Making the right
choices in this environment isn’t easy. Focusing on critical areas for improving
grid performance is one key to achieving the best results. One emerging trend in
the industry is to develop strategies that better control and optimize distribution
network operations with advanced distribution management systems (DMS) and
to start with a “proof of concept” (POC) approach.
‘Pilot’ projects can pose challenges for many utilities. How to start? How to
avoid the perception of yet another small-scale Smart Grid effort that won’t lead
to tangible benefits? This paper will address the benefits, issues, and internal
buy-ins necessary to start a pilot project, and will provide a project approach
to achieve success and position the utility organization for a full solution
evaluation.
Getting Started with Advanced Network Operations
Getting Started with Advanced Network Operations
White paper | 04
Why a fastrack DMS?
Many utilities are stymied by the enormity of
implementing a full Smart Grid with the issues of
network reinforcement, device assessment, algorithm
investigation, production or project software,
integration within OT and IT environments, and many
more issues that need to be addressed. To gain
the benefits that are associated with implementing
Smart Grid initiatives, “you have to start somewhere”.
Implementing a manageable pilot can not only
successfully demonstrate the possibilities, but
provide enormous support for building internal
utility momentum with stake holders, managers,
employees, and regulators.
At Schneider Electric, we often work with customers
to implement a DMS pilot over a three to four month
period through a four phase approach (Build —
Learn — Plan — Execute):
• Build —
- Install DMS software on a laptop
- Build the network model utilizing the utility’s GIS
or engineering analysis data
- Add missing electrical data (typical consumer load
profiles, standard transformer characteristics,
other typical equipment data)
• Learn —
- Learn just what specific data is missing in the
currently available network model
- Investigate the location and quality of the missing
data within the current utility data stores
- Assess steps that will be necessary to maintain a
“timely and accurate” network model to support
an operational DMS
- Investigate what can be achieved through
systems integration and what can be acquired
through bulk import or manual data loads
• Plan —
- Develop a ranking of analytic functions and their
benefit to the utility (i.e. switching orders, FLISR,
VVO, Voltage Reduction, Load Shedding, etc.)
- Develop a plan for identifying data sources and
methods for accurately maintaining those sources
- Develop an organizational communications
plan utilizing the POC laptop for “show and tell”
meetings
Getting Started with Advanced Network Operations
White paper | 05
• Execute —
- Contract for software and services
> Specify requirements
> Identify delivery and support services
- Design
> Train core team
> Review requirements
- Develop
> Data conversion
> System configuration
- Deploy
> Site acceptance testing
> Production roll out
To successfully achieve the benefits of a DMS POC,
we recommend putting together a small team of key
personnel within the organization that can address
the three main areas of emphasis; assessing data,
evaluating engineering analytics, and gaining internal
management support. To assess the data needs, we
recommend a high energy, self-starter individual that
can diligently dig deep into the internal data stores
of the utility and find those “nuggets” of information.
An innovative engineer thoroughly schooled in
distribution planning and operations should be able
to analyze the appropriateness of various analytical
functions and their benefit to the organization. And of
course, there is the need to have a mid-level or higher
manager that can champion the project to upper
management, various stake holder organizations, and
the regulators.
Build
Design
Develop
Deploy
Learn
Execute
Plan
Getting Started with Advanced Network Operations
White paper | 06
Build
At the heart of all DMS implementations is a
sufficiently accurate load flow model. To achieve this
goal, data must not only be complete, but “timely
and accurate.” Electrical network data for distribution
planning and analysis is usually updated only yearly
and includes only peak load information. To properly
build an operational DMS model, the “current”
state of the distribution network must be accurately
modeled. In an operational DMS, the network
model is usually imported from the GIS (keeper of
the “as-built” model) into the DMS (keeper of the
“as-operated” model. Electrical catalog information
not maintained within the GIS is added from other
data sources to complete the DMS electrical network
model. Typical consumer load curves are usually
obtained from regulator rate filing information;
however, with the advent of AMI/MDM systems, finer
granularity of consumer load profile data may be
available.
For the POC, it is not possible to obtain all of the
aforementioned data; therefore, a subset of the
network is used with typical electrical catalog and
typical consumer data added.
• POC Scope
- Two HV/MV substations
- Four to eight feeders
- Ideally sum of the feeders connect with tie
switches
- Does not have to be “end state” data sources (i.e.
no automated integration)
• Build phase
- Draw substation 1-line connectivity model
- Import feeders from electrical connectivity model
data source
- Add several typical consumer load profiles (i.e.
residential, small commercial, large commercial,
industrial)
• Data Sources
- Substations — CAR files, SCADA 1-lines, paper
drawings, equipment records
- Feeders — GIS, SynerGEE, CYME, WindMill,
paper maps, equipment records
- Load profiles — AMI/MDM histories, load survey
data, engineering judgment
Figure above. Typical Consumer Load Profile Curves
Getting Started with Advanced Network Operations
White paper | 07
Learn
The purpose this phase is to capture the lessons
learned during the Build phase. With the DMS
installed on a laptop and the small portion of the
network verified and now a working electrical model,
the team can begin to compare load flow results
against field measurements. Where distribution
SCADA exists, the team can input telemetered values
from the SCADA 1-line displays and compare the
load flow results. Immediate verification of model
accuracy will become evident. If an electrical element
is modeled in error, load flow results will not match.
This is where the electrical engineering and utility
experience comes into play. Since the DMS provides
all electrical quantities (i.e. volts, amps, real/reactive
power, etc.) for every element in the network, it
should be fairly easy to investigate the circuit and
find the offending element. If errors exist, there is one
of two possible problems — bad field measurements,
or bad modeling. Tuning the model will build
confidence within the team of their understanding of
the data required and the accuracy of the basic DMS
algorithms. Accumulating results of this investigative
effort will be useful input to any planning for
implementing an operational network model.
After the model is producing good results, the DMS
analytical functions can be used to demonstrate the
positive effects that implementation of the DMS could
bring the utility. Learn what it takes to construct a
useful DMS model and:
• Identify data deficiencies
• Perform DMS functions and rank analytic
functions
• Topology/Connectivity Analysis
• State Estimation
• Voltage Reduction (VVO/VVC)
• Improve efficiency of the distribution network
• Define requirements and validate business needs
• Build organization confidence and consensus
Figure above. Geographic and Schematic Views of Network
Getting Started with Advanced Network Operations
White paper | 08
Plan
The key to any successful Smart Grid implementation
project is having a well thought out and tested
plan. Using the lessons learned from the previous
phase as a micro implementation, areas needing
further investigation can be identified. Stake holder
feedback from taking the POC laptop throughout
the organization should provide valuable insight into
obstacles that will need to be overcome before any
project implementation can begin.
Analyzing the current business situation is a must.
Internal and external drivers toward a Smart Grid
along with the political and regulatory environment
must be considered. A good plan will identify all of
these elements and provide a strategy for removing
obstacles and achieving goals.
One key item often overlooked is developing a
strategic vision of utility operations in the next five
to 10 years. Forgetting to plan long range can
result in solutions being implemented that meet
current targets, but are inadequate for future
utility operations. One particular area of emphasis
should be on having a robust, secure, and scalable
distribution SCADA infrastructure. Current utility
SCADA systems can adequately handle present
telemetry needs for several hundred substation
RTUs, but they cannot handle the demands of a
fully automated and telemetered smart distribution
network with tens of thousands of field devices (i.e.
switches, controllers, and sensors).
“As-is” and “to-be” processes should also
be mapped out at a very high level to identify
opportunities for improvement. A gap analysis of
current state versus future state will reveal areas
that need further investigation. Business process
re-engineering will be critical to ensuring all of the
identified benefits are achieved and the return on
investment maximized. Also of consideration is the
development of a strategy to ensure the organization
can achieve future goals.
Plan for executing Smart Grid projects• Assess internal and external drivers for grid
automation
- Balance of supply and load
- System efficiency
- Operations reliability
• Evaluate internal resources
• Develop business case metrics for a DMS system
• Plan for complete DMS deployment, including
change management
Getting Started with Advanced Network Operations
White paper | 09
Execute
The last stage is Execute. At this point the Utility is
now positioned to act on the information gathered
from the Build - Learn - Plan phases. Typically an
Execution plan looks like the following:
• Contract for software and services
- Specify requirements
- Identify delivery and support services
• Design
- Train core team
- Review requirements
• Develop
- Data conversion
- System configuration
• Deploy
- Site acceptance testing
- Production roll out
Build
Design
Develop
Deploy
Learn
Execute
Plan
Getting Started with Advanced Network Operations
White paper | 10
Move at the ‘speed of value’
Schneider Electric is an industry leader in open-
architecture solutions that allow full integration
with existing and future standardized information
systems, ‘future-proofing’ its deliverables. Utilizing
the existing GIS connectivity model, the fastrack
DMS can leverage existing investments and help
validate network model accuracy. The more accurate
the network model, the better your utility identifies
operational and economic goals and develops a
realistic and effective Smart Grid strategy to realize
those goals.
Conclusion
White paper | 11
Getting Started with Advanced Network Operations
Utilities can take the first step toward achieving the benefits of DMS by
implementing a proof-of-concept DMS pilot project. This pilot will help the
utility identify data requirements and resources needed, as well as demonstrate
operational and economic benefits and build ‘buy-in’ from stakeholders.
A four-phased approach to carrying out this pilot — including creation of an ‘as
operated’ model of a subset of the network — has shown to help utilities put
network data and analysis functions to work to realize automated control and
performance optimization. Schneider Electric has helped utilities worldwide get
started with DMS technology to deliver better service to their customers and
improve overall operations efficiency and reliability.
Schneider Electric USA, Inc.
4701 Royal Vista CircleFort Collins, CO 80528Phone: 1-866-537-1091 + (34) 9-17-14-70-02Fax: 1-970-223-5577www.schneider-electric.com/us
June 2012
©20
12 S
chne
ider
Ele
ctric
. All
right
s re
serv
ed.