Geotechnical Engineering SNU Geotechnical and Geoenvironmental Engineering Lab. 124 ii) Settlements of group piles Imaginary Raft Footing Method Replace pile group with an imaginary raft footing. Friction pile at a depth of 2/3L End bearing pile at pile tip Δ ) ( z p can be determined by 2:1 method ( or o 30 frustum) Can determine elastic and consolidation settlement. Add elastic compression of pile. B g L g

Transcript of Geotechnical Engineering 124 - ocw.snu.ac.kr

Page 1: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

124

ii) Settlements of group piles

① Imaginary Raft Footing Method

� Replace pile group with an

imaginary raft footing.

� Friction pile ⇒ at a depth of

2/3L

� End bearing pile ⇒ at pile tip

� ⇒∆ )(zp can be determined by 2:1 method ( or o30 frustum)

� Can determine elastic and consolidation settlement.

� Add elastic compression of pile.

Bg

Lg

Page 2: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

125

))(()(

zLzB

Qzp

gg

g

++=∆

Page 3: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

126

② Empirical recommendations for elastic settlement of pile group

- Based on oS = settlement of single pile

� Empirical Recommendations

a) Skempton ; 2

)( )12

94(

+

+=

g

g

oegB

BSS

where gB = width of the pile group section in feet

b) Meyerhof (including the geometry of pile group)

))/11(

)3/5((

2)(r

SRSRSS oeg +

−=

where D

d

diameterpile

spacingpileSR ==

and r = no. of rows for a square group (or average no. of

rows and columns for a rectangular group)

� Using SPT results, elastic settlement on sand and gravel by Meyerhof,

cor

g

egN

IBqinS

2)()( =

where )/( ggg BLQq = (in US tons/ and ft)

60( )corN N= ≡ average corrected SPT N value within

seat of settlement ( gB≈ deep below

the tip of the piles)

≡I Influence factor 5.0)8/(1 ≥−= gBL

L = length of embedment of piles (ft)

Page 4: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

127

Similarly using CPT (Meyerhof)

c

g

egq

IqBS

2)( =

where all symbols have consistent units.

c) Vesic,

D

BSS

g

oeg =)(

where D = width or diameter of each pile in the group

Page 5: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

128

12) Negative Skin Friction

� Side friction resistance

� Downdrag force develops when relative downward movements of soil to

the pile occur due to consolidation of surrounding soils.

⇒ Observations show that relative displacements of 0.6(in) is needed to

generate full downdrag force.

� Downdrag movement caused by any increase in effective stress;

� Dewatering.

� Surface loads after installation of piles.

- Granular soil fill over clay

⇐ consolidation of clay layer by fill load

- Clay fill over granular soil

⇐ self-consolidation of clay fill

� Dissipation of excess pore water pressure after pile driving.

In general Downdrag force

Page 6: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

129

ex)

⇒ Lower water level to the sand.

⇒ Cause consolidation settlements by vertical effective stress.

At excavation site, construction dewatering causes downdrag forces.

Lowering

Page 7: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

130

� Estimation of downdrag (similar to β method)

i) Clay fill over granular soils

� The unit negative skin friction on the pile is

)(tan' '''

vsvn NKf σδσ ==

where ≡'K earth pressure coefficient

φsin10 −== K

zfv '' γσ =

=δ soil-pile friction angle φ)7.05.0( −≈

� Hence the total downward drag force, Qn on a pil e is

∫ ⋅=fH

fn dzzpKQ0

' }tan'{ δγ

δγ tan'2

1 2'

ff HpK=

where p = perimeter of pile.

fH = height of fill.

Page 8: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

131

ii) Granular soil fill over clay

� The negative skin friction on the pile exists from z=0 to z=L₁as shown

below.

Page 9: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

132

� Neutral depth L1 : up to L1, the negative skin friction is activated.

'

H2]

'

H

2

HL[

L

)HL(L

f

'

ff

'

ff

1

f

1 γ

γ

γ

γ−+

−−=

For end bearing piles, the neutral depth may be assumed to be located

at pile tip (L1=L-Hf).

∫∫ +==11

0

'

0tan)'('

L

ff

L

nn dzzHpKdzpfQ δγγ

δγδγ tan''2

1)tan''( 2

11 pKLLHpK f +=

� Applying loads = ncappile QQ +

� Resistance = ps QQ + (Qs not for fully embedded length of pile but only

for length where upward frictional resistance is

mobilized.)

� ncappile

ps

allow QQFS

QQQ +≥

+=

� To reduce downdrag

1. Predrilled hole, then install pile (reduce K).

2. Coat the pile with bitumen(reducing δ ).

Page 10: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

133

13) Drilled Piers and Caissons

i) Drilled Piers (Drilled Shafts)

� Cast-in-place pile with D>75cm

� Advantages

1.

2.

3.

4.

5.

6.

� Disadvantage

1.

2.

Page 11: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

134

� Construction Procedures

1. Dry method of construction (Stiff soils above the water table).

a) initial drilling

b) starting concrete pour

c) placing rebar cage

d) completing shaft

Page 12: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

135

2. Casing method of construction

a) initial drilling

b) drilling with slurry

c) introducing casing

d) casing is sealed and slurry is being removed from interior of casing

Page 13: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

136

e) drilling below casing

f) underreaming

g) pouring concrete and placing rebar (removing casing)

h) completing shaft

* Note : Either all casing or partial casing can be used.

Page 14: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

137

3. Wet method of construction.

a) drilling to full depth with slurry and removing slurry

b) placing rebar cage

c) pouring concrete

d) completing shaft

Page 15: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

138

� Analytical approach to predict capacity

: Same procedures as driven piles

(but different values of fs are used)

ii) Caissons

� Substructure element used at wet construction sites such as rivers, lakes

and docks

� Types of Caissons

1) Open caissons

-

-

-

-

Page 16: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

139

2) Box caissons

-

-

Should be leveled

Page 17: Geotechnical Engineering 124 - ocw.snu.ac.kr

Geotechnical Engineering

SNU Geotechnical and Geoenvironmental Engineering Lab.

140

3) Pneumatic caissons

-

-